A floating support assembly method for a super large floating crane arm
By using 144-axis modular trucks and barges and pontoons for hinge point assembly at the wharf, the efficient installation of large floating crane booms is achieved, which solves the problems of long site occupancy and equipment dependence in traditional methods, improves installation efficiency and reduces costs. cost.
Patent Information
- Application Number
- CN202411086431.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-08-08
AI Technical Summary
Large-scale floating crane booms require large-scale gantry crane equipment when installed on the shore, resulting in long site occupancy time, low efficiency and high cost.
A 144-axis modular truck is used to transfer the boom to the dock, and barges and pontoons are used for hinge point assembly. The precise installation and adjustment of the boom is achieved through winches, jacks and floating cranes, reducing reliance on dock space and equipment.
The installation time is shortened, the assembly efficiency is improved, the equipment usage and cost are reduced, the operation is simple and time-consuming.
Smart Images

Figure CN118597370B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of floating crane vessel installation, and in particular to a floating support assembly method for a super-large floating crane arm. Background Art
[0002] The large floating boom structure is a boom mounted on a floating vessel, which is generally arranged in an inclined state with respect to the surface of the floating vessel. One end of the floating boom is hinged on the floating vessel, and the other end is tightened on the herringbone frame on the floating vessel by a steel wire rope.
[0003] Conventional large floating crane boom structures are very troublesome to install on floating vessels; the traditional floating crane installation and maintenance methods are to use gantry cranes to lift the boom and thread the hull. However, this method is too dependent on the site and lifting equipment. When there is no large lifting equipment, it is often necessary to rent large lifting equipment for construction. The floating crane installation and maintenance process is relatively long, generally taking 2 to 3 months, and it is necessary to occupy important production sites for a long time, and the construction cost is expensive. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a method for assembling a super-large floating crane arm by floating support, which can solve the problem that a general super-large floating crane arm is installed on the shore using a large gantry crane, which occupies a long time and has low efficiency.
[0005] In order to solve the above technical problems, the technical solution of the present invention is: a method for assembling a super-large floating crane arm, and its innovation lies in: the specific assembly method is as follows:
[0006] S1: Transfer of boom: After the boom is assembled in the 1200T gantry crane area, the transportation path of the boom is cleared; the 144-axis modular vehicle is used in conjunction with the boom support frame to transfer the boom to the dock's transshipment area to wait for transshipment;
[0007] S2: Preparation of barge and pontoon: The barge is moored to the shore of the wharf by means of cables, and a pad is laid between the barge and the wharf to ensure the stability of the boom on board; the pontoon is moored to the shore of the wharf by means of cables and moored beside the barge;
[0008] S3: Boom on barge: The 144-axis modular vehicle transports the boom on the boom support frame from the dock to the barge, and the 144-axis modular vehicle is withdrawn from the barge, so that the boom is placed on the barge through the boom support frame;
[0009] S4: Barge steering and docking: remove the mooring rope of the barge, use the tugboat to turn the barge to a direction parallel to the dock shore, then tow the barge to the stern of the pontoon and align the barge with the center of the pontoon, adjust the hinged end of the boom to the hinge point of the pontoon, roughly position the barge, drop anchor, tie the cable, adjust the draft to the set requirements, and prepare for the hinge point assembly;
[0010] S5: Axis insertion between the hinge point of the boom and the pontoon: A winch is set between the barge and the pontoon, and the barge is pulled by the winch so that the hinged end of the boom is slowly inserted into the hinge point on the pontoon; if the structure collides during the process, the direction should be adjusted in time until the distance between the two hinge holes is less than 100mm; the height difference between the two hinge holes is re-measured, and the next adjustment plan is determined in combination with the draft and ballast conditions of the barge and the pontoon; the height deviation of the hinge hole is eliminated by adjusting the load of the barge or the pontoon to prevent excessive adjustment and collision. Therefore, the jacking tooling is used as the height limiter first. When the hinge point hole is fine-tuned and aligned, the sleeper is replaced with a jack, and the jack can be used to jack up and fine-adjust to achieve precise alignment in the height direction; after the height direction is adjusted in place, the winch is used to fine-tune the barge to achieve precise positioning of the hinge point hole in the length direction of the ship; in order to prevent the arm from colliding with the hinge seat structure due to excessive towing, the arm can be limited by setting a limit block at the end of the arm on the floating ship; then the pre-prepared process shaft is quickly inserted into the hinge point hole;
[0011] S6: Rope threading and lifting of the boom: multiple sets of steel wire ropes are set between the top of the herringbone frame on the floating ship and the lifting end of the boom to achieve the connection between the end of the boom and the herringbone frame on the floating ship; at the same time, a 5000T floating crane is set at the lifting end of the boom, and the lifting end of the boom is lifted by the floating crane, rotated around the hinge point of the floating ship, and the steel wire ropes between the floating ship and the boom are tightened until the boom forms a set inclination angle on the floating ship;
[0012] S7: Installation of main and auxiliary hooks: After the boom is installed, the barge is moved out of the end of the floating vessel; then the floating vessel carrying the boom is moved to the dock, and the main and auxiliary hooks are installed on the lifting end of the boom at the dock.
[0013] Furthermore, in the S4 barge steering docking, a pulling mooring rope is used to connect the end of the barge and the end of the floating vessel to ensure that the center lines of the floating vessel and the barge are aligned.
[0014] Furthermore, the S5 boom and the floating vessel hinge are intersected by an axis, the length of the ship is adjusted by two 30T pulling winches, and the width of the ship is adjusted by a river side positioning anchor.
[0015] The advantages of the present invention are:
[0016] 1) In the present invention, the boom is loaded on the barge and matched with the hinge point of the floating boat, and the floating boat and the barge are connected to each other and the shaft is inserted; this installation method of the boom can reduce the occupation time of the dock space, and can also reduce the occupation time of the large lifting equipment on the dock, which greatly improves the assembly efficiency; in addition, after the boom is inserted, the inclination angle of the boom is directly adjusted by a large floating crane and connected to the floating boat with a wire rope and the wire rope is tightened; the assembly efficiency of the boom is greatly improved; the floating support assembly method of the super-large floating crane boom is simple to operate, short in time, less in equipment use, and low in cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0018] Figure 1 The present invention is a flow chart of a method for assembling a super-large floating crane arm by floating support.
[0019] Figures 2 to 8 The present invention is a state diagram of a super-large floating crane arm float-over assembly method. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] like Figures 1 to 8 A floating assembly method for a super-large floating crane arm is shown, and the specific assembly method is as follows:
[0023] S1: Transfer of boom: After the boom is assembled in the 1200T gantry crane area, the transportation path of the boom is cleared; the 144-axis modular vehicle is used in conjunction with the boom support frame to transfer the boom to the dock's transshipment area to wait for transshipment;
[0024] S2: Preparation of barge and pontoon: The barge is moored to the shore of the wharf by means of cables, and a pad is laid between the barge and the wharf to ensure the stability of the boom on board; the pontoon is moored to the shore of the wharf by means of cables and moored beside the barge;
[0025] S3: Boom on barge: The 144-axis modular vehicle transports the boom on the boom support frame from the dock to the barge, and the 144-axis modular vehicle is withdrawn from the barge, so that the boom is placed on the barge through the boom support frame;
[0026] S4: Barge steering and docking: remove the mooring rope of the barge, use the tugboat to turn the barge to a direction parallel to the dock shore, then tow the barge to the stern of the pontoon and align the barge with the center of the pontoon, adjust the hinged end of the boom to the hinge point of the pontoon, roughly position the barge, drop anchor, tie the cable, adjust the draft to the set requirements, and prepare for the hinge point assembly;
[0027] S5: Axis insertion between the hinge point of the boom and the pontoon: A winch is set between the barge and the pontoon, and the barge is pulled by the winch so that the hinged end of the boom is slowly inserted into the hinge point on the pontoon; if the structure collides during the process, the direction should be adjusted in time until the distance between the two hinge holes is less than 100mm; the height difference between the two hinge holes is re-measured, and the next adjustment plan is determined in combination with the draft and ballast conditions of the barge and the pontoon; the height deviation of the hinge hole is eliminated by adjusting the load of the barge or the pontoon to prevent excessive adjustment and collision. Therefore, the jacking tooling is used as the height limiter first. When the hinge point hole is fine-tuned and aligned, the sleeper is replaced with a jack, and the jack can be used to jack up and fine-adjust to achieve precise alignment in the height direction; after the height direction is adjusted in place, the winch is used to fine-tune the barge to achieve precise positioning of the hinge point hole in the length direction of the ship; in order to prevent the arm from colliding with the hinge seat structure due to excessive towing, the arm can be limited by setting a limit block at the end of the arm on the floating ship; then the pre-prepared process shaft is quickly inserted into the hinge point hole;
[0028] S6: Rope threading and lifting of the boom: multiple sets of steel wire ropes are set between the top of the herringbone frame on the floating ship and the lifting end of the boom to achieve the connection between the end of the boom and the herringbone frame on the floating ship; at the same time, a 5000T floating crane is set at the lifting end of the boom, and the lifting end of the boom is lifted by the floating crane, rotated around the hinge point of the floating ship, and the steel wire ropes between the floating ship and the boom are tightened until the boom forms a set inclination angle on the floating ship;
[0029] S7: Installation of main and auxiliary hooks: After the boom is installed, the barge is moved out of the end of the floating vessel; then the floating vessel carrying the boom is moved to the dock, and the main and auxiliary hooks are installed on the lifting end of the boom at the dock.
[0030] During the S4 barge steering docking, a pulling mooring rope is used to connect the end of the barge and the end of the pontoon to ensure that the center lines of the pontoon and the barge are aligned.
[0031] The S5 boom and the floating vessel are hinged at the axis, and the length of the ship is adjusted by two 30T pulling winches, and the width of the ship is adjusted by the river side positioning anchor.
[0032] Those skilled in the art should understand that the present invention is not limited to the above-mentioned embodiments. The above-mentioned embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may be subject to various changes and improvements, and these changes and improvements shall all fall within the scope of the present invention claimed for protection.
Claims
1. A method for assembling a super-large floating crane arm, characterized by: The specific assembly method is as follows: S1: Transfer of boom: After the boom is assembled in the 1200T gantry crane area, the transportation path of the boom is cleared; the 144-axis modular vehicle is used in conjunction with the boom support frame to transfer the boom to the dock's transshipment area to wait for transshipment; S2: Preparation of barge and pontoon: The barge is moored to the shore of the wharf by means of cables, and a pad is laid between the barge and the wharf to ensure the stability of the boom on board; the pontoon is moored to the shore of the wharf by means of cables and moored beside the barge; S3: Boom on barge: The 144-axis modular vehicle transports the boom on the boom support frame from the dock to the barge, and the 144-axis modular vehicle is withdrawn from the barge, so that the boom is placed on the barge through the boom support frame; S4: Barge steering and docking: remove the mooring rope of the barge, use the tugboat to turn the barge to a direction parallel to the dock shore, then tow the barge to the stern of the pontoon and align the barge with the center of the pontoon, adjust the hinged end of the boom to the hinge point of the pontoon, roughly position the barge, drop anchor, tie the cable, adjust the draft to the set requirements, and prepare for the hinge point assembly; S5: Axis insertion between the hinge point of the boom and the pontoon: A winch is set between the barge and the pontoon, and the barge is pulled by the winch so that the hinged end of the boom is slowly inserted into the hinge point on the pontoon; if the structure collides during the process, the direction should be adjusted in time until the distance between the two hinge holes is less than 100mm; the height difference between the two hinge holes is re-measured, and the next adjustment plan is determined in combination with the draft and ballast conditions of the barge and the pontoon; the height deviation of the hinge hole is eliminated by adjusting the load of the barge or the pontoon to prevent excessive adjustment and collision. Therefore, the jacking tooling is used as the height limiter first. When the hinge point hole is fine-tuned and aligned, the sleeper is replaced with a jack, and the jack can be used to jack up and fine-adjust to achieve precise alignment in the height direction; after the height direction is adjusted in place, the winch is used to fine-tune the barge to achieve precise positioning of the hinge point hole in the length direction of the ship; in order to prevent the arm from colliding with the hinge seat structure due to excessive towing, the arm can be limited by setting a limit block at the end of the arm on the floating ship; then the pre-prepared process shaft is quickly inserted into the hinge point hole; S6: Rope threading and lifting of the boom: multiple sets of steel wire ropes are set between the top of the herringbone frame on the floating ship and the lifting end of the boom to achieve the connection between the end of the boom and the herringbone frame on the floating ship; at the same time, a 5000T floating crane is set at the lifting end of the boom, and the lifting end of the boom is lifted by the floating crane, rotated around the hinge point of the floating ship, and the steel wire ropes between the floating ship and the boom are tightened until the boom forms a set inclination angle on the floating ship; S7: Installation of main and auxiliary hooks: After the boom is installed, the barge is moved out of the end of the floating vessel; then the floating vessel carrying the boom is moved to the dock, and the main and auxiliary hooks are installed on the lifting end of the boom at the dock.
2. A method for floating assembly of a super-large floating crane arm according to claim 1, characterized in that: In the S4 barge steering docking, a pulling mooring rope is used to connect the end of the barge and the end of the floating vessel to ensure that the center lines of the floating vessel and the barge are aligned.
3. The method for floating assembly of a super-large floating crane arm according to claim 1, characterized in that: The S5 boom and the floating vessel are hinged at the axis, and the length of the ship is adjusted by two 30T pulling winches, and the width of the ship is adjusted by the river side positioning anchor.