Auxiliary pipe pulling device suitable for pipe jacking and jacking and pulling combined construction method
Through the combined construction method of auxiliary pipe pulling device and top-pull, the problems of pipe section damage and high construction complexity in long-distance pipe pulling construction are solved, and efficient construction of top and pulling is achieved, reducing the pinch force of the main jack and reducing the loading force. Construction costs.
Patent Information
- Application Number
- CN202410672464.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-28
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-05-28
Smart Images

Figure CN118499568B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe jacking construction, and in particular to an auxiliary pipe pulling device suitable for pipe jacking and a jacking and pulling combined construction method. Background Art
[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] In the construction of modern urban underground space, as the material basis for urban water supply and drainage, energy supply such as electricity and gas, waste disposal, and information transmission, underground pipelines are important infrastructure for urban construction and development. Pipe jacking technology has been widely used and promoted in the fields of water supply and drainage, power cables, communications, and integrated pipe galleries due to its advantages of small impact on ground traffic, good structural integrity, convenient construction, and no interference with residents' daily lives. Pipe jacking technology is a trenchless pipeline propulsion method used in underground construction. It relies on propulsion force and a guiding system to achieve the laying and replacement of underground pipelines without large-scale excavation of the ground or damage to the surface.
[0004] During long-distance pipe jacking construction, the distance of the pipe jacking construction is long. As the pipe section continues to lengthen, the thrust of the main jack is too large, which can easily cause damage to the pipe section. The traditional method of long-distance pipe jacking construction is to add a relay room. By utilizing its segmented thrust function, the burden of the pipe jacking force can be dispersed, so that the thrust of the main jack can be reduced, while ensuring that the thrust in each section of the pipe is within an acceptable range. However, the construction of the relay room makes the construction more complicated, and after the relay room is installed between the pipe sections, the jacks in the relay room can only be removed after the pipe jacking construction is completed. In addition, the cost of the relay room is high, which leads to high overall construction costs. Summary of the invention
[0005] In view of the deficiencies in the prior art, the purpose of the present invention is to provide an auxiliary pipe pulling device and a combined jacking and pulling construction method suitable for pipe jacking, which can prevent pipe sections from being damaged due to excessive force without setting up a relay room, thus avoiding the defects of setting up a relay room.
[0006] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0007] In a first aspect, an embodiment of the present invention provides an auxiliary pipe pulling device suitable for pipe jacking, comprising:
[0008] The pipe pulling driving mechanism is used to be arranged in the receiving well, and includes a base, the base is provided with a first top iron and a second top iron, the second top iron is fixed to the base, the first top iron is slidably connected to the base, and a telescopic component is provided between the first top iron and the second top iron;
[0009] The tool tube mechanism comprises a tool tube body, a connecting component is arranged in the tool tube body, the connecting component is connected to one end of a plurality of supporting mechanisms distributed along the annular direction, and the other end of the supporting mechanism is connected to the tool tube body;
[0010] Steel strand: one end of the steel strand can be detachably connected to the first top iron, and the other end can be detachably connected to the connecting component;
[0011] Pull tube assembly: It is composed of multiple pull tubes that are detachably connected in sequence and is used to be sleeved on the outer circumference of the steel strand.
[0012] Optionally, one end of the support mechanism is rotatably connected to the connecting component, and the other end is rotatably connected to the inner side of the tool body.
[0013] Optionally, the supporting mechanism includes a rotating cylinder, and both ends of the inner side surface of the rotating cylinder are provided with internal thread structures with opposite rotation directions, wherein the internal thread structure at one end is threadedly connected to one end of a first support rod, and the other end of the first support rod is rotatably connected to the tool body, and the internal thread structure at the other end of the rotating cylinder is threadedly connected to one end of a second support rod, and the other end of the second support rod is rotatably connected to the connecting component.
[0014] Optionally, a pipe wall of the set pulling pipe is provided with a plurality of water outlet holes, and the pulling pipe provided with the water outlet holes is used to be arranged in front of the pipe jacking machine.
[0015] Optionally, one end of the pull tube is provided with an external thread joint, and the other end is provided with an internal thread structure matching the external thread joint, and adjacent pull tubes are detachably connected via the external thread head and the internal thread structure.
[0016] Optionally, the steel strand can be detachably connected to the connecting component through an anchoring component, the anchoring component includes an anchor plate, the anchor plate is provided with a plurality of openings, an extrusion sleeve is provided at the openings, the extrusion sleeve is used to extrude and fix the steel strand, and a water injection hole is provided at the center of the anchor plate, the water injection hole is connected to the internal cavity of the pulling tube assembly through a water injection channel provided in the connecting component.
[0017] Optionally, the tool tube body includes a first tool tube and a second tool tube that are plug-connected, the first tool tube is connected to a supporting mechanism, and a detachable locking component is provided between the first tool tube and the second tool tube to achieve switching between locking and unlocking states of the first tool tube and the second tool tube.
[0018] Optionally, a groove is provided at the end of the first tool tube, a protrusion matching the groove is provided at the end of the second tool tube, the protrusion is inserted into the groove to achieve a plug-in connection between the first tool tube and the second tool tube, and a rubber sleeve is provided between the protrusion and the groove.
[0019] Optionally, the telescopic mechanism adopts a jack, one end of the jack is fixedly connected to the annular second top iron, and the other end is fixedly connected to the disc-shaped first top iron.
[0020] In a second aspect, an embodiment of the present invention provides a jacking and pulling construction method of the auxiliary pipe pulling device suitable for pipe jacking as described in the first aspect, comprising the following steps:
[0021] In the receiving well, the front pipe pulling assembly of the pipe jacking machine is pushed into the soil along the direction from the receiving well to the starting well;
[0022] Lower the pipe jacking machine into the starting well, pass the inner pipe pulling assembly of the pipe jacking machine through the pipe jacking machine, and fix the inner pipe pulling assembly of the pipe jacking machine with the front pipe pulling assembly of the pipe jacking machine pushed out of the soil;
[0023] Pass the steel strand through the front pipe pulling assembly of the pipe jacking machine and the inner pipe pulling assembly of the pipe jacking machine, and fix one end of the steel strand to the rear end of the inner pipe pulling assembly of the pipe jacking machine;
[0024] The pipe pulling drive mechanism is lowered into the receiving well, wherein the second top iron is attached to the inner wall of the receiving well, and the other end of the steel strand is fixed to the first top iron;
[0025] The main jack in the starting well is used to push the pipe jacking machine into the soil, and the jacking construction of the pipe jacking section is started. The pipe jacking machine moves forward in the soil while receiving the telescopic drive mechanism in the well. When the first jacking iron pulls out a section of steel strand, the pulled steel strand is cut off and the corresponding pulled pipe is removed. The telescopic drive mechanism returns to its position and the steel strand is fixed to the first jacking iron again.
[0026] After the set number of jacking pipe sections are pushed in, the fixed state of the steel strand and the pipe pulling assembly in the jacking machine is released, the tool pipe mechanism is lowered in the starting well, and the steel strand is passed through the pipe pulling assembly again in the receiving well, and one end of the steel strand is fixed to the connecting component, and the other end is fixed to the first jacking iron;
[0027] While the main jack is constructing the jacking pipe section behind the tool pipe mechanism, the telescopic drive mechanism pulls the steel strand, driving the jacking pipe section in front of it forward through the tool pipe mechanism, thus realizing the combined jacking and pulling construction.
[0028] The beneficial effects of the present invention are as follows:
[0029] 1. The auxiliary pipe pulling device and the combined jacking and pulling construction method of the present invention are provided with a pipe pulling driving mechanism in the receiving well, and the first jacking iron of the pipe pulling driving mechanism can be connected to the connecting component in the tool pipe mechanism through a steel strand. The tool pipe mechanism is pushed into the soil body to set the jacking pipe section and then lowered into the receiving well. The pipe pulling driving mechanism can drive the jacking pipe section in front of it to move through the steel strand and the tool pipe mechanism, and the jacking pipe section behind it is pushed in by the main jack in the starting well, thereby realizing the combined jacking and pulling construction, so that the jacking force of the main jack is reduced, avoiding damage to the pipe section caused by excessive jacking force, and there is no need to set up a relay room, thus avoiding the defects of complex construction and high construction cost caused by the use of a relay room.
[0030] 2. The auxiliary pipe-pulling device and the jacking-pulling combined construction method of the present invention are configured with a water outlet hole in the pulling pipe, and the pulling pipe with the water outlet hole is used to be arranged in front of the pipe jacking machine. During construction, water can be sprayed toward the soil in front of the pipe jacking machine, thereby disturbing the soil in front of the pipe jacking machine and facilitating the advancement of the pipe jacking machine.
[0031] 3. In the auxiliary pipe pulling device and the top-pulling combined construction method of the present invention, the support mechanism is rotatably connected to the connecting component and the tool pipe body, and the two ends of the rotating cylinder are threadedly connected to the first support rod and the second support rod. The internal threads at the two ends of the rotating cylinder rotate in opposite directions, thereby realizing the adjustment of the length of the support mechanism and the angle of the support mechanism, thereby improving the force of the support mechanism.
[0032] 4. The auxiliary pipe pulling device and construction method of the present invention, the tool pipe body includes a first tool pipe and a second tool pipe, the first tool pipe and the second tool pipe are connected by protrusions and grooves, when the pipe pulling drive mechanism pulls the first tool pipe forward through the steel strand, the second tool pipe will not move directly, to prevent the main jack of the starting well from applying a jacking force that is not synchronized with the pulling of the pipe pulling drive mechanism, resulting in the disconnection of adjacent pipe sections. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0034] Figure 1 It is a schematic diagram of the overall structure of Embodiment 1 of the present invention;
[0035] Figure 2 This is a schematic diagram of the structure of the tube-drawing driving mechanism of Example 1 of the present invention;
[0036] Figure 3 This is a schematic diagram of the cooperation between the first top iron and the drawing tube assembly in Example 1 of the present invention;
[0037] Figure 4 This is a schematic diagram of the structure of the tool tube body according to Embodiment 1 of the present invention;
[0038] Figure 5 This is a schematic diagram of the exploded structure of the tool tube body according to Embodiment 1 of the present invention;
[0039] Figure 6 is a schematic diagram of the support mechanism structure of Example 1 of the present invention;
[0040] Figure 7 is a schematic diagram of the assembly of the first support rod and the first tool tube in Example 1 of the present invention;
[0041] Figure 8 It is an exploded schematic diagram of the assembly of the second support rod and the connecting component in Embodiment 1 of the present invention;
[0042] Fig. 9 This is a schematic diagram of anchoring the steel strand and the connecting component in Embodiment 1 of the present invention;
[0043] Fig.10 This is a schematic diagram of the assembly of a steel strand, a drawing tube assembly and a tool tube mechanism according to Embodiment 1 of the present invention;
[0044] Fig.11 Schematic diagram of anchoring of a steel strand and a first top iron in Embodiment 1 of the present invention;
[0045] Fig.12 This is a schematic diagram of the assembly of a steel strand, a tube drawing assembly and a tube drawing drive mechanism according to Embodiment 1 of the present invention;
[0046] Fig.13 This is a schematic diagram of the first tube drawing structure of Example 1 of the present invention;
[0047] Fig.14 This is a state diagram of step 5 of embodiment 2 of the present invention;
[0048] Among them, 1. pipe pulling driving mechanism, 2. steel strand, 3. pipe pulling assembly, 4. tool pipe body, 5. connecting component, 6. supporting mechanism, 7. hinge bolt, 8. nut, 9. anchor plate, 10. extrusion sleeve, 11. water injection hole, 12. water outlet hole, 13. pipe jacking machine;
[0049] 1-1. Base, 1-2. First top iron, 1-3. Second top iron, 1-4. Jack, 1-5. Guide rail, 1-6. Rubber sleeve;
[0050] 3-1. The first draw tube, 3-2. The second draw tube;
[0051] 4-1. First tool tube, 4-2. Second tool tube, 4-3. Rubber sleeve, 4-4. First fixed ear plate, 4-5. Second fixed ear plate, 4-6. Articulated ear plate;
[0052] 5-1. hinged ear plate, 5-2. through hole;
[0053] 6-1. Rotating drum, 6-2. First support rod, 6-3. Second support rod. DETAILED DESCRIPTION
[0054] Example 1
[0055] This embodiment provides an auxiliary pipe pulling device suitable for pipe jacking. Figure 1 As shown, it includes a tube drawing drive mechanism 1, a tool tube mechanism, a steel strand 2 and a tube drawing assembly 3.
[0056] The pipe pulling drive mechanism 1 is used to be arranged in the receiving well, including a base 1-1, on which a first top iron 1-2 and a second top iron 1-3 are arranged parallel to and opposite to each other, the second top iron 1-3 is used to fit the well wall of the receiving well close to the starting well, the second top iron 1-3 is fixedly connected to the base 1-1, the first top iron 1-2 is slidably connected to the base 1-1, and a plurality of telescopic drive mechanisms are arranged between the second top iron 1-3 and the first top iron 1-2. The telescopic drive mechanism adopts a jack 1-4, and the telescopic drive mechanism can drive the first top iron 1-2 to slide along the base 1-1 to realize movement toward or away from the second top iron 1-3.
[0057] The tool tube assembly includes a tool tube body 4, which includes a first tool tube 4-1 and a second tool tube 4-2 that are plug-connected. When in use, the first tool tube 4-1 is located in the front, and a connecting component 5 is provided in the first tool tube 4-1. The connecting component 5 is rotatably connected to one end of a plurality of supporting mechanisms 6 arranged along the annular direction, and the other end of the supporting mechanism is rotatably connected to the inner side surface of the first tool tube.
[0058] One end of the steel strand 2 is used for detachable fixed connection with the center position of the first top iron 1-2, and the other end is used for detachable connection with the connecting component 5. The telescopic driving mechanism can drive the first top iron 1-2 to move, and the first top iron 1-2 drives the tool tube assembly to move through the steel strand 2 and the connecting component 5.
[0059] The pulling tube assembly 3 is composed of a plurality of pulling tubes that are detachably connected, and the pulling tube assembly is used to be sleeved on the outside of the steel strand.
[0060] like Figure 2-Figure 3 As shown, the first top iron 1-2 adopts a disc-shaped structure with an opening in the center for connecting with the drawing tube of the drawing tube assembly 3, and a rubber sleeve 1-6 is arranged between the drawing tube assembly 3 and the hole surface for sealing. A slide groove is arranged at the bottom of the first top iron 1-2, and the slide groove cooperates with the guide rail 1-5 arranged on the base 1-1. The first top iron 1-2 is slidably connected with the base 1-1 through the slide groove and the guide rail 1-5.
[0061] The second top iron 1-3 adopts a circular ring structure, and its bottom is fixedly connected to the base 1-1.
[0062] The telescopic driving mechanism adopts jacks 1-4, and multiple jacks 1-4 are distributed circumferentially along the circumference of the first top iron 1-2 and the second top iron 1-3. The fixed part of the jack 1-4 is fixed to the second top iron 1-3 by a flange and bolts, and its telescopic part is fixed to the first top iron 1-2 by bolts.
[0063] like Figure 4-Figure 5As shown, the tool tube body 4 includes a first tool tube 4-1 and a second tool tube 4-2. When in use, the first tool tube 4-1 is located in front of the second tool tube 4-2. The rear end face of the first tool tube 4-1 is provided with an annular groove, and the front end face of the second tool tube 4-2 is provided with an annular protrusion matching the annular groove. The protrusion is inserted into the groove to realize the plug-in connection between the first tool tube 4-1 and the second tool tube 4-2. In order to prevent water leakage at the plug-in position of the first tool tube 4-1 and the second tool tube 4-2, a rubber sleeve 4-3 is provided between the groove surface of the protrusion and the groove, and the rubber sleeve 4-3 is fixed on the surface of the protrusion. The rubber sleeve 4-3 seals the gap between the groove surface of the protrusion and the groove.
[0064] Since the first tool tube 4 - 1 and the second tool tube 4 - 2 are plug-connected, the first tool tube 4 - 1 and the second tool tube 4 - 2 can generate relative movement along the axial direction thereof.
[0065] In order to facilitate the use of lifting equipment to lower the first tool pipe 4-1 and the second tool pipe 4-2 into the starting well, a locking component is detachably provided between the first tool pipe 4-1 and the second tool pipe 4-2, and the locking component can realize the switching of the locking and unlocking states of the first tool pipe 4-1 and the second tool pipe 4-2. The locking component includes a first fixing ear plate, a second fixing ear plate, a locking bolt and a locking nut. Specifically, a plurality of first fixing ear plates 4-4 are circumferentially provided at the rear end of the inner side surface of the first tool pipe 4-1, and a plurality of second fixing ear plates 4-5 matching the first fixing ear plates 4-4 are provided at the front end of the inner side surface of the second tool pipe 4-2. The locking bolts pass through the first fixing ear plates 4-4 and the second fixing ear plates 4-5, and the locking nuts are tightened to realize the locking of the first tool pipe 4-1 and the second tool pipe 4-2. The locking nuts are loosened and the locking bolts are removed to realize the releasing of the locking state of the first tool pipe 4-1 and the second tool pipe 4-2.
[0066] The connecting component 5 is arranged inside the first tool tube, and is connected to the first tool tube 4-1 via a plurality of supporting mechanisms 6 arranged along the circumferential direction. In this embodiment, four supporting mechanisms 6 are arranged, and the four supporting mechanisms 6 are arranged at equal intervals along the circumferential direction.
[0067] In this embodiment, Figure 6-Figure 8 As shown, the support mechanism 6 includes a rotating drum 6 - 1 , and internal thread structures are provided at both ends of the rotating drum 6 - 1 , and the internal thread structures at the two ends have opposite rotation directions.
[0068] The outer end of the rotating drum 6-1 is threadedly connected to one end of the first strut 6-2. The other end of the first strut 6-2 is provided with a through hole and extends into two hinged ear plates 4-6 provided on the inner side of the first tool tube 4-1. The two hinged ear plates 4-6 and the end of the first strut 6-2 are passed through by hinge bolts 7. The hinge bolts 7 are tightened with nuts 8. The through hole is a smooth hole. The first strut 6-2 is rotatably connected to the first tool tube 4-1 through the hinge bolts.
[0069] The inner end of the rotating drum 6-1 is threadedly connected to one end of the second support rod 6-3. The other end of the second support rod 6-3 is provided with a through hole and extends into two hinged ear plates 5-1 arranged on the outer side of the connecting component 5. The two hinged ear plates 5-1 and the end of the second support rod 6-3 are passed through by hinge bolts 7. The hinge bolts 7 are tightened with nuts 8. The through hole is a smooth hole. The second support rod 6-3 is rotatably connected to the connecting component 5 through the hinge bolts 7.
[0070] By rotating the rotating drum 6-1, the length of the entire support mechanism can be adjusted. At the same time, since the support mechanism 6 is rotatably connected to the connecting component 5 and the first tool tube 4-1, the angle of the support mechanism can be adjusted, thereby increasing the force on the support mechanism.
[0071] A through hole 5-2 is provided at the center of the connecting component 5, and the through hole 5-2 passes through the front and rear end surfaces of the connecting component. The through hole on the connecting component 5 is used for passing the steel strand 2 on the one hand, and serves as a water injection channel on the other hand.
[0072] One end of the steel strand 2 can be detachably fixedly connected to the connecting component 5 through an anchoring component, and the other end can be detachably fixedly connected to the center position of the first top iron 1-2 through an anchoring component.
[0073] The anchoring component can be an existing anchoring tool, including an anchor plate 9, which is provided with a plurality of openings corresponding to the steel strands 2, and an extrusion sleeve 10 is provided at the openings. The steel strands 2 pass through the openings and are fixed by the extrusion sleeve 10.
[0074] Among them, Figure 9-10 As shown, the anchor plate 9 used to cooperate with the connecting component 5 is spot-welded and fixed to the rear end surface of the connecting component 5 , and a water injection hole 11 is provided on the anchor plate, and the water injection hole 11 is connected to the water injection channel of the connecting component 5 .
[0075] like Figure 11-Figure 12 As shown, the anchor plate 9 used to cooperate with the first top iron 1 - 2 is spot-welded and fixed to the front end surface of the first top iron 1 - 2 , and no water injection hole is provided on the anchor plate 9 .
[0076] The pulling tube assembly 3 is composed of a plurality of pulling tubes which are detachably connected in sequence, and the length of the pulling tubes is 2 meters to 4 meters.
[0077] One end of the pull tube is provided with an external thread joint, and the other end is provided with an internal thread structure matching the external thread joint. Adjacent pull tubes are threadedly connected through the external thread joint and the internal thread structure to achieve detachable connection of the pull tubes.
[0078] like Fig.13 As shown, a drawing pipe is set with multiple water outlet holes 12 on its wall as the first drawing pipe 3 - 1 , and the remaining drawing pipes are not set with water outlet holes as the second drawing pipe 3 - 2 . The first drawing pipe 3 - 1 is used to be set in front of the pipe jacking machine 13 .
[0079] In this embodiment, the water outlet holes 12 are arranged in multiple groups, and the multiple groups of water outlet holes 12 are arranged at equal intervals along the circumferential direction of the first pulling pipe 3-1. Preferably, four groups of water outlet holes 12 are arranged, and each group of water outlet holes 12 includes multiple water outlet holes 12 distributed along the axis of the first pulling pipe 3-1. The spacing between adjacent water outlet holes 12 is 0.2 meters. The first pulling pipe 3-1 is used to be arranged in front of the jacking machine. When working, the water outlet holes 12 spray water to the soil, disturb the soil in front of the jacking machine 13, and facilitate the movement of the jacking machine.
[0080] The auxiliary tube drawing device of this embodiment has various components pre-processed in the factory and assembled on site, and can be recycled and reused, which is economical and efficient.
[0081] Example 2
[0082] This embodiment provides a construction method of the auxiliary pipe pulling device suitable for pipe jacking as described in Embodiment 1, comprising the following steps:
[0083] Step 1: The construction unit determines the specifications and dimensions of each component of the auxiliary pipe pulling device according to the design requirements of the drawings, and processes each component in the factory.
[0084] Step 2: Push the front pipe pulling assembly of the pipe jacking machine into the soil.
[0085] First, in the receiving well, the first pull pipe 3-1 with the water outlet 12 is pushed into the soil. Then, during the pushing process of the first pull pipe 3-1, multiple second pull pipes 3-2 are installed in sequence until the first pull pipe 3-1 is pushed out of the soil in the starting well.
[0086] Specifically: in the receiving well, determine the center point of the jacking pipe excavation section, install a drill bit at the head of the first pull pipe 3-1, use a horizontal directional drilling rig to push the first pull pipe 3-1 into the soil along the center point of the jacking pipe excavation interface, threadedly install the second pull pipe 3-2 behind the first pull pipe 3-1, continue to push it into the soil, and then push and install multiple second pull pipes 3-2 in sequence, and push them in reverse according to the jacking route until the first pull pipe 3-1 is pushed into the starting well and the drill bit is removed.
[0087] When the front pipe pulling assembly of the pipe jacking machine 13 is pushed into the soil, a ground radar is provided on the ground to monitor the position of the pipe pulling assembly at all times to prevent the pipe pulling assembly from deviating from the prescribed route during the jacking process.
[0088] Step 3: The pipe jacking machine 13 is in place and lowered into the starting well by a crane. The pipe jacking machine 13 is processed in advance so that a hole is reserved in the middle.
[0089] The pipe pulling assembly in the pipe jacking machine 13 passes through the pipe jacking machine, wherein the pipe pulling assembly in the pipe jacking machine adopts a second pipe pulling assembly 3-2, which is threadedly connected with the first pipe pulling assembly 3-1 passing through the soil after passing through the pipe jacking machine 13. The second pipe pulling assembly 3-2 is firmly fixed to the pipe jacking machine, and the second pipe pulling assembly 3-2 is fixed in the soil bin behind the cutter head, and is fixed by an existing mechanical method. At this time, the first pipe pulling assembly is arranged in front of the pipe jacking machine, and a set number of second pipe pulling assembly is spaced between the first pipe pulling assembly and the head of the pipe jacking machine, preferably two second pipe pulling assembly.
[0090] A winch is used to pass the steel strand 2 through the front pipe drawing assembly and the inner pipe drawing assembly of the pipe jacking machine, and the rear end of the steel strand 2 is fixed to the rear end of the second drawing pipe 3-2 in the pipe jacking machine through an anchoring component with a water injection hole, wherein the anchor plate 9 of the anchoring component has a water injection hole and is spot welded to the rear end of the second drawing pipe 3-2.
[0091] Step 4: Lower the pulling pipe driving mechanism into the receiving well, wherein the second top iron 1-3 fits tightly against the well wall of the receiving well close to the starting well, and the jack 1-4 works to insert the second pulling pipe 3-2 passing through the soil in the receiving well into the opening in the center of the first top iron 1-2, and insert the rubber sleeve 1-6 between the second pulling pipe 3-2 and the hole surface for sealing. After passing through the first top iron 1-2, the steel strand 2 is anchored and fixed to the first top iron 1-2 through an anchoring component without a water injection hole, wherein the anchor plate 9 is spot welded to the outer side of the first top iron 1-2, and the steel strand 2 is fixed by an extrusion sleeve 10.
[0092] Step 5: Fig.14As shown, the main jack in the starting well is used to push the pipe jacking machine 13 into the soil, and then the jacking construction of the pipe jacking section is started. While the pipe jacking machine 13 is being pushed forward, the jacks 1-4 in the receiving well work to pull back the steel strand 2. During the pulling back process, the water injection hole of the anchor plate 9 between the steel strand 2 and the second pulling pipe 3-2 in the pipe jacking machine 13 is connected to the water source, and the water flows out from the water outlet hole of the first pulling pipe 3-1, that is, the water is sprayed toward the soil in front of the pipe jacking machine 13, disturbing the soil, and facilitating the advancement of the pipe jacking machine 13. In the receiving well, the jacks 1-4 pull out a set length each time. For the steel strand 2, turn off the water source and let it stand for one minute. After the water in the pulling tube assembly is drained, untie the extrusion sleeve 10 of the anchoring component between the steel strand 2 and the first top iron 1-2, and then extend the jack 1-4 to the set distance again, remove the second pulling tube 3-2 at the front end, and then return the jack 1-4 to the initial position, and cooperate with the new second pulling tube 3-2 at the front end through the central opening again, and then cut off the steel strand 2 on the front side of the first top iron 1-2, and use the anchoring component to fix the steel strand 2 and the first top iron 1-2 again for the next pull back.
[0093] Step 6: According to construction requirements, after the main jack has pushed in a set number of jacking pipe sections, the pre-assembled first tool pipe 4-1, the second tool pipe 4-2 and the integral tool pipe mechanism formed by the supporting mechanism 6 and the connecting component 5 are lowered into the starting well. After the tool pipe mechanism is lowered, the locking bolts and locking nuts are removed, the anchoring state of the second pull pipe 3-2 and the steel strand 2 in the jacking machine 13 is released, the anchoring component is removed, and the second pull pipe 3-2 is assembled in sequence to the position of the connecting component 5 in the jacking pipe section that has been constructed, and the second pull pipe 3-2 is in contact with the front end surface of the connecting component 5.
[0094] Step 7: Release the anchoring state between the steel strand 2 and the first top iron 1-2, pull out the steel strand 2, and then reinsert the steel strand 2. The steel strand 2 passes through all the pulling tubes, one end of which is anchored and fixed to the first top iron 1-2 through an anchor component without a water injection hole, and the other end is anchored and fixed to the connecting component 5 through an anchor component with a water injection hole, and the water injection hole of the anchor plate 9 is connected to an external water source.
[0095] Step 8: In the starting well, the main jack pushes the tool pipe mechanism into the soil, and then continues the jacking construction of the jacking pipe section. At the same time, the jack 1-4 in the receiving well pulls the tool pipe mechanism through the steel strand 2, and pulls the jacking pipe section in front of it through the tool pipe mechanism. During the process, the water outlet 12 of the first pull pipe 3-1 sprays water to disturb the soil. In this step, every time the steel strand is pulled out for a certain distance, it is necessary to turn off the water injection source before removing the second pull pipe, and then let it stand for one minute. After the water in the pull pipe assembly is drained, the second pull pipe is removed. The removal method of the second pull pipe is the same as the removal method in step 5, and it will not be repeated here. After the second pull pipe is removed, the steel strand is connected to the first top iron, and then the front end of the second pull pipe is inserted into the opening in the center of the first top iron, and then the water source is turned on.
[0096] In this embodiment, when the jack 1-4 pulls the first tool pipe 4-1 forward, the second tool pipe 4-2 will not move directly, to prevent the main jack of the launch well from applying a jacking force that is not synchronized with the pulling device, causing adjacent pipe sections to become disconnected.
[0097] Moreover, during the jacking process of the jacking pipe section, the jacking pipe section can be jacked along the pipe pulling route, so that the pipe pulling device has a positioning and guiding function.
[0098] Step 9: After the pipe jacking machine is pushed out from the receiving well, the construction of the pipe jacking is completed, the anchoring state of the two ends of the steel strand 2 is released, the supporting mechanism 6, the connecting component 5 and each pulling pipe are removed from the pipe section and transported out for next use, and the pulling pipe drive mechanism and the pipe jacking machine 13 in the receiving well are lifted away by a crane for next use.
[0099] By adopting the auxiliary pipe pulling device and construction method of this embodiment, a combined construction of pushing and pulling is realized, so that the pushing force of the main jack can be reduced, and damage to the pipe joints caused by excessive pushing force can be avoided. There is no need to set up a relay room, thus avoiding the defects of complex construction and high construction cost caused by the use of a relay room.
[0100] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. An auxiliary pipe pulling device suitable for pipe jacking. It is characterized in that include: The pipe pulling driving mechanism is used to be arranged in the receiving well, and includes a base, the base is provided with a first top iron and a second top iron, the second top iron is fixed to the base, the first top iron is slidably connected to the base, and a telescopic component is provided between the first top iron and the second top iron; The tool tube mechanism comprises a tool tube body, a connecting component is arranged in the tool tube body, the connecting component is connected to one end of a plurality of supporting mechanisms distributed along the annular direction, and the other end of the supporting mechanism is connected to the tool tube body; Steel strand: one end of the steel strand can be detachably connected to the first top iron, and the other end can be detachably connected to the connecting component; Pulling tube assembly: It is composed of multiple pulling tubes that are detachably connected in sequence and used to be sleeved on the outer periphery of the steel strand; One end of the support mechanism is rotatably connected to the connecting component, and the other end is rotatably connected to the inner side of the tool tube body; The support mechanism comprises a rotating drum, and two ends of the inner side surface of the rotating drum are provided with internal thread structures with opposite rotation directions, wherein the internal thread structure at one end is threadedly connected to one end of a first support rod, and the other end of the first support rod is rotatably connected to the tool tube body, and the internal thread structure at the other end of the rotating drum is threadedly connected to one end of a second support rod, and the other end of the second support rod is rotatably connected to the connecting component; The wall of the set pulling pipe is provided with a plurality of water outlet holes, and the pulling pipe provided with the water outlet holes is used to be arranged in front of the pipe jacking machine; The steel strand is detachably connected to the connecting component through an anchoring component, the anchoring component includes an anchor plate, the anchor plate is provided with a plurality of openings, an extrusion sleeve is provided at the opening, the extrusion sleeve is used to squeeze and fix the steel strand, a water injection hole is provided at the center of the anchor plate, and the water injection hole is connected to the internal cavity of the pulling tube assembly through a water injection channel provided by the connecting component; The tool tube body includes a first tool tube and a second tool tube that are plug-connected. The first tool tube is connected to a supporting mechanism. A detachable locking component is provided between the first tool tube and the second tool tube to achieve switching between locking and unlocking states of the first tool tube and the second tool tube.
2. An auxiliary pipe pulling device suitable for pipe jacking as claimed in claim 1, It is characterized in that One end of the pull tube is provided with an external thread joint, and the other end is provided with an internal thread structure matching the external thread joint. Adjacent pull tubes are detachably connected via the external thread head and the internal thread structure.
3. An auxiliary pipe pulling device suitable for pipe jacking as claimed in claim 1, It is characterized in that The end of the first tool tube is provided with a groove, the end of the second tool tube is provided with a protrusion matching the groove, the protrusion is inserted into the groove to achieve the plug-in connection between the first tool tube and the second tool tube, and a rubber sleeve is provided between the protrusion and the groove.
4. An auxiliary pipe pulling device suitable for pipe jacking as claimed in claim 1, It is characterized in that The telescopic component adopts a jack, one end of the jack is fixedly connected to the annular second top iron, and the other end is fixedly connected to the disc-shaped first top iron.
5. A jacking and pulling construction method of an auxiliary pipe pulling device suitable for pipe jacking according to any one of claims 1 to 4, It is characterized in that The following steps are involved: In the receiving well, the front pipe pulling assembly of the pipe jacking machine is pushed into the soil along the direction from the receiving well to the starting well; Lower the pipe jacking machine into the starting well, pass the inner pipe pulling assembly of the pipe jacking machine through the pipe jacking machine, and fix the inner pipe pulling assembly of the pipe jacking machine with the front pipe pulling assembly of the pipe jacking machine pushed out of the soil; Pass the steel strand through the front pipe pulling assembly of the pipe jacking machine and the inner pipe pulling assembly of the pipe jacking machine, and fix one end of the steel strand to the rear end of the inner pipe pulling assembly of the pipe jacking machine; The pipe pulling drive mechanism is lowered into the receiving well, wherein the second top iron is attached to the inner wall of the receiving well, and the other end of the steel strand is fixed to the first top iron; The main jack in the starting well is used to push the pipe jacking machine into the soil, and the jacking construction of the pipe jacking section is started. The pipe jacking machine moves forward in the soil while the pipe pulling drive mechanism in the receiving well works. When the first jacking iron pulls out a section of steel strand, the pulled steel strand is cut off and the corresponding pulled pipe is removed. The telescopic component returns to its original position, and the steel strand is fixed to the first jacking iron again. After the set number of jacking pipe sections are pushed in, the fixed state of the steel strand and the pipe pulling assembly in the jacking machine is released, the tool pipe mechanism is lowered in the starting well, and the steel strand is passed through the pipe pulling assembly again in the receiving well, and one end of the steel strand is fixed to the connecting component, and the other end is fixed to the first jacking iron; While the main jack is constructing the jacking pipe section behind the tool pipe mechanism, the pipe pulling drive mechanism pulls the steel strand, driving the jacking pipe section in front of it forward through the tool pipe mechanism, thus realizing the combined jacking and pulling construction.