Construction method for reconstructing existing tunnel into subway station in hard rock
By using technical means such as temporary reinforcement in the hard rock formation, precise drill cutting, static cutting of diamond rope saw and shock-absorbing holes, the problem of lack of targeted design and low construction efficiency of tunnel reconstruction construction in hard rock is solved. It significantly improves construction safety and efficiency, protects existing tunnel structures, and improves the operation level of the subway station.
Patent Information
- Application Number
- CN202411100610.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-12
AI Technical Summary
The reconstruction of existing tunnels in hard rock formations faces the problems of lack of targeted design, low construction efficiency and high safety risks. The existing technology is difficult to effectively overcome the high compressive strength and shear strength of hard rock formations, resulting in high construction difficulty , high costs and serious safety hazards.
Technical means such as temporary reinforcement of intervals, rhinestone cutting, static cutting of diamond rope saws, shock absorption hole setting and monitoring and measurement are adopted to ensure construction safety and efficiency and minimize damage to existing tunnel structures and geological disaster risks.
It improves construction safety and efficiency, protects the stability and safety of existing tunnel structures, shortens the construction cycle, reduces the probability of geological disasters, and improves the operational efficiency of subway stations and citizens' travel experience.
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a construction method for reconstructing an existing tunnel in hard rock into a subway station. Background Art
[0002] As urbanization continues to accelerate, subways are an important part of urban public transportation. Their construction and development are of great significance to alleviating urban traffic pressure and improving urban operation efficiency. However, in the process of expanding urban subway networks, due to the shortage of land resources, the reconstruction and expansion of existing tunnels (such as traffic tunnels, drainage tunnels, etc.) has become an economical and effective solution. Especially in hard rock formations, the reconstruction of existing tunnels for the construction of subway stations faces many technical challenges and engineering problems.
[0003] The demand for renovating existing tunnels into subway stations is mainly due to the need for urban planning and traffic network optimization. With the growth of urban population and the increase in traffic demand, the original tunnel structure may no longer be able to meet the new traffic function requirements, such as adding transfer stations and expanding the station hall area. At the same time, in order to improve the overall operational efficiency and service level of the subway system, it is also necessary to renovate and upgrade the existing tunnels.
[0004] Hard rock formations usually have the characteristics of high strength, high rigidity, high stress and high wear resistance, which makes tunnel construction in hard rock extremely difficult. During the reconstruction process, it is necessary to overcome the high compressive strength and shear strength of the rock while ensuring the stability and safety of the tunnel. In addition, the complexity of hard rock formations may also lead to geological disasters during the construction process, such as rock bursts and landslides, further increasing the difficulty and risk of construction.
[0005] At present, the technical research on the reconstruction of subway stations from existing tunnels in hard rock is not sufficient, and there are the following deficiencies:
[0006] 1. Lack of targeted design: Existing technologies often lack in-depth research on the characteristics of hard rock formations, resulting in a lack of targeted and scientific design solutions.
[0007] 2. Low construction efficiency: Due to the difficulty of construction in hard rock formations, existing technologies often lead to low construction efficiency, increasing construction costs and construction period.
[0008] 3. High safety risk: Tunnel reconstruction in hard rock formations has high safety risks during construction, and geological disasters and safety accidents are prone to occur.
[0009] In order to overcome the above technical difficulties, we propose a construction method for converting existing tunnels in hard rock into subway stations. Summary of the invention
[0010] In order to solve the technical problems existing in the above-mentioned prior art, the present invention proposes a construction method for reconstructing an existing tunnel in hard rock into a subway station.
[0011] The technical solution adopted by the present invention is as follows:
[0012] A construction method for converting an existing tunnel in hard rock into a subway station comprises the following steps:
[0013] Construction preparation, including site cleaning, material preparation, equipment inspection and arrangement of safety measures;
[0014] Temporary reinforcement of the section: install temporary steel frames on both sides of the tunnel that needs to be demolished, and fill the gap between the temporary steel frames and the lining concrete with concrete. The temporary steel frames can be removed only after the tunnel concrete pouring is completed and reaches 100% strength;
[0015] The portal was removed by using a water drill to cut the concrete and leaving an area for manual chiseling;
[0016] Excavation and support of the platform pilot tunnel, layout of shock-absorbing holes along the tunnel portal contour, excavation along the tunnel portal centerline, control of excavation progress, and timely arch anchor support;
[0017] The remaining portals are removed by wire saws. After the excavation of the platform pilot tunnel is completed, the remaining portals are cut statically using a diamond wire saw.
[0018] After completing the above steps, the platform lining structure is constructed.
[0019] In a further technical solution, in the temporary reinforcement step of the interval, the temporary steel frame is processed by double-pieced 25 I-beams and longitudinally connected into a whole using steel pipes to increase the support stability, and the gap between the temporary steel frame and the lining concrete is filled with C20 fine stone concrete.
[0020] In a further technical solution, during the portal removal step, a water drill uses a drill bit with a diameter of 100 mm, with a 10 mm bite between each hole, and 600 mm is reserved around the contour for manual chiseling to facilitate the later anchoring of lining steel bars.
[0021] In a further technical solution, in the door removal step, the water drill cutting method is as follows:
[0022] a. Before cutting, plan and mark the cutting part. To facilitate hoisting and transportation, the cutting block should not be larger than 1×1m. Cut in blocks, and chisel away the concrete within the planned range to expose the main reinforcement. The size of the exposed main reinforcement should be sufficient for hoisting and dragging with the clamping ring;
[0023] b. Use a water drill with φ100@90 close-packed cutting. To prevent the cutting body from losing stability and falling off naturally, a part of the cutting body is reserved for concrete. The reserved part is the plain concrete part within the longitudinal and transverse reinforcement range of the lining;
[0024] c. After cutting is completed, install the clamp ring and wire rope at the exposed main reinforcement position of the cutting body;
[0025] d. Spread 30cm of gravel and wood blocks on the bottom lining of the section within the cutting range to prevent the cut body from falling and damaging the original lining bottom slab concrete;
[0026] e. Use an excavator connected to the other end of the wire rope to drag the cutting body to separate the cutting body from the main lining structure;
[0027] f. Complete the cutting within the portal area piece by piece and transport it to the slag dump.
[0028] In a further technical solution, in the platform pilot tunnel excavation and support steps, shock-absorbing holes are arranged near the existing tunnel lining structure, and small zoned pilot tunnels are blasted first to form an open surface before outer side expansion blasting. At the same time, a smooth blasting layer is reserved for smooth surface blasting, thereby reducing the impact of blasting vibration on the existing tunnel.
[0029] In a further technical solution, in the platform guide tunnel excavation and support steps, the shock-absorbing holes are arranged in a plum blossom shape with a hole diameter of 10 cm, a spacing of 30 cm, a length of 30 m, and an overlap of 5 m between adjacent holes; the small guide tunnel is 1-2 m ahead of the main cavern excavation surface; during zone blasting, the smooth blasting detonation sequence starts from the auxiliary eye and advances layer by layer outward to the surrounding holes; mechanical excavation is used in the shock-absorbing hole area, and initial support is carried out in a timely manner.
[0030] In a further technical solution, in the platform guide tunnel excavation and support steps, the diameter of the shock-absorbing holes is 100 mm, the spacing is 300 mm, and the excavation depth each time is 50 cm.
[0031] In a further technical solution, in the remaining portal rope saw removal steps, the diamond rope saw adjusts the rope saw machine position and the position direction of the guide wheel to achieve the conversion of the diamond rope saw tension, longitudinal cutting and horizontal cutting to complete the static cutting of the portal.
[0032] In a further technical solution, a monitoring and measurement step is also included, which includes setting observation points at the arch crown, arch waist, primary support and lining structure to monitor the arch crown settlement, clearance convergence, primary support and lining stress and blasting shock velocity to ensure construction safety and quality.
[0033] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0034] Improve construction safety: Through measures such as temporary reinforcement of intervals, setting of shock-absorbing holes, and static cutting, the safety risks during the construction process are effectively reduced and the probability of geological disasters is reduced.
[0035] Protecting the existing tunnel structure: Using precisely controlled water drill cutting and static wire saw demolition technology, the damage to the existing tunnel structure is minimized, ensuring the stability and safety of the tunnel after reconstruction.
[0036] Improve construction efficiency: Through reasonable planning and careful organization of construction steps, the construction difficulty is reduced, the continuity and efficiency of the construction process are achieved, and the construction period is shortened.
[0037] Improve the construction environment: Cleaning and arranging the site during the construction preparation stage improves the cleanliness of the construction environment, which is beneficial to the physical and mental health of construction workers and improves the quality of construction.
[0038] Enhance the functionality of subway stations: The renovated subway stations can meet the needs of urban planning and transportation network optimization, improve the overall operational efficiency and service level of the subway system, and provide citizens with a more convenient and comfortable travel experience. DETAILED DESCRIPTION
[0039] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0040] A construction method for converting an existing tunnel in hard rock into a subway station comprises the following steps:
[0041] Construction preparation, including site cleaning, material preparation, equipment inspection and arrangement of safety measures;
[0042] Temporary reinforcement of the section: install temporary steel frames on both sides of the tunnel that needs to be demolished, and fill the gap between the temporary steel frames and the lining concrete with concrete. The temporary steel frames can be removed only after the tunnel concrete pouring is completed and reaches 100% strength;
[0043] The portal was removed by using a water drill to cut the concrete and leaving an area for manual chiseling;
[0044] Excavation and support of the platform pilot tunnel, layout of shock-absorbing holes along the tunnel portal contour, excavation along the tunnel portal centerline, control of excavation progress, and timely arch anchor support;
[0045] The remaining portals are removed by wire saws. After the excavation of the platform pilot tunnel is completed, the remaining portals are cut statically using a diamond wire saw.
[0046] After completing the above steps, the platform lining structure is constructed.
[0047] The above plan details a series of steps for the construction process of converting existing tunnels in hard rock into subway stations, aiming to ensure safe and efficient construction and minimize the impact on the existing tunnel structure, creating a precedent for the construction of subway stations in hard rock, and providing first-hand information for the construction of additional stations on existing subway lines in future urban development planning. It is mainly reflected in the following aspects:
[0048] Construction preparation stage: through site cleaning, material preparation, equipment inspection and safety measures, favorable conditions are created for subsequent construction. This not only ensures a clean and orderly construction environment, but also guarantees the timely supply of construction materials, the stable operation of equipment, and effectively improves the safety awareness and operation standards of construction personnel.
[0049] Temporary reinforcement measures for the section: temporary steel frames are installed on both sides of the portals that need to be demolished, and the gaps are filled with concrete to form a stable support structure. The purpose of this step is to enhance the stability of the structure around the portals before they are demolished, to prevent structural damage caused by stress concentration during the demolition process, and thus to avoid adverse effects on the reconstruction of the existing tunnel structure.
[0050] Portal demolition: Innovative water drill cutting technology is used to finely divide the portal concrete, while cleverly reserving areas for manual chiseling. The precision of water drill cutting ensures the accuracy of the cutting position and strict control of the cutting depth, minimizing the disturbance to the surrounding structures and reducing damage to the surrounding structures. The reserved manual chiseling area facilitates the subsequent fine processing of the cutting edge, ensures the demolition effect, and provides convenient conditions for the subsequent anchoring of the lining steel bars.
[0051] Platform pilot tunnel excavation and support: Shock-absorbing holes are arranged along the outline of the tunnel portal. By controlling the excavation progress and timely carrying out arch anchor support, the impact of blasting vibration on the existing tunnel is effectively reduced, and the stability of the tunnel during the excavation process is ensured. The setting of shock-absorbing holes can absorb and disperse the energy fluctuations generated by blasting, reduce the propagation range and intensity of vibration waves, ensure the stability of the tunnel during the excavation process, and improve the safety of construction.
[0052] Wire saw removal of the remaining portals: Use diamond wire saw to perform static cutting of the remaining portals. Wire saw removal has the advantages of high precision, low vibration, and little impact on the existing structure. It can ensure the smooth removal of the portals, help protect the safety of infrastructure such as buildings, roads and pipelines around the portals, and minimize damage to the portals and surrounding structures, reducing repair costs.
[0053] Platform lining structure construction: After completing the above steps, the platform lining structure construction is carried out. As one of the core links in the construction of subway stations, the construction quality of the platform lining structure is directly related to the use function and long-term safety of the subway station. Therefore, the construction at this stage must strictly follow the design requirements and construction specifications to ensure the accuracy of each process and the excellence and reliability of the overall quality.
[0054] According to this method of construction, the beneficial effects that can be obtained are as follows:
[0055] Improve construction safety: Through measures such as temporary reinforcement of intervals, setting of shock-absorbing holes, and static cutting, the safety risks during the construction process are effectively reduced and the probability of geological disasters is reduced.
[0056] Protecting the existing tunnel structure: Using precisely controlled water drill cutting and static wire saw demolition technology, the damage to the existing tunnel structure is minimized, ensuring the stability and safety of the tunnel after reconstruction.
[0057] Improve construction efficiency: Through reasonable planning and careful organization of construction steps, the construction difficulty is reduced, the continuity and efficiency of the construction process are achieved, and the construction period is shortened.
[0058] Improve the construction environment: Cleaning and arranging the site during the construction preparation stage improves the cleanliness of the construction environment, which is beneficial to the physical and mental health of construction workers and improves the quality of construction.
[0059] Enhance the functionality of subway stations: The renovated subway stations can meet the needs of urban planning and transportation network optimization, improve the overall operational efficiency and service level of the subway system, and provide citizens with a more convenient and comfortable travel experience.
[0060] In this embodiment, in the temporary reinforcement step of the interval, the temporary steel frame is processed by double-jointed 25 I-beams and longitudinally connected into a whole using steel pipes to increase the support stability, and the gap between the temporary steel frame and the lining concrete is filled with C20 fine stone concrete.
[0061] With this reinforcement method, the cooperation of the double-jointed 25 I-beam temporary steel frame and the steel pipe forms a stable support system, which enables the entire structure to show higher resistance and reliability when dealing with the complex loads generated during construction and the dynamic stress during the demolition process. In the treatment of the gap between the temporary steel frame and the existing lining concrete, C20 fine stone concrete was selected for filling. Due to its fine particles and good fluidity, this concrete can be filled more tightly into a small space, reducing the existence of voids and gaps. At the same time, the strength grade of C20 fine stone concrete also ensures that the filling layer can have a certain bearing capacity after curing, further enhancing the overall stability of the supporting structure. In addition, the design of the temporary steel frame and steel pipe takes into account the convenience of demolition and the recycling of materials. After the construction is completed, these temporary structures can be dismantled relatively easily, and their materials have a high recycling value, which is in line with the concept of green construction and sustainable development.
[0062] In this embodiment, in the tunnel door removal step, a water drill uses a drill bit with a diameter of 100 mm, with a 10 mm bite between each hole, and 600 mm is reserved around the contour for manual chiseling to facilitate the later anchoring of lining steel bars.
[0063] During the demolition of the portal, a drill with a diameter of 100mm was selected for precise drilling. This size of drill ensures the accuracy and efficiency of drilling. In order to ensure the continuity and stability of the cutting surface, a 10mm bite part between the holes was specially designed, which can effectively prevent the fragments from falling off or the structure from loosening during the cutting process. At the same time, in order to take into account the convenience of later construction and the stability of the lining structure, a 600mm wide area was reserved around the outline of the portal for manual chiseling. This step not only provides more flexible operating space for construction personnel, but more importantly, it enables the anchoring of the lining steel bars in the later stage to be carried out more smoothly and accurately, thereby enhancing the structural safety and stability of the entire reconstruction project. This combination of water drill cutting and manual chiseling has shown significant advantages in effectively controlling the demolition scope, protecting the existing structure, improving construction efficiency and quality, and reducing construction risks and costs.
[0064] In this embodiment, in the door removal step, the water drill cutting method is as follows:
[0065] a. Before cutting, plan and mark the cutting part. To facilitate hoisting and transportation, the cutting block should not be larger than 1×1m. Cut in blocks, and chisel away the concrete within the planned range to expose the main reinforcement. The size of the exposed main reinforcement should be sufficient for hoisting and dragging with the clamping ring;
[0066] b. Use a water drill with φ100@90 close-packed cutting. To prevent the cutting body from losing stability and falling off naturally, a part of the cutting body is reserved for concrete. The reserved part is the plain concrete part within the longitudinal and transverse reinforcement range of the lining;
[0067] c. After cutting is completed, install the clamp ring and wire rope at the exposed main reinforcement position of the cutting body;
[0068] d. Spread 30cm of gravel and wood blocks on the bottom lining of the section within the cutting range to prevent the cut body from falling and damaging the original lining bottom slab concrete;
[0069] e. Use an excavator connected to the other end of the wire rope to drag the cutting body to separate the cutting body from the main lining structure;
[0070] f. Complete the cutting within the portal area piece by piece and transport it to the slag dump.
[0071] The water drill cutting technology used in the tunnel door removal step has the following beneficial effects:
[0072] Precise planning and cutting: The planning and marking before cutting ensures the accuracy of the cutting operation, avoiding unnecessary material waste and structural damage. At the same time, the cutting block is controlled within the range of no more than 1×1m, which is convenient for subsequent lifting and transportation, and improves construction efficiency.
[0073] Structural stability guarantee: During the cutting process, by reserving some plain concrete, mainly within the range of the longitudinal and transverse reinforcement of the lining, the natural instability and falling off of the cutting body is effectively prevented, ensuring the structural safety during the construction process.
[0074] Convenience of lifting: The size of the exposed main reinforcement has been carefully designed to meet the needs of lifting and dragging clamps, so that the cutting body can be lifted and transported easily and safely, reducing the investment of manpower and material resources.
[0075] Perfect protection measures: 30cm thick gravel is laid on the bottom lining of the section within the cutting range and wooden planks are placed. This measure effectively prevents the damage to the original lining bottom concrete that may be caused by the falling of the cutting body, and protects the integrity of the existing structure.
[0076] Efficient separation and cleaning: The excavator is connected to the wire rope to drag the cutting body, which realizes the rapid and safe separation of the cutting body from the main lining structure. Afterwards, the cutting body within the tunnel gate is separated piece by piece and shipped to the slag yard, ensuring the cleanliness and orderliness of the construction site.
[0077] In summary, the water drill cutting technology solution demonstrated multiple advantages such as accuracy, safety, convenience and efficiency during the portal demolition process, providing a strong guarantee for the smooth progress of the entire reconstruction project.
[0078] It is worth mentioning that during the implementation of the water diamond cutting technology plan, the following safety precautions should be strictly implemented:
[0079] (1) A safety fence is set up within the cutting range and guarded by a dedicated person. Unauthorized persons are prohibited from entering.
[0080] (2) Climbers should be equipped with safety ropes, safety helmets, non-slip shoes and other safety protection equipment.
[0081] (3) Cut off piece by piece from top to bottom in the order of cutting. Do not cut off the whole piece, do not cut it up and down at the same time, and do not cut it in reverse from bottom to top. The main reinforcement must be chiseled out before cutting.
[0082] (4) When using an excavator to tow, drag slowly and evenly, and continue to pay attention to the changes in the force on the wire rope and the connecting clip. It is strictly forbidden to impact or pull violently.
[0083] (5) All irrelevant personnel must evacuate during the towing process.
[0084] (6) When the wire rope and the clamp are subjected to excessive force during dragging and the cutting body does not fall off, stop dragging and only carry out inspection after an excavator supports the cutting body.
[0085] In this embodiment, in the platform pilot tunnel excavation and support steps, shock-absorbing holes are arranged near the existing tunnel lining structure, and small partitioned pilot tunnels are blasted first to form an open surface before outer expansion blasting is carried out. At the same time, a smooth blasting layer is reserved for smooth surface blasting, so as to reduce the impact of blasting vibration on the existing tunnel.
[0086] The setting of shock-absorbing holes can effectively absorb and disperse the energy generated by blasting, significantly reduce the impact of blasting vibration on the existing tunnel lining structure, and reduce the safety risks in the construction process by reducing the impact of blasting vibration on the existing tunnel, thus ensuring the safety of construction workers. The blasting of small pilot holes in different areas can form an open surface in advance, providing favorable conditions for the subsequent blasting of the outer side, so that the blasting energy can be better released and utilized. Through blasting in different areas, large-scale blasting operations can be decomposed into multiple small-scale blasting operations, which is conducive to controlling the scale of blasting and reducing the impact of a single blasting on the existing tunnel. In addition, the smooth blasting technology can reduce the disturbance to the surrounding rock, keep the excavation surface flat and smooth, thereby reducing the damage to the existing tunnel lining structure. Smooth blasting can reduce the amount of over-excavation and under-excavation, improve the excavation accuracy and construction quality, and provide better conditions for the subsequent support and lining construction. The comprehensive application of the above measures can significantly reduce the impact of blasting construction on the existing tunnel lining structure and protect its structural safety and stability.
[0087] In this embodiment, in the platform pilot tunnel excavation and support steps, the shock-absorbing holes are arranged in a plum blossom shape with a hole diameter of 10 cm, a spacing of 30 cm, a length of 30 m, and an overlap of 5 m between adjacent holes; the small pilot tunnel is 1-2 m ahead of the main cavern excavation surface; during zone blasting, the smooth blasting detonation sequence starts from the auxiliary eye and advances layer by layer outward to the surrounding holes; mechanical excavation is used in the shock-absorbing hole area, and initial support is carried out in a timely manner.
[0088] Through the above design, the shock-absorbing holes are arranged in a plum blossom shape, with a hole diameter of 10cm and a spacing of 30cm. This arrangement can absorb and disperse the energy generated by blasting to the maximum extent, effectively reduce the impact of blasting vibration on the existing tunnel lining structure, and protect its structural safety. The length of the shock-absorbing holes is 30m, and the overlap between adjacent holes is 5m. This design can form a stable shock-absorbing area, further improve the shock-absorbing effect, and enhance the stability of the excavation area. The small pilot hole is excavated 1-2m ahead of the main cavern excavation surface, which can form an open surface in advance, provide favorable conditions for subsequent blasting operations, and enable better release and utilization of blasting energy. In addition, during zone blasting, the smooth surface blasting detonation sequence starts from the auxiliary hole and advances outward layer by layer to the surrounding holes. This detonation sequence can reduce the disturbance of blasting vibration to the surrounding rock and keep the excavation surface flat and smooth. Mechanical excavation is used in the shock-absorbing hole area to avoid the potential impact of blasting operations on the area. Timely initial support can quickly reinforce the excavation area, improve the stability of the excavation surface, and provide safety guarantees for subsequent construction.
[0089] In this embodiment, in the platform guide tunnel excavation and support steps, the diameter of the shock-absorbing holes is 100 mm, the spacing is 300 mm, and the excavation depth each time is 50 cm.
[0090] The diameter of the shock-absorbing holes is 100mm, and the spacing is 300mm. The reasonable arrangement of the diameter and spacing of the shock-absorbing holes can form an effective shock-absorbing area, fully absorb and disperse the energy generated by the blasting, and significantly reduce the impact of the blasting vibration on the existing tunnel lining structure. Each excavation advance is 50cm. This small advance excavation method is conducive to controlling the excavation accuracy, reducing over-excavation and under-excavation, maintaining the flatness and verticality of the excavation surface, allowing the support operation to keep up with the excavation surface, and timely reinforce and support the excavation area to improve the overall support effect.
[0091] In this embodiment, in the remaining portal wire saw removal steps, the diamond wire saw achieves the conversion of tensioning, longitudinal cutting and horizontal cutting of the diamond wire saw by adjusting the position of the wire saw machine and the position direction of the guide wheel to complete the static cutting of the portal.
[0092] By using a diamond wire saw, the position of the wire saw machine and the position and direction of the guide wheel can be adjusted to achieve the tension of the diamond wire saw, the conversion between longitudinal cutting and horizontal cutting, so as to complete the static cutting of the tunnel portal. It is not only highly flexible and can accurately control the cutting direction, but also can operate continuously to improve construction efficiency.
[0093] In this embodiment, a monitoring and measurement step is also included, which includes setting observation points at the arch crown, arch waist, primary support and lining structure to monitor the arch crown settlement, clearance convergence, primary support and lining stress and blasting shock velocity to ensure construction safety and quality.
[0094] Setting up observation points to monitor the settlement of the arch, the convergence of clearance, the stress of the initial support and lining, and the blasting shock velocity is of great significance and role in tunnel construction. It can not only timely discover and warn of potential risks, optimize construction plans and support parameters, improve construction quality and efficiency, and ensure the safety of construction personnel, but also ensure that the construction process complies with specifications and standards.
[0095] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the specification of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A construction method for converting an existing tunnel in hard rock into a subway station, characterized in that: The following steps are involved: Construction preparation, including site cleaning, material preparation, equipment inspection and arrangement of safety measures; Temporary reinforcement of the section: install temporary steel frames on both sides of the tunnel that needs to be demolished, and fill the gap between the temporary steel frames and the lining concrete with concrete. The temporary steel frames can be removed only after the tunnel concrete pouring is completed and reaches 100% strength; The portal was removed by using a water drill to cut the concrete and leaving an area for manual chiseling; Excavation and support of the platform guide tunnel, layout of shock-absorbing holes along the outline of the tunnel portal, excavation along the centerline of the tunnel portal, control of excavation progress, and timely implementation of arch spraying and anchor support; The remaining portals are removed by wire saws. After the excavation of the platform pilot tunnel is completed, the remaining portals are cut statically using a diamond wire saw. After completing the above steps, the platform lining structure is constructed.
2. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the temporary reinforcement step of the interval, the temporary steel frame is processed by double-piece 25 I-beams and connected longitudinally into a whole using steel pipes to increase the support stability, and the gap between the temporary steel frame and the lining concrete is filled with C20 fine stone concrete.
3. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the tunnel gate removal step, a water drill uses a drill bit with a diameter of 100 mm, with a 10 mm bite between each hole, and 600 mm is reserved around the contour for manual chiseling to facilitate the later anchoring of the lining steel bars.
4. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the above-mentioned door removal step, the water drill cutting method is as follows: a. Before cutting, plan and mark the cutting part. To facilitate hoisting and transportation, the cutting block should not be larger than 1×1m. Cut in blocks, and chisel away the concrete within the planned range to expose the main reinforcement. The size of the exposed main reinforcement should be sufficient for hoisting and dragging with the clamping ring; b. Use a water drill with φ100@90 close-packed cutting. To prevent the cutting body from losing stability and falling off naturally, a part of the cutting body is reserved for concrete. The reserved part is the plain concrete part within the longitudinal and transverse reinforcement range of the lining; c. After cutting is completed, install the clamp ring and wire rope at the exposed main reinforcement position of the cutting body; d. Spread 30cm of gravel and wood blocks on the bottom lining of the section within the cutting range to prevent the cut body from falling and damaging the original lining bottom slab concrete; e. Use an excavator connected to the other end of the wire rope to drag the cutting body to separate the cutting body from the main lining structure; f. Complete the cutting within the portal area piece by piece and transport it to the slag dump.
5. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the platform guide tunnel excavation and support steps, shock-absorbing holes are arranged near the existing tunnel lining structure, and small zoned guide tunnels are blasted first to form an open surface before outer side expansion blasting. At the same time, a smooth blasting layer is reserved for smooth surface blasting, so as to reduce the impact of blasting vibration on the existing tunnel.
6. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 5, characterized in that: In the platform guide tunnel excavation and support steps, the shock-absorbing holes are arranged in a plum blossom shape with a hole diameter of 10 cm, a spacing of 30 cm, a length of 30 m, and an overlap of 5 m between adjacent holes; the small guide tunnel is 1-2 m ahead of the main cavern excavation surface; during zone blasting, the smooth blasting detonation sequence starts from the auxiliary eye and advances layer by layer outward to the surrounding holes; mechanical excavation is used in the shock-absorbing hole area, and initial support is carried out in a timely manner.
7. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the platform guide tunnel excavation and support steps, the diameter of the shock-absorbing holes is 100 mm, the spacing is 300 mm, and the excavation depth each time is 50 cm.
8. The construction method for converting an existing tunnel in hard rock into a subway station according to claim 1, characterized in that: In the remaining steps of removing the portal rope saw, the diamond rope saw realizes the tensioning of the diamond rope saw and the conversion of longitudinal cutting and horizontal cutting by adjusting the position of the rope saw machine and the position direction of the guide wheel to complete the static cutting of the portal.
9. A construction method for converting an existing tunnel in hard rock into a subway station according to any one of claims 1 to 8, characterized in that: It also includes a monitoring and measurement step, which includes setting observation points at the arch crown, arch waist, primary support and lining structure to monitor the arch crown settlement, clearance convergence, primary support and lining stress and blasting shock velocity to ensure construction safety and quality.