Mooring unmanned aerial vehicle cooperative photovoltaic power station assembly installation system and method

By coordinating the tethered drone with the photovoltaic power plant component installation system and utilizing drones with high-precision positioning and communication modules, the efficient handling and installation of photovoltaic modules is achieved, solving the low efficiency and manpower requirements in the construction of photovoltaic power plants in complex environments. problems and reduce construction risks.

CN118723148APending Publication Date: 2024-10-01GUANGDONG SOUTHERN PLANNING & DESIGNING INST OF TELECOM CONSULTATION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410872451.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-01
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

During the construction of photovoltaic power plants, especially in complex environments such as mountains, water, and desert Gobi, there are difficulties in transporting and installing photovoltaic modules, resulting in low construction efficiency and large demand for personnel, which increases construction risks.

Method used

The tethered drone is used to coordinate the photovoltaic power station component installation system, including drones equipped with outdoor high-precision positioning modules, outdoor communication modules and collaborative control modules, through the drone's automatic cable retractor, component pickup device and remote control command center , realizes efficient handling and installation of photovoltaic modules, can position and coordinate control with centimeter-level accuracy, has a load capacity of more than 60 kilograms, and is equipped with obstacle avoidance cameras and backup batteries to ensure the safety and efficiency of installation.

Benefits of technology

It greatly improves the efficiency of photovoltaic power station construction, reduces the operational risks of construction personnel, is highly adaptable, and can efficiently complete the transportation and installation of components in different scenarios, solving the difficulties and risks of manual transportation in traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118723148A_ABST
    Figure CN118723148A_ABST
Patent Text Reader

Abstract

The system comprises the mooring unmanned aerial vehicle, an unmanned aerial vehicle automatic cable take-up and pay-off disc, an unmanned aerial vehicle power supply transfer box, an unmanned aerial vehicle assembly pickup device, an assembly pickup table, a photovoltaic assembly, photovoltaic support rows and columns and a remote control command center. The mooring unmanned aerial vehicle is provided with an outdoor high-precision positioning module, an outdoor communication module and a cooperative control module, a mooring cable of the mooring unmanned aerial vehicle is wound and unwound through an unmanned aerial vehicle automatic cable winding and unwinding disc, and a cable plug of the unmanned aerial vehicle automatic cable winding and unwinding disc is inserted into an unmanned aerial vehicle power supply transfer box. According to the system and method for installing the mooring unmanned aerial vehicle and the photovoltaic power station assembly, on one hand, the problem that the photovoltaic assembly is difficult to carry in the current mountainous region and mud flat photovoltaic power station construction scene can be solved, and on the other hand, the installation efficiency can be greatly improved in the large-scale base photovoltaic power station construction project; and meanwhile, the labor intensity of construction workers can be greatly reduced, and the engineering construction safety degree is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of photovoltaic power station construction, and in particular to a system and method for installing photovoltaic power station components in coordination with a tethered unmanned aerial vehicle. Background Art

[0002] With the continuous advancement of the country's dual-carbon strategy, the scale of photovoltaic power station construction has grown rapidly year by year. Among them, large-scale photovoltaic power stations are large in scale and have complex construction conditions. For example, the mountain slope is large, the construction of photovoltaic power stations on water is difficult, and the photovoltaic climate conditions in the desert Gobi are harsh, which restricts the construction efficiency. In particular, the transportation and installation of photovoltaic components bring a lot of difficulties and large-scale manpower. There is an urgent need to use new technologies and new tools to overcome difficulties and improve efficiency. Summary of the invention

[0003] The purpose of the present invention is to provide a system and method for installing photovoltaic power station components in coordination with a tethered drone, so as to solve the problems raised in the above-mentioned background technology.

[0004] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a system and method for tethered drones to coordinate the installation of photovoltaic power station components, comprising a tethered drone, a drone automatic cable retractable disk, a drone power adapter box, a drone component picking device, a component picking platform, photovoltaic components, photovoltaic bracket arrays and a remote control command center, the tethered drone is configured with an outdoor high-precision positioning module, an outdoor communication module, and a collaborative control module, the tethered cable of the tethered drone is retracted and released through the drone automatic cable retractable disk, the cable plug of the drone automatic cable retractable disk is inserted into the drone power adapter box, and the drone power adapter box is connected to a power source nearby, the tethered drone, after hanging the drone component picking device, flies to the top of the component picking platform to automatically / manually assist in picking up photovoltaic components, carries the photovoltaic components to the position above the corresponding photovoltaic bracket array according to the drone planned flight route planned by the control module, and automatically / manually assists in placing the photovoltaic components.

[0005] Preferably, the tethered UAV uses an outdoor high-precision positioning module to achieve centimeter-level positioning based on Beidou / GPS / wireless private network. The tethered UAV uses an outdoor communication module to communicate with the remote control command center: upload / download data and instructions. The tethered UAV collaborative control module controls the flight route, status, and parameters of the UAV according to stored planning instructions, the UAV's planned flight route, or instructions received in real time.

[0006] Preferably, the tethered drone collaborative control module stores system information such as the center position and altitude of the component picking platform, the round-trip flight path and altitude, the center line position and altitude of the photovoltaic bracket rows, the order of photovoltaic component placement rows, the initial position, the end position and the interval according to the actual longitude and latitude.

[0007] Preferably, the tethered drone has a load capacity greater than 60 kg, and a drone component picking device is hung underneath. The drone component picking device has a swing angle of less than 5 degrees. The drone component picking device is divided into left and right arms, and the two arms grab from the direction of the short side of the photovoltaic component respectively. Two sets of grabbing palms are provided at the bottom of the two arms, and the interval between the two sets of grabbing is 40 cm. Anti-slip suction cups are provided on the grabbing palms.

[0008] Preferably, the photovoltaic module should be placed on a module picking table, and the grid lines or reference lines at corresponding positions of the photovoltaic module should coincide with the supporting positions of the module picking table, ensuring that the center of the photovoltaic module deviates from the center of the module picking table by less than 5 cm.

[0009] A method for installing a system for installing photovoltaic power station components in cooperation with a tethered drone. The photovoltaic components should be placed on a component picking table before being grabbed by a tethered drone. The grid lines or reference lines at the corresponding positions of the photovoltaic components should coincide with the supporting positions of the component picking table to ensure that the center of the photovoltaic component deviates from the center of the component picking table by less than 5 centimeters.

[0010] Preferably, the tethered drone can grab photovoltaic modules in sequence according to the planned route and sequence within the allowable range of the tethered cable length, and place them on the rows of brackets; the tethered drone is equipped with an obstacle avoidance camera, a backup battery and an over-load circuit breaker mechanism, and can be physically disconnected from the tethered cable in emergencies or situations and still have the ability and power to balance and avoid obstacles for more than 15 minutes.

[0011] Compared with the prior art, the beneficial effects of the present invention are: the present invention has strong adaptability, which can meet the requirements of efficient transportation and installation of components in conventional photovoltaic power station scenarios, and can also solve the problems of difficult transportation of photovoltaic components in mountainous areas and tidal flats and large number of personnel requirements, thereby greatly improving the efficiency of station construction, and at the same time reducing the operating risks of construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a structural schematic diagram of the present invention;

[0013] Figure 2 It is a configuration diagram of the tethered drone of the present invention.

[0014] In the figure: 1. Tethered drone; 2. Drone component picking device; 3. Component picking platform; 4. Photovoltaic component; 5. Power supply; 6. Drone power adapter box; 7. Drone automatic cable retractable tray; 8. Array of photovoltaic brackets; 9. Drone flight route planning; 10. Remote control command center. DETAILED DESCRIPTION

[0015] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0016] See also Figure 1-2 The present invention provides a system and method for installing photovoltaic power station components in coordination with a tethered drone, including a tethered drone 1, a drone automatic cable retracting tray 7, a drone power adapter box 6, a drone component picking device 2, a component picking platform 3, a photovoltaic component 4, a photovoltaic bracket array 8 and a remote control command center 10. The tethered drone 1 is configured with an outdoor high-precision positioning module, an outdoor communication module, and a coordinated control module. The tethered cable of the tethered drone 1 is retracted and released through the drone automatic cable retracting tray 7, and the cable plug of the drone automatic cable retracting tray 7 is inserted into the drone power adapter box 6. The drone power adapter box 6 is connected to a power source 5 nearby. After the tethered drone 1 is hung with the drone component picking device 2, it flies to the top of the component picking platform 3 to automatically / manually assist in picking up the photovoltaic component 4, and carries the photovoltaic component 4 to the corresponding position above the photovoltaic bracket array 8 according to the drone planned flight route 9 planned by the control module, and automatically / manually assists in placing the photovoltaic component 4.

[0017] The tethered drone 1 uses an outdoor high-precision positioning module to achieve centimeter-level positioning based on Beidou / GPS / wireless private network. The tethered drone 1 uses an outdoor communication module to communicate with the remote control command center 10: upload / download data and instructions. The tethered drone 1 collaborative control module controls the flight route, status, and parameters of the drone according to the stored planning instructions, the drone's planned flight route 9, or the instructions received in real time.

[0018] The collaborative control module of the tethered drone 1 stores system information such as the center position and altitude of the component picking platform 3, the round-trip flight path and altitude, the center line position and altitude of the photovoltaic support row 8, the placement row order, initial position, end position and interval of the photovoltaic components 4 according to the actual longitude and latitude.

[0019] The tethered drone 1 has a load-carrying capacity greater than 60 kg, and a drone component picking device 2 is hung underneath. The drone component picking device 2 has a swing angle of less than 5 degrees. The drone component picking device 2 is divided into left and right arms, and the two arms grab from the direction of the short side of the photovoltaic component 4 respectively. Two sets of grabbing palms are provided at the bottom of the two arms, and the interval between the two sets of grabbing is 40 cm. Anti-slip suction cups are provided on the grabbing palms.

[0020] The photovoltaic module 4 should be placed on the module picking platform 3, and the grid line or reference line at the corresponding position of the photovoltaic module 4 should coincide with the supporting position of the module picking platform 3, ensuring that the center of the photovoltaic module 4 deviates from the center of the module picking platform 3 by less than 5 cm.

[0021] A method for installing a system for installing photovoltaic power station components in cooperation with a tethered drone. The photovoltaic component 4 should be placed on a component picking platform 3 before being grabbed by a tethered drone 1. The grid line or reference line at the corresponding position of the photovoltaic component 4 should coincide with the support position of the component picking platform 3 to ensure that the center of the photovoltaic component 4 deviates from the center of the component picking platform 3 by less than 5 cm.

[0022] The tethered drone 1 can grab the photovoltaic modules 4 in sequence according to the planned route and sequence within the allowable range of the tethered cable length, and place them on the support rows; the tethered drone 1 is equipped with an obstacle avoidance camera, a backup battery and an over-load circuit breaker mechanism. In the event of an emergency or situation, it can be physically disconnected from the tethered cable and still have the ability and power to balance and avoid obstacles for more than 15 minutes.

[0023] When the embodiment of the present application is in use: before the photovoltaic components 4 are installed, it should be ensured that the rows and columns of photovoltaic brackets 8 in the installation sub-area (including six rows and columns in this example) have completed the installation of brackets and guide rails, and the remote control command center 10 should set the position of the component picking table 3 (the picking table should be preferably set on the maintenance channel of the photovoltaic array), the planned flight route 9 of the drone, and the flight status and parameters of the tethered drone 1 for picking up and releasing items according to the position planning of the photovoltaic array; the component picking table 3 is set at the corresponding position according to the planned position and the corresponding number of photovoltaic components 4 in the installation sub-area are placed next to it; the power supply 5, the drone power adapter box 6 and the drone automatic cable collection and release tray 7 are set in the same maintenance channel of the component picking table 3 according to the planned flight route 9 of the drone; the drone automatic cable collection and release tray 7 should be placed above the power supply 5 and the drone power adapter box 6 to avoid the power supply 5 and the drone power adapter box 6 from forming obstacles to the tethered cable; the tethered drone 1 takes off close to the drone automatic cable collection and release tray 7, and before takeoff The drone component picking device 2 should be installed, the cable should be connected to the drone automatic cable retracting disk 7, and the planning instruction data in the remote control command center 10 should be synchronized; after the tethered drone 1 takes off, it will execute the planned task, fly along the maintenance channel to the set position above the component picking platform 3, hover after positioning, release the grabbing arm of the drone component picking device 2, automatically / manually assist in grabbing the photovoltaic component 4 placed on the component picking platform 3, lock the grabbing arm and grabbing palm and then lift off to the planned height, and fly along the photovoltaic array maintenance channel to the planned position above the photovoltaic bracket row 8 in the installation area according to the drone's planned flight route 9, lower the flight altitude to the planned altitude and hover, release the lock of the grabbing arm and grabbing palm with automatic / manual assistance, and place the photovoltaic component 4; after placement, the tethered drone 1 will be lifted to the planned height and return to the component picking platform 3 along the original route to continue to complete the grabbing, transportation and placement of the next photovoltaic component 4, until all photovoltaic components 4 in this planned area have been placed, and the tethered drone 1 returns to the take-off position.

[0024] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A system for installing photovoltaic power station components in coordination with a tethered drone, comprising a tethered drone (1), a drone automatic cable retracting tray (7), a drone power adapter box (6), a drone component picking device (2), a component picking platform (3), a photovoltaic component (4), a photovoltaic bracket array (8) and a remote control command center (10), characterized in that: The tethered drone (1) is equipped with an outdoor high-precision positioning module, an outdoor communication module, and a collaborative control module. The tethered cable of the tethered drone (1) is retracted and released by a drone automatic cable retracting and releasing disk (7). The cable plug of the drone automatic cable retracting and releasing disk (7) is inserted into a drone power adapter box (6). The drone power adapter box (6) is connected to a power source (5) nearby. After the drone component picking device (2) is hung below, the tethered drone (1) flies above the component picking platform (3) to automatically / manually assist in picking up the photovoltaic component (4). The tethered drone (1) carries the photovoltaic component (4) and flies to a position above the corresponding photovoltaic support row (8) according to the drone planned flight route (9) planned by the control module, and automatically / manually assists in placing the photovoltaic component (4).

2. A system for installing tethered drones in cooperation with photovoltaic power station components according to claim 1, characterized in that: The tethered drone (1) uses an outdoor high-precision positioning module to achieve centimeter-level positioning based on Beidou / GPS / wireless private network. The tethered drone (1) uses an outdoor communication module to communicate with a remote control command center (10): upload / download data and instructions. The tethered drone (1) cooperative control module controls the flight route, status, and parameters of the drone according to stored planning instructions, the drone's planned flight route (9), or instructions received in real time.

3. The system for installing tethered drones in cooperation with photovoltaic power station components according to claim 1, characterized in that: The tethered drone (1) cooperative control module stores system information such as the center position and altitude of the component picking platform (3), the round-trip flight path and altitude, the center line position and altitude of the photovoltaic support array (8), the photovoltaic component (4) placement array sequence, initial position, end position and interval according to the actual longitude and latitude.

4. A system for installing tethered drones in cooperation with photovoltaic power station components according to claim 1, characterized in that: The tethered drone (1) has a load capacity of more than 60 kilograms, and a drone component picking device (2) is hung below, the drone component picking device (2) has a swing angle of less than 5 degrees, and the drone component picking device (2) is divided into left and right arms, and the two arms grab from the direction of the short side of the photovoltaic component (4) respectively, and two groups of grabbing palms are provided at the bottom of the two arms, and the two groups of grabbing are spaced 40 centimeters apart, and anti-slip suction cups are provided on the grabbing palms.

5. The system for installing tethered drones in cooperation with photovoltaic power station components according to claim 1, characterized in that: The photovoltaic module (4) should be placed on the module picking platform (3), and the grid line or reference line at the corresponding position of the photovoltaic module (4) should coincide with the supporting position of the module picking platform (3), ensuring that the center of the photovoltaic module (4) deviates from the center of the module picking platform (3) by less than 5 centimeters.

6. A method for installing a system for installing tethered drones in cooperation with photovoltaic power station components according to any one of claims 1 to 5, characterized in that: The photovoltaic module (4) should be placed on the module picking platform (3) before being grabbed by the tethered drone (1), and the grid lines or reference lines at the corresponding positions of the photovoltaic module (4) should coincide with the supporting positions of the module picking platform (3), ensuring that the center of the photovoltaic module (4) deviates from the center of the module picking platform (3) by less than 5 centimeters.

7. The method for installing a system for installing tethered drones in cooperation with photovoltaic power station components according to claim 6, characterized in that: The tethered drone (1) can sequentially grab photovoltaic modules (4) according to a planned route and sequence within the permitted length range of the tethered cable, and place them on the support array; the tethered drone (1) is equipped with an obstacle avoidance camera, a backup battery, and an overload circuit breaker mechanism, and can be physically disconnected from the tethered cable in the event of an emergency or situation and still have the ability and power to balance and avoid obstacles for more than 15 minutes.