A construction method for shield tunneling through long-distance ventilation shaft

Through the shield-structure air-pushing method, the continuous construction of the tunnel is achieved using the guide axis and propulsion device, which solves the problems of low construction efficiency, high cost and high safety risks in the existing technology, improves the construction speed and safety, and reduces costs .

CN118653843BActive Publication Date: 2024-11-05CHINA RAILWAY 11TH BUREAU GRP CORP LTD +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411151375.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-11-05
Estimated Expiration
2044-08-21

AI Technical Summary

Technical Problem

The existing tunnel construction methods have problems such as low construction efficiency, high cost and high safety risks when over long distance air wells.

Method used

The shield air push method is used to determine the guide construction through the guide axis, install the guide rails and use the hole door curtain to close the starting door opening, disconnect the shield of the shield machine from the connection bridge, and use the propulsion device to push the shield to the receiving door opening. Move and perform secondary backfilling and debugging after receiving the door opening, and finally seal the door opening.

Benefits of technology

It improves construction speed and efficiency, reduces safety risks and costs, reduces the number of negative rings, simplifies the construction process, and realizes continuous air push of the shield machine and overall translation of the trolley.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118653843B_ABST
    Figure CN118653843B_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for empty-pushing a shield through a long-distance air shaft, comprising: determining a guide platform axis according to a starting portal, a receiving portal and a tunnel centerline, and constructing the guide platform along the guide platform axis; installing a guide rail on the top of the guide platform, and installing a tunnel door curtain on the outer side of the starting portal; empty-pushing the shield machine onto the guide rail, and closing the starting portal by means of the tunnel door curtain after the shield machine is separated from a pipe segment; arranging a propulsion device on both sides of a shield body on the guide platform, and pushing the shield body toward the receiving portal by means of the propulsion device; after the shield body reaches the receiving portal, performing a secondary backfilling on the guide platform, and then pulling a trolley and a connecting bridge toward the receiving portal by means of an electric vehicle; connecting the shield body and the connecting bridge into a complete shield machine, and performing secondary starting debugging on the shield machine; and after the debugged shield machine completely enters the receiving portal, blocking the receiving portal. The invention effectively solves the problems of low construction efficiency, high cost and high safety risk existing in the existing construction methods.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a construction method for a shield machine to push through a long-distance ventilation shaft. Background Art

[0002] In the process of tunnel construction, shield machines are increasingly widely used due to their safety, speed, high degree of mechanization and automation. Urban subway construction usually adopts construction methods such as open excavation, dark excavation, and shield construction. The earth pressure balance shield construction method has been widely used due to its wide adaptability, low environmental impact, high safety and high construction efficiency. When designing long-distance and large-section subways, it is necessary to set up interval ventilation shafts at appropriate locations to meet the requirements of tunnel ventilation, drainage, fire protection and civil air defense. When shield tunneling, it is necessary to pass through interval ventilation shafts or station construction.

[0003] At present, when the length of the ventilation shaft or station is short, the shield machine directly passes through the ventilation shaft or station by splicing pipe segments; when the length of the ventilation shaft or station is long, it is hoisted out of the station for transfer, then assembled in the shaft, and then started again to pass through the interval ventilation shaft. This has the problems of low construction efficiency, high cost and high safety risks. Summary of the invention

[0004] The invention provides a construction method for shield empty pushing through a long-distance air shaft, which solves the problems of low construction efficiency, high cost and great safety risk in the existing construction method.

[0005] In order to achieve the above object, the present invention adopts the following technical scheme:

[0006] The present invention provides a construction method for shield tunneling through a long-distance ventilation shaft, the method comprising:

[0007] The guide platform axis is determined according to the starting portal, the receiving portal and the tunnel centerline, and the guide platform is constructed along the guide platform axis; the guide platform is U-shaped, and holes for installing the reaction force support device are reserved on both sides of the top of the guide platform along the guide platform axis direction;

[0008] A guide rail is installed on the top of the guide platform along the axis direction of the guide platform, and a tunnel door curtain is installed on the outside of the starting doorway; the tunnel door curtain is used to close the starting doorway after the shield machine exits the tunnel;

[0009] The shield machine is pushed onto the guide rail in vain, and the starting doorway is closed by the door curtain after the shield machine is separated from the pipe segment;

[0010] Disconnect the shield body of the shield machine from the connecting bridge, set a propulsion device on both sides of the shield body on the guide platform, and push the shield body to move in the direction of the receiving door opening through the propulsion device; the fixed end of the propulsion device is fixed through the hole, and the output end of the propulsion device is connected to the shield body;

[0011] After the shield reaches the receiving door opening, the guide platform is backfilled for a second time, and then the trolley and the connecting bridge are pulled toward the receiving door opening by a battery vehicle;

[0012] Connecting the shield body and the connecting bridge into a complete shield machine, and performing secondary initial commissioning on the shield machine;

[0013] After the debugged shield machine completely enters the receiving doorway, the receiving doorway is blocked.

[0014] In a possible implementation, the guide platform axis is determined according to the originating portal, the receiving portal and the tunnel centerline, specifically including:

[0015] A circle is drawn with the starting doorway as the center and a preset length as the radius, and the secant of the tunnel centerline on the circle is used as the starting axis; the preset length is greater than the radius of the starting doorway;

[0016] Taking the receiving door opening as the center and a preset length as the radius, draw a circle, and use the secant of the tunnel centerline on the circle as the receiving axis;

[0017] A straight line connects the end points of the starting axis and the receiving axis that are close to each other to obtain the guide platform axis.

[0018] In a possible implementation, the guide platform is constructed along the guide platform axis, specifically including:

[0019] Along the axis direction of the guide platform, in a short U-shaped form, the steel cage is tied, the embedded steel plate is installed, the reserved hole template is installed, and the guide platform template is installed in sequence;

[0020] Concrete is poured into the steel cage, and a guide platform is obtained after the concrete is dried.

[0021] In a possible implementation, the guide rail includes a starting section, an intermediate section, and a receiving section, wherein the starting section is close to the starting door opening, and the receiving section is close to the receiving door opening; the guide rail is installed on the top of the guide platform along the axis direction of the guide platform, specifically including:

[0022] Before the shield machine reaches the starting portal, the starting section is positioned according to the starting axis and the actual center of the starting portal;

[0023] Connecting the intermediate section along the direction of the guide platform axis according to the position of the starting section;

[0024] The receiving section is positioned according to the posture of the shield machine, the position of the middle section and the position of the receiving doorway.

[0025] In a possible implementation, before installing the guide rail on the top of the guide platform along the axis direction of the guide platform, the method further includes:

[0026] The standard height of the guide rails of the wind shaft guide platform is determined according to the position of the starting doorway, the position of the receiving doorway, the standard height of the wind shaft bottom plate and the size of the shield machine.

[0027] In a possible implementation, before the shield machine is pushed onto the guide rail, the method further includes:

[0028] When receiving the preset ring before the shield machine, the guide rail is corrected according to the actual center coordinates of the starting tunnel portal and the design coordinates of the starting tunnel portal.

[0029] In a possible implementation, before the shield machine is pushed onto the guide rail, the method further includes:

[0030] When the shield machine penetrates the first preset length before the starting portal, the tunneling parameters of the shield machine are collected to reduce the thrust of the shield machine.

[0031] In a possible implementation, the shield machine is pushed onto the guide rail without any support, and the starting doorway is closed by the door curtain after the shield machine is separated from the segment, which specifically includes:

[0032] After receiving the cutterhead of the shield machine, the cutterhead is selected to a preset position, and the shield machine is started to be pushed onto the guide rail;

[0033] In the process of the shield machine being pushed onto the guide rail without any support, the guide rail is reinforced at the location where the abnormal noise is emitted, and the tunnel door curtain is tightened at the same time;

[0034] When the tail of the shield machine is completely out of the segment for the second preset length, grouting is performed behind the segment wall to fill the gap around the starting portal;

[0035] Perform secondary receiving to push the shield machine onto the guide rail completely.

[0036] In a possible implementation, the propulsion device is a hydraulic jack, a fixed end of the hydraulic jack is connected to a fixed connecting frame plugged into the hole, and an output end of the hydraulic jack is welded to a fixed block of a side wall of the shield machine.

[0037] In one possible implementation, the secondary initial debugging includes shield machine connection assembly debugging, tool replacement, shield tail brush replacement, shield tail grease application, connection measurement and hanging basket installation, measurement system installation and debugging, negative ring segment assembly and tunnel gate breaking.

[0038] The construction method for empty-pushing a shield through a long-distance ventilation shaft provided by the embodiment of the present invention has fast construction speed, high construction efficiency and short construction period; before the shield is received, the guide platform is prepared in advance according to the guide platform axis; after the shield is received, the shield machine is empty-pushed through the station and arrives at the receiving doorway for secondary backfilling, and the trolley track is laid, and then the trolley passes the station as a whole, thereby improving the construction efficiency of the shield machine passing the station and greatly shortening the construction period of the shield machine passing the ventilation shaft.

[0039] The construction method for shield empty pushing through a long-distance ventilation shaft provided by an embodiment of the present invention is highly safe and reliable. Compared with the existing construction methods, this construction method uses fewer negative rings, thereby reducing the risk of poor stability caused by too many negative rings. At the same time, the shield machine empty pushing process is simple and the safety risk is relatively small.

[0040] The construction method of shield empty pushing through a long-distance ventilation shaft provided by the embodiment of the present invention is more cost-effective; compared with the existing construction methods, this construction method uses less negative ring segments, has a faster construction speed, and requires fewer people during the construction process, thereby saving the cost of using negative rings and labor costs.

[0041] The construction method of shield empty pushing through a long-distance ventilation shaft provided by the embodiment of the present invention is simpler and more practical; during the empty pushing construction of the shield machine, only one set of propulsion devices is needed to realize continuous empty pushing of the shield machine, and the trolley is directly translated as a whole using a battery vehicle. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 A flowchart of the steps of a construction method for shield tunneling through a long-distance ventilation shaft provided by an embodiment of the present invention;

[0043] Figure 2 A schematic diagram of a scenario for determining the guide platform axis in a construction method for a shield machine to push through a long-distance ventilation shaft provided by an embodiment of the present invention;

[0044] Figure 3 A cross-sectional view of the manufacturing of a guide platform in a construction method for a shield machine to push through a long-distance ventilation shaft provided by an embodiment of the present invention;

[0045] Figure 4 A schematic diagram of a shield empty pushing structure in a construction method for empty pushing of a shield through a long-distance ventilation shaft provided in an embodiment of the present invention.

[0046] Reference numerals and description of the drawings:

[0047] 11. Starting portal; 12. Receiving portal; 13. Tunnel centerline; 14. Starting axis; 15. Receiving axis; 16. Guide platform axis; 17. Guide platform; 171. Steel plate; 172. Holes; 173. Reserved dowel bars in the bottom plate; 174. Line centerline; 18. Shield machine; 19. Hydraulic jack; 20. Fixed connecting frame; 21. Fixed block. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] In the following, the terms "first" and "second" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present disclosure, unless otherwise specified, "multiple" means two or more. In addition, the use of "based on" or "according to" means openness and inclusiveness, because the process, steps, calculations or other actions "based on" or "according to" one or more of the conditions or values ​​may be based on additional conditions or values ​​beyond the described values ​​in practice.

[0050] In order to solve the problems of low construction efficiency, high cost and great safety risk in the existing construction methods, an embodiment of the present invention provides a construction method of shield empty pushing through a long-distance ventilation shaft.

[0051] like Figure 1 As shown, the present embodiment provides a construction method for shield tunneling through a long-distance ventilation shaft, comprising the following steps:

[0052] Step 101, determine the guide platform axis according to the starting portal, the receiving portal and the tunnel center line, and construct the guide platform along the guide platform axis.

[0053] Among them, the center line of the tunnel is the center line of the shield advancement, that is, the center line of the entire tunnel.

[0054] The position of the guide platform axis is determined according to the position and size of the shield's starting portal and receiving portal. The guide platform axis can coincide with the tunnel centerline or have a certain offset from the tunnel centerline.

[0055] The guide platform is U-shaped, and holes for installing the reaction force support device are reserved on both sides of the top of the guide platform along the axis direction of the guide platform.

[0056] There are multiple reserved holes, and the multiple holes are arranged at equal intervals along the axis direction of the guide platform, and the holes located on both sides of the axis of the guide platform are symmetrically arranged.

[0057] Step 102: Install a guide rail on the top of the guide platform along the axis of the guide platform, and install a door curtain on the outer side of the starting doorway.

[0058] Among them, the guide rail is used to facilitate the user to push the shield machine towards the receiving portal, and the portal curtain is used to close the starting portal after the shield machine exits the tunnel.

[0059] Step 103: The shield machine is pushed onto the guide rails in vain, and the starting portal is closed by a portal curtain after the shield machine is separated from the segments.

[0060] Specifically, when installing the door curtain, first you need to clean and tap the bolt holes of the embedded steel ring of the starting door, then install and tighten the door curtain, ring plate and folding plate in sequence according to the installation drawing. When installing the door curtain, you also need to pay attention to the front and back of the curtain. At the exit end of the door curtain, you also need to install a steel wire rope to facilitate tightening the curtain after receiving it to prevent soil erosion.

[0061] Step 104, disconnect the shield body of the shield machine from the connecting bridge, set a propulsion device on both sides of the shield body on the guide platform, and push the shield body to move in the direction of the receiving door opening through the propulsion device.

[0062] Specifically, the positions of the holes on both sides of the guide platform axis where the propulsion device is installed are adjusted to achieve step-by-step advancement of the shield body of the shield machine.

[0063] Wherein, the fixed end of the propulsion device is fixed through a hole, and the output end of the propulsion device is connected to the shield body.

[0064] Step 105: After the shield reaches the receiving door opening, the guide platform is backfilled for a second time, and then the trolley and the connecting bridge are pulled toward the receiving door opening by an electric vehicle.

[0065] Specifically, the guide platform is backfilled with concrete for a second time, and then the trolley track and the tram track are built to realize the movement of the electric vehicle and the trolley.

[0066] Step 106: Connect the shield body and the connecting bridge to form a complete shield machine, and perform secondary startup debugging on the shield machine.

[0067] That is to say, after the shield body and the shield machine are reconnected, the connected shield machine is assembled and debugged so that it can be put into the next section of excavation work.

[0068] Step 107: After the debugged shield machine completely enters the receiving portal, the receiving portal is sealed.

[0069] Specifically, after the shield machine completely enters the receiving portal, the receiving portal end is closed and the shield machine continues to excavate forward.

[0070] like Figure 2 As shown, further, the guide platform axis 16 is determined according to the starting portal 11, the receiving portal 12 and the tunnel centerline 13, specifically including:

[0071] A circle is drawn with the starting portal 11 as the center and a preset length as the radius, and the secant of the tunnel centerline 13 on the circle is used as the starting axis 14 ; the preset length is greater than the radius of the starting portal 11 .

[0072] A circle is drawn with the receiving door opening 12 as the center and a preset length as the radius, and the secant line of the tunnel center line 13 on the circle is used as the receiving axis 15 .

[0073] A straight line connects the end points of the originating axis 14 and the receiving axis 15 which are close to each other to obtain the guide platform axis 16.

[0074] In this embodiment, the interval ventilation shaft is located on a circular curve, the tunnel centerline 13 matches the circular curve, and the preset length is 10 meters.

[0075] The interval ventilation shaft is located on a circular curve with a radius of 700m. With the starting portal 11 as the center and a circle with a radius of 10m, the two intersection points of the tunnel centerline 13 on the circle are connected by a straight line to obtain the starting axis 14; with the receiving portal 12 as the center and a circle with a radius of 10m, the two intersection points of the tunnel centerline 13 on the circle are connected by a straight line to obtain the receiving axis 15.

[0076] The axis connecting the two end points of the starting axis 14 and the receiving axis 15 which are close to each other is referred to as the guide platform axis 16 .

[0077] like Figure 3 As shown, further, the guide platform axis 16 is used to construct the guide platform 17, which specifically includes:

[0078] Along the guide platform axis 16, a short U-shaped structure is used to sequentially carry out steel cage binding, embedded steel plate installation, reserved hole template installation and guide platform template installation.

[0079] Concrete is poured into the steel cage, and the guide platform 17 is obtained after the concrete is dried.

[0080] In this embodiment, the guide platform 12 is made in a short U-shaped form, and the backfill surface from the small mileage tunnel to the large mileage tunnel needs to be sloped by 0.93%. The guide platform axis 16 is located directly below the line centerline 174, a steel cage is tied below the starting doorway 11, and a guide platform template is set outside the steel cage; steel plates 171 are set obliquely along the length direction at both ends of the notch of the U-shaped groove, the length of the steel plate 171 is 50cm, the width is 50cm, the spacing between adjacent steel plates 171 on the same side of the notch is 50cm, and the angle between the two steel plates 171 on both sides of the notch and the line centerline 174 is 50°; multiple reserved hole templates are set at equal intervals on the side of the steel plate 171 away from the starting doorway 11, and multiple holes 172 set at intervals are formed after concrete pouring. The reserved holes 172 are spaced 1m apart along the guide platform axis direction, and the holes 172 are set to avoid the embedded pipeline.

[0081] Pressure sensors or displacement sensors are evenly arranged on each steel plate 171 fixed on the guide platform. For example, one of the above sensors can be set at the four corners and the center point of each steel plate to comprehensively monitor the pressure distribution and displacement. The steel plate 171 is fixed on the guide platform 12, and the sensor can stably detect the inclination or misalignment of the shield machine. The data of all sensors are transmitted to the data acquisition module via wired or wireless means. The data acquisition module has multi-channel input capabilities and can process data from multiple sensors at the same time. The data analysis system analyzes the sensor data in real time and determines whether the shield machine is tilted or misaligned by comparing the benchmark data under normal working conditions. When abnormal pressure or displacement is detected, the system will determine whether it deviates from the predetermined starting axis, guide platform axis and receiving axis to ensure that the shield machine is excavated along the predetermined path during the construction process. When the system detects a deviation, it will promptly issue an early warning signal and provide corresponding corrective measures. This design can not only monitor the posture changes of the shield machine in real time, but also optimize the operation through the intelligent analysis system, improve the safety and stability of the shield machine operation, ensure that the tunnel can be excavated accurately along the designed axis during the tunnel construction process, and avoid potential construction risks. In addition, the reasonable layout of sensors and the introduction of data analysis systems make the entire shield construction process more intelligent and efficient.

[0082] When making the guide platform 17, the measurement and positioning must be accurate, the height setting of the guide platform 17 must be accurate, the installation of the guide platform template must be stable, and the steel cage of the guide platform must be firmly welded to the pre-embedded steel bars 173 of the bottom plate to enhance the stability of the guide platform 17 and prevent the steel bars from floating up during concrete pouring.

[0083] The entry into the tunnel is a curved one, and the starting secant line must be ensured to ensure the entry posture. Therefore, the axis control of the starting section guide platform is more important. The guide platform close to one end of the starting portal should be checked many times, and the horizontal position and elevation of the guide rail should be adjusted in time to ensure that the starting axis is in accordance with the predetermined axis.

[0084] Before receiving the shield machine, ensure that the posture deviation of the shield machine leaving the hole is no more than ±20mm.

[0085] The guide platform is the support body for receiving and launching shield machines, and its accuracy is the prerequisite for ensuring the receiving axis and the launching axis. Before the construction of the guide platform, accurate triangle orientation measurement and steel ruler hanging method elevation connection measurement are carried out from the ground through the vertical shaft to transfer the coordinates, direction and elevation of the ground control wire network to the underground. After the guide platform construction template is positioned, it must be measured and verified, and the elevation must be re-measured after the concrete is poured to ensure that the construction accuracy of the guide platform is within 0 to 10 mm.

[0086] When the reserved hole template interacts with the steel bars during installation, the position of the reserved hole template can be moved appropriately, but the movement of the reserved hole template cannot exceed 20cm.

[0087] During the construction of the guide platform, it is necessary to ensure the dimensional accuracy and the stability of each formwork when pouring concrete. If it is found that the guide platform is not flat enough when dismantling the formwork, it needs to be polished to meet the design requirements of the drawing.

[0088] Furthermore, the guide rail includes a starting section, a middle section and a receiving section, the starting section is close to the starting door opening, and the receiving section is close to the receiving door opening.

[0089] The guide rail is installed on the top of the guide platform along the axis direction of the guide platform, specifically including:

[0090] Before the shield machine reaches the starting portal, the starting section is positioned according to the starting axis and the actual center of the starting portal;

[0091] According to the position of the starting section, the middle section is connected along the direction of the guide platform axis;

[0092] The receiving section is positioned according to the posture of the shield machine, the position of the middle section and the position of the receiving portal.

[0093] That is to say, before the shield machine reaches the starting portal, the guide rails are installed using 43 rails. The receiving section is installed to position the guide rails according to the receiving posture, and the starting section is installed to position the guide rails according to the starting axis and the actual center of the starting portal; the middle section track is connected.

[0094] When installing the guide rail, determine its specific position based on the guide platform axis, and adjust it while measuring. The elevations on both sides of the guide rail must be consistent. When the shield receiving cutterhead arrives at the tunnel portal, adjust the elevation of the receiving section guide rail based on actual conditions.

[0095] The guide rail and the guide platform embedded parts are fixed with a 7-shaped pressure plate. At the same time, in order to ensure that the guide rail will not move with the shield machine, the guide rail and the embedded plate are welded and fixed at the rear end of the receiving section.

[0096] Furthermore, before installing the guide rail on the top of the guide platform along the axis direction of the guide platform, the method further includes:

[0097] The standard height of the guide rails of the wind shaft guide platform is determined based on the position of the starting doorway, the position of the receiving doorway, the standard height of the wind shaft bottom plate and the size of the shield machine.

[0098] Furthermore, before the shield machine is pushed onto the guide rail, the method further includes:

[0099] When the preset ring is set before receiving the shield machine, the guide rail is corrected according to the actual center coordinates of the starting tunnel portal and the design coordinates of the starting tunnel portal.

[0100] That is to say, a pre-acceptance review is required before the shield machine is pushed onto the guide rails.

[0101] Specifically, the preset ring is 50 rings. When measuring the 50 rings before receiving the shield machine, multiple verifications are required, including contact measurement, re-measurement of the guide wire points in the tunnel, manual posture verification, and segment posture verification. After all are accurate, the receiving posture is comprehensively determined based on the center coordinates of the starting tunnel portal and the design coordinates of the portal, and corrective measures are formulated.

[0102] Furthermore, before the shield machine is pushed onto the guide rail, the method further includes:

[0103] When the shield machine passes through the first preset length before the starting portal, the excavation parameters of the shield machine are collected to reduce the thrust of the shield machine.

[0104] That is to say, before the shield machine is pushed onto the guide rails, it is necessary to control the excavation of the shield receiving section.

[0105] Specifically, the first preset length is 25 meters. After the shield enters the first 25 meters of the breakthrough, pay attention to the excavation parameters in time, gradually slow down the excavation speed, reduce the thrust of the shield machine, and after the shield machine enters the reinforced body, gradually reduce the upper soil pressure to 0 bar, control the thrust within 1000t, and the excavation speed is 10-20mm / min; after the shield machine reaches the retaining pile, empty the soil bin, slowly advance the pile, control the speed at 10mm / min, and control the thrust within 800t to prevent the pile from breaking due to excessive frontal thrust.

[0106] Furthermore, the shield machine is pushed onto the guide rails in vain, and the starting portal is closed by the portal curtain after the shield machine is separated from the segments, specifically including:

[0107] After receiving the cutterhead of the shield machine, select the cutterhead to the preset position and start pushing the shield machine onto the guide rail;

[0108] When the shield machine is pushed onto the guide rail, the guide rail is reinforced at the location where the abnormal noise is emitted, and the tunnel curtain is tightened at the same time;

[0109] When the tail of the shield machine is fully out of the segment before the second preset length, grouting is performed behind the segment wall to fill the gap around the starting portal;

[0110] Carry out secondary receiving to push the shield machine onto the guide rails completely.

[0111] Among them, the second preset length is 50cm.

[0112] That is to say, after receiving the shield cutterhead, rotate the cutterhead to the appropriate position and start to push it onto the guide rail. Grease the guide rail to reduce the friction between the shield machine and the guide rail. When the shield machine is on the guide rail, pay close attention to the guide rail. When abnormal noise occurs, check it in time, reinforce it, and tighten the tunnel curtain to prevent water and sand leakage. In order to prevent water and sand from gushing out of the tunnel after the shield tail and the pipe segment are separated, the shield tail of the shield machine is reserved 50cm in the pipe segment, and double liquid slurry is injected behind the pipe segment wall to fill the gap near the tunnel door. Finally, the shield machine is received for the second time and pushed onto the guide rail.

[0113] After the shield machine is separated from the segment, the curtain is pulled back in time. After the curtain is tightened, holes are opened on the segment, and double-liquid slurry is slowly injected to seal the tunnel door in time.

[0114] Because the guide rails are not straight, there is great friction between the shield body of the shield machine and the guide rails, resulting in excessive pressure during advancement or even inability to push. Therefore, when installing the guide rails, it is necessary to ensure that the guide rails are straight and apply butter on the guide rails to reduce friction.

[0115] In order to provide quality assurance for the shield machine exiting the tunnel, the quality of the soil reinforcement at the end is checked before the shield machine arrives to ensure that the reinforcement quality meets the design requirements.

[0116] 100 meters before the shield machine penetrates, the connection measurement and tunnel portal posture review are carried out, and the shield machine posture is adjusted according to the measurement results. The adjustment range of the shield machine posture should not be too large, and the deviation of each ring is controlled within 5mm.

[0117] Prepare communication tools inside and outside the cave and lighting equipment inside the cave.

[0118] The assembled pipe segments should be tightened in time, and connecting and fastening measures should be taken with flat iron or channel steel.

[0119] Increase the frequency of surface subsidence monitoring and provide timely feedback of monitoring results to guide construction.

[0120] Apply grease to the inside of the rubber cord to prevent the blade from scratching the cord and affecting the sealing effect.

[0121] When the cutter head of the shield machine is 0.5m away from the pier wall, the debris in the soil bin should be emptied as much as possible to reduce the squeeze on the pier wall and secondary lining.

[0122] When installing several rings of segments after the shield has penetrated, it is imperative to ensure that the grouting is full and dense, and it must be tightened in time to prevent the segments from sinking, shifting, and leaking.

[0123] Control the guide platform elevation and lower it by 2cm during construction to ensure that the elevation does not exceed the preset elevation after the guide rail is installed.

[0124] After the guide platform and guide rail are completed, the guide rail elevation needs to be remeasured.

[0125] like Figure 4 As shown, the propulsion device is a hydraulic jack, the fixed end of the hydraulic jack 19 is connected to the fixed connecting frame 20 inserted in the hole 172, and the output end of the hydraulic jack 19 is welded to the fixed block 21 of the side wall of the shield machine 18.

[0126] That is to say, after the shield machine 18 is received, the connecting bridge is disconnected from the shield body, the fixed blocks 21 are symmetrically welded at appropriate positions on the left and right sides of the shield body, the pre-made fixed connecting frame 20 is inserted into the hole 172 to form a reaction force providing device, and two hydraulic jacks 19 are installed between the fixed connecting frame 20 and the fixed block 21. The hydraulic pump station is started to push the shield machine 18 forward. After the hydraulic jack 19 has extended its stroke, the hydraulic jack 19 is moved forward to move the fixed connecting frame 20 forward to the next hole 172, and the shield machine 18 is continued to be pushed forward. This cycle is repeated until the shield machine 18 is pushed empty onto the guide rail near the receiving doorway, and the construction of the shield machine 18 being pushed empty through the air shaft is completed.

[0127] A triangular rib is provided on one side of the fixed connecting frame 20 away from the hydraulic jack 19, and these ribs are supported on the guide platform 17, providing the necessary reaction force so that it can be firmly fixed on the guide platform 17. The rib is triangular, with a wider bottom and gradually narrowing upwards, and the bottom plane of the rib is in contact with the guide platform 17, providing stable support.

[0128] In order to ensure the cleanliness of the inside of the hole, a cover plate with a torsion spring is provided on the hole opening of the hole 172. Under the action of the torsion spring, the cover plate is in a horizontal state and covers the hole. When the fixed connecting frame 20 is inserted, the cover plate is pressed down, and the cover plate is flipped into the hole 172 and clamped between the fixed connecting frame 20 and the side wall of the hole 172. At this time, the cover plate is located on the side close to the rib plate, which plays a fixing role for the fixed connecting frame 20 to prevent shaking when the hydraulic jack 19 is working, and at the same time ensures that the bottom plane of the rib plate is in close contact with the guide platform 17. When the fixed connecting frame 20 is taken out, the cover plate will cover the hole again under the restoring force of the torsion spring.

[0129] Furthermore, when the shield is pushed forward on the guide rail, the shield may rotate due to different guide rail elevations or asynchronous advancement of the two sides. Therefore: by symmetrically welding fixed blocks on both sides of the shield machine, use a hydraulic jack to slowly push one side of the shield machine to make the shield machine slowly rotate and adjust the side roll of the shield machine back to the allowable range; when positioning the guide rail, the elevations on both sides must be consistent to prevent rotation to the lower side during advancement; during the push process, the hydraulic jacks on both sides apply force at the same time and keep the size consistent to make the shield machine move forward symmetrically.

[0130] When the shield reaches the starting door opening, the guide platform at the rear of the shield is backfilled for the second time, including the embedded parts of the reaction frame and the back wall of the reaction support.

[0131] After measuring the backfill elevation, install the formwork, locate the embedded parts of the reaction frame, tie the steel bars of the embedded parts of the reaction frame, and embed the reaction frame supporting steel plates, and finally backfill the concrete.

[0132] After the secondary backfill of the guide platform is completed, the battery car track and the trolley track are laid. After the laying is completed, the connecting bridge and the trolley are dragged to the starting wellhead by the battery car.

[0133] When hauling, personnel observe the track conditions to prevent derailment.

[0134] Furthermore, the secondary start-up debugging includes shield machine connection, assembly and debugging, tool replacement, shield tail brush replacement, shield tail grease application, connection measurement and hanging basket installation, measurement system installation and debugging, negative ring segment assembly and tunnel gate breaking.

[0135] Specifically, attention should be paid when the shield machine enters the tunnel for initial excavation. Since it starts by breaking half of the tunnel gate piles, stones should be padded at the bottom to prevent the shield machine from falling headfirst into the tunnel. At the same time, the outer guide rail should be made according to the actual slope.

[0136] After the tunnel gate is broken, it must be carefully inspected to ensure that when the cutter disc reaches the face, it passes the tunnel gate curtain of the starting portal.

[0137] The posture cannot be adjusted during the initial excavation. Therefore, the initial posture of the shield machine must meet the requirements. The posture changes before the shield machine fully enters the tunnel can be roughly judged through posture simulation.

[0138] When breaking down the tunnel gate, first break down the pilot point for inspection. Once leakage occurs, immediately use sacks wrapped with square wood to push into the leaking point. After sand stops gushing out of the leaking point, drive expansion screws around the water outlet and weld on the prepared steel mesh. After it is fixed, fill the mesh with sacks and other water-stopping means. When the water flow is small, build cement mortar outside the mesh and then use sandbags to apply pressure near the leaking point.

[0139] After controlling the water outflow, adjust the geological drilling rig and use a 70mm diameter diamond drill bit to drill through the bored piles of the retaining structure around the tunnel portal, introduce the water flow into the pre-buried steel pipe, and install a valve at one end of the pre-buried steel pipe after pulling out the drill rod to control the water outflow. At least two holes are drilled in the steel pipes on both sides of the tunnel portal.

[0140] After drilling is completed, insert the grouting pipe from the embedded steel pipe and inject double liquid slurry into the gap. The water glass content in the double liquid slurry is 3% to 5%. The grouting pressure is 0.1 to 1 MPa. Observe the changes of the leaking point on site and try to avoid excessive pressure to break the leaking point blockage.

[0141] The construction method for empty-pushing a shield through a long-distance ventilation shaft provided by the embodiment of the present invention has fast construction speed, high construction efficiency and short construction period; before the shield is received, the guide platform is prepared in advance according to the guide platform axis; after the shield is received, the shield machine is empty-pushed through the station and arrives at the receiving doorway for secondary backfilling, and the trolley track is laid, and then the trolley passes the station as a whole, thereby improving the construction efficiency of the shield machine passing the station and greatly shortening the construction period of the shield machine passing the ventilation shaft.

[0142] The construction method for shield empty pushing through a long-distance ventilation shaft provided by an embodiment of the present invention is highly safe and reliable. Compared with the existing construction methods, this construction method uses fewer negative rings, thereby reducing the risk of poor stability caused by too many negative rings. At the same time, the shield machine empty pushing process is simple and the safety risk is relatively small.

[0143] The construction method of shield empty pushing through a long-distance ventilation shaft provided by the embodiment of the present invention is more cost-effective; compared with the existing construction methods, this construction method uses less negative ring segments, has a faster construction speed, and requires fewer people during the construction process, thereby saving the cost of using negative rings and labor costs.

[0144] The construction method of shield empty pushing through a long-distance ventilation shaft provided by the embodiment of the present invention is simpler and more practical; during the empty pushing construction of the shield machine, only one set of propulsion devices is needed to realize continuous empty pushing of the shield machine, and the trolley is directly translated as a whole using a battery vehicle.

[0145] The construction method of shield machine empty pushing through long-distance ventilation shaft of the present invention is suitable for shield machine passing through long-distance interval ventilation shaft or shield machine passing through station construction.

[0146] The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A construction method for shield tunneling through a long-distance ventilation shaft, characterized in that: include: The guide platform axis is determined according to the starting portal, the receiving portal and the tunnel centerline, and the guide platform is constructed along the guide platform axis; the guide platform is U-shaped, and holes for installing the reaction force support device are reserved on both sides of the top of the guide platform along the guide platform axis direction; A guide rail is installed on the top of the guide platform along the axis direction of the guide platform, and a tunnel door curtain is installed on the outside of the starting doorway; the tunnel door curtain is used to close the starting doorway after the shield machine exits the tunnel; The shield machine is pushed onto the guide rail in vain, and the starting doorway is closed by the door curtain after the shield machine is separated from the pipe segment; Disconnect the shield body of the shield machine from the connecting bridge, set a propulsion device on both sides of the shield body on the guide platform, and push the shield body to move in the direction of the receiving door opening through the propulsion device; the fixed end of the propulsion device is fixed through the hole, and the output end of the propulsion device is connected to the shield body; After the shield reaches the receiving door opening, the guide platform is backfilled for a second time, and then the trolley and the connecting bridge are pulled toward the receiving door opening by a battery vehicle; Connecting the shield body and the connecting bridge into a complete shield machine, and performing secondary initial commissioning on the shield machine; After the debugged shield machine completely enters the receiving doorway, the receiving doorway is blocked; Among them, the guide platform axis is determined according to the starting portal, the receiving portal and the tunnel center line, including: A circle is drawn with the starting doorway as the center and a preset length as the radius, and the secant of the tunnel centerline on the circle is used as the starting axis; the preset length is greater than the radius of the starting doorway; Taking the receiving door opening as the center and a preset length as the radius, draw a circle, and use the secant of the tunnel centerline on the circle as the receiving axis; A straight line connects the end points of the originating axis and the receiving axis that are close to each other to obtain the guide platform axis; Wherein, before the shield machine is pushed onto the guide rail, the method further comprises: When the shield machine passes through the first preset length before the starting portal, collecting the tunneling parameters of the shield machine and reducing the thrust of the shield machine; The shield machine is pushed onto the guide rail without any support, and the starting doorway is closed by the door curtain after the shield machine is separated from the segment, which specifically includes: After receiving the cutterhead of the shield machine, the cutterhead is selected to a preset position, and the shield machine is started to be pushed onto the guide rail; In the process of the shield machine being pushed onto the guide rail without any support, the guide rail is reinforced at the location where the abnormal noise is emitted, and the tunnel door curtain is tightened at the same time; When the tail of the shield machine is completely out of the segment for the second preset length, grouting is performed behind the segment wall to fill the gap around the starting portal; Perform secondary receiving to push the shield machine onto the guide rail completely.

2. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 1 is characterized in that: The guide platform is constructed along the guide platform axis, specifically including: Along the axis direction of the guide platform, in a short U-shaped form, the steel cage is tied, the embedded steel plate is installed, the reserved hole template is installed, and the guide platform template is installed in sequence; Concrete is poured into the steel cage, and a guide platform is obtained after the concrete is dried.

3. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 2 is characterized in that: The guide rail includes a starting section, an intermediate section and a receiving section, wherein the starting section is close to the starting door opening, and the receiving section is close to the receiving door opening; the guide rail is installed on the top of the guide platform along the axis direction of the guide platform, specifically including: Before the shield machine reaches the starting portal, positioning the starting section according to the starting axis and the actual center of the starting portal; Connecting the intermediate section along the direction of the guide platform axis according to the position of the starting section; The receiving section is positioned according to the posture of the shield machine, the position of the middle section and the position of the receiving doorway.

4. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 3 is characterized in that: Before installing the guide rail on the top of the guide platform along the axis direction of the guide platform, the method further includes: The standard height of the guide rails of the wind shaft guide platform is determined according to the position of the starting doorway, the position of the receiving doorway, the standard height of the wind shaft bottom plate and the size of the shield machine.

5. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 1 is characterized in that: Before the shield machine is pushed onto the guide rail, the method further comprises: When receiving the preset ring in front of the shield machine, the guide rail is corrected according to the actual center coordinates of the starting portal and the design coordinates of the starting portal.

6. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 1 is characterized in that: The propulsion device is a hydraulic jack, the fixed end of the hydraulic jack is connected to a fixed connecting frame plugged into the hole, and the output end of the hydraulic jack is welded to a fixed block on the side wall of the shield machine.

7. The construction method of shield empty pushing through long-distance ventilation shaft according to claim 1 is characterized in that: The secondary start-up debugging includes shield machine connection, assembly and debugging, replacement of cutters, replacement of shield tail brushes, application of shield tail grease, connection measurement and hanging basket installation, measurement system installation and debugging, negative ring segment assembly and tunnel gate breaking.

Citation Information

Patent Citations

  • Secondary launching construction method for overall station-crossing of sliding steel sleeve and shield tunneling machine

    CN109899074A

  • Mining method tunnel section shield large longitudinal slope empty pushing and translation transition construction method

    CN114526083A

  • Shield guide table made of concrete and construction method

    CN117052413A

  • Shield receiving and launching construction method for small-clear-distance large-burial-depth vertical shaft

    CN118030094A

  • Construction structure for shield empty pushing to pass through subsurface tunnel and secondary launching

    CN209040835U