A rail transit operation plan optimization method and system based on cost analysis

By constructing a multi-mode transportation network based on cost analysis, identifying passenger travel modes and predicting passenger flow, and designing multi-objective optimization algorithms, it solves the shortcomings of traditional rail transit operation plan optimization methods and achieves more efficient and lower-cost operations and Higher passenger satisfaction.

CN118657260BActive Publication Date: 2024-10-29FOSHAN URBAN PLANNING & DESIGN INST
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411139860.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-10-29
Estimated Expiration
2044-08-20

AI Technical Summary

Technical Problem

Traditional rail transit operation plan optimization methods rely on experience and a single factor, are difficult to cope with diverse passenger needs and dynamic traffic environments, and lack all-round coverage of multi-modal transportation networks, resulting in insufficiently refined traffic models.

Method used

Using a method based on cost analysis, a graphical multi-modal transportation network is constructed by collecting traffic data, identifying passenger travel modes, predicting passenger flow, and designing a multi-objective optimization algorithm to automatically recommend the optimal operation plan. Specific steps include coordinating the coding of transportation modes, identifying transfer relationships, using the improved DBSCAN algorithm for dynamic spatio-temporal clustering, calculating the importance of connection points, designing hierarchical connection plans, and minimizing operating costs and maximizing operation costs through multi-objective optimization algorithms. Passenger satisfaction and environmental impact.

Benefits of technology

It improves the accuracy of passenger flow prediction, realizes efficient utilization of transportation resources and refined management of connection plans, reduces operating costs, and improves passenger experience and system efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118657260B_ABST
    Figure CN118657260B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for optimizing rail transit operation plans based on cost analysis, which relates to the field of data processing technology, including collecting data and constructing a graphical multi-modal transportation network; identifying typical passenger travel patterns and predicting passenger flow at each connection point; designing a connection plan based on the results of travel patterns and passenger flow prediction; designing a multi-objective optimization algorithm based on cost analysis, and automatically recommending the optimal plan based on the operation goals. The present invention enables the rail transit system to operate at a lower cost and higher efficiency, while improving the travel experience and satisfaction of passengers, and ultimately achieving the purpose of improving the overall efficiency of the rail transit system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing, and in particular to a method and system for optimizing a rail transit operation plan based on cost analysis. Background Art

[0002] With the acceleration of urbanization, the rail transit system has become an important part of the modern urban transportation system. With its advantages of high efficiency, environmental protection and large capacity, rail transit has played a key role in alleviating urban traffic congestion and reducing pollution emissions. However, with the continuous expansion of urban scale and the continuous growth of population, the rail transit system is facing increasingly complex operational management challenges.

[0003] Traditional rail transit operation plans mostly rely on experience and single factor considerations, and are unable to fully respond to diverse passenger needs and dynamically changing traffic environments.

[0004] Current rail transit operation plan optimization methods are often limited to a single data source in terms of data collection and lack comprehensive coverage of multimodal transportation networks, resulting in the constructed transportation models being less sophisticated. Summary of the invention

[0005] In view of the above-mentioned problems existing in the current rail transit operation plan optimization method, the present invention is proposed.

[0006] Therefore, the problem to be solved by the present invention is how to provide a method and system for significantly improving the scientificity and practicality of rail transit operation plans.

[0007] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0008] In the first aspect, an embodiment of the present invention provides a method for optimizing rail transit operation plans based on cost analysis, which includes collecting traffic data and constructing a graphical multimodal transportation network; identifying typical passenger travel patterns and predicting passenger flow at each connection point; designing connection plans based on travel patterns and passenger flow prediction results; designing a multi-objective optimization algorithm based on cost analysis, and automatically recommending the optimal plan based on the operation objectives.

[0009] As a preferred solution of the rail transit operation plan optimization method based on cost analysis described in the present invention, the construction of a graphical multimodal transportation network includes: coordinating all transportation modes in the transportation system and uniformly encoding each transportation mode; identifying the connection mode between each transportation mode and determining the transfer relationship; locking the transfer relationship between each transportation mode according to the connection mode; forming a multimodal transportation network connection tree according to the transfer relationship, when new transportation facilities are added, the connection tree is expanded, when the original transportation facilities are abandoned, the connection tree is reduced, and when the transfer relationship changes, the connection tree is refreshed; the entire urban area is divided into several grids, various types of transportation facilities are marked in each grid, and similar transportation facilities in adjacent grids are connected to form a multimodal transportation network.

[0010] As a preferred solution of the rail transit operation plan optimization method based on cost analysis described in the present invention, the identification of typical passenger travel patterns includes the following steps: extracting passenger travel data from a multimodal transportation network, and discretizing and weighting the time dimension; developing a dynamic spatiotemporal clustering algorithm based on DBSCAN, introducing a time decay factor, discretizing the time dimension into multiple time segments, performing spatial clustering in each time segment, and using a sliding time window technology to achieve a smooth transition of clustering results in continuous time periods, including: setting Define the space-time distance function for the travel trajectories of different passengers:

[0011]

[0012] Modify the neighborhood query function of DBSCAN to consider the time weight, that is:

[0013]

[0014] Determine the weighted core points:

[0015]

[0016] in, , , , They are The starting and ending coordinates of the trajectory; , , , They are The starting and ending coordinates of the trajectory; for The time coordinate of the trajectory; for The time coordinate of the trajectory; is the time weight factor; is the query point; Q is The points in the neighborhood, is the neighborhood radius; is the time weight of point Q; is the minimum time weight threshold; The minimum point threshold required to become a core point; set the sliding window size to 7 days and the step size to 1 day, execute the improved DBSCAN algorithm for each time window, and save the clustering results; calculate the similarity of the clustering results of adjacent time windows, and set the similarity threshold to achieve a smooth transition of the clustering results, where the time window is a specific time period selected when the sliding window moves.

[0017] As a preferred solution of the rail transit operation plan optimization method based on cost analysis described in the present invention, the design process of the connection plan is as follows: extracting typical travel mode data, combining passenger flow prediction results, and calculating the importance of the connection point, including:

[0018] The connection point importance index IPI of the connection point p is:

[0019]

[0020] in, is the weight coefficient associated with the connection point p, is a fixed value, represents the predicted passenger flow using transportation mode i to reach the connecting point p within the time block (j, k), and n is the type of transportation mode; the time block (j, k) refers to dividing a day into multiple time periods, j represents the hour of the time block, that is, from 0 to 23, and k represents the day of the time block, that is, from 0 to 6; the connecting points are graded to form a graded connecting plan; high-importance connecting points include configuring full-mode transportation connections, increasing the waiting area area and the width of the transfer channel, increasing the frequency of flights, and reducing the average waiting time; medium-importance connecting points include configuring main-mode transportation connections, maintaining standard waiting areas and transfer channels, and maintaining regular frequency; low-importance connecting points include configuring basic-mode transportation connections, setting up simple waiting facilities, and adjusting the frequency of flights according to actual needs.

[0021] As a preferred solution of the rail transit operation plan optimization method based on cost analysis of the present invention, the classification of the connection points includes: if the connection point importance index is > , then it is a high-importance connection point; if the connection point importance index ≤ ≤ , then it is a connection point of medium importance; if the connection point importance index < , then it is a low-importance connection point; among them, and is the set threshold.

[0022] As a preferred solution of the rail transit operation plan optimization method based on cost analysis of the present invention, wherein: the multi-objective optimization algorithm designed according to cost analysis includes: the fixed cost is calculated as follows:

[0023]

[0024] Among them, FC is the total fixed cost, is the investment cost of equipment q, is the annual maintenance cost of equipment q, is the annual depreciation cost of equipment q, is the number of equipment; variable cost calculation:

[0025]

[0026] Where VC is the total variable cost, is the unit energy cost of transportation mode i, is the annual energy use of transport mode i, is the hourly labor cost of transportation mode i, is the number of hours worked in the year; is the unit fuel cost of transportation mode i; is the annual fuel consumption of transport mode i; For the type of transportation; total cost calculation:

[0027] TC = FC + VC

[0028] Ticket revenue forecast:

[0029]

[0030] in, is the ticket revenue of the connecting point p, is the annual passenger flow of transportation mode i, is the average ticket price; non-ticket revenue forecast:

[0031]

[0032] in, is the non-ticket revenue of the connection point p, is the advertising space area, For unit advertising revenue, For commercial space area, For unit rent; is the income amount of other income source K of the connection point p; Unit income of other income sources K; K is the income source; o is the total number of other income sources; total income calculation includes:

[0033]

[0034] in, is the total number of docking points; the objectives of the multi-objective optimization algorithm include minimizing the overall operating cost MinTC, maximizing the passenger satisfaction MaxCS, minimizing the environmental impact MinEI and the lower limit of the revenue MinTR; wherein the overall operating cost is TC, the passenger satisfaction is CS, the environmental impact is EI, and the revenue is TR; based on the hierarchical docking scheme, the objective function value OF is calculated for each candidate scheme:

[0035]

[0036] in, , , and are the normalized values ​​of TC, CS, EI and TR, ~ 4 are weight coefficients respectively; the top 5 schemes with the highest OF objective function values ​​are selected for re-evaluation.

[0037] As a preferred solution of the rail transit operation plan optimization method based on cost analysis described in the present invention, the re-evaluation includes: evaluating and grading each plan based on its benefit-cost ratio, service quality and environmental impact; simulating situations where passenger flow increases or decreases, energy costs rise and service quality requirements increase, and for each situation, recalculating the OF objective function value and grading the plans according to the magnitude of the change in the OF objective function value; comprehensively scoring each plan, selecting the plan with the highest comprehensive score as the recommended plan, and when there are multiple plans with the highest comprehensive score, selecting the plan with the largest benefit-cost ratio as the recommended plan.

[0038] On the second aspect, in order to further solve the problems existing in the current rail transit operation plan optimization method, the present invention provides a rail transit operation plan optimization system based on cost analysis in an embodiment, which includes: a data acquisition and construction module: used to collect data and build a graphical multi-modal transportation network; a pattern recognition and passenger flow prediction module: used to identify typical passenger travel patterns, predict the passenger flow of each docking point, and analyze the key factors affecting the docking demand; a docking plan generation module: used to generate a docking plan based on a heuristic algorithm; a multi-objective optimization and recommendation module: used to design a multi-objective optimization algorithm and automatically recommend the optimal plan according to the operation objectives.

[0039] In a third aspect, an embodiment of the present invention provides a computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: when the computer program is executed by the processor, any step of the method for optimizing a rail transit operation plan based on cost analysis as described in the first aspect of the present invention is implemented.

[0040] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein: when the computer program is executed by a processor, any step of the method for optimizing a rail transit operation plan based on cost analysis as described in the first aspect of the present invention is implemented.

[0041] The beneficial effects of the present invention are as follows: the present invention can effectively improve the accuracy of passenger flow prediction and avoid waste of resources by accurately identifying passenger travel patterns and passenger flow; design connection plans according to the results of travel patterns and passenger flow prediction, thereby achieving efficient utilization of transportation resources and refined management of connection plans; and through cost analysis, understand the composition of various costs and formulate reasonable optimization strategies; the rail transit operation plan optimization method based on cost analysis of the present invention realizes the comprehensive optimization of the rail transit system, so that the rail transit system can operate at a lower cost and higher efficiency, while improving the travel experience and satisfaction of passengers, and ultimately achieving the purpose of improving the overall efficiency of the rail transit system. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:

[0043] Figure 1 This is a flow chart of the rail transit operation plan optimization method based on cost analysis.

[0044] Figure 2 The structural diagram of the rail transit operation plan optimization system based on cost analysis. DETAILED DESCRIPTION

[0045] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0046] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0047] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0048] Example 1

[0049] Reference Figure 1 and Figure 2 , which is the first embodiment of the present invention, and provides a rail transit operation plan optimization method based on cost analysis, comprising the following steps:

[0050] S1: Collect traffic data and build a graphical multi-modal transportation network.

[0051] Coordinate all modes of transportation in the transportation system, including rail transit, buses, bicycle rentals, taxis, and walking / cycling, and uniformly code each mode of transportation. For example, rail transit is coded as Rr, bus is coded as Bb, bicycle rental points are coded as Cc, taxi pick-up and drop-off points are coded as Ss, and main walking / cycling routes are coded as Ww.

[0052] Identify the connection mode between each mode of transportation and determine the transfer relationship; according to the connection mode, lock the transfer relationship between each mode of transportation. For example, when a passenger transfers from rail transit Rr1 to bus Bb2, if he needs to walk Ww1 in the middle, it is recorded as Rr1→Ww1→Bb2.

[0053] Based on the transfer relationship, a multimodal transportation network connection tree is formed. When new transportation facilities (such as new subway stations, bus stops, etc.) are added, the connection tree is expanded. When the original transportation facilities are abandoned, the connection tree is reduced. When the transfer relationship changes (such as new transfer channels, etc.), the connection tree is refreshed.

[0054] The entire urban area is divided into several grids, for example, each grid is 500m×500m in size, and various transportation facilities are marked in each grid, including rail transit stations, bus stops, bicycle rental points, taxi pick-up and drop-off points, etc. Similar transportation facilities in adjacent grids are connected to form a multimodal transportation network.

[0055] It can be seen that through the construction of unified coding and connection trees, complex transportation systems can be better understood and managed, and the gridding method helps to accurately locate various types of transportation facilities, facilitating subsequent spatial analysis and optimization.

[0056] S2: Identify typical passenger travel patterns and predict passenger flow at each connection point.

[0057] S2.1: Extract passenger travel data from the multimodal transportation network and discretize and assign weights in the time dimension.

[0058] Specifically, passenger travel data is extracted from the multimodal transportation network to construct the original dataset , each record contains the following fields:

[0059]

[0060] in, is the passenger's ID, is the timestamp of the data record, is the starting position of the passenger trip, The destination of the passenger trip. The mode of transportation used by passengers during their travels. It is the place where passengers change trains during their trip;

[0061] right Perform time sorting to ensure that the data is processed in chronological order. The sorted data set is recorded as ; Divide the entire observation period into N e Time segments: Tg = {t1, t2, ..., tN e};right Each record in is assigned a corresponding time segment label, and we get ; Introduce the time decay function:

[0062]

[0063] in, is the decay rate parameter, Peak time refers to the time point when the observed data or flow reaches the maximum value within a certain time segment. The central moment of the current time segment.

[0064] for Calculate the time weight for each record in Get the weighted dataset .

[0065] S2.2: Develop a dynamic spatiotemporal clustering algorithm based on DBSCAN, introduce a time decay factor, discretize the time dimension into multiple time segments, perform spatial clustering in each time segment, and use a sliding time window technique to achieve a smooth transition of clustering results in continuous time periods.

[0066] Preferably, Define the space-time distance function for the travel trajectories of different passengers:

[0067]

[0068] Modify the neighborhood query function of DBSCAN to consider the time weight, that is:

[0069]

[0070] Determine the weighted core points:

[0071]

[0072] in, , , , They are The starting and ending coordinates of the trajectory; , , , They are The starting and ending coordinates of the trajectory; for The time coordinate of the trajectory; for The time coordinate of the trajectory; is the time weight factor; is the query point; Q is The points in the neighborhood, is the neighborhood radius; is the time weight of point Q; is the minimum time weight threshold; The minimum number of points required to become a core point.

[0073] The sliding time window clustering analysis includes: setting the sliding window size to 7 days and the step size to 1 day, executing the improved DBSCAN algorithm for each time window [ti, ti+7], and saving the clustering results; calculating the similarity of the clustering results of adjacent time windows, and setting the similarity threshold to achieve a smooth transition of the clustering results, where the time window is the specific time period selected when the sliding window moves.

[0074] Analyze the characteristics of each cluster to identify typical passenger travel modes, such as short-distance bus + walking mode, long-distance rail transit + bicycle mode, or medium-distance bus + taxi mode, and assign a unique identifier to each identified mode.

[0075] The connection point passenger flow forecast includes: pre-processing the historical passenger flow data of each connection point, and building a time series model that considers seasonal factors, cyclical factors, and trend factors, including:

[0076] Use STL decomposition to decompose the time series into trend, seasonality, and residual components, and model each component separately, such as using the SARIMA model to predict passenger flow in the short term (next 24 hours) and medium to long term (next week).

[0077] Set a passenger flow threshold. When the predicted passenger flow exceeds the threshold, the early warning mechanism is triggered. Different levels of early warnings are set according to different degrees of passenger flow predictions.

[0078] S3: Design a connection plan based on the travel pattern and passenger flow forecast results.

[0079] S3.1: Integrate travel pattern analysis with passenger flow forecasts.

[0080] Extract typical travel mode data from step S2, including: the proportion of short-distance bus + walking mode, the proportion of long-distance rail transit + bicycle mode, and the proportion of medium-distance bus + taxi mode; combined with the passenger flow prediction results, calculate the importance of the connection point including:

[0081] The connection point importance index (IPI) of connection point p is:

[0082]

[0083] in, is the weight coefficient associated with the connection point p, is the fixed value of the connection point p, n is the type of transportation, To represent the predicted passenger flow using transportation mode i to reach connection point p within the time block (j, k); all connection points are sorted from high to low according to IPI, and the connection points are divided into three levels of importance: high, medium, and low.

[0084] Time block (j, k) refers to dividing a day into multiple time periods, j represents the hour of the time block, that is, from 0 to 23, and k represents the day of the time block, that is, from 0 to 6.

[0085] S3.2: Design a hierarchical docking scheme and optimize the layout of docking points.

[0086] Specifically, if the connection point importance index > , then it is a high-importance connection point; if the connection point importance index ≤ ≤ , then it is a connection point of medium importance; if the connection point importance index < , it is a low-importance connection point;

[0087] in, and It is a threshold set according to actual conditions.

[0088] High-importance connection points include configuring full-mode transportation connections (rail, bus, bicycle, taxi), increasing the waiting area and transfer channel width, increasing the frequency of service, and reducing the average waiting time;

[0089] Medium-importance connection points include: configuring major mode transportation connections (rail, bus, bicycle), maintaining standard waiting areas and transfer channels, and maintaining regular frequency;

[0090] Low-importance transfer points include the configuration of basic modes of transportation transfer (bus, bicycle), the consideration of setting up simple waiting facilities, and adjusting the frequency of services based on actual needs.

[0091] Furthermore, for high-importance access points, ensure full-mode coverage within 500m, for medium-importance access points, ensure primary-mode coverage within 1km, and for low-importance access points, the coverage range can be appropriately increased to 1.5km.

[0092] If the distance between two low-importance connection points is less than 1 km, they will be considered for merging, and the importance level of the merged connection points will be re-evaluated.

[0093] Preferably, a time block matrix (24 hours × 7 days) is established, and for each time block, the calculation process of the demand coefficient of each transportation mode is as follows:

[0094] Assume that a day is divided into 24 hours and a week has 7 days, then the time block matrix is ​​T, where T is a 24×7 matrix, and each element represents a time block for each hour of the day and each day of the week, that is, ; Suppose there are n modes of transportation, and the demand coefficient of each mode of transportation in each time block is , where i represents the i-th mode of transportation, j represents the hour of the time block (from 0 to 23), and k represents the day of the time block (from 0 to 6).

[0095] Demand coefficient The calculation formula is:

[0096]

[0097] in, , and is the coefficient associated with transportation mode i, and is the traffic flow and population density of time block (j,k).

[0098] Formulate time-slot scheduling strategy: When 0.8 ≤ <1, maintain the current capacity; when ≥ 1, increase capacity by 10% until <1; when <0.8, reduce capacity by 10% until 0.8 ≤ <1.

[0099] It should be noted that the time-phased dispatching strategy refers to the adjustment of the carrying capacity of a certain mode of transportation in a specific time block, which specifically includes increasing or decreasing the invested transportation resources, such as the number of buses, subway trains, etc. That is, increasing the transportation capacity means increasing the invested transportation resources, and reducing the transportation capacity means reducing the invested transportation resources.

[0100] When optimizing the layout of docking points, the multimodal transportation network constructed in S1 is combined with the topological structure and connectivity of the network. For example, for high-importance docking points, ensure that their node degree (the number of other nodes directly connected to them) in the network is high to improve their accessibility and influence.

[0101] S4: Design a multi-objective optimization algorithm based on cost analysis and automatically recommend the best solution based on operational objectives.

[0102] First, construct a comprehensive cost model and potential benefit model.

[0103] Fixed costs are calculated as follows:

[0104]

[0105] Among them, FC is the total fixed cost, is the investment cost of equipment q, is the annual maintenance cost of equipment q, is the annual depreciation cost of equipment q, is the number of devices.

[0106] Variable costing:

[0107]

[0108] Where VC is the total variable cost, is the unit energy cost of transportation mode i, is the annual energy use of transport mode i, is the hourly labor cost of transportation mode i, is the number of hours worked in the year; is the unit fuel cost of transportation mode i; is the annual fuel consumption of transport mode i; Types of transportation.

[0109] Total cost calculation:

[0110] TC = FC + VC

[0111] Ticket revenue forecast:

[0112]

[0113] in, is the ticket revenue of the connecting point p, is the annual passenger flow of transportation mode i, The average ticket price.

[0114] Non-ticket revenue forecast:

[0115]

[0116] in, is the non-ticket revenue of the connection point p, is the advertising space area, For unit advertising revenue, For commercial space area, For unit rent; is the income amount of other income source K of the connection point p; Unit income of other income sources K; K is the income source; o is the total number of other income sources.

[0117] The total benefit calculation includes:

[0118]

[0119] in, is the total number of connection points.

[0120] Furthermore, the design of the multi-objective optimization algorithm includes the following contents:

[0121] Define the objective function, which includes minimizing the total operating cost Min(TC), maximizing passenger satisfaction Max(CS), minimizing the environmental impact Min(EI) and the lower limit of revenue Min(TR). The calculation of maximizing passenger satisfaction CS is as follows:

[0122]

[0123] in, is the weight of each satisfaction index, Give each satisfaction score;

[0124] The calculation formula of environmental impact EI is as follows:

[0125]

[0126] in, is the annual energy use of transport mode i, is the corresponding carbon emission factor.

[0127] The constraints include: budget limit: TC ≤ budget; lower limit of service quality: CS ≥ CSmin; upper limit of environmental impact: EI ≤ EImax; lower limit of revenue: TR ≥ TRmin; where the total operating cost is TC, the passenger satisfaction is CS, the environmental impact is EI, and the revenue is TR.

[0128] Based on the hierarchical feeder plan in S3, multiple candidate plans are generated, the objective function value OF is calculated for each candidate plan, and the top 5 plans with the highest OF values are selected for re-evaluation.

[0129] Among them, the calculation formula for the objective function value OF is as follows:

[0130]

[0131] Among them, , , and are the normalized values of TC, CS, EI, and TR, ~ 4 are the weight coefficients respectively.

[0132] For each plan entering the detailed evaluation, the following analysis is carried out:

[0133] Benefit-cost ratio analysis:

[0134] Calculate the benefit-cost ratio CBR of the plan: If CBR < 1, mark the plan as "room for improvement in economy"; if 1 ≤ CBR < 1.2, mark it as "average economy"; if CBR ≥ 1.2, mark it as "good economy".

[0135] Among them, the calculation of the benefit-cost ratio is:

[0136] CBP .

[0137] Service quality assessment:

[0138] Evaluate the passenger satisfaction CS of the plan: If CS < CSmin, mark the plan as "service quality not up to standard"; if CSmin ≤ CS < CSmin + 10%, mark it as "service quality up to standard"; if CS ≥ CSmin + 10%, mark it as "excellent service quality".

[0139] Environmental impact assessment:

[0140] Calculate the environmental impact index EI of the calculation plan: If EI > EImax, mark this plan as "exceeding the environmental impact standard"; if EImax - 10% < EI ≤ EImax, mark it as "critical environmental impact"; if EI ≤ EImax - 10%, mark it as "environmentally friendly".

[0141] Simulate the changes in passenger flow of ±10% and ±20%; simulate the situations of a 15% and 30% increase in energy costs; simulate the situations of a 5% and 10% increase in service quality requirements; for each situation, recalculate the OF value. If the change range of the OF value exceeds 20%, mark this plan as "high sensitivity"; if the change range is between 10% and 20%, mark it as "medium sensitivity"; if the change range is less than 10%, mark it as "low sensitivity".

[0142] Based on the above evaluation results, conduct a comprehensive score for each plan. The scoring criteria are as follows: Economy: Good +3 points, Average +2 points, To be improved +1 point; Service quality: Excellent +3 points, Meeting the standard +2 points, Not meeting the standard +0 points; Environmental impact: Environmentally friendly +3 points, Critical environmental impact +2 points, Exceeding the environmental impact standard +0 points; Sensitivity: Low +3 points, Medium +2 points, High +1 point; Select the plan with the highest comprehensive score as the recommended plan. When there are multiple plans with the highest comprehensive score, select the plan with the largest benefit-cost ratio as the recommended plan.

[0143] Utilize the multi-modal transportation network constructed in S1 to evaluate the overall connectivity of the network, ensuring that the optimized plan will not cause some areas to be isolated or the connectivity to be significantly reduced; calculate the average shortest path length between any two points in the network. If the optimized average path length increases significantly, mark this plan as "network efficiency to be improved"; if the average path length decreases by more than 5%, mark it as "network efficiency improved"; it is also necessary to identify the key nodes in the network (such as nodes with higher importance) to ensure that these nodes are given sufficient attention in the optimized plan.

[0144] Utilize the travel mode analysis and passenger flow prediction results in the previous steps, and through multi-objective optimization algorithms and dynamic programming methods, realize the intelligent optimization and real-time adjustment of the rail transit operation plan. At the same time, factors such as benefit-cost ratio analysis and environmental impact are also considered, making the entire plan more comprehensive and sustainable.

[0145] This embodiment also provides a rail transit operation plan optimization system based on cost analysis, including: a data collection and construction module: used to collect data and build a graphical multi-modal transportation network; a pattern recognition and passenger flow prediction module: used to identify typical passenger travel patterns, predict the passenger flow of each docking point, and analyze the key factors affecting the docking demand; a docking plan generation module: used to generate a docking plan based on a heuristic algorithm; a multi-objective optimization and recommendation module: used to design a multi-objective optimization algorithm and automatically recommend the optimal plan according to the operation objectives.

[0146] This embodiment also provides a computer device, which is suitable for the case of a rail transit operation plan optimization method based on cost analysis, including: a memory and a processor; the memory is used to store computer executable instructions, and the processor is used to execute computer executable instructions to implement the rail transit operation plan optimization method based on cost analysis proposed in the above embodiment.

[0147] The computer device may be a terminal, and the computer device includes a processor, a memory, a communication interface, a display screen and an input device connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be achieved through WIFI, an operator network, NFC (near field communication) or other technologies. The display screen of the computer device may be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device may be a touch layer covered on the display screen, or a key, trackball or touchpad provided on the housing of the computer device, or an external keyboard, touchpad or mouse, etc.

[0148] The present embodiment also provides a storage medium on which a computer program is stored. When the program is executed by a processor, the method for optimizing a rail transit operation plan based on cost analysis as proposed in the above embodiment is implemented; the storage medium can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as a static random access memory (SRAM), an electrically erasable programmable read-only memory (EEPROM), an erasable programmable read-only memory (EPROM), a programmable read-only memory (PROM), a read-only memory (ROM), a magnetic storage device, a flash memory, a disk or an optical disk.

[0149] In summary, the present invention can effectively improve the accuracy of passenger flow prediction and avoid waste of resources by accurately identifying passengers' travel patterns and passenger flow; design docking plans according to the results of travel patterns and passenger flow predictions, thereby achieving efficient utilization of transportation resources and refined management of docking plans; and through cost analysis, understand the composition of various costs and formulate reasonable optimization strategies; the rail transit operation plan optimization method based on cost analysis of the present invention realizes the comprehensive optimization of the rail transit system, so that the rail transit system can operate at a lower cost and higher efficiency, while improving passengers' travel experience and satisfaction, and ultimately achieving the purpose of improving the overall efficiency of the rail transit system.

[0150] Example 2

[0151] Referring to Table 1, which is the second embodiment of the present invention, in order to further verify the beneficial effects of the present invention, experimental data of a rail transit operation plan optimization method based on cost analysis is provided.

[0152] In the rail transit system of a large city, a rail transit operation plan optimization method based on cost analysis was applied. The city has a complex multi-modal transportation network, including subways, buses, shared bicycles, taxis and other transportation modes. In order to optimize the operating efficiency of the entire system, the following steps were adopted for optimization:

[0153] Firstly, we collected traffic data of the city within one month and constructed a graphical multimodal transportation network. Using a unified coding method, we coded rail transit as R1-R8 (8 subway lines in total), buses as B1-B200 (200 bus lines in total), bicycle rental points as C1-C500 (500 rental points in total), taxi pick-up and drop-off points as S1-S1000 (1000 pick-up and drop-off points in total), and main walking / cycling paths as W1-W2000 (2000 main walking / cycling paths in total). By analyzing the connection relationship between different transportation modes, we constructed a multimodal transportation network connection tree.

[0154] The entire urban area is divided into 10,000 500m×500m grids, various types of transportation facilities are marked in each grid, and similar transportation facilities in adjacent grids are connected to form a road network for various modes of transportation. This gridding method helps to accurately locate various types of transportation facilities, facilitating subsequent spatial analysis and optimization.

[0155] Next, we extracted passenger travel data for one month from the multimodal transportation network, totaling 10 million records. Each record contained information such as passenger ID, timestamp, departure point, destination, mode of transportation used, and transfer point. We sorted these data in chronological order and divided the entire observation period into 2,880 15-minute time segments (24 hours × 4 × 30 days). We introduced a time decay function to calculate the time weight for each record.

[0156] Dynamic spatiotemporal clustering analysis is performed based on the improved DBSCAN algorithm. The sliding time window technology is used with a window size of 7 days and a step size of 1 day. The improved DBSCAN algorithm is executed for each time window. By analyzing the clustering results, the following typical passenger travel patterns are identified:

[0157] Short-distance bus + walking mode (code: M1);

[0158] Long-distance rail transit + bicycle mode (code: M2);

[0159] Medium-distance bus + taxi mode (code: M3);

[0160] Rail transit + bus + walking mode (code: M4);

[0161] Bicycle + rail transit + walking mode (code: M5);

[0162] The historical passenger flow data of each connection point is decomposed into trend, seasonal and residual components using STL decomposition, and the SARIMA model is used to predict the passenger flow in the short term (next 24 hours) and medium to long term (next week).

[0163] Based on the travel pattern analysis and passenger flow forecast results, the mode distribution forecast of each connecting point is calculated. Taking an important connecting point P1 as an example, the mode distribution forecast during the morning rush hour (7:00-9:00) on weekdays is as follows: M1 accounts for 30%, M2 accounts for 25%, M3 accounts for 15%, M4 accounts for 20%, and M5 accounts for 10%.

[0164] An importance assessment of docking points is conducted, the importance index of docking points (IPI) is calculated, ThresholdHigh = 0.8, ThresholdLow = 0.4 is set, and docking points are divided into three levels of importance: high, medium, and low. For high-importance docking points, all-mode transportation connections are configured, the waiting area and transfer channel width are increased, and the frequency of service is improved. For medium-importance docking points, main-mode transportation connections are configured, and standard waiting areas and transfer channels are maintained. For low-importance docking points, basic-mode transportation connections are configured, and simple waiting facilities are set up.

[0165] Optimize transportation mode scheduling, establish a time block matrix (24 hours × 7 days), calculate the demand coefficient of each transportation mode, and formulate a time-phase scheduling strategy. When the demand coefficient is between 0.8-1, maintain the current capacity. When it is greater than or equal to 1, increase the capacity by 10% steps. When it is less than 0.8, reduce the capacity by 10% steps.

[0166] Based on cost analysis, a multi-objective optimization algorithm was designed, a comprehensive cost model and a potential revenue model were constructed, and fixed costs, variable costs, total costs, ticket revenue, and non-ticket revenue were calculated to decide which solution to use. Based on the above optimization method, multiple candidate solutions were generated and each candidate solution was evaluated in detail. The evaluation results are shown in the following table:

[0167] Table 1 Evaluation results

[0168]

[0169] It can be seen from the above table that Plan E is recommended as the optimal plan. This plan performs well in all aspects, especially in economic benefits and stability, achieving a high benefit-cost ratio (1.31), and also achieving a good balance in passenger satisfaction (87 points) and environmental friendliness; at the same time, its low sensitivity means that this plan has strong adaptability in the face of various uncertainties.

[0170] The successful implementation of Scheme E demonstrates the effectiveness of the rail transit operation plan optimization method based on cost analysis. By comprehensively considering multiple objective functions and constraints, this method can find the best balance between economic benefits, service quality and environmental impact.

[0171] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. A rail transit operation plan optimization method based on cost analysis, characterized in that: include: Collect traffic data and build a graphical multi-modal transportation network; Identify typical passenger travel patterns and predict passenger flow at each connection point; Design connection plans based on travel patterns and passenger flow forecasts; Design a multi-objective optimization algorithm based on cost analysis and automatically recommend the best solution based on operational objectives; The constructing of a graphical multi-modal transportation network includes: Coordinate all modes of transportation in the transportation system and uniformly code each mode of transportation; Identify the connection mode between various modes of transportation and determine the transfer relationship; according to the connection mode, lock the transfer relationship between various modes of transportation; According to the transfer relationship, a multi-modal transportation network connection tree is formed. When new transportation facilities are added, the connection tree is expanded. When the original transportation facilities are abandoned, the connection tree is reduced. When the transfer relationship changes, the connection tree is refreshed. Divide the entire urban area into several grids, mark various types of transportation facilities in each grid, and connect similar transportation facilities in adjacent grids to form a multi-modal transportation network; The identification of typical passenger travel patterns comprises the following steps: Extract passenger travel data from multimodal transportation networks and discretize and assign weights in the time dimension; Develop a dynamic spatiotemporal clustering algorithm based on DBSCAN, introduce a time decay factor, discretize the time dimension into multiple time segments, perform spatial clustering in each time segment, and use the sliding time window technology to achieve a smooth transition of clustering results in continuous time periods, including: set up Define the space-time distance function for the travel trajectories of different passengers: Modify the neighborhood query function of DBSCAN to consider the time weight, expressed as: Determine the weighted core points: in, , , , They are The starting and ending coordinates of the trajectory; , , , They are The starting and ending coordinates of the trajectory; for The time coordinate of the trajectory; for The time coordinate of the trajectory; is the time weight factor; is the query point; Q is The points in the neighborhood, is the neighborhood radius; is the time weight of point Q; is the minimum time weight threshold; The minimum number of points required to become a core point; Set the sliding window size to 7 days and the step size to 1 day, execute the improved DBSCAN algorithm for each time window, and save the clustering results; The similarity of clustering results of adjacent time windows is calculated, and a similarity threshold is set to achieve a smooth transition of clustering results, wherein the time window is a specific time period selected when the sliding window moves.

2. The method for optimizing rail transit operation plan based on cost analysis according to claim 1, characterized in that: The design process of the connection scheme is as follows: Extract typical travel mode data, combine it with passenger flow forecast results, and calculate the importance of connecting points, including: The connection point importance index IPI of the connection point p is: in, is the weight coefficient associated with the connection point p, is a fixed value, represents the predicted passenger flow using transportation mode i to reach the connecting point p in the time block (j, k), and n is the type of transportation mode; Classify the connection points and form a graded connection plan; The time block (j, k) refers to dividing a day into multiple time periods, j represents the hour of the time block, that is, from 0 to 23, and k represents the day of the time block, that is, from 0 to 6; High-importance transfer points include configuring full-mode transportation transfers, increasing the waiting area and transfer channel width, increasing the frequency of service, and reducing the average waiting time; Medium-importance connection points include configuring major mode transportation connections, maintaining standard waiting areas and transfer channels, and maintaining regular service frequencies; Low-importance transfer points include configuring basic mode transportation transfers, setting up simple waiting facilities, and adjusting the frequency of trips based on actual needs.

3. The method for optimizing rail transit operation plan based on cost analysis according to claim 2, characterized in that: The classification of the connection points includes: If the connection point importance index > , then it is a high-importance connection point; if the connection point importance index ≤ ≤ , then it is a connection point of medium importance; if the connection point importance index < , it is a low-importance connection point; in, and is the set threshold.

4. The method for optimizing rail transit operation plan based on cost analysis according to claim 3, characterized in that: The multi-objective optimization algorithm designed according to cost analysis includes: Fixed costs are calculated as follows: Among them, FC is the total fixed cost, is the investment cost of equipment q, is the annual maintenance cost of equipment q, is the annual depreciation cost of equipment q, is the number of devices; Variable cost calculation: Where VC is the total variable cost, is the unit energy cost of transportation mode i, is the annual energy use of transport mode i, is the hourly labor cost of transportation mode i, is the number of hours worked in the year; is the unit fuel cost of transportation mode i; is the annual fuel consumption of transport mode i; For the type of transportation; Total cost calculation: TC = FC + VC Ticket revenue forecast: in, is the ticket revenue of the connecting point p, is the annual passenger flow of transportation mode i, is the average ticket price; Non-ticket revenue forecast: in, is the non-ticket revenue of the connection point p, is the advertising space area, For unit advertising revenue, For commercial space area, For unit rent; is the income amount of other income source K of the connection point p; Unit income of other income sources K; K is the income source; o is the total number of other income sources; The total benefit calculation includes: in, is the total number of connection points; The objectives of the multi-objective optimization algorithm include minimizing the overall operating cost MinTC, maximizing the passenger satisfaction MaxCS, minimizing the environmental impact MinEI and the lower limit of the revenue MinTR; Among them, the total operating cost is TC, passenger satisfaction is CS, environmental impact is EI, and revenue is TR; Based on the hierarchical connection scheme, the objective function value OF is calculated for each candidate scheme: in, , , and are the normalized values ​​of TC, CS, EI and TR, ~ 4 are weight coefficients respectively; The top five solutions with the highest OF objective function values ​​are selected for re-evaluation.

5. The method for optimizing rail transit operation plan based on cost analysis according to claim 4, characterized in that: The reassessment includes: Evaluate and grade each plan based on its benefit-cost ratio, service quality and environmental impact; Simulate the situation of increased or decreased passenger flow, rising energy costs and higher service quality requirements. For each situation, recalculate the OF objective function value and classify it according to the magnitude of the change in the OF objective function value; Give each plan a comprehensive score, and select the plan with the highest comprehensive score as the recommended plan. When there are multiple plans with the highest comprehensive score, the plan with the largest benefit-cost ratio is selected as the recommended plan.

6. A rail transit operation plan optimization system based on cost analysis, executing the rail transit operation plan optimization method based on cost analysis according to any one of claims 1 to 5, characterized in that: include: Data collection and construction module: used to collect data and build a graphical multi-modal transportation network; Pattern recognition and passenger flow prediction module: used to identify typical passenger travel patterns and predict passenger flow at each connection point; The identification of typical passenger travel patterns comprises the following steps: Extract passenger travel data from multimodal transportation networks and discretize and assign weights in the time dimension; Develop a dynamic spatiotemporal clustering algorithm based on DBSCAN, introduce a time decay factor, discretize the time dimension into multiple time segments, perform spatial clustering in each time segment, and use the sliding time window technology to achieve a smooth transition of clustering results in continuous time periods, including: set up Define the space-time distance function for the travel trajectories of different passengers: Modify the neighborhood query function of DBSCAN to consider the time weight, expressed as: Determine the weighted core points: in, , , , They are The starting and ending coordinates of the trajectory; , , , They are The starting and ending coordinates of the trajectory; for The time coordinate of the trajectory; for The time coordinate of the trajectory; is the time weight factor; is the query point; Q is The points in the neighborhood, is the neighborhood radius; is the time weight of point Q; is the minimum time weight threshold; The minimum number of points required to become a core point; Set the sliding window size to 7 days and the step size to 1 day, execute the improved DBSCAN algorithm for each time window, and save the clustering results; Calculate the similarity of clustering results of adjacent time windows and set a similarity threshold to achieve a smooth transition of clustering results, wherein the time window is a specific time period selected when the sliding window moves; Connection plan generation module: used to design connection plans based on travel patterns and passenger flow forecast results; Multi-objective optimization and recommendation module: used to design multi-objective optimization algorithms and automatically recommend the best solution based on operational objectives.

Citation Information

Patent Citations

  • Rail transit station connection facility supply and demand balance optimization and adjustment method