A circulating water treatment equipment for silicon carbide micropowder production
By designing a separation and stirring device in the production of silicon carbide micropowder, combining pretreatment filtration and stirring mixing processes, and using technologies such as pushing and vibration removal structures, the problem of low wastewater treatment efficiency in the existing technology is solved, and more efficient Water treatment.
Patent Information
- Application Number
- CN202410832010.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-06-26
AI Technical Summary
During the circulating water treatment process in the existing silicon carbide micropowder production, debris are not easy to float when wastewater is injected into the precipitation box, resulting in low treatment efficiency. You need to wait for the debris to float before processing, which affects the process efficiency.
A circulating water treatment device including a separation and stirring device is designed. The pretreatment filtration process and the stirring and mixing process are combined through the separation mechanism, the stirring and stirring and mixing process through the separation mechanism, the stirring and removal structure and the The accumulation material discharge structure improves the efficiency of debris treatment, and the mixing mechanism and the treatment agent discharge structure can achieve uniform mixing of wastewater and chemical agents.
The efficiency of wastewater treatment has been improved, the waiting time has been reduced, the treatment efficiency of water in the production of silicon carbide micropowder has been improved, and the pretreatment filtration and stirring and mixing technology has been combined to reduce the total time of wastewater treatment.
Smart Images

Figure CN118515328B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of circulating water treatment, in particular to a circulating water treatment device for producing silicon carbide micropowder. Background Art
[0002] Silicon carbide micropowder requires a large amount of water in the production process. Water treatment in the production process of silicon carbide micropowder is an important link. Its goal is to remove suspended matter, metal ions, sodium silicate, polyethylene glycol and other pollutants in the wastewater to meet the emission standards, and at the same time realize the recovery and resource utilization of silicon carbide micropowder. The treatment of water in the production of silicon carbide micropowder includes the following steps: pre-filtration treatment, stirring and mixing, precipitation separation, membrane separation and dehydration recovery.
[0003] The Chinese patent CN215946978U discloses a circulating water treatment system for silicon carbide micropowder processing, and its working principle is: when wastewater treatment is carried out, wastewater is continuously injected into the sedimentation tank, micropowder falls to the bottom of the sedimentation tank, and debris floats on the surface of the wastewater. The drive motor is started, and the drive motor drives the drive rod to rotate, and the drive rod drives the second transmission wheel to rotate, and the second transmission wheel drives the first transmission wheel to rotate through the transmission belt, and the first transmission wheel drives the rotating rod to rotate, and the rotating rod drives the rotating disk to rotate, and the rotating disk drives the first curved rod to move through the rotation of the first curved rod. The activity drives the second curved rod to move back and forth along the return frame, and the second curved rod drives the push plate to move back and forth on the surface of the wastewater through the connecting block. The sundries on the wastewater are pushed to the chute by the push of the push plate, and then fall into the collection box; at the same time, the pump is started, and the pump sucks the wastewater into the connecting pipe through the suction pipe, and then enters the treatment box from the connecting pipe, and the treatment liquid is injected into the treatment box through the feed hopper. The driving rod drives the stirring blade to rotate, and the wastewater and the treatment liquid are fully stirred by the rotation of the stirring blade. When the wastewater is completely treated, the solenoid valve is opened to discharge the treated water from the outlet pipe.
[0004] The above scheme still has the following problems. During the process of injecting wastewater into the sedimentation tank, some of the debris already in the sedimentation tank will not float to the surface of the wastewater due to the influence of subsequent wastewater entering. It is necessary to inject a certain amount of wastewater into the sedimentation tank, wait for the debris to completely float to the surface of the wastewater and then remove the debris. After the debris is completely removed, the wastewater is pumped into the treatment tank, and then the wastewater and the treatment liquid are stirred and mixed in the treatment tank. In this process, the process of removing debris and the process of stirring the wastewater and the treatment liquid both require a long waiting time, which affects the wastewater treatment efficiency. Summary of the invention
[0005] In view of the above problems, a circulating water treatment equipment for the production of silicon carbide micropowder is provided. The present invention is provided with a separation mechanism, a stirring mechanism, a treatment agent delivery structure and an adjustment mechanism, so as to realize the merging of the pretreatment filtration process and the stirring and mixing process and improve the treatment efficiency of the wastewater.
[0006] In order to solve the problems of the prior art, the present invention provides a circulating water treatment equipment for the production of silicon carbide micropowder, including a separation and stirring device, the separation and stirring device including a treatment box, a first mounting plate, a separation mechanism, a stirring mechanism, a treatment agent delivery structure and an adjustment mechanism; a treatment box; the first mounting plate is arranged above the treatment box; the separation mechanism is arranged at the lower end of the first mounting plate, the separation mechanism includes a separation bin and two collection bins, and the two collection bins are respectively arranged at the two ends of the separation bin; the stirring mechanism is arranged at both ends of the first mounting plate; the treatment agent delivery structure is arranged on the stirring mechanism; the adjustment mechanism is arranged at the upper end of the first mounting plate.
[0007] Preferably, the separation mechanism also includes a pushing structure, which includes a pushing plate and a first linear motion structure; the pushing plate is arranged inside the separation bin, and the upper end of the pushing plate extends from the upper end of the separation bin; the first linear motion structure is arranged at the upper end of the pushing plate.
[0008] Preferably, the lower bottom surface of the separation bin is divided into two parts, and both parts of the lower bottom surface are inclined toward the middle surface of the separation bin.
[0009] Preferably, the pushing structure further includes a storage structure, and the storage structure is arranged at the upper end of the pushing plate.
[0010] Preferably, the separation mechanism also includes a vibrating material removal structure, which includes a first rectangular frame, a first elastic connection structure and a vibration generator; the first rectangular frame is arranged on the upper part of the push plate; there are several first elastic connection structures, and the several first elastic connection structures are symmetrically arranged at both ends of the first rectangular frame about the push plate; the vibration generator is arranged at one end of the first rectangular frame.
[0011] Preferably, the vibration material removal structure further includes a second elastic connection structure, and the second elastic connection structure is arranged between the first rectangular frame and the vibration generator.
[0012] Preferably, the separation mechanism also includes a material accumulation and discharge structure, which includes two material accumulation plates, a first driving structure and an auxiliary structure; the two material accumulation plates are respectively arranged at the bottom of the separation bin; the first driving structure is arranged on one side of the separation bin, and the first driving structure is used to drive the two material accumulation plates to move; the auxiliary structure is arranged on the other side of the separation bin.
[0013] Preferably, the stirring mechanism includes two hanging plates, two stirring structures and an unfolding mechanism; the two hanging plates are respectively arranged at the two ends of the first mounting plate, and the hanging plates are hinged to the first mounting plate; the two stirring structures are respectively arranged on the two hanging plates; the unfolding mechanism is arranged on the first mounting plate, and the unfolding mechanism includes two driving plates and a second driving structure, the two driving plates respectively correspond to the two hanging plates, one end of the driving plate is connected to the hanging plate, and the other end of the driving plate is connected to the second driving structure.
[0014] Preferably, the adjustment mechanism includes a third mounting plate, a second linear moving structure and a lifting structure; the third mounting plate is arranged above the first mounting plate; the second linear moving structure is mounted on the upper end of the processing box, and the second linear moving structure is used to drive the third mounting plate to move back and forth along the processing box; the lifting structure is arranged on the third mounting plate, and the lifting structure is connected to the first mounting plate.
[0015] A method for using a circulating water treatment device for producing silicon carbide micropowder comprises the following steps:
[0016] S1, wastewater continues to pass through the separation bin, and the debris in the wastewater will remain in the separation bin, and the pushing structure pushes the debris in the wastewater into the two collection bins;
[0017] S2, when the water level in the treatment box reaches a fixed height, the introduction of wastewater into the separation bin is stopped, the regulating mechanism raises the separation mechanism and the stirring mechanism, the staff removes the two collection bins, handles the debris in the collection bins, and exposes the stirring mechanism at the same time;
[0018] S3, the regulating mechanism lowers the height of the separation mechanism and the stirring mechanism so that the stirring mechanism extends into the wastewater, and at the same time, the chemical agent is placed in the treatment agent delivery structure;
[0019] S4, the chemical agent falls near the stirring mechanism, and the stirring mechanism stirs the wastewater to make the wastewater and the chemical agent mixed evenly;
[0020] S5, then the wastewater mixed with chemical reagents is introduced into a sedimentation tank for standing.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] 1. The present invention is provided with a separation mechanism, a stirring mechanism, a treatment agent delivery structure and an adjustment mechanism. Wastewater continuously passes through the separation bin, and debris in the wastewater falls into two collecting bins from the separation ports at both ends of the separation bin. At the same time, silicon carbide particles in the wastewater also fall into the collecting bin. The stirring mechanism stirs the debris, silicon carbide particles and wastewater in the collecting bin, so that the silicon carbide particles flow out of the collecting bin. When the water level in the treatment box reaches a fixed height, the introduction of wastewater into the separation bin is stopped. The adjustment mechanism raises the separation mechanism and the stirring mechanism, removes the two collecting bins, and exposes the stirring mechanism at the same time. The adjustment mechanism lowers the height of the separation mechanism and the stirring mechanism, so that the stirring mechanism extends into the wastewater. At the same time, chemical agents are put into the treatment agent delivery structure, and the chemical agents fall near the stirring mechanism. The stirring mechanism stirs the wastewater, so that the wastewater and the chemical agents are evenly mixed, thereby realizing the merging of the pretreatment filtration process and the stirring and mixing process, and improving the treatment efficiency of the wastewater.
[0023] 2. The present invention is provided with a pushing structure, the first screw rotates forward, the first screw sleeve moves along the first screw, the first screw sleeve drives the pushing plate to move from one end of the first screw to the other end, the pushing plate pushes the debris in the wastewater into the collecting bin, and then the first screw is reversed, the first screw sleeve drives the pushing plate to return, the pushing plate pushes the debris in the wastewater into another collecting bin, so that the content of debris in the wastewater in the separation bin is lower, thereby avoiding a large amount of wastewater flowing into the two collecting bins. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a three-dimensional diagram of a circulating water treatment equipment for the production of silicon carbide micropowder.
[0025] Figure 2 This is a left view of a circulating water treatment equipment for the production of silicon carbide micropowder.
[0026] Figure 3 yes Figure 2 Cross-sectional view at AA in the middle.
[0027] Figure 4 It is a three-dimensional diagram of the separation bin, filter screen, gantry hanger, material pushing structure, vibration material removal structure and material accumulation and discharge structure in the circulating water treatment equipment for silicon carbide micropowder production.
[0028] Figure 5 It is a three-dimensional diagram of the separation bin, gantry hanger, material pushing structure and vibration material removal structure in the circulating water treatment equipment for the production of silicon carbide micropowder.
[0029] Figure 6 It is a three-dimensional diagram of the push plate and storage structure in a circulating water treatment equipment for the production of silicon carbide micropowder.
[0030] Figure 7 It is a three-dimensional diagram of the U-shaped storage bin and vibrating material removal structure in a circulating water treatment equipment for the production of silicon carbide micropowder.
[0031] Figure 8 The present invention is a stereoscopic diagram of a first rectangular frame, a vibration generator and a second elastic connection structure in a circulating water treatment device for producing silicon carbide micropowder.
[0032] Fig. 9 It is a three-dimensional structure of separation bin, gantry hanger and material accumulation and discharge structure in the circulating water treatment equipment for silicon carbide micropowder production. Figure 1 .
[0033] Fig.10 It is a three-dimensional structure of separation bin, gantry hanger and material accumulation and discharge structure in the circulating water treatment equipment for silicon carbide micropowder production. Figure 2 .
[0034] Fig.11It is a three-dimensional diagram of the first mounting plate and stirring mechanism in the circulating water treatment equipment for the production of silicon carbide micropowder. Figure 1 .
[0035] Fig.12 It is a three-dimensional diagram of the first mounting plate and stirring mechanism in the circulating water treatment equipment for the production of silicon carbide micropowder. Figure 2 .
[0036] Fig.13 The present invention is a stereoscopic diagram of a first mounting plate and an adjusting mechanism in a circulating water treatment device for producing silicon carbide micropowder.
[0037] The numbers in the figure are: 1, processing box; 2, first mounting plate; 3, separation mechanism; 31, separation bin; 32, collection bin; 33, filter screen; 34, gantry hanger; 35, pusher structure; 351, pusher plate; 352, first linear moving structure; 3521, first screw rod; 3522, first guide cross bar; 3523, first screw sleeve; 3524, first moving block; 353, storage structure; 3531, U-shaped storage bin; 3532, first guide column; 3533, first spring; 3534, scraper; 36, vibration Removal structure; 361, first rectangular frame; 362, first elastic connection structure; 3621, second guide column; 3622, second spring; 363, vibration generator; 364, second elastic connection structure; 3641, second mounting plate; 3642, third guide column; 3643, third spring; 37, material accumulation and discharge structure; 371, material accumulation plate; 372, first driving structure; 3721, second screw; 3722, The second screw sleeve; 3723, driving arm; 3724, driving rod; 3725, limiting block; 373, auxiliary structure; 3731, second guide cross bar; 3732, second moving block; 3733, auxiliary arm; 4, stirring mechanism; 41, lifting plate; 411, first connecting cover; 42, stirring structure; 421, rotating driver; 422, stirring frame; 43, unfolding mechanism; 431, driving plate; 432, second driving structure; 4321, second rectangular frame; 4322, third screw; 4323, third guide cross bar; 4324, third moving block; 5, treatment agent delivery structure; 51, discharge funnel; 6, adjustment mechanism; 61, third mounting plate; 62, second linear moving structure; 621, third rectangular block; 622, fourth screw; 623, fourth guide cross bar; 63, lifting structure; 631, lifter; 632, second connecting cover. DETAILED DESCRIPTION
[0038] In order to further understand the features, technical means, specific objectives and functions of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0039] Reference Figures 1 to 13As shown: A circulating water treatment equipment for silicon carbide micropowder production, including a separation and stirring device, the separation and stirring device includes a treatment box 1, a first mounting plate 2, a separation mechanism 3, a stirring mechanism 4, a treatment agent delivery structure 5 and an adjustment mechanism 6; the inner bottom of the treatment box 1 is inclined toward one side, and a drainage port is provided at the lower end of the inner bottom of the treatment box 1; the first mounting plate 2 is arranged above the treatment box 1; the separation mechanism 3 is arranged at the lower end of the first mounting plate 2, the separation mechanism 3 includes a separation bin 31 and two collection bins 32, the two collection bins 32 are respectively arranged at the two ends of the separation bin 31, and the two opposite surfaces of the separation bin 31 are respectively provided with a liquid inlet and a liquid outlet, and a filter is provided at the liquid outlet 33, separation ports are provided at both ends of the separation bin 31, and the two separation ports are respectively inserted into the interior of the two collecting bins 32, and gantry hangers 34 are provided at both ends of the separation bin 31, and the two gantry hangers 34 respectively connect the two ends of the separation bin 31 with the two ends of the first mounting plate 2; a stirring mechanism 4 is provided at both ends of the first mounting plate 2, and the stirring mechanism 4 has two stirring ends, and the two stirring ends respectively extend into the interior of the two separation bins 31; a treatment agent delivery structure 5 is provided on the stirring mechanism 4, and the treatment agent delivery structure 5 includes two discharge funnels 51, and the two discharge funnels 51 respectively deliver chemical agents to the stirring ends at both ends of the stirring mechanism 4; an adjusting mechanism 6 is provided at the upper end of the first mounting plate 2.
[0040] The wastewater continues to pass through the separation bin 31, and the debris in the wastewater will fall into the two collection bins 32 from the separation ports at both ends of the separation bin 31. There is no need to wait for the debris to float to the surface of the wastewater before cleaning it. At the same time, the silicon carbide particles in the wastewater will also fall into the collection bin 32. The stirring mechanism 4 stirs the debris, silicon carbide particles and wastewater in the collection bin 32 to make the silicon carbide particles flow out of the collection bin 32. When the water level in the treatment box 1 reaches a fixed height, the wastewater is stopped from being introduced into the separation bin 31, and the regulating mechanism 6 adjusts the separation mechanism 3 and The stirring mechanism 4 is raised, and the staff removes the two collecting bins 32 to deal with the debris in the collecting bins 32, while exposing the stirring mechanism 4. The adjusting mechanism 6 lowers the height of the separation mechanism 3 and the stirring mechanism 4, so that the stirring mechanism 4 extends into the wastewater. At the same time, chemical agents are put into the treatment agent delivery structure 5, and the chemical agents fall near the stirring mechanism 4. The stirring mechanism 4 stirs the wastewater to mix the wastewater and the chemical agents evenly, thereby realizing the combination of the pretreatment filtration process and the stirring and mixing process to improve the treatment efficiency of the wastewater.
[0041] Reference Figure 3 , Figure 4 and Figure 5As shown: the separation mechanism 3 also includes a pushing structure 35, which includes a pushing plate 351 and a first linear moving structure 352; the pushing plate is arranged inside the separation bin 31, and the upper end of the pushing plate extends from the upper end of the separation bin 31, and a plurality of water-permeable holes are provided on the pushing plate; the first linear moving structure 352 is arranged at the upper end of the pushing plate, and the first linear moving structure 352 includes a first screw rod 3521, a first guide cross bar 3522, a first screw sleeve 3523 and a first moving block 3524, and the first screw 3521 and the first guide cross bar 3522 are respectively arranged in parallel on both sides of the push plate, the two ends of the first screw rod 3521 are respectively connected to the two gantry hangers 34, the two ends of the first guide cross bar 3522 are respectively connected to the two gantry hangers 34, the first screw sleeve 3523 is sleeved on the first screw rod 3521, and the first screw sleeve 3523 is connected to one side of the push plate, the first moving block 3524 is slidably arranged on the first guide cross bar 3522, and the first moving block 3524 is connected to the other side of the push plate.
[0042] Most of the wastewater will flow out of the separation chamber 31 directly from the liquid outlet, causing a large amount of debris to adhere to the filter screen 33, causing the filter screen 33 to be blocked, and the wastewater will be diverted to the two collection chambers 32 in large quantities, resulting in the water inflow into the collection chamber 32 being much greater than the water outflow. The water level in the collection chamber 32 rises, causing the debris collected in the collection chamber 32 to flow back into the separation chamber 31. By setting the pushing structure 35, the first screw 3521 rotates forward, and the first screw sleeve 3523 rotates along the first screw 35 21 moves, the first screw sleeve 3523 drives the push plate 351 to move from one end of the first screw 3521 to the other end, the push plate 351 pushes the debris in the wastewater into the collecting bin 32, and then the first screw 3521 is reversed, the first screw sleeve 3523 drives the push plate 351 to return, and the push plate 351 pushes the debris in the wastewater into the other collecting bin 32, so that the content of debris in the wastewater in the separation bin 31 is low, thereby avoiding a large amount of wastewater flowing into the two collecting bins 32.
[0043] Reference Figure 3 and Figure 4 As shown, the lower bottom surface of the separation chamber 31 is divided into two parts, both of which are inclined toward the middle surface of the separation chamber 31 , and the liquid outlet of the separation chamber 31 is lower than the two separation ports of the separation chamber 31 .
[0044] If the height of the two separation ports is flush with the height of the liquid outlet, wastewater will flow into the collecting bin 32 more easily from the two separation ports, and the wastewater will bring a large amount of silicon carbide particles into the collecting bin 32. By setting the bottom of the separation bin 31 to be inclined toward the middle of the collecting bin 32, and the height of the liquid outlet is lower than the two separation ports, the water pressure at the liquid outlet is greater, and the wastewater will flow out from the liquid outlet first. The silicon carbide particles in the wastewater will also flow out from the liquid outlet in large quantities. In addition, the bottom of the separation bin 31 is in an inverted triangle shape. The silicon carbide particles in the separation bin 31 that have not flowed out with the wastewater in time will gather at the bottom of the separation bin 31, thereby preventing a large amount of silicon carbide particles from entering the collecting bin 32.
[0045] Reference Figure 4 , Figure 5 and Figure 6 As shown: the pushing structure 35 also includes a storage structure 353, which is arranged at the upper end of the pushing plate 351. The storage structure 353 includes a U-shaped storage bin 3531, two guide columns, two first springs 3533 and two scrapers 3534. The U-shaped storage bin 3531 is covered at the upper end of the pushing plate 351, and the two side plates of the U-shaped storage bin 3531 respectively cover the two surfaces of the pushing plate 351, and the two first guide columns 3532 are arranged in parallel at the upper end of the pushing plate 351, one end of the first guide column 3532 is fixedly connected to the pushing plate 351, and the other end of the first guide column 3532 passes through the U-shaped storage bin 3531 upward, and the two first springs 3533 are respectively sleeved on the two first guide cross bars 3522, and the two ends of the first spring 3533 are respectively abutted against the ends of the U-shaped storage bin 3531 and the first guide cross bar 3522.
[0046] Since the surfaces of the inner bottom of the separation bin 31 are not coplanar, the lower end of the push plate 351 cannot abut against all parts of the inner bottom of the separation bin 31, and the debris at the bottom of the separation bin 31 cannot be pushed into the collection bin 32 by the push plate 351. By setting the storage structure 353, the first spring 3533 applies a downward force to the push plate 351, and the position of the lower end of the push plate 351 can change with the change of the inner bottom surface of the separation bin 31. Therefore, the lower end of the push plate 351 can maintain contact with the inner bottom surface of the separation bin 31, thereby achieving the goal of pushing the debris at the bottom of the separation bin 31 into the collection bin 32.
[0047] Reference Figure 5 and Figure 7As shown: the separation mechanism 3 also includes a vibration material removal structure 36, which includes a first rectangular frame 361, a first elastic connection structure 362 and a vibration generator 363; the first rectangular frame 361 is arranged on the upper part of the push plate 351; the first elastic connection structure 362 has a plurality of first elastic connection structures 362, which are symmetrically arranged at both ends of the first rectangular frame 361 about the push plate 351, and the first elastic connection structure 362 includes a second guide column 3621 and a second spring 3622, one end of the second guide column 3621 is connected to the U-shaped storage bin 3531, and the other end of the second guide column 3621 extends out of the first rectangular frame 361, the second spring 3622 is sleeved on the second guide column 3621, and the two ends of the second spring 3622 are respectively abutted against the ends of the first rectangular frame 361 and the second guide column 3621; the vibration generator 363 is arranged at one end of the first rectangular frame 361.
[0048] When the push plate 351 is moving, the wastewater will exert a force in the opposite direction on the push plate 351, and the debris in the wastewater will stick to the push plate 351. The increase of debris on the push plate 351 will cause the resistance encountered by the push plate 351 to increase during the movement. By setting the vibration removal structure 36, after the push plate 351 moves to one end of the separation bin 31, the vibration generator 363 works, and the vibration generator 363 cooperates with a plurality of first elastic connection structures 362 to make the storage structure 353 vibrate, and the storage structure 353 drives the push plate 351 to vibrate. The two side surfaces of the push plate 351 collide with the wastewater on both sides, and the wastewater washes away the debris on the surface of the push plate 351, thereby keeping the surface of the push plate 351 clean and avoiding the increase of resistance encountered by the push plate 351 when it moves.
[0049] Reference Figure 7 and Figure 8 As shown: the vibration removal structure 36 also includes a second elastic connection structure 364, which is arranged between the first rectangular frame 361 and the vibration generator 363. The second elastic connection structure 364 includes a second mounting plate 3641, four third guide columns 3642 and four third springs 3643. The vibration generator 363 is installed on the second mounting plate 3641. The four third guide columns 3642 are respectively arranged on the four corners of the second mounting plate 3641. One end of the third guide column 3642 passes through the second mounting plate 3641 and is connected to the first rectangular frame 361. The four third springs 3643 are respectively mounted on the four third guide columns 3642. The two ends of the third spring 3643 are respectively abutted against the ends of the second mounting plate 3641 and the third guide column 3642.
[0050] When the push plate 351 moves toward the side away from the vibration generator 363, the push plate 351 is affected by the resistance of the wastewater, and the push plate 351 moves toward the vibration generator 363, while the vibration generator 363 hinders the movement of the push plate 351, which may cause the push plate 351 to bend or the vibration generator 363 to be damaged. By setting the second elastic connecting structure 364, the push plate 351 applies a force to the vibration generator 363, and the vibration generator 363 transmits the force to the second mounting plate 3641. The second mounting plate 3641 compresses a plurality of third springs 3643, and the plurality of third springs 3643 absorb the force of the push plate 351 on the vibration generator 363, thereby preventing the push plate 351 from bending or the vibration generator 363 from being damaged.
[0051] Reference Figure 3 , Figure 4 , Fig. 9 and Fig.10As shown: the separation mechanism 3 also includes a material accumulation and discharge structure 37, which includes two material accumulation plates 371, a first drive structure 372 and an auxiliary structure 373; the two material accumulation plates 371 are respectively arranged at the bottom of the separation bin 31, and two discharge ports are symmetrically opened at the bottom of the separation bin 31, and the two material accumulation plates 371 are respectively matched with the two discharge ports, and one end of the material accumulation plate 371 is hinged to the bottom of the separation bin 31. When the separation operation is performed, the two material accumulation plates 371 block the two discharge ports; the first drive structure 372 is arranged on one side of the separation bin 31, and the first driving structure 372 is used to drive the two material accumulation plates 371 to move. The first driving structure 372 includes a second screw rod 3721, two second screw sleeves 3722, two driving arms 3723, two driving rods 3724 and two limit blocks 3725. The second screw rod 3721 is a double-headed screw rod, and the two ends of the second screw rod 3721 are respectively connected to the two gantry hangers 34, and the two second screw sleeves 3722 are respectively arranged at the two ends of the second screw rod 3721. The two driving arms 3723 are respectively arranged at the two ends of the second screw rod 3721. 723 respectively correspond to the two second screw sleeves 3722, one end of the driving arm 3723 is connected to the second screw sleeve 3722, the two driving rods 3724 respectively correspond to the two driving arms 3723, one end of the driving rod 3724 is connected to the other end of the driving arm 3723, the two limit blocks 3725 are respectively installed on the two material accumulation plates 371, the limit blocks 3725 are provided with limit grooves, and the middle part of the driving rod 3724 is arranged in the limit groove; the auxiliary structure 373 is arranged on the other side of the separation bin 31, and the auxiliary structure 373 includes a second guide cross bar 3731, two second moving blocks 3732 and two auxiliary arms 3733. The two ends of the second guide cross bar 3731 are respectively connected to the two gantry hangers 34. The two second moving blocks 3732 are respectively slidably arranged at the two ends of the second guide cross bar 3731. The two auxiliary arms 3733 respectively correspond to the two second moving blocks 3732. One end of the auxiliary arm 3733 is connected to the second moving block 3732, and the other end of the auxiliary arm 3733 is connected to the other end of the driving rod 3724.
[0052] When the introduction of wastewater into the separation bin 31 stops, the water level in the separation bin 31 drops, and the silicon carbide particles in the wastewater will remain at the bottom of the separation bin 31. By setting the material accumulation and discharge structure 37, in the initial state, the two material accumulation plates 371 are tightly attached to the lower part of the separation bin 31, and the second screw 3721 rotates, and the two second screw sleeves 3722 drive the two driving arms 3723 to move away from each other, and the driving arms 3723 drive the driving rod 3724 to move, and the cooperation of the driving rod 3724 and the limit block 3725 drives the material accumulation plate 371 to move, and the material accumulation plate 371 rotates around the hinge with the separation bin 31, so that the lower end of the separation bin 31 is opened, and the silicon carbide particles in the separation bin 31 slide along the material accumulation plate 371 into the processing box 1, thereby avoiding the silicon carbide particles from being trapped at the inner bottom of the separation bin 31.
[0053] Reference Figure 3 , Fig.11 and Fig.12 As shown: the stirring mechanism 4 includes two hanging plates 41, two stirring structures 42 and an unfolding mechanism 43; the two hanging plates 41 are respectively arranged at the two ends of the first mounting plate 2, the hanging plates 41 are hinged to the first mounting plate 2, and the lower end of the hanging plate 41 is provided with a first connecting cover 411, the lower end of the first connecting cover 411 is connected to the collecting bin 32, and the discharge funnel 51 is connected to the first connecting cover 411; the two stirring structures 42 are respectively arranged on the two hanging plates 41, the stirring structure 42 includes a rotating driver 421 and a stirring frame 422, the rotating driver 421 is installed on the hanging plate 41, and one end of the stirring frame 422 is connected to the output shaft of the rotating driver 421; the unfolding mechanism 43 is arranged on the first mounting plate 2, and the unfolding mechanism 43 includes two driving plates 431 and a second driving structure 432, the two driving plates 431 are respectively connected to the two Corresponding to the hanging plate 41, one end of the driving plate 431 is connected to the hanging plate 41, and the other end of the driving plate 431 is connected to the second driving structure 432. The second driving structure 432 includes a second rectangular frame 4321, a third screw 4322, a third guide cross bar 4323 and two third moving blocks 4324. The second rectangular frame 4321 is installed on the first mounting plate 2. The third screw 4322 is a double-headed screw. The two ends of the third screw 4322 are respectively connected to the two ends of the second rectangular frame 4321. The third guide cross bar 4323 is arranged in parallel on one side of the third screw 4322. The two third moving blocks 4324 are respectively arranged at the two ends of the third screw 4322, and the two third moving blocks 4324 are respectively slidably arranged at the two ends of the third guide cross bar 4323. The two third moving blocks 4324 are respectively connected to the two driving plates 431.
[0054] After the water level in the treatment box 1 reaches a certain height, the regulating mechanism 6 lifts the separation mechanism 3 and the stirring mechanism 4 to remove the wastewater, and the opening and closing mechanism works. The third screw 4322 rotates forward to make the two third moving blocks 4324 move away from each other, and the two third moving blocks 4324 respectively apply pulling force to the two driving plates 431, and the two driving plates 431 respectively apply pulling force to the two hanging plates 41, and the driving plate 431 rotates around the connection between it and the first mounting plate 2, and the driving plate 431 drives the collecting bin 32 to move, so that the staff can remove the collecting bin 32 from the first connecting cover 411, so that the stirring frame 422 is exposed to the outside, and then the third screw 4322 is reversed, and the two hanging plates 41 are rotated to be parallel to the first mounting plate 2, and the regulating mechanism 6 inserts the stirring frame 422 into the wastewater, and the chemical agent is put near the stirring frame 422, and the stirring frame 422 mixes the wastewater and the chemical agent evenly, thereby accelerating the reaction time of the wastewater and the chemical agent.
[0055] Reference Figure 1 and Fig.13As shown: the adjustment mechanism 6 includes a third mounting plate 61, a second linear moving structure 62 and a lifting structure 63; the third mounting plate 61 is arranged above the first mounting plate 2; the second linear moving structure 62 is mounted on the upper end of the processing box 1, and the second linear moving structure 62 is used to drive the third mounting plate 61 to move back and forth along the processing box 1. The second linear moving structure 62 includes a third rectangular frame, a fourth screw 622 and a fourth guide cross bar 623. The two ends of the third rectangular frame are respectively connected to the two ends of the processing box 1, and the two ends of the fourth screw 622 are respectively connected to the third rectangular frame. The two ends are connected, the fourth guide cross bar 623 is arranged in parallel on one side of the fourth screw 622, and the two ends of the third mounting plate 61 are respectively connected to the fourth screw 622 and the fourth guide cross bar 623; the lifting structure 63 is arranged on the third mounting plate 61, and the lifting structure 63 is connected to the first mounting plate 2. The lifting structure 63 includes a lifter 631 and a second connecting cover 632. The lifter 631 is fixed on the third mounting plate 61, and the lower end of the second connecting cover 632 is connected to the middle part of the first mounting plate 2, and the output end of the lifter 631 is connected to the upper end of the second connecting cover 632.
[0056] The stirring mechanism 4 and the chemical agent are in a fixed position in the treatment box 1. The content of chemical agents in the local wastewater in the treatment box 1 is relatively large. Through the second linear moving structure 62 and the lifting structure 63, the lifting structure 63 can change the depth of the stirring frame 422 inserted into the wastewater, so that the deeper wastewater can be stirred and mixed with the chemical agent. The second linear moving structure 62 drives the stirring mechanism 4 and the treatment agent delivery structure 5 to move back and forth along the treatment box 1, so that the chemical agent is evenly delivered to various places in the treatment box 1, thereby achieving uniform mixing of the wastewater in various places in the treatment box 1 with the chemical agent.
[0057] A method for using a circulating water treatment device for producing silicon carbide micropowder comprises the following steps:
[0058] S1, wastewater continues to pass through the separation bin 31, and debris in the wastewater will remain in the separation bin 31, and the pushing structure 35 pushes the debris in the wastewater into the two collection bins 32;
[0059] S2, when the water level in the treatment box 1 reaches a fixed height, the introduction of wastewater into the separation bin 31 is stopped, the adjustment mechanism 6 raises the separation mechanism 3 and the stirring mechanism 4, and the staff removes the two collection bins 32 to process the debris in the collection bin 32, while exposing the stirring mechanism 4;
[0060] S3, the adjusting mechanism 6 lowers the height of the separation mechanism 3 and the stirring mechanism 4 so that the stirring mechanism 4 extends into the wastewater, and at the same time, a chemical agent is placed in the treatment agent delivery structure 5;
[0061] S4, the chemical agent falls near the stirring mechanism 4, and the stirring mechanism 4 stirs the wastewater to mix the wastewater and the chemical agent evenly;
[0062] S5, then the wastewater mixed with chemical reagents is introduced into a sedimentation tank for standing.
[0063] The above embodiments only express one or several implementation modes of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that, for those of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the attached claims.
Claims
1. A circulating water treatment equipment for the production of silicon carbide micropowder, characterized in that: The separation and stirring device comprises a treatment box (1), a first mounting plate (2), a separation mechanism (3), a stirring mechanism (4), a treatment agent delivery structure (5) and an adjustment mechanism (6); Processing box (1); The first mounting plate (2) is arranged above the processing box (1); The separation mechanism (3) is arranged at the lower end of the first mounting plate (2), and the separation mechanism (3) comprises a separation bin (31) and two collection bins (32), and the two collection bins (32) are respectively arranged at two ends of the separation bin (31); The stirring mechanism (4) is arranged at two ends of the first mounting plate (2); The treatment agent delivery structure (5) is arranged on the stirring mechanism (4); The adjustment mechanism (6) is arranged at the upper end of the first mounting plate (2); Two opposite surfaces of the separation bin (31) are respectively provided with a liquid inlet and a liquid outlet, a filter screen (33) is provided at the liquid outlet, separation ports are provided at both ends of the separation bin (31), the two separation ports are respectively inserted into the interior of the two collection bins (32), and gantry hangers (34) are provided at both ends of the separation bin (31), and the two gantry hangers (34) respectively connect the two ends of the separation bin (31) to the two ends of the first mounting plate (2); The separation mechanism (3) further comprises a material pushing structure (35), wherein the material pushing structure (35) comprises a material pushing plate (351) and a first linear moving structure (352); The push plate is arranged inside the separation bin (31), and the upper end of the push plate extends out from the upper end of the separation bin (31); The first linear moving structure (352) is arranged at the upper end of the push plate; The stirring mechanism (4) comprises two hanging plates (41), two stirring structures (42) and an unfolding mechanism (43); Two hanging plates (41) are respectively arranged at two ends of the first mounting plate (2), and the hanging plates (41) are hinged to the first mounting plate (2); The two stirring structures (42) are respectively arranged on the two hanging plates (41); The unfolding mechanism (43) is arranged on the first mounting plate (2), and comprises two drive plates (431) and a second drive structure (432). The two drive plates (431) correspond to the two hanging plates (41) respectively, one end of the drive plate (431) is connected to the hanging plate (41), and the other end of the drive plate (431) is connected to the second drive structure (432); The adjustment mechanism (6) comprises a third mounting plate (61), a second linear moving structure (62) and a lifting structure (63); The third mounting plate (61) is arranged above the first mounting plate (2); The second linear moving structure (62) is mounted on the upper end of the processing box (1), and the second linear moving structure (62) is used to drive the third mounting plate (61) to move back and forth along the processing box (1); The lifting structure (63) is arranged on the third mounting plate (61), and the lifting structure (63) is connected to the first mounting plate (2); The adjusting mechanism (6) raises the separation mechanism (3) and the stirring mechanism (4), and the staff removes the two collecting bins (32) to process the debris in the collecting bins (32), while exposing the stirring mechanism (4). The adjusting mechanism (6) lowers the height of the separation mechanism (3) and the stirring mechanism (4), so that the stirring mechanism (4) extends into the wastewater.
2. The circulating water treatment equipment for producing silicon carbide micropowder according to claim 1, characterized in that: The lower bottom surface of the separation bin (31) is divided into two parts, and the lower bottom surfaces of the two parts are both inclined toward the middle surface of the separation bin (31).
3. The circulating water treatment equipment for producing silicon carbide micropowder according to claim 1, characterized in that: The material pushing structure (35) further comprises a storage structure (353), and the storage structure (353) is arranged at the upper end of the material pushing plate (351).
4. The circulating water treatment equipment for producing silicon carbide micropowder according to claim 1, characterized in that: The separation mechanism (3) further comprises a vibration material removal structure (36), wherein the vibration material removal structure (36) comprises a first rectangular frame (361), a first elastic connection structure (362) and a vibration generator (363); The first rectangular frame (361) is arranged on the upper part of the push plate (351); There are a plurality of first elastic connection structures (362), and the plurality of first elastic connection structures (362) are symmetrically arranged at two ends of the first rectangular frame (361) with respect to the push plate (351); The vibration generator (363) is arranged at one end of the first rectangular frame (361).
5. The circulating water treatment equipment for producing silicon carbide micropowder according to claim 4, characterized in that: The vibration material removal structure (36) further comprises a second elastic connection structure (364), and the second elastic connection structure (364) is arranged between the first rectangular frame (361) and the vibration generator (363).
6. The circulating water treatment equipment for producing silicon carbide micropowder according to claim 4, characterized in that: The separation mechanism (3) further comprises a material accumulation and discharge structure (37), wherein the material accumulation and discharge structure (37) comprises two material accumulation plates (371), a first driving structure (372) and an auxiliary structure (373); Two material accumulation plates (371) are respectively arranged at the bottom of the separation bin (31); The first driving structure (372) is arranged on one side of the separation bin (31), and the first driving structure (372) is used to drive the two material accumulation plates (371) to move; The auxiliary structure (373) is arranged on the other side of the separation bin (31).
7. A method for using a circulating water treatment device for producing silicon carbide micropowder, applied to a circulating water treatment device for producing silicon carbide micropowder as claimed in any one of claims 1 to 6, characterized in that: The following steps are involved: S1, wastewater continues to pass through the separation bin (31), debris in the wastewater remains in the separation bin (31), and the pushing structure (35) pushes the debris in the wastewater into the two collection bins (32); S2, when the water level in the treatment box (1) reaches a fixed height, the introduction of wastewater into the separation bin (31) is stopped, the regulating mechanism (6) raises the separation mechanism (3) and the stirring mechanism (4), and the staff removes the two collection bins (32) to process the debris in the collection bins (32), while exposing the stirring mechanism (4); S3, the adjusting mechanism (6) lowers the height of the separation mechanism (3) and the stirring mechanism (4) so that the stirring mechanism (4) extends into the wastewater, and at the same time, a chemical agent is placed in the treatment agent placement structure (5); S4, the chemical agent falls to the vicinity of the stirring mechanism (4), and the stirring mechanism (4) stirs the wastewater so that the wastewater and the chemical agent are evenly mixed; S5, then the wastewater mixed with chemical reagents is introduced into a sedimentation tank for standing.