Transformer loss suppression method, device, electronic device and storage medium

By constructing the distribution network topology and target load rate control method, the problem of low efficiency in suppressing transformer operating losses is solved, and effective suppression of transformer losses and improvement of system energy efficiency are achieved.

CN118523321BActive Publication Date: 2024-10-29FOSHAN POWER SUPPLY BUREAU GUANGDONG POWER GRID
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410989303.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-10-29
Estimated Expiration
2044-07-23

AI Technical Summary

Technical Problem

In the existing technology, the efficiency of suppressing the operating loss of the transformer is low and there is a lack of effective control methods.

Method used

By obtaining the distribution network topology composed of multiple transformers in the preset power supply area, a loss suppression objective function is constructed based on the power demand data of the equipment to be powered and the distribution network parameters, and the target load ratio of multiple transformers is determined. The target load factor controls the operation of the transformer so that its operating loss is less than the preset loss.

Benefits of technology

Effectively reduce overall losses, improve system energy efficiency, extend the service life of transformers, and reduce energy consumption and operating costs of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118523321B_ABST
    Figure CN118523321B_ABST
Patent Text Reader

Abstract

The present invention discloses a method, device, electronic device and storage medium for suppressing transformer losses. The method includes: obtaining a distribution network topology composed of multiple transformers arranged in a preset power supply area; constructing a loss suppression objective function based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters, wherein the distribution network parameters are used to represent the power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent the functional relationship established with the total loss of multiple transformers as the target; determining the target load rate of multiple transformers based on the loss suppression objective function, wherein the target load rate is used to represent the transformer load rate assigned to multiple transformers; and controlling the operation of multiple transformers based on the target load rate so that the operating loss of multiple transformers is less than the preset loss. The present invention solves the technical problem of low efficiency in suppressing the loss of transformers in the related art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of transformer control, and in particular to a transformer loss suppression method, device, electronic equipment and storage medium. Background Art

[0002] In the power industry, by taking a series of measures to reduce the losses generated by transformers during operation, that is, suppressing the losses of transformers during operation, the operating losses of transformers can be effectively suppressed, the efficiency and performance of transformers can be improved, their service life can be extended, and the energy consumption and operating costs of power systems can be reduced.

[0003] At present, the relevant technology usually reduces the operating loss of the transformer by reasonably designing the structure and parameters of the transformer, such as improving the efficiency of the transformer, reducing the magnetic density, reducing the winding resistance, reducing the temperature rise of the core and the winding, etc. However, there is a lack of methods for controlling the transformer during the operation of the transformer to effectively suppress the loss of the transformer, resulting in low efficiency in suppressing the loss of the transformer.

[0004] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention

[0005] The embodiments of the present invention provide a method, device, electronic device and storage medium for suppressing transformer losses, so as to at least solve the technical problem of low efficiency in suppressing transformer losses in the related art.

[0006] According to one aspect of an embodiment of the present invention, a method for suppressing transformer losses is provided, comprising: obtaining a distribution network topology composed of a plurality of transformers arranged in a preset power supply area, wherein the distribution network topology is used to represent a topological structure of a distribution network composed of connection relationships between a plurality of transformers; constructing a loss suppression objective function based on power demand data of equipment to be powered in the preset power supply area and distribution network parameters, wherein the distribution network parameters are used to represent power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent a functional relationship established with the total loss of a plurality of transformers as a target; determining a target load rate of a plurality of transformers based on the loss suppression objective function, wherein the target load rate is used to represent a transformer load rate assigned to a plurality of transformers; and controlling the operation of a plurality of transformers based on the target load rate so that the operation loss of the plurality of transformers is less than a preset loss.

[0007] Optionally, based on the power demand data of the equipment to be powered in a preset power supply area and the distribution network parameters, a loss suppression objective function is constructed, including: obtaining the power demand power in the power demand data, and the received power of the equipment to be powered in the distribution network parameters, wherein the received power of the equipment to be powered is used to represent the electric power actually received by the equipment to be powered; based on the power demand power and the received power of the equipment to be powered, a loss suppression objective function is constructed.

[0008] Optionally, the target load rates of multiple transformers are determined based on the loss suppression objective function, including: constructing a target constraint relationship set of the distribution network topology based on power demand data and distribution network parameters, wherein the target constraint relationship set is used to represent a set of constraints that need to be satisfied when multiple transformers provide normal power supply to power supply equipment through the distribution network topology; determining the target load rate based on the target constraint relationship set and the loss suppression objective function.

[0009] Optionally, based on the power demand data and the distribution network parameters, a target constraint relationship set of the distribution network network topology is constructed, including: based on the distribution network port power in the distribution network parameters and a preset port power threshold, constructing the distribution network port constraint conditions of the distribution network network topology, wherein the distribution network port power is used to represent the port power of the switching device connecting multiple transformers in the distribution network network topology; based on the power demand power in the power demand data and the distribution network port power, constructing the power supply power constraint relationship of the distribution network network topology; based on the distribution network port constraint conditions and the power supply power constraint relationship, constructing a target constraint relationship set.

[0010] Optionally, the target load rate is determined based on the target constraint relationship set and the loss suppression objective function, including: using a target cluster search model to search for the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, wherein the target cluster search model is used to represent a model for searching for feasible solutions to the objective function in parallel through multiple processing units.

[0011] Optionally, the target cluster search model includes a surface membrane and multiple basic membranes, the input end of the surface membrane is connected to the output ends of the multiple basic membranes, and the target cluster search model is used to search the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, including: determining multiple load rate feasible solutions of the target load rate based on the target constraint relationship set, wherein the multiple load rate feasible solutions are used to represent the allowable values ​​of the target load rate that satisfy the target constraint relationship set; inputting the multiple load rate feasible solutions into the multiple basic membranes of the target cluster search model; parallel screening of the multiple load rate feasible solutions through the multiple basic membranes to obtain at least one target feasible solution; updating at least one target feasible solution through the surface membrane to obtain the target load rate.

[0012] Optionally, at least one target feasible solution is updated through the surface membrane to obtain a target load rate, including: exchanging information for at least one target feasible solution based on the surface membrane, and recording the number of exchanges; comparing the number of exchanges with a preset number of exchanges to obtain a comparison result; when the comparison result is that the number of exchanges is less than the preset number of exchanges, re-inputting at least one target feasible solution into multiple basic membranes, and repeating the step of parallel screening of multiple load rate feasible solutions through multiple basic membranes; when the comparison result is that the number of exchanges is greater than or equal to the preset number of exchanges, determining at least one target feasible solution as the target load rate.

[0013] Optionally, multiple load rate feasible solutions are screened in parallel based on multiple basic membranes to obtain at least one target feasible solution, including: multiple load rate feasible solutions are screened in parallel in different cluster screening modes based on multiple basic membranes to obtain at least one target feasible solution, wherein the cluster screening mode is used to represent a cluster screening mode for screening multiple load rate feasible solutions.

[0014] According to another aspect of an embodiment of the present invention, a transformer loss suppression device is also provided, including: an acquisition module, used to acquire a distribution network network topology composed of multiple transformers arranged in a preset power supply area, wherein the distribution network network topology is used to represent the topological structure of the distribution network composed of the connection relationship between multiple transformers; a construction module, used to construct a loss suppression objective function based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters, wherein the distribution network parameters are used to represent the power supply parameters of the distribution network network topology, and the loss suppression objective function is used to represent the functional relationship established with the total loss of multiple transformers as the target; a determination module, used to determine the target load rate of multiple transformers based on the loss suppression objective function, wherein the target load rate is used to represent the transformer load rate assigned to multiple transformers; a control module, used to control the operation of multiple transformers based on the target load rate so that the operation loss of multiple transformers is less than the preset loss.

[0015] According to another aspect of an embodiment of the present invention, there is further provided an electronic device, comprising: a memory storing an executable program; and a processor for running the program, wherein the method in each embodiment of the present invention is executed when the program is running.

[0016] According to another aspect of an embodiment of the present invention, a computer-readable storage medium is provided. The computer-readable storage medium includes a stored executable program, wherein when the executable program is running, the device where the computer-readable storage medium is located is controlled to execute the methods in various embodiments of the present invention.

[0017] According to another aspect of an embodiment of the present invention, a computer program product is provided, including a computer program. When the computer program is executed by a processor, the method in each embodiment of the present invention is implemented.

[0018] According to another aspect of an embodiment of the present invention, a computer program product is provided, including a non-volatile computer-readable storage medium, wherein the non-volatile computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method in each embodiment of the present invention is implemented.

[0019] According to another aspect of the embodiments of the present invention, a computer program is further provided. When the computer program is executed by a processor, the methods in the embodiments of the present invention are implemented.

[0020] In an embodiment of the present invention, a method for suppressing transformer losses is provided, comprising: obtaining a distribution network topology composed of a plurality of transformers arranged in a preset power supply area, wherein the distribution network topology is used to represent a topological structure of a distribution network composed of connection relationships between a plurality of transformers; constructing a loss suppression objective function based on power demand data of equipment to be powered in the preset power supply area and distribution network parameters, wherein the distribution network parameters are used to represent power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent a functional relationship established with the total loss of a plurality of transformers as a target; determining target load rates of a plurality of transformers based on the loss suppression objective function, wherein the target load rate is used to represent the transformer load rate assigned to a plurality of transformers; and controlling the operation of a plurality of transformers based on the target load rate so that the The operating loss is less than the preset loss. It is easy to notice that the present application proposes that multiple transformers in a preset power supply area can be connected and networked to obtain a distribution network topology. The operating status of multiple transformers is analyzed based on the distribution network topology. Attention can be paid to the synergy between multiple transformers to suppress the losses of multiple transformers. The present application proposes that the operation of multiple transformers can be controlled based on a target load rate. By controlling the load rates of multiple transformers, multiple transformers can be coordinated to minimize the overall loss. The operating status of each transformer is adjusted according to the actual load conditions so that each transformer can operate together within the optimal load rate range. This can effectively reduce the overall loss and improve the energy efficiency of the system, thereby solving the technical problem of low efficiency in suppressing the losses of transformers in related technologies. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0022] Figure 1is a flow chart of a transformer loss suppression method according to an embodiment of the present invention;

[0023] Figure 2 is a schematic diagram of an optional distribution network topology according to an embodiment of the present invention;

[0024] Figure 3 is a schematic diagram of an optional target cluster search model structure according to an embodiment of the present invention;

[0025] Figure 4 is a flow chart of an optional method for determining target load rates of multiple transformers according to an embodiment of the present invention;

[0026] Figure 5 is a schematic diagram of a transformer loss suppression device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0027] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0028] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0029] According to an embodiment of the present invention, an embodiment of a method for suppressing losses of a transformer is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0030] Figure 1 is a flow chart of a transformer loss suppression method according to an embodiment of the present invention. Figure 1 As shown, the method comprises the following steps:

[0031] Step S102, obtaining a power distribution network topology composed of a plurality of transformers arranged in a preset power supply area.

[0032] Among them, the distribution network topology is used to represent the topological structure of the distribution network composed of the connection relationship between multiple transformers.

[0033] The above-mentioned preset power supply area may refer to a pre-selected or set power supply area, which may include multiple transformers and equipment to be powered, etc. The preset power supply area may be determined and divided according to actual needs and is not limited here.

[0034] The above-mentioned transformer may refer to an electrical device for changing AC voltage. The transformer may be composed of two or more coil windings and an iron core, and may transmit electrical energy through magnetic coupling. The transformer may increase or decrease the voltage at the input end and output the corresponding voltage at the output end. In the power system, transformers are widely used in power transmission, distribution and electronic equipment. Multiple transformers may be transformers of the same type or different types, which may be determined according to actual needs. The type of transformer is not specifically limited here.

[0035] In an optional embodiment, the present application proposes that multiple transformers in a preset power supply area can be connected and networked to obtain a distribution network topology, and the operating status of multiple transformers can be analyzed based on the distribution network topology, and the synergy between multiple transformers can be paid attention to to suppress the losses of multiple transformers. Figure 2 is a schematic diagram of an optional distribution network topology according to an embodiment of the present invention, such as Figure 2 As shown, multiple transformers are connected to a multi-port flexible switch through interconnection lines, wherein the multi-port flexible switch can be a network device with multiple ports that can connect multiple devices, and can flexibly switch and configure ports according to network traffic requirements. The multi-port flexible switch can automatically adjust the use of ports according to changes in network load to improve network performance and reliability. The switch type in the distribution network topology can also be determined according to actual needs, and the specific structure of the distribution network topology can be determined according to actual needs, which is not limited here.

[0036] The present application can establish a complete distribution network topology by acquiring and analyzing the positions and connection relationships of multiple transformers in a preset power supply area. The location information of each transformer in the preset power supply area can be obtained, which may include the specific location coordinates of each transformer and the connection method with other transformers. The information can be obtained through field surveys, power system drawings, and power supply network management systems. According to the location information of each transformer, a network topology diagram is established to clearly show the connection relationship and power supply path between each transformer, which is helpful to analyze the structural characteristics of the entire distribution network and provide an important basis for the formulation of further loss suppression strategies. Through in-depth analysis of the distribution network topology, potential energy loss points and optimization plans can be identified, thereby effectively reducing the energy loss of the entire system and improving power supply efficiency.

[0037] Step S104: constructing a loss suppression objective function based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters.

[0038] Among them, the distribution network parameters are used to represent the power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent the functional relationship established with the total loss of multiple transformers as the target.

[0039] The above-mentioned electricity demand data may refer to the amount of electric energy consumption required by the equipment to be powered within a specific time period. The electricity demand data may be used to analyze and calculate the electric energy consumption of the equipment in the power supply area, so as to design suitable transformers and power systems to achieve loss suppression and improve power supply efficiency. The specific data type of the electricity demand data may be determined according to actual needs and is not limited here.

[0040] The above-mentioned distribution network parameters may refer to various parameters when multiple transformers supply power to power supply equipment through the distribution network topology. The power supply parameters of the distribution network topology may include but are not limited to line current, line voltage, load power, power factor, etc. By monitoring and regulating the distribution network parameters, the transformer loss can be effectively suppressed and the power supply efficiency and stability of the system can be improved.

[0041] In an optional embodiment, a loss suppression objective function can be constructed based on the power demand data of the equipment to be powered in a preset power supply area and the distribution network parameters. The distribution network parameters can be used to represent the power supply parameters of the distribution network topology, including line impedance, load conditions, node voltage and other information. The loss suppression objective function can be a mathematical model used to represent the functional relationship established with the total loss of multiple transformers as the target. The loss suppression objective function can involve parameters such as the output power, loss, efficiency of the transformer, and the overall power balance of the distribution network. By comprehensively considering and optimizing the above parameters, the transformer loss can be minimized, thereby improving the efficiency and reliability of the power supply system. When constructing the loss suppression objective function, the specific conditions and needs of the preset power supply area, as well as the operating status and performance characteristics of the transformer, can be considered. The overall structure and operating conditions of the distribution network can be considered to ensure the feasibility and effectiveness of the loss suppression objective function. By comprehensively analyzing and modeling the above factors, effective control and management of transformer losses can be achieved, thereby improving the overall performance and operating efficiency of the power supply system.

[0042] Step S106, determining target load factors of the plurality of transformers based on the loss suppression objective function.

[0043] The target load factor is used to represent the transformer load factor allocated to the plurality of transformers.

[0044] In an optional embodiment, the target load rate can be used to represent the transformer load rate assigned to multiple transformers. When determining the target load rates of multiple transformers, calculations can be performed based on a loss suppression objective function. The loss suppression objective function is used to describe how to effectively distribute the load under given grid conditions to minimize the loss of the entire system. The loss suppression objective function can consider parameters such as the rated capacity, loss coefficient, current, voltage, and grid topology, load conditions, and other factors. When determining the target load rates of multiple transformers, an overall optimization goal can be set based on the grid conditions and the loss suppression objective function. The target load rate of each transformer is obtained by solving the optimization algorithm based on the parameters and constraints of each transformer, so that the loss of the entire system is minimized. Through the above steps, the load can be effectively distributed to each transformer, so that the loss of the system is effectively suppressed, and the operating efficiency and reliability of the system are improved. By continuously optimizing the target load rate, intelligent management and optimization of the transformer can be achieved, further improving the performance and energy-saving effects of the system.

[0045] Step S108, controlling the operation of the plurality of transformers based on the target load rate so that the operation loss of the plurality of transformers is less than a preset loss.

[0046] In an optional embodiment, the present application proposes that the operation of multiple transformers can be controlled based on a target load rate. By controlling the load rates of multiple transformers, the multiple transformers can be operated in coordination to minimize the overall loss. A preset loss target can be determined, that is, the total loss of multiple transformers should be less than this preset loss value. The optimal operating load rate range of each transformer can be determined based on the performance characteristics and load rate curve of each transformer. The load rate of each transformer can be monitored in real time, and the operating status of each transformer can be adjusted according to the actual load conditions so that each transformer can operate together within the optimal load rate range. This can effectively reduce the overall loss and improve the energy efficiency of the system. By controlling the operation of multiple transformers based on the target load rate, the loss of the entire system can be minimized, the stability and reliability of the system can be improved, and energy can be saved and operating costs can be reduced.

[0047] In an embodiment of the present invention, a method for suppressing transformer losses is provided, comprising: obtaining a distribution network topology composed of a plurality of transformers arranged in a preset power supply area, wherein the distribution network topology is used to represent a topological structure of a distribution network composed of connection relationships between a plurality of transformers; constructing a loss suppression objective function based on power demand data of equipment to be powered in the preset power supply area and distribution network parameters, wherein the distribution network parameters are used to represent power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent a functional relationship established with the total loss of a plurality of transformers as a target; determining target load rates of a plurality of transformers based on the loss suppression objective function, wherein the target load rate is used to represent the transformer load rate assigned to a plurality of transformers; and controlling the operation of a plurality of transformers based on the target load rate so that the The operating loss is less than the preset loss. It is easy to notice that the present application proposes that multiple transformers in a preset power supply area can be connected and networked to obtain a distribution network topology. The operating status of multiple transformers is analyzed based on the distribution network topology. Attention can be paid to the synergy between multiple transformers to suppress the losses of multiple transformers. The present application proposes that the operation of multiple transformers can be controlled based on a target load rate. By controlling the load rates of multiple transformers, multiple transformers can be coordinated to minimize the overall loss. The operating status of each transformer is adjusted according to the actual load conditions so that each transformer can operate together within the optimal load rate range. This can effectively reduce the overall loss and improve the energy efficiency of the system, thereby solving the technical problem of low efficiency in suppressing the losses of transformers in related technologies.

[0048] Optionally, based on the power demand data of the equipment to be powered in a preset power supply area and the distribution network parameters, a loss suppression objective function is constructed, including: obtaining the power demand power in the power demand data, and the received power of the equipment to be powered in the distribution network parameters, wherein the received power of the equipment to be powered is used to represent the electric power actually received by the equipment to be powered; based on the power demand power and the received power of the equipment to be powered, a loss suppression objective function is constructed.

[0049] The above-mentioned power demand may refer to the total power consumed by the equipment to be powered in a preset power supply area when the equipment is working, or may refer to the power consumed by each equipment to be powered when the equipment is working, which is not limited here.

[0050] In an optional embodiment, the power demand power in the power demand data and the received power of the power supply equipment in the distribution network parameters can be obtained. When constructing the loss suppression objective function, it can be considered how to minimize the energy loss of the transformer while ensuring the user's power demand. The construction of the loss suppression objective function can consider multiple factors, such as the rated power, load conditions, loss curve, etc. of the transformer. By reasonably constructing the loss suppression objective function, the transformer can be made more efficient and stable during operation, thereby reducing energy consumption, extending equipment life, and improving power supply quality. The present application can construct the following loss suppression objective function :

[0051] ;

[0052] in, can represent the loss of the i-th transformer, D can represent the number of interconnected transformers in the preset power supply area, Can indicate the The iron loss of a transformer, Can indicate the The copper loss of a transformer, Can indicate the The load factor of each transformer, It can represent the actual power obtained by the preset power supply area of ​​the transformer or the i-th transformer of the multi-port, that is, the power received by the device to be powered; It can represent the load demand of the power supply equipment corresponding to the i-th transformer, that is, the power demand. H can be the penalty coefficient, which penalizes whether the updated individual meets the load demand constraint. This can improve the population update efficiency and the loss suppression objective function. It can also be determined according to actual needs and is not limited here.

[0053] Optionally, the target load rates of multiple transformers are determined based on the loss suppression objective function, including: constructing a target constraint relationship set of the distribution network topology based on power demand data and distribution network parameters, wherein the target constraint relationship set is used to represent a set of constraints that need to be satisfied when multiple transformers provide normal power supply to power supply equipment through the distribution network topology; determining the target load rate based on the target constraint relationship set and the loss suppression objective function.

[0054] In an optional embodiment, a target constraint relationship set of the distribution network topology can be constructed through power demand data and distribution network parameters. The target constraint relationship set may include a set of constraints that need to be satisfied when multiple transformers provide normal power supply to power supply equipment through the distribution network topology. The target constraint relationship set may include voltage stability, line capacity, system load balance, etc. Based on the target constraint relationship set and the loss suppression objective function, the target load rate can be determined. Through the optimization algorithm, a better load rate distribution can be determined to minimize losses. By comprehensively considering factors such as the distribution network topology, power demand and transformer load rate, a better distribution network operation mode can be found to minimize the losses of each transformer and improve energy utilization efficiency.

[0055] Optionally, based on the power demand data and the distribution network parameters, a target constraint relationship set of the distribution network network topology is constructed, including: based on the distribution network port power in the distribution network parameters and a preset port power threshold, constructing the distribution network port constraint conditions of the distribution network network topology, wherein the distribution network port power is used to represent the port power of the switching device connecting multiple transformers in the distribution network network topology; based on the power demand power in the power demand data and the distribution network port power, constructing the power supply power constraint relationship of the distribution network network topology; based on the distribution network port constraint conditions and the power supply power constraint relationship, constructing a target constraint relationship set.

[0056] The above-mentioned distribution network port power may refer to the power flowing through the port corresponding to the i-th transformer in the distribution network network topology. A positive number of the distribution network port power may represent an inflow port, and a negative number of the distribution network port power may represent an outflow port. It may also be determined according to actual needs and is not limited here.

[0057] The above-mentioned preset port power threshold may refer to a preset maximum and / or minimum power threshold of the power flowing through the port. The preset port power may be determined according to actual needs and is not limited here.

[0058] In an optional embodiment, the distribution network port constraints of the distribution network network topology can be constructed based on the distribution network port power and the preset port power threshold in the distribution network parameters. The maximum power carrying capacity of each port can be determined based on the distribution network port power and the preset port power threshold in the distribution network parameters. The distribution network port power can refer to the port power of a switch device connected to multiple transformers. The preset port power threshold refers to the power limit set to avoid overload. The distribution network port constraints of the distribution network network topology can be constructed based on the maximum power carrying capacity of each port. The distribution network port constraints can ensure that each port in the distribution network does not exceed its maximum power carrying capacity, thereby avoiding the occurrence of overload. For the actual power demand of each port, The power demand power in the power demand data and the distribution network port power are used to construct the power supply power constraint relationship of the distribution network topology. The power supply power constraint relationship can ensure that the power supply power at each port can meet the actual power demand while avoiding exceeding the maximum power carrying capacity of the port; combining the distribution network port constraint conditions and the power supply power constraint relationship, a target constraint relationship set is constructed. The target constraint relationship set can monitor and manage the port power when the distribution network is running, ensuring the stable operation and efficient power supply of the entire distribution network, and can effectively construct the distribution network topology constraint conditions in the field of transformer loss suppression, thereby realizing effective management and control of the distribution network port power and power supply power, which helps to improve the operation efficiency of the distribution network, reduce energy loss, and ensure power supply quality.

[0059] Optionally, the distribution network port constraint in this application can be expressed as:

[0060] ;

[0061] in, It can represent the power flowing through the corresponding port of the i-th transformer in the distribution network topology, that is, the distribution network port power, It can represent the preset maximum power threshold flowing through the port, that is, the preset port power threshold; the distribution network port constraint condition can also be determined according to actual needs and is not limited here;

[0062] The power supply constraint relationship in this application can be expressed as:

[0063] ;

[0064] in, It can represent the useful power output by the i-th transformer in the distribution network topology, It can represent the total electric power that needs to be consumed by the equipment to be powered in the preset power supply area when it is working, that is, the power demand; the power supply power constraint relationship can also be determined according to actual needs, which is not limited here;

[0065] This application can also set the following distribution network topology constraints:

[0066] ;

[0067] in, can represent the loss of the i-th transformer, D can represent the number of interconnected transformers in the preset power supply area, Can indicate the The iron loss of a transformer, Can indicate the The copper loss of a transformer, Can indicate the The load factor of each transformer;

[0068] ;

[0069] in, It can represent the apparent power output of the i-th transformer in the distribution network topology, It can represent the capacity of the i-th transformer in the distribution network topology;

[0070] ;

[0071] in, It can represent the useful power output by the i-th transformer in the distribution network topology, It can represent the total load demand of each device to be powered;

[0072] ;

[0073] in, It can represent the apparent power output of the i-th transformer in the distribution network topology, It can represent the current capacity of the i-th transformer in the distribution network topology; thus, the target constraint relationship set can be constructed based on the constraint relationship of the above distribution network topology.

[0074] Optionally, the target load rate is determined based on the target constraint relationship set and the loss suppression objective function, including: using a target cluster search model to search for the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, wherein the target cluster search model is used to represent a model for searching for feasible solutions to the objective function in parallel through multiple processing units.

[0075] The above-mentioned target cluster search model can be a model that searches for feasible solutions to the target function in parallel through multiple processing units. The target cluster search model can include but is not limited to the Crossing Search Optimization (CSO) algorithm. The target cluster search model can also be determined according to actual needs, which is not limited here.

[0076] In an optional embodiment, in order to effectively reduce losses and improve efficiency, the present application proposes that a target cluster search model can be used for optimization. The target cluster search model can search for the loss suppression objective function based on a set of target constraint relationships to obtain the optimal target load rate. The target cluster search model can divide the search space into multiple subspaces, and search these subspaces simultaneously through multiple processing units to speed up the search and improve the search efficiency. Each processing unit is responsible for searching a subspace, and different processing units can exchange information and collaborate to further optimize the search results. By using the target cluster search model, the optimal solution of the loss suppression objective function can be searched more effectively and the optimal target load rate can be obtained.

[0077] Optionally, the target cluster search model includes a surface membrane and multiple basic membranes, the input end of the surface membrane is connected to the output ends of the multiple basic membranes, and the target cluster search model is used to search the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, including: determining multiple load rate feasible solutions of the target load rate based on the target constraint relationship set, wherein the multiple load rate feasible solutions are used to represent the allowable values ​​of the target load rate that satisfy the target constraint relationship set; inputting the multiple load rate feasible solutions into the multiple basic membranes of the target cluster search model; parallel screening of the multiple load rate feasible solutions through the multiple basic membranes to obtain at least one target feasible solution; updating at least one target feasible solution through the surface membrane to obtain the target load rate.

[0078] In an optional embodiment, the target cluster search model may include a surface membrane and multiple basic membranes. The target cluster search model can determine the optimal target load rate under a given target constraint relationship set through multiple iterations. Specifically, the input end of the surface membrane is connected to the output ends of the multiple basic membranes to realize information transmission and communication. Based on the target constraint relationship set, multiple load rate feasible solutions of the target load rate can be determined, and these feasible solutions are allowable values ​​of the target load rate that satisfy the target constraint relationship set; multiple load rate feasible solutions can be input into multiple basic membranes of the target cluster search model for further processing and screening; multiple load rate feasible solutions can be screened in parallel through multiple basic membranes to obtain at least one target feasible solution, that is, the optimal target load rate is determined under the condition of satisfying the constraint conditions; at least one target feasible solution can be updated through the surface membrane to obtain the final target load rate, that is, the optimal load rate state is achieved under the given constraint conditions. Through the above steps, the target cluster search model can effectively determine the optimal load rate of the transformer under complex constraint conditions, thereby achieving loss suppression and efficiency improvement.

[0079] Optionally, at least one target feasible solution is updated through the surface membrane to obtain a target load rate, including: exchanging information for at least one target feasible solution based on the surface membrane, and recording the number of exchanges; comparing the number of exchanges with a preset number of exchanges to obtain a comparison result; when the comparison result is that the number of exchanges is less than the preset number of exchanges, re-inputting at least one target feasible solution into multiple basic membranes, and repeating the step of parallel screening of multiple load rate feasible solutions through multiple basic membranes; when the comparison result is that the number of exchanges is greater than or equal to the preset number of exchanges, determining at least one target feasible solution as the target load rate.

[0080] In an optional embodiment, an optimization algorithm based on a surface film can be used to exchange information with at least one target feasible solution, record the number of exchanges, and then compare the number of exchanges with a preset number of exchanges to determine whether it is necessary to re-enter the target feasible solution into multiple basic films for parallel screening; if the comparison result shows that the number of exchanges is less than the preset number of exchanges, it means that there is still room for improvement in the target feasible solution, and multiple basic films can be used for parallel screening to obtain a better load rate feasible solution, which can improve the efficiency and accuracy of the algorithm and more effectively suppress the loss of the transformer; and if the comparison result shows that the number of exchanges is greater than or equal to the preset number of exchanges, it means that the target feasible solution is close to the optimal solution and can be determined as the target load rate. In this case, the algorithm can directly determine the target feasible solution as the final result, thereby reducing computing time and resource consumption. The above steps can help the optimization algorithm find the optimal solution in transformer loss suppression and improve system efficiency and performance.

[0081] Optionally, multiple load rate feasible solutions are screened in parallel based on multiple basic membranes to obtain at least one target feasible solution, including: multiple load rate feasible solutions are screened in parallel in different cluster screening modes based on multiple basic membranes to obtain at least one target feasible solution, wherein the cluster screening mode is used to represent a cluster screening mode for screening multiple load rate feasible solutions.

[0082] In an optional embodiment, the step of performing parallel screening of multiple load rate feasible solutions based on multiple basic membranes in different cluster screening modes is to find at least one target feasible solution. Multiple different basic membranes can be selected, and each basic membrane may have different optimization strategies or parameter settings. The cluster screening mode can be a method for screening multiple load rate feasible solutions. Multiple load rate feasible solutions can be divided into different groups according to different cluster screening modes, and each group can be screened; in order to improve efficiency, multiple load rate feasible solutions can be screened at the same time, that is, parallel processing, which can save time and quickly find at least one target feasible solution; after parallel screening of multiple basic membranes and different cluster screening modes, at least one target feasible solution can be obtained, and by performing parallel screening of multiple load rate feasible solutions based on multiple basic membranes in different cluster screening modes, at least one target feasible solution can be found, thereby achieving better optimization effect in the field of transformer loss suppression.

[0083] Figure 3 is a schematic diagram of an optional target cluster search model structure according to an embodiment of the present invention. Figure 3 As shown, the target cluster search model includes three basic membranes and one surface membrane. The input end of the surface membrane is connected to the output ends of the three basic membranes. Among them, each surface membrane can use randomly assigned population 1 (optimization algorithm 1), randomly assigned population 2 (optimization algorithm 2) and randomly assigned population 3 (optimization algorithm 3) to interact with the surface membrane.

[0084] The cluster screening modes adopted by multiple basic membranes may include but are not limited to a criss-cross pattern, a small-world network criss-cross pattern, and a ring topology criss-cross pattern. The cluster screening mode can be determined according to actual needs and is not limited here.

[0085] Figure 4 is a flow chart of an optional method for determining target load rates of multiple transformers according to an embodiment of the present invention. Figure 4 As shown:

[0086] Step S402: determining multiple load rate feasible solutions of the target load rate based on the target constraint relationship set.

[0087] Step S404: input multiple load rate feasible solutions into multiple basic membranes of the target cluster search model.

[0088] Step S406: screening multiple load rate feasible solutions in parallel through multiple basic membranes to obtain at least one target feasible solution.

[0089] Step S408, based on the surface membrane, information exchange is performed on at least one target feasible solution, and the number of exchanges is recorded; the number of exchanges is compared with the preset number of exchanges to obtain a comparison result; when the comparison result is that the number of exchanges is less than the preset number of exchanges, at least one target feasible solution is re-input into multiple basic membranes, and the step of parallel screening of multiple load rate feasible solutions through multiple basic membranes is repeated; when the comparison result is that the number of exchanges is greater than or equal to the preset number of exchanges, at least one target feasible solution is determined as the target load rate.

[0090] According to another aspect of an embodiment of the present invention, a transformer loss suppression device is also provided, which can execute the transformer loss suppression method of the above embodiment. The specific implementation method and preferred application scenario are the same as the above embodiment and will not be repeated here.

[0091] Figure 5 is a schematic diagram of a transformer loss suppression device according to an embodiment of the present application, such as Figure 5 As shown, the device includes the following: an acquisition module 502 , a construction module 504 , a determination module 506 , and a control module 508 .

[0092] Among them, the acquisition module 502 is used to obtain the distribution network topology composed of multiple transformers set in a preset power supply area, wherein the distribution network network topology is used to represent the topological structure of the distribution network composed of the connection relationship between multiple transformers; the construction module 504 is used to construct a loss suppression objective function based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters, wherein the distribution network parameters are used to represent the power supply parameters of the distribution network network topology, and the loss suppression objective function is used to represent the functional relationship established with the total loss of multiple transformers as the target; the determination module 506 is used to determine the target load rate of multiple transformers based on the loss suppression objective function, wherein the target load rate is used to represent the transformer load rate assigned to multiple transformers; the control module 508 is used to control the operation of multiple transformers based on the target load rate so that the operating loss of multiple transformers is less than the preset loss.

[0093] Among them, the construction module is also used to obtain the power demand power in the power demand data and the received power of the equipment to be powered in the distribution network parameters, wherein the received power of the equipment to be powered is used to represent the electric power actually received by the equipment to be powered; based on the power demand power and the received power of the equipment to be powered, a loss suppression objective function is constructed.

[0094] Among them, the determination module is also used to construct a target constraint relationship set of the distribution network topology based on the power demand data and the distribution network parameters, wherein the target constraint relationship set is used to represent the set of constraints that need to be met when multiple transformers provide normal power supply to the power supply equipment through the distribution network topology; based on the target constraint relationship set and the loss suppression objective function, the target load rate is determined.

[0095] Among them, the determination module is also used to construct the distribution network port constraint conditions of the distribution network network topology based on the distribution network port power and the preset port power threshold in the distribution network parameters, wherein the distribution network port power is used to represent the port power of the switch device connecting multiple transformers in the distribution network network topology; based on the power demand power in the power demand data and the distribution network port power, construct the power supply power constraint relationship of the distribution network topology; based on the distribution network port constraint conditions and the power supply power constraint relationship, construct a target constraint relationship set.

[0096] Among them, the determination module is also used to use the target cluster search model to search for the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, wherein the target cluster search model is used to represent a model for searching for feasible solutions to the objective function in parallel through multiple processing units.

[0097] Among them, the target cluster search model includes a surface membrane and multiple basic membranes, the input end of the surface membrane is connected to the output ends of the multiple basic membranes, and the determination module is also used to determine multiple load rate feasible solutions of the target load rate based on the target constraint relationship set, wherein the multiple load rate feasible solutions are used to represent the allowable values ​​of the target load rate that satisfies the target constraint relationship set; the multiple load rate feasible solutions are input into the multiple basic membranes of the target cluster search model; the multiple load rate feasible solutions are screened in parallel through the multiple basic membranes to obtain at least one target feasible solution; at least one target feasible solution is updated through the surface membrane to obtain the target load rate.

[0098] Among them, the determination module is also used to exchange information on at least one target feasible solution based on the surface membrane, and record the number of exchanges; compare the number of exchanges with the preset number of exchanges to obtain a comparison result; when the comparison result is that the number of exchanges is less than the preset number of exchanges, re-input the at least one target feasible solution into multiple basic membranes, and repeat the step of parallel screening of multiple load rate feasible solutions through multiple basic membranes; when the comparison result is that the number of exchanges is greater than or equal to the preset number of exchanges, determine at least one target feasible solution as the target load rate.

[0099] Among them, the determination module is also used to parallelly screen multiple load rate feasible solutions based on multiple basic membranes in different cluster screening modes to obtain at least one target feasible solution, wherein the cluster screening mode is used to represent the cluster screening mode for screening multiple load rate feasible solutions.

[0100] An embodiment of the present application further provides an electronic device, comprising: a memory storing an executable program; and a processor for running the program, wherein the program executes the methods in various embodiments of the present invention when running.

[0101] The above-mentioned memory may refer to a device inside a computer for storing data and programs, and may include memory, hard disk, etc., wherein the memory may be used to temporarily store running programs and data, the hard disk may be used to store programs and data for a long time, and the memory may be used to enable the computer to read and write data, and execute programs; the above-mentioned processor may be responsible for executing instructions in computer programs and performing data processing, and may be responsible for controlling and executing various operations, including arithmetic operations, logical operations, data transmission, etc.

[0102] An embodiment of the present application further provides a computer-readable storage medium, which includes a stored executable program, wherein when the executable program is running, the device where the computer-readable storage medium is located is controlled to execute the methods in various embodiments of the present invention.

[0103] The above-mentioned computer storage medium may refer to a medium in a computer memory used to store certain discontinuous physical quantities. Computer storage media mainly include semiconductors, magnetic cores, magnetic drums, magnetic tapes, laser disks, etc.; the stored program included in the computer-readable storage medium may be a set of instructions that can be recognized and executed by a computer, running on an electronic computer, and is an information tool that meets certain needs of people.

[0104] An embodiment of the present application further provides a computer program product, including a computer program, which implements the methods in various embodiments of the present invention when executed by a processor.

[0105] The above-mentioned computer program product may refer to a software program that has been written, tested and released and can be run on a computer or other device. The computer program product may include an application, an operating system, tool software, etc., which is used to implement specific functions or solve specific problems.

[0106] An embodiment of the present application further provides a computer program product, including a non-volatile computer-readable storage medium, wherein the non-volatile computer-readable storage medium is used to store a computer program, and when the computer program is executed by a processor, the method in each embodiment of the present invention is implemented.

[0107] The above-mentioned non-volatile computer-readable storage medium may refer to a medium for storing data. The non-volatile computer-readable storage medium can keep the data from being lost when the power is off, and can be used to store long-term data, such as operating systems, applications, and user files. The non-volatile storage medium may include hard disk drives, solid-state drives, optical disks, and flash memory storage devices, etc.

[0108] The embodiments of the present application further provide a computer program, which implements the methods in the above-mentioned embodiments of the present invention when executed by a processor.

[0109] The above-mentioned computer program may refer to a collection of instructions used to tell a computer to perform a specific task or operation. A computer program may be written by a programmer using a specific programming language and may include algorithms, data structures, logic, and control flows. A computer program may be used for a variety of purposes, including application software, operating systems, and the like.

[0110] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0111] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.

[0112] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0113] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0114] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, disk or optical disk, etc. Various media that can store program codes.

[0115] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for suppressing transformer losses, characterized in that: include: Acquire a distribution network topology composed of a plurality of transformers arranged in a preset power supply area, wherein the distribution network topology is used to represent a topological structure of a distribution network composed of a connection relationship between the plurality of transformers; Based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters, a loss suppression objective function is constructed, wherein the distribution network parameters are used to represent the power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent the functional relationship established with the total loss of the multiple transformers as the target; determining target load rates of the plurality of transformers based on the loss suppression objective function, wherein the target load rates are used to represent transformer load rates allocated to the plurality of transformers; Controlling the operation of the plurality of transformers based on the target load rate so that the operation loss of the plurality of transformers is less than a preset loss; Among them, determining the target load rate of the multiple transformers based on the loss suppression objective function includes: using a target cluster search model to search the loss suppression objective function based on a target constraint relationship set to obtain the target load rate, wherein the target cluster search model is used to represent a model for searching for feasible solutions of the objective function in parallel through multiple processing units, and the target constraint relationship set is used to represent a set of constraints that need to be satisfied when the multiple transformers provide normal power supply to the powered equipment through the distribution network topology.

2. The transformer loss suppression method according to claim 1, characterized in that: Based on the power demand data of the equipment to be powered in the preset power supply area and the distribution network parameters, a loss suppression objective function is constructed, including: Obtaining the power demand power in the power demand data and the received power of the device to be powered in the power distribution network parameters, wherein the received power of the device to be powered is used to represent the electric power actually received by the device to be powered; The loss suppression objective function is constructed based on the power demand and the power received by the device to be powered.

3. The transformer loss suppression method according to claim 1, characterized in that: Determining target load rates of the plurality of transformers based on the loss suppression objective function includes: Based on the power demand data and the distribution network parameters, construct a target constraint relationship set of the distribution network topology; The target load ratio is determined based on the target constraint relationship set and the loss suppression objective function.

4. The transformer loss suppression method according to claim 3, characterized in that: Based on the power demand data and the distribution network parameters, a target constraint relationship set of the distribution network topology is constructed, including: Based on the distribution network port power in the distribution network parameters and the preset port power threshold, constructing the distribution network port constraint condition of the distribution network network topology, wherein the distribution network port power is used to represent the port power of the switch device connected to the multiple transformers in the distribution network network topology; Based on the power demand power in the power demand data and the power of the distribution network port, constructing a power supply power constraint relationship of the distribution network topology; The target constraint relationship set is constructed based on the distribution network port constraint condition and the power supply constraint relationship.

5. The transformer loss suppression method according to claim 1, characterized in that: The target cluster search model includes a surface membrane and a plurality of basic membranes, the input end of the surface membrane is connected to the output ends of the plurality of basic membranes, and the target cluster search model is used to search the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, including: Determining a plurality of load rate feasible solutions of the target load rate based on the target constraint relationship set, wherein the plurality of load rate feasible solutions are used to represent allowable values ​​of the target load rate that satisfy the target constraint relationship set; inputting the plurality of load rate feasible solutions into the plurality of basic membranes of the target cluster search model; Screening the plurality of load rate feasible solutions in parallel through the plurality of basic membranes to obtain at least one target feasible solution; The at least one target feasible solution is updated through the surface film to obtain the target load rate.

6. The transformer loss suppression method according to claim 5, characterized in that: The at least one target feasible solution is updated through the surface film to obtain the target load rate, including: Exchanging information on the at least one target feasible solution based on the surface membrane, and recording the number of exchanges; Comparing the number of exchanges with a preset number of exchanges to obtain a comparison result; When the comparison result is that the number of exchanges is less than the preset number of exchanges, re-inputting the at least one target feasible solution into the multiple basic membranes, and repeatedly performing the step of parallel screening of the multiple load rate feasible solutions through the multiple basic membranes; When the comparison result is that the number of exchanges is greater than or equal to the preset number of exchanges, the at least one target feasible solution is determined as the target load rate.

7. The transformer loss suppression method according to claim 5, characterized in that: The plurality of load rate feasible solutions are screened in parallel based on the plurality of basic membranes to obtain at least one target feasible solution, including: Based on the multiple basic membranes, the multiple load rate feasible solutions are screened in parallel in different cluster screening modes to obtain at least one target feasible solution, wherein the cluster screening mode is used to represent the cluster screening mode for screening the multiple load rate feasible solutions.

8. A transformer loss suppression device, characterized in that: include: An acquisition module, used to acquire a distribution network topology composed of a plurality of transformers arranged in a preset power supply area, wherein the distribution network topology is used to represent a topological structure of a distribution network composed of a connection relationship between the plurality of transformers; A construction module, configured to construct a loss suppression objective function based on power demand data of the equipment to be powered in the preset power supply area and distribution network parameters, wherein the distribution network parameters are used to represent power supply parameters of the distribution network topology, and the loss suppression objective function is used to represent a functional relationship established with the total loss of the multiple transformers as a target; A determination module, configured to determine target load rates of the plurality of transformers based on the loss suppression objective function, wherein the target load rates are used to represent transformer load rates allocated to the plurality of transformers; A control module, configured to control the operation of the plurality of transformers based on the target load rate so that the operation loss of the plurality of transformers is less than a preset loss; Among them, the determination module is also used to use the target cluster search model to search the loss suppression objective function based on the target constraint relationship set to obtain the target load rate, wherein the target cluster search model is used to represent a model for searching for feasible solutions of the objective function in parallel through multiple processing units, and the target constraint relationship set is used to represent the set of constraints that need to be satisfied when the multiple transformers provide normal power supply to the powered equipment through the distribution network topology.

9. An electronic device, characterized in that: include: A memory storing an executable program; A processor is used to run the program, wherein the program, when running, executes the transformer loss suppression method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored executable program, wherein when the executable program is executed, the device where the storage medium is located is controlled to execute the transformer loss suppression method according to any one of claims 1 to 7.

11. A computer program product, characterized in that The invention comprises a computer program, which, when executed by a processor, implements the transformer loss suppression method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Multi-transformer imminent economic operation method, device, equipment and medium

    CN115549308A

  • Power grid total factor resource coordination control method and system

    CN117117876A