Integral moving construction method for cast-in-place segmental beam bottom die of arched beam combination bridge
By using hanging basket construction and sliding form technology in the construction of the arch-beam composite bridge, the problem of slow construction progress of the upper chord beam was solved, the synchronous construction of the upper chord beam and the lower chord arch was realized, and the construction efficiency and stability were improved.
Patent Information
- Application Number
- CN202410900426.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2024-10-01
AI Technical Summary
During the construction process of the arch-beam composite bridge, the construction progress of the upper chord beam was slow, and it was difficult to ensure the simultaneous construction of the upper chord beam and the lower chord arch, resulting in a delay in the overall progress.
The cast-in-place segment beam bottom formwork of the arch-girder composite bridge is adopted as an integral mobile construction method, and the hanging basket construction and sliding form technology are used to realize the rapid construction of the upper chord beam, including the erection of brackets and upper chord formwork on the lower chord arch, and the use of sliding rods and drive systems. Realize the sliding pouring of the upper chord formwork, reduce the time of setting up and removing the formwork, and improve the construction efficiency.
It speeds up the construction of the upper chord beam, ensures the synchronous construction of the upper chord beam and the lower chord arch, saves construction time, improves construction efficiency, and enhances the stability and ease of movement of the formwork through unitized design and sliding form technology.
Smart Images

Figure CN118727604A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of arch-beam combination bridges, and in particular to an overall moving construction method for a bottom formwork of a cast-in-place segmental beam of an arch-beam combination bridge. Background Art
[0002] In the prior art, the arch-beam composite bridge adopts a combination of an upper chord beam and a lower chord arch, and the lower chord arch provides support for the upper chord beam. The mid-span deflection is small, the maximum span is larger, and the deadweight is reduced, which is more economical.
[0003] For the construction of arch-beam composite bridges, our company has developed a variety of construction plans. The initial plan is: give priority to the construction of the lower chord arch, install cables on the lower chord arch, set up brackets on the lower chord arch, and set up the upper chord formwork on the brackets for construction.
[0004] Usually, the upper chord and the lower chord are constructed in sections. To ensure the balance between the tension of the cables and the load of the upper chord, the upper chord is constructed synchronously with the lower chord. However, the construction of the upper chord requires the erection of a scaffold first and then the erection of the upper chord formwork. The closer to the pier, the higher the scaffold that needs to be erected, and the slower the construction progress of the upper chord. It is difficult to ensure the synchronous construction of the upper chord and the lower chord, thus delaying the overall progress.
[0005] Therefore, a construction method suitable for arch-beam composite bridges is needed to speed up the construction of the upper chord beam. Summary of the invention
[0006] The present invention aims to provide a method for integrally moving the bottom formwork of a cast-in-place segmental beam of an arch-beam composite bridge, which can accelerate the construction speed of an upper chord beam.
[0007] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a construction method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge,
[0008] The arch-beam composite bridge includes an upper chord beam and a lower chord arch. One end of the upper chord beam and the arch foot of the lower chord arch are connected to the bridge pier, and the other end of the upper chord beam is closed with the arch top of the lower chord arch. The upper chord beam and the lower chord arch are cast in several sections. The arch-beam composite bridge adopts a hanging basket construction, which is cantilevered from the top of the pier to both sides.
[0009] The following steps are involved:
[0010] Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord arch, use a hanging basket to cast the lower chord arch in sections, set up a bracket on the lower chord arch, set up the upper chord formwork on the bracket, and use the sliding formwork construction method to cast the upper chord beam in sections;
[0011] The method of erecting the support and adopting the slipform construction is:
[0012] Step a1, erect a bracket on the cast section of the lower chord arch, a plurality of top supports are arranged on the top of the bracket, a plurality of support units are connected to the top supports, each support unit includes a small cross bar and a slide bar, the small cross bar is transversely arranged on the top support, a plurality of small cross bars are arranged longitudinally, a plurality of slide bars are welded longitudinally on the small cross bar, the upper chord template is slidably supported on the slide bar, and adjacent support units are detachably connected;
[0013] Step a2, setting up the upper chord formwork on the support unit and pouring concrete;
[0014] Step a3, the top support drives the support unit of the current mold to move downward, thereby completing demoulding, setting up the support unit of the next mold and connecting it to the support unit of the current mold, preparing the sliding drive system, connecting the sliding drive system to the cast section of the upper chord beam, and the sliding drive system drives the upper chord formwork to slide from the support unit of the current mold to the support unit of the next mold along the direction of the slide rod;
[0015] Step a4, disconnect the support unit of the current mold from the support unit of the next mold, and use the jacking to drive the support unit of the current mold to move upward and directly support the cast upper chord beam; the jacking drives the upper chord formwork to move upward to the designed height.
[0016] Step 2: Pour the concrete of the closing section of the upper chord beam and the lower chord arch.
[0017] The beneficial effects of this program are:
[0018] 1. In this scheme, the upper chord beam is cast by means of slipforms, which saves the time of setting up and removing the formwork, speeds up the construction of the upper chord beam, ensures the construction progress, and ensures the synchronous construction of the upper chord beam and the lower chord arch.
[0019] 2. Based on the scheme of coordination between the bracket and the formwork, a targeted slipform construction method was designed; specifically, the top of the traditional bracket was improved, with a small cross bar as support and a sliding bar as a sliding rail. The traditional bracket connection method of connecting the small cross bar and the sliding bar was replaced by welding, so that when the upper chord formwork slides on the upper surface of the sliding bar, there is no interference from the fasteners and it is unobstructed.
[0020] 3. Normally, the slipform is usually used in the case of vertically movable formwork such as piers. The moving direction of the formwork is consistent with the direction of gravity, the force is simple, easy to control and has good stability. After the formwork moves vertically, the newly poured concrete structure is based on the concrete poured in the previous mold, and the vertical load is borne by the concrete poured in the previous mold. The slipform does not need to bear the vertical load;
[0021] In this solution, in order to adapt to the construction process of the upper chord beam, it is necessary to move the formwork in the horizontal direction. The direction of formwork movement is perpendicular to the direction of gravity. The load of the concrete structure is mainly borne by the bottom formwork of the upper chord formwork, which increases the friction between the formwork and the concrete structure. Therefore, before sliding the upper chord formwork, it is necessary to first use the top support to drive the bottom formwork to move downward and demold, thereby reducing the pressure between the bottom formwork and the concrete structure to facilitate the sliding of the upper chord formwork.
[0022] In order to facilitate the sliding of the upper template, it is necessary to connect the sliding rods of all the supporting structures together to ensure the continuity of the template sliding. However, this also brings some problems. During the demolding process, the supporting structure needs to move downward to drive the bottom template to be demolded. If all the supporting structures on the bracket are moved downward at the same time, it will be time-consuming and labor-intensive and difficult to complete. Therefore, in this solution, the supporting structure adopts a unitized design, and adjacent supporting units are connected in a detachable manner. Each time the demolding is performed, only the supporting unit of the mold needs to be moved downward to complete the demolding.
[0023] 4. The template is subjected to both horizontal and vertical external forces at the same time, and the forces are complex, which reduces the stability of the template when it moves. Therefore, this solution uses the sliding rod as the track, and connects several sliding rods into a whole through a small cross bar to enhance the integrity of the supporting structure, thereby increasing the stability of the template when it moves;
[0024] In addition, after the support structure adopts a unitized design, during construction, it is only necessary to ensure the integrity of the interior of the support unit, and the accuracy of the sliding rod installation of the support unit is more controllable; after disconnecting the connection between adjacent support units, if the misalignment between adjacent support units is large, it means that the support unit has previously been subjected to a large internal force and deformation, which was only released after the connection was disconnected. Therefore, it is necessary to adjust the position of the support unit in time to reduce the internal force and deformation of the support unit.
[0025] Furthermore, a driving embedded part is embedded in the cast section of the upper chord beam, a driving connecting block is provided on the upper chord formwork, and the sliding drive system includes a driving motor and a threaded rod. The driving motor is connected to the driving embedded part, one end of the threaded rod is connected to the output shaft of the driving motor, and the other end of the threaded rod is threadedly connected to the driving connecting block, and the threaded rod and the sliding rod are parallel.
[0026] Furthermore, in step a1, a plurality of sliding blocks are provided on the lower side of the upper chord template, and the lower surface of the sliding block is an arc shape matching the shape of the upper side of the slide rod.
[0027] Furthermore, the hanging basket is divided into an upper hanging basket and a lower hanging basket; both the upper hanging basket and the lower hanging basket include a traveling system, a main truss system, a suspension system and a bottom basket system, the traveling system is installed on the upper surface of the upper chord beam or the lower chord arch, the main truss system is installed on the traveling system and extends toward the cantilever end, the upper end of the suspension system is detachably connected to the main truss system, the lower end of the suspension system is connected to the bottom basket system, and the bottom basket system serves as a supporting platform to bear the construction load;
[0028] In step 1, the specific construction method of the upper chord beam and the lower chord arch and pier column connection position is:
[0029] Step 1.1, complete the construction of the bridge pier, cast the 0# section of the upper chord beam on the top of the bridge pier, install the upper chord hanging basket on the 0# section of the upper chord beam, use the upper chord hanging basket to cast the 1# section of the upper chord beam, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;
[0030] Step 1.2, the lifting system drives the bottom basket system to move downward to the arch foot position of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support;
[0031] Step 1.3, the walking system of the upper chord hanging basket drives the main truss system, lifting system, suspension system and bottom basket system to move forward together, and the bottom basket system is used as a support to cast the lower chord arch 2# section;
[0032] Step 1.4, install the walking system and main truss system of the lower chord hanging basket on the lower chord arch section 1# and section 2#, connect the main truss system of the lower chord hanging basket with the upper end of the suspension system of the upper chord hanging basket, and convert the suspension system and bottom basket system of the upper chord hanging basket into the suspension system and bottom basket system of the lower chord hanging basket;
[0033] Step 1.5, cast the lower chord arch section 3#, remove the upper chord hanging basket, set up brackets on the lower chord arch sections 1# and 2# as support for the upper chord formwork, and cast the upper chord beam section 2#.
[0034] Further, the lifting system includes a plurality of electric hoists;
[0035] In step 1.1, during the construction of the bridge pier, the horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system;
[0036] In step 1.2, when the electric hoist drives the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, the template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#.
[0037] Furthermore, the suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod, an upper connecting piece and a lower connecting piece are respectively provided at the upper and lower ends of the suspension rod, the upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece, and the upper connecting piece is supported on the main truss system;
[0038] In step 1.2, remove the upper connector, temporarily fix the steel cables of the boom and the electric hoist with iron wire, drive the bottom basket system downward with the electric hoist, and pass the upper end of the extension rod through the main truss system of the upper chord hanging basket and threadedly connect with the upper connector. The upper connector is supported on the main truss system, and the extension rod is threadedly connected with the extension connector at the lower end of the extension rod. The lower end of the extension connector is threadedly connected with the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed.
[0039] Furthermore, the thread directions of the suspension rod and the extension rod are the same, a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the main truss system of the upper chord hanging basket and the lower chord hanging basket both include a main truss, a front crossbeam and a rear crossbeam are provided on the main truss, the front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad; the bottom basket system of the upper chord hanging basket includes a front cantilever beam and a rear cantilever beam, and a plurality of longitudinal beams are provided between the front cantilever beam and the rear cantilever beam;
[0040] In step 1.4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is:
[0041] Step 1.4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam;
[0042] Step 1.4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.
[0043] Furthermore, one ends of several longitudinal beams are hinged to the front cantilever beam, and several horizontally arranged support tubes are provided on the rear cantilever beam. The other ends of the longitudinal beams are supported on the support tubes, and the other ends of the longitudinal beams can slide on the support tubes.
[0044] Furthermore, the conversion pad is provided with four strip-shaped bolt holes, each of which can be equipped with a limit bolt;
[0045] In step 1.4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.
[0046] Furthermore, in step 1.1, a longitudinal temporary prestress is applied to the upper side of the upper chord beam section 1#;
[0047] In step 1.5, after the support is erected, the temporary prestress applied to the upper chord beam section 1# is removed.
[0048] 1. After pouring the lower chord arch section 2#, set up the lower chord hanging basket, and use the main truss system of the lower chord hanging basket to provide support for the bottom basket system, so that the bottom basket system of the upper chord hanging basket can be transferred to the lower chord hanging basket, eliminating the tedious steps of reinstalling the bottom basket system of the lower chord hanging basket, thereby improving construction efficiency.
[0049] 2. As the construction progresses, the upper chord and the lower chord gradually approach each other to facilitate their final closure. If both the upper chord and the lower chord are constructed using a hanging basket, the upper chord hanging basket and the lower chord hanging basket are prone to collision due to their close distance, thus affecting the efficiency of construction. In this solution, after the construction of section 1 of the upper chord is completed, the upper chord hanging basket is cancelled and slipform construction is adopted, which occupies a smaller construction space, greatly saves construction space, and avoids the collision between the upper chord hanging basket and the lower chord hanging basket.
[0050] 3. When constructing on high bridge piers, the wind load is large, the lower end of the hanger is in a free state, and it shakes violently; when the bottom basket system moves downward, the wind load on the hanger gradually increases, the hanger shakes more violently, and it is easy to deform and damage; in this solution, the steel cable of the electric hoist is more flexible than the hanger, and it can recover even if it is deformed under wind load. The upper end of the hanger is no longer fixed, and the hanger shakes with the steel cable, so it is not easy to deform; when the bottom basket system reaches the arch foot position of the lower chord arch and is connected to the 0# section of the lower chord arch through the template, the bottom basket system tends to be stable under the support of the 0# section of the lower chord arch. At this time, the shaking of the lower end of the hanger affected by the wind load is reduced. At this time, an extension rod is used to extend the hanger, and the hanger is not easy to deform.
[0051] 4. In step 1.4, since the boom is the main load-bearing component, if the boom and the extension rod are suddenly disconnected, the steel cable of the electric hoist becomes the main load-bearing component, and the steel cable is subjected to increased force and becomes longer, which can easily cause the electric hoist to be impacted and damaged; if the main truss system of the boom and the lower chord hanging basket is to be fixed first, the boom and the extension rod still need to be disconnected first, so as to connect the upper connector to the upper end of the boom;
[0052] In this solution, the bottom basket system of the upper-chord basket is transferred to the lower-chord basket without disconnecting the boom and the extension rod, and this function is achieved through a specially designed extension connector. The extension connector can connect the boom and the extension rod, and can also serve as a nut and a pad to support the lower-chord basket.
[0053] Specifically, in this solution, since the front crossbeam or the rear crossbeam is composed of two I-beams, when welding the front crossbeam, the hanger is located between the two I-beams, so that the hanger passes through the front crossbeam or the rear crossbeam without disconnecting the hanger and the extension rod; then, the extension connector is rotated to move the extension connector downward until the conversion pad at the lower end of the extension connector is supported on the front crossbeam or the rear crossbeam of the lower chord hanging basket. At this time, the hanger and the extension rod are still connected through the extension connector, and the conversion of the load-bearing part is realized in advance. At this time, if the connection between the hanger and the extension rod is disconnected, the electric hoist or other parts that can bear force will not be greatly impacted due to the conversion of the load-bearing part.
[0054] The extension connector in this solution is not a simple combination of nuts and pads. The extension connector needs to be long enough to not only connect the suspension rod and the extension rod at the same time, but also to move one end downward to allow the conversion pad to contact the front beam or the rear beam while maintaining the connection with the extension rod. Finally, the lower end of the extension rod is disengaged from the extension connector by rotating the extension rod.
[0055] 5. After constructing the upper chord beam section 1# and installing the upper chord hanging basket on the upper chord beam section 1#, the upper chord beam section 1# is in a cantilever state, and the end portion sinks and deforms due to gravity. Therefore, it is necessary to apply a longitudinal temporary prestress on the upper side of the upper chord beam section 1#, and the temporary prestress is used to make the end portion of the upper chord beam section 1# warp to reduce this deformation. After the bracket is erected, the upper chord beam section 1# is no longer in a cantilever state, and the end portion no longer sinks and deforms. Therefore, the temporary prestress is cancelled to prevent the end portion of the upper chord beam section 1# from warping.
[0056] 6. In step 1.1, mark the connection position between the upper end of the boom and the front beam or rear beam of the upper string hanging basket;
[0057] In step 1.2, the connection position of the extension rod and the front crossbeam or rear crossbeam of the upper chord hanging basket is also at the positioning mark. When installing the extension rod, a tower crane is used to fix the upper end of the extension rod. At this time, the extension rod remains vertical under the action of gravity. Only when there is no wind, the boom will also remain vertical, and the lower end of the extension rod can be aligned and connected with the upper end of the boom. Then check whether the boom and the extension rod are in the same straight line, and adjust them in time; since the connection position of the lower end of the boom and the front cantilever beam or rear cantilever beam of the bottom basket system remains unchanged, it is ensured that the extension rod and the boom always remain vertical in a windless state, and the force direction in a windless state is always the axial direction of the rod, without eccentric force, thereby ensuring the load-bearing capacity of the extension rod and the boom.
[0058] The higher the height of the bridge pier, the greater the wind load. Since the length of the hanger plus the extension rod is longer, it is more affected by the wind load. The verticality described in this plan can only ensure verticality in a windless state, and it is impossible to be vertical at all times. Therefore, it is impossible to wait until the wind stops to check the verticality every time. It can only ensure that the upper end of the hanger is always in a fixed state so that the verticality remains unchanged.
[0059] In step 1.4 of this solution, before the upper end of the boom and the front crossbeam of the lower line hanging basket are fixed, the boom and the extended boom are always kept connected to prevent the upper end of the boom from changing its verticality due to loss of connection, thereby ensuring the vertical alignment of the central axes of the upper chord hanging basket and the lower chord hanging basket, and then ensuring the vertical alignment of the central axes of the cast upper chord beam and the lower chord arch, preventing the load of the upper chord beam from generating eccentric force on the lower chord arch.
[0060] 7. In step 1.2, when the lifting system drives the bottom rail system to move downward, due to the inclination of the bottom of the lower chord arch, the longitudinal beam in the bottom rail system needs to be tilted as well, and the template of the lower chord arch is supported on the longitudinal beam.
[0061] If the two connection positions of the longitudinal beam and the front and rear cantilever beams are fixed, after the longitudinal beam is tilted, the horizontal distance between the front and rear cantilever beams is reduced, resulting in a reduction in the distance between the lower ends of the suspension rods connected to the front and rear cantilever beams, causing the suspension rods to tilt. No matter how the operator makes adjustments, it is impossible to keep all the suspension rods vertical at the same time, which will lead to the following adverse effects:
[0062] a. At this time, the operator cannot judge whether there is wind by whether the suspension rod is vertical, and thus cannot adjust the construction progress of the lower chord arch formwork on the bottom rail system in time according to whether there is wind, thereby reducing the construction accuracy of the lower chord arch formwork.
[0063] b. In step 1.4, when installing the main truss of the lower chord hanging basket, the two I-beams on the front and rear crossbeams on the main truss clamp the boom to prevent it from shaking. However, when the boom is no longer vertical, the two I-beams clamping the boom will pull the upper end of the boom back to a vertical state, while the lower end of the boom is still tilted, causing the boom to deform and a large internal force to exist, thereby reducing the durability of the boom.
[0064] In this solution, one end of the longitudinal beam is hinged to the front beam, and the other end is slidably connected to the rear beam (sliding can be ensured by applying lubricating oil on the contact surface), so that the horizontal distance between the front beam and the rear beam will not change when the longitudinal beam is tilted, and the suspension rod can still remain vertical under the action of gravity;
[0065] For adverse effect a, the operator can judge whether there is wind by whether the hanger is vertical, thereby ensuring the construction accuracy of the lower chord arch formwork; for adverse effect b, the hanger can be prevented from generating internal force, thereby ensuring the durability of the hanger.
[0066] 8. Regarding effect 7, during the process of adjusting the inclination of the longitudinal beam, if the friction increases and the sliding is abnormal due to insufficient lubricating oil on the contact surface between the longitudinal beam and the rear cantilever beam, or the friction increases and the rotation is abnormal due to rust at the hinge position between the longitudinal beam and the front cantilever beam, or the concrete falls on the connection position between the longitudinal beam and the front cantilever beam or the rear cantilever beam during the previous concrete pouring, the hanger cannot remain vertical. At this time, by clamping the hanger with the two I-beams that form the front cantilever beam or the rear cantilever beam, a reaction force can be provided for the longitudinal beam to overcome the friction; when the hanger connection position is near the end of the I-beam, the end of the I-beam is easily deformed due to the cantilever effect, and the distance between the two I-beams is easily enlarged when the hanger is tilted, and the I-beam cannot clamp the hanger, so that the hanger cannot remain vertical; and this solution uses a limit bolt to limit the distance between the two I-beams, thereby ensuring that the two I-beams can clamp the hanger and the distance is not enlarged as much as possible. BRIEF DESCRIPTION OF THE DRAWINGS
[0067] Figure 1 It is a schematic diagram of the overall structure of Example 1;
[0068] Figure 2 It is a three-dimensional axonometric drawing of the upper chord template and the top of the bracket of Example 1;
[0069] Figure 3 It is a front view of the upper chord template and the top of the bracket of Example 1;
[0070] Figure 4 It is a right side view of the upper chord template and the top of the bracket of Example 1;
[0071] Figure 5 It is a schematic diagram of the upper hanging basket of Example 2;
[0072] Figure 6 It is a schematic diagram of the suspension system and bottom basket system of the upper hanging basket of Example 2 when they are transferred to the lower hanging basket;
[0073] Figure 7 is a perspective view of an extended connector of Example 2;
[0074] Figure 8 This is a schematic diagram of the structure of step 1.1 of Example 3;
[0075] Fig. 9 This is a schematic diagram of the structure of step 1.2 of Example 3;
[0076] Fig.10 This is a schematic diagram of the structure of step 1.3 of Example 3;
[0077] Fig.11 This is a schematic diagram of the structure of step 1.4 of Example 3;
[0078] Fig.12 This is a schematic diagram of the structure of step 1.5 of Example 3;
[0079] Fig.13 This is a schematic diagram of the structure of step 1.6 of Example 3;
[0080] Fig.14 This is a schematic diagram of the conversion pad in the state of step 1.4.2 of Example 4;
[0081] Fig.15 Schematic diagram of point P in Example 4. DETAILED DESCRIPTION
[0082] The following is further described in detail through specific implementation methods:
[0083] The reference numerals in the drawings of the specification include: pier 1, upper chord beam 2, upper chord beam 0# section 20, upper chord beam 1# section 21, closing section 22, lower chord arch 3, lower chord arch 0# section 30, lower chord arch 1# section 31, lower chord arch 2# section 32, lower chord arch 3# section 33, upper chord hanging basket 41, lower chord hanging basket 42, temporary buckle cable 43, walking system 50, main truss 51, front cross beam 52, rear cross beam 53, front cantilever beam 61, rear cantilever beam 62, longitudinal beam 63, connecting block 64, Latch 65, electric hoist 7, upper connecting piece 81, upper nut 811, upper pad 812, extension connecting piece 82, conversion pad 83, strip bolt hole 831, limit bolt 832, suspension rod 84, extension rod 85, bracket 9, small cross bar 91, slide bar 92, upper chord formwork 10, front form 101, side form 102, drive connecting block 103, bottom form 104, slider 105, drive motor 106, threaded rod 107, cast section 108, top support 109.
[0084] Example 1
[0085] Example 1 is basically as Figure 1-Figure 4 As shown: the upper chord formwork and its bracket are suitable for arch-beam composite bridges; arch-beam composite bridges such as Figure 1 As shown in FIG. 1 , with the center line of pier 1 as the axis of symmetry, both sides of pier 1 are constructed synchronously and symmetrically. Take the segment on the right side of pier 1 as an example: the segment includes an upper chord beam 2 and a lower chord arch 3. The left end of the upper chord beam 2 and the left arch foot of the lower chord arch 3 are both connected to pier 1. The right end of the upper chord beam 2 and the arch top of the lower chord arch 3 are closed. Figure 1As shown in the figure, the upper chord beam 2 and the lower chord arch 3 are divided into 13 sections for casting, among which the thirteenth section is the closing section 22 of the upper chord beam 2 and the lower chord arch 3, the upper chord beam 0# section 20 is above the pier 1, and the upper chord beam 1# section 21, the upper chord beam 2# section 22 from near to far are respectively, and so on; the lower chord arch 0# section 30 is cast on both sides of the pier 1 together with the pier 1, and the lower chord arch 0# section 30 from near to far are respectively. 1# section 31, lower chord arch 2# section 32, and so on; the purpose of casting the lower chord arch 0# section 30 and the bridge pier 1 together is to reserve in advance for connection with the lower chord arch 1# section 31; a number of temporary cables 43 are set on the bridge pier 1, and the temporary cables 43 all pass through the bridge pier 1. The two ends of the temporary cables 43 are respectively anchored in the lower chord arch 3 on both sides of the bridge pier 1. Starting from the lower chord arch 2# section 32, each casting of a segment, a temporary cable 43 is constructed;
[0086] The upper chord template and its support include an upper chord template 10, a support 9 and two sliding drive systems, such as Figure 2 As shown, the top of the bracket 9 is provided with a plurality of adjustable top supports 109, which are prior art and will not be described in detail. The top supports 109 are provided with a plurality of longitudinally arranged support units, each of which includes a plurality of small cross bars 91 and slide bars 92, the small cross bars 91 are arranged transversely and the lower side is welded to the top supports 109, a plurality of small cross bars 91 are longitudinally arranged on the top of the top supports 109, a plurality of slide bars 92 are longitudinally arranged on the small cross bars 91, and the upper side of the small cross bars 91 and the lower side of the slide bars 92 are welded; for ease of display, Figure 2-Figure 4 The parts other than the top of the bracket 9 are omitted, and the parts other than the top of the bracket 9 are constructed with fasteners and steel pipes; adjacent support units are detachably connected, specifically, connecting blocks are provided between the ends of the slide rods 92 of different support units, and the connecting blocks are simultaneously connected to the lower side bolts of the two slide rod ends.
[0087] The upper mold 10 includes a front mold 101, a bottom mold 104 and two side molds 102. The fixing method between the molds is the existing technology, such as Figure 2 As shown, the front mold 101, the side mold 102 and the bottom mold 104 cooperate with the cast section 108 of the upper chord beam 2 to form a template for the segment to be cast. Figure 3 As shown, the front mold 101 is located at the end of the segment to be cast, the side molds 102 are located between the segment to be cast and the front mold 101, and two drive connection blocks 103 are welded at equal heights on the side molds 102; the cast section 108 of the upper chord beam 2 is pre-embedded with a drive embedded part, and the sliding drive system includes a drive motor 106 and a threaded rod 107, the drive motor 106 is bolted to the drive embedded part, the left end of the threaded rod 107 is bolted to the output shaft of the drive motor 106, the other end of the threaded rod 107 passes through the two drive connection blocks 103 and is threadedly connected to the two drive connection blocks 103, and the threaded rod 107 is parallel to the slide bar 92; a plurality of sliders 105 are welded on the lower side of the bottom mold 104, as shown in FIG. Figure 4 As shown, the lower surface of the slider 105 is an arc shape that matches the shape of the upper side of the slide bar 92 , and the slider 105 can slide on the slide bar 92 , thereby driving the upper chord template 10 to slide longitudinally on the slide bar 92 .
[0088] Example 2
[0089] Example 2 is basically the same Figure 5-Figure 6 As shown: the hanging basket with lifting function is suitable for the arch-beam combination bridge described in Example 1. The upper chord beam 2 and the lower chord arch 3 are constructed by the hanging basket with lifting function, which is cantilevered from the top of the pier 1 to both sides. The hanging basket with lifting function includes an upper chord hanging basket 41 and a lower chord hanging basket 42. The upper chord hanging basket 41 and the lower chord hanging basket 42 both include a walking system 50, a main truss system, a suspension system and a bottom basket system. The walking system 50 is installed on the upper surface of the upper chord beam 2 or the lower chord arch 3. The main truss system is installed on the walking system 50 and extends in the direction of the cantilever end. The upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load. In this solution, the walking system 50 and the main truss system of the hanging basket with lifting function are the same as those in the prior art. The focus of this embodiment is: through the lifting system, the upper chord hanging basket 41 is given a lifting function, so that the bottom basket system can move downward, so that the upper chord hanging basket 41 and the lower chord hanging basket 42 can alternately use the suspension system and the bottom basket system.
[0090] like Figure 5 As shown, the main truss system of the upper chord hanging basket 41 and the lower chord hanging basket 42 both include a prismatic main truss 51, a front crossbeam 52 is welded to the front end of the main truss 51, and a rear crossbeam 53 is welded to the middle of the main truss 51. The front crossbeam 52 and the rear crossbeam 53 are both formed by combining two parallel I-beams, and a gap is left between the two parallel I-beams; Figure 6 As shown, the main truss systems of the upper chord cradle 41 and the lower chord cradle 42 differ in that the slopes of the bottoms of the main trusses 51 are different to accommodate walking on the upper chord beam 2 and the lower chord arch 3, respectively.
[0091] The bottom basket system of the upper chord hanging basket 41 includes a front cantilever beam 61 and a rear cantilever beam 62. The front cantilever beam 61 is located directly below the front cross beam 52, and the rear cantilever beam 62 is located directly below the rear cross beam 53. Two longitudinal beams 63 are arranged between the front cantilever beam 61 and the rear cantilever beam 62. The longitudinal beam 63 can provide support for the formwork of the lower chord arch 3. The front cantilever beam 61 and the rear cantilever beam 62 are both formed by a combination of two parallel I-beams, and a gap is left between the two parallel I-beams. Two hinged units are arranged on the front cantilever beam 61, and each hinged unit includes two connecting blocks 64. The two connecting blocks 64 are welded to the front cross beam 52. The left end of the longitudinal beam 63 is slidably supported on the rear cantilever beam 62. A pin 65 is arranged at the right end of the longitudinal beam 63. The pin 65 passes through the right end of the longitudinal beam 63 and the two connecting blocks 64 at the same time and is rotatably connected to the three. The right end of the longitudinal beam 63 is arranged between the two connecting blocks 64.
[0092] The lifting system includes four lifting devices (not shown in the figure), the lifting devices are winches or electric hoists 7. In this embodiment, the lifting devices are electric hoists 7; the upper ends of the electric hoists 7 are bolted to the main truss system of the upper chord hanging basket 41, specifically located at the two ends of the front crossbeam 52 and the rear crossbeam 53, and the lower ends of the steel cables of the electric hoists 7 are hung at the two ends of the front cantilever beam 61 and the rear cantilever beam 62 respectively;
[0093] The suspension system of the upper chord hanging basket 41 includes four suspension units, and the positions of the suspension units and the electric hoists 7 correspond one to one. The suspension units all include a suspension rod 84 and an extension rod 85. The upper and lower ends of the suspension rod 84 are respectively provided with an upper connecting piece 81 and a lower connecting piece. The upper end of the suspension rod 84 passes through the front cross beam 52 or the rear cross beam 53 of the main truss system of the upper chord hanging basket 41. The upper connecting piece 81 includes an upper nut 811 and an upper pad 812. The upper pad 812 is supported on the front cross beam 52 or the rear cross beam 53 and is passed through by the suspension rod 84. The upper nut 811 is threadedly connected to the upper nut 811. Connect to the upper end of the suspension rod 84, tighten the upper nut 811, the upper nut 811 cooperates with the front cross beam 52 or the rear cross beam 53 to clamp the upper pad 812; similarly, the composition of the lower connecting member is the same as that of the upper nut 811, the lower connecting member includes a lower nut and a lower pad, the lower pad is arranged at the lower side of the front cantilever beam 61 or the rear cantilever beam 62 and is passed through by the lower end of the suspension rod 84, the lower nut is threadedly connected to the lower end of the suspension rod 84, tighten the lower nut, the lower nut cooperates with the front cantilever beam 61 or the rear cantilever beam 62 to clamp the lower pad, thereby providing support for the front cantilever beam 61 or the rear cantilever beam 62;
[0094] like Figure 7 As shown, when the suspension rod 84 is extended, the suspension rod 84 and the extension rod 85 can be connected by an extension connector 82. The extension connector 82 is a sleeve with an internal thread. The lower end of the extension connector 82 is threadedly connected to the upper end of the suspension rod 84. The threads on the suspension rod 84 and the extension rod 85 have the same direction. A conversion pad 83 is welded at the lower end of the extension connector 82, and the upper end of the suspension rod 84 can pass through the conversion pad 83.
[0095] Example 3
[0096] The overall moving construction method of the bottom formwork of the cast-in-place segmental beam of the arch-beam composite bridge, such as Figure 8-Figure 13 As shown, the construction is carried out based on the upper chord formwork and its bracket in Example 1 and the hanging basket with lifting function in Example 2, including the following steps:
[0097] Step 1: Complete the construction of the bridge pier 1, cast the upper chord arch section 0#, use a hanging basket to cast the lower chord arch 3 in sections, set up a bracket 9 on the lower chord arch 3, set up an upper chord formwork 10 on the bracket 9, and use a sliding formwork construction method to cast the upper chord beam 2 in sections on the upper chord formwork 10;
[0098] The drive embedded parts are pre-embedded in the cast section 108 of the upper chord beam 2 in advance, and the bracket 9 is set up and the slipform construction method is as follows:
[0099] Step a1, a support 9 is set up on the cast section 108 of the lower chord arch 3, a plurality of top supports 109 are provided on the top of the support 9, a support unit is set up on the top supports 109, each support unit can independently support the upper chord formwork 10, the upper chord formwork 10 is set up on the support unit, and the slider 105 at the bottom of the upper chord formwork 10 is slidably supported on the slide rod 92;
[0100] Step a2, setting up the upper chord formwork 10 on the support unit and pouring concrete;
[0101] Step a3, adjusting the height of the top support 109 to drive the support unit of the current mold to move downward, thereby completing demoulding, setting up the support unit of the next mold and connecting it with the support unit of the current mold;
[0102] The driving motor 106 is bolted to the driving embedded part of the cast section 108 of the upper chord beam 2, one end of the threaded rod 107 is bolted to the output shaft of the driving motor 106, the other end of the threaded rod 107 passes through the two driving connection blocks 103 and is threadedly connected to the two driving connection blocks 103, and the threaded rod 107 is parallel to the sliding rod 92; the driving motor 106 drives the threaded rod 107 to rotate, thereby pushing the upper chord formwork 10 to slide from the current mold support unit to the next mold support unit along the direction of the sliding rod 92;
[0103] Step a4, disconnect the support unit of the current mold from the support unit of the next mold, and the top support 109 drives the support unit of the current mold to move upward and directly support the cast upper chord beam 2; the top support 109 drives the upper chord formwork 10 to move upward to the designed height.
[0104] The specific construction method of the connection position between the upper chord beam 2, the lower chord arch 3 and the pier column is as follows:
[0105] Step 1.1: Figure 8As shown in the figure, the construction of the bridge pier 1 is completed. During the construction of the bridge pier 1, a horizontally arranged lower chord arch 0# segment 30 is reserved on both sides of the bridge pier 1, an upper chord beam 0# segment 20 is cast on the top of the bridge pier 1, an upper chord hanging basket 41 is installed on the upper chord beam 0# segment 20, and the upper chord hanging basket 41 is used to cast the upper chord beam 1# segment 21, and a longitudinal temporary prestress is applied to the upper side of the upper chord beam 1# segment 21. The method of applying the temporary prestress is as follows: a longitudinal steel strand is buried in the upper part of the upper chord beam 2, and a jack is used to lift the upper chord beam 2 along the longitudinal direction. Figure 8 The longitudinal steel strands are tensioned in the direction of the middle arrow, and the ends of the longitudinal steel strands are anchored with anchors, thereby generating pre-compression stress on the upper part of the upper chord beam 2 to prevent the end of the upper chord beam 2 from sinking; a lifting system is installed on the main truss system of the upper chord hanging basket 41, and the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;
[0106] Step 1.2, remove the upper connector 81 at the upper end of the suspension rod 84, temporarily tie and fix the suspension rod 84 and the steel cable of the electric hoist by iron wire, and the four electric hoists 7 jointly drive the bottom basket system to move downward, the lower end of the electric hoist on the rear crossbeam 53 descends faster than the lower end of the electric hoist 7 on the front crossbeam 52, and the right end of the longitudinal beam 63 rotates around the latch 65 on the front crossbeam 52, so that the slope of the longitudinal beam 63 of the bottom basket system is the same as the slope of the bottom of the lower chord arch 1# section 31, and the main truss system, the suspension system and the bottom basket system are driven backward by the walking mechanism of the upper chord hanging basket 41, and the bottom basket system is driven to move to the arch foot position of the lower chord arch 3, and the template of the lower chord arch 1# section 31 is set on the bottom basket system, and the bottom basket system and the template of the lower chord arch 1# section 31 are detachably connected by fasteners or other connecting parts, and the template of the lower chord arch 1# section 31 is connected to the lower chord arch 0# section 30;
[0107] like Fig. 9 As shown, the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket 41: the upper end of the extension rod 85 passes through the main truss system of the upper chord hanging basket 41 and is threadedly connected to the upper connecting piece 81, the upper connecting piece 81 is supported on the main truss system, the extension connecting piece 82 is threadedly connected to the lower end of the extension rod 85, the iron wire on the suspension rod 84 and the steel cable of the electric hoist is removed, and the lower chord arch 1# section 31 is cast with the bottom basket system as support;
[0108] Step 1.3: Fig.10 As shown, the walking system 50 of the upper chord hanging basket 41 drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch 2# section 32 is cast with the bottom basket system as support; the two ends of a temporary cable 43 are respectively anchored in the lower chord arch 2# section 32 on both sides of the pier 1;
[0109] Step 1.4: Fig.11As shown, the walking system 50 and the main truss system of the lower chord hanging basket 42 are installed on the lower chord arch 1# segment 31 and 2# segment, the main truss system of the lower chord hanging basket 42 is connected to the upper end of the suspension system of the upper chord hanging basket 41, and the suspension system and the bottom basket system of the upper chord hanging basket 41 are converted into the suspension system and the bottom basket system of the lower chord hanging basket 42;
[0110] The method for converting the suspension system and bottom basket system of the upper hanging basket 41 into the suspension system and bottom basket system of the lower hanging basket 42 is as follows:
[0111] Step 1.4.1, during the installation of the main truss system of the lower chord hanging basket 42, the suspension rod 84 of the upper chord hanging basket 41 is passed through the front cross beam 52 or the rear cross beam 53 of the lower chord hanging basket 42. Since the front cross beam 52 or the rear cross beam 53 is composed of two I-beams, when welding the front cross beam 52, the suspension rod 84 is located between the two I-beams, so that the suspension rod 84 can pass through the front cross beam 52 or the rear cross beam 53 without disconnecting the suspension rod 84 and the extension rod 85;
[0112] The upper end of the electric hoist 7 is bolted to the front crossbeam 52 or the rear crossbeam 53 of the lower string hanging basket 42, and the lower end of the electric hoist 7 is hung on the front cantilever beam 61 or the rear cantilever beam 62 of the upper line hanging basket;
[0113] Step 1.4.2, such as Figure 7 As shown, rotate the extension connector 82 to move it downward so that the conversion pad 83 at the lower end of the extension connector 82 is supported on the main truss system of the lower chord hanging basket 42, remove the upper connector 81 at the upper end of the extension rod 85, rotate the extension rod 85 to disengage the lower end of the extension rod 85 from the extension connector 82, and remove the extension rod 85 and the electric hoist 7.
[0114] Step 1.5: Fig.12 As shown, the lower chord arch section 3# 33 is cast, and the two ends of a temporary cable 43 are anchored in the lower chord arch section 3# 33 on both sides of the pier 1; the upper chord hanging basket 41 is removed, and a bracket 9 is set up on the lower chord arch section 1# 31 and the lower chord arch section 2# 32 as a support for the upper chord formwork 10, and the temporary prestress applied to the upper chord beam section 1# 21 is removed, that is, the anchors at the ends of the longitudinal steel strands are removed, and the upper chord beam section 2# 22 is cast;
[0115] Step 1.6: Fig.13 As shown in the figure, the upper chord beam 2 is constructed by slipform, and the lower chord arch 3 is constructed by hanging basket. Repeat step 1.5, and the upper chord beam 2 lags behind the lower chord arch 32 segments and advances the construction synchronously until the pouring is as shown in the figure. Figure 1 The upper section of the closed section 22 of the upper chord beam 2 and the lower chord arch 3 is shown.
[0116] Step 2: pouring concrete for the closing section 22 of the upper chord beam 2 and the lower chord arch 3.
[0117] Example 4
[0118] Embodiment 4 is based on Embodiment 3: four strip-shaped bolt holes 831 are opened on the conversion pad 83, and a limiting bolt 832 can be installed in each bolt hole;
[0119] In step 1.4.2, the conversion pad 83 is supported on the front beam 52 or the rear beam 53 of the main truss system of the lower chord hanging basket 42, and four limit bolts 832 are installed on the conversion pad 83. Taking the front beam 52 as an example, Fig.14 As shown, four limit bolts 832 are evenly distributed and fit on both sides of the front cross beam 52, so as to limit the distance between the two I-beams constituting the front cross beam 52. The limit bolts 832 need to be fixed in the strip bolt holes 831 in cooperation with nuts. When limiting the distance between the two I-beams by the limit bolts 832, the size of the nuts needs to be considered.
[0120] The effect of embodiment 4 is as follows Fig.15 As shown in the figure, the weight of the formwork of the lower chord arch 3, the concrete, and the loads generated by various components will all be transmitted to the longitudinal beam 63. Since the longitudinal beam 63 and the front cantilever beam 61 are hinged, most of the load of the longitudinal beam 63 is transmitted to the front cantilever beam 61 through the latch 65. If only the latch 65 is considered to bear most of the load, the strength of the latch 65 is often difficult to bear. In this embodiment, the direct contact point P between the longitudinal beam 63 and the front cantilever beam 61 needs to be considered. When the longitudinal beam 63 rotates to a certain angle, the load of the longitudinal beam 63 The pressure is transmitted to the longitudinal beam 63 through point P. However, at this time, the longitudinal beam 63 generates a pressure perpendicular to the length direction of the longitudinal beam 63 on the front cantilever beam 61 (in the direction of the arrow in the figure), thereby driving the lower end of the suspension rod 84 to move to the right through the front cantilever beam 61, thereby driving the suspension rod 84 to tilt. The greater the pressure change, the greater the back-and-forth swing. In this solution, by setting a limit bolt 832, the upper end of the suspension rod 84 is clamped through the front cross beam 52 of the lower chord hanging basket 42 to limit the tilting of the suspension rod 84, thereby reducing this swing and ensuring construction safety.
[0121] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. The overall moving construction method of the bottom formwork of the cast-in-place segmental beam of the arch-beam composite bridge is characterized by: The arch-beam composite bridge includes an upper chord beam and a lower chord arch. One end of the upper chord beam and the arch foot of the lower chord arch are connected to the bridge pier, and the other end of the upper chord beam is closed with the arch top of the lower chord arch. The upper chord beam and the lower chord arch are cast in several sections. The arch-beam composite bridge adopts a hanging basket construction, which is cantilevered from the top of the pier to both sides. The following steps are involved: Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord arch, use a hanging basket to cast the lower chord arch in sections, set up a bracket on the lower chord arch, set up the upper chord formwork on the bracket, and use the sliding formwork construction method to cast the upper chord beam in sections; The method of erecting the support and adopting the slipform construction is: Step a1, erect a bracket on the cast section of the lower chord arch, a plurality of top supports are arranged on the top of the bracket, a plurality of support units are connected to the top supports, each support unit includes a small cross bar and a slide bar, the small cross bar is transversely arranged on the top support, a plurality of small cross bars are arranged longitudinally, a plurality of slide bars are welded longitudinally on the small cross bar, the upper chord template is slidably supported on the slide bar, and adjacent support units are detachably connected; Step a2, setting up the upper chord formwork on the support unit and pouring concrete; Step a3, the top support drives the support unit of the current mold to move downward, thereby completing demoulding, setting up the support unit of the next mold and connecting it to the support unit of the current mold, preparing the sliding drive system, connecting the sliding drive system to the cast section of the upper chord beam, and the sliding drive system drives the upper chord formwork to slide from the support unit of the current mold to the support unit of the next mold along the direction of the slide rod; Step a4, disconnect the support unit of the current mold from the support unit of the next mold, and use the jacking to drive the support unit of the current mold to move upward and directly support the cast upper chord beam; the jacking drives the upper chord formwork to move upward to the designed height. Step 2: Pour the concrete of the closing section of the upper chord beam and the lower chord arch.
2. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 1 is characterized in that: A driving embedded part is embedded in the cast section of the upper chord beam, a driving connecting block is provided on the upper chord formwork, and the sliding driving system includes a driving motor and a threaded rod. The driving motor is connected to the driving embedded part, one end of the threaded rod is connected to the output shaft of the driving motor, and the other end of the threaded rod is threadedly connected to the driving connecting block, and the threaded rod is parallel to the sliding rod.
3. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 2 is characterized in that: In step a1, a plurality of sliders are provided on the lower side of the upper chord template, and the lower surface of the slider is an arc shape matching the shape of the upper side of the slide rod.
4. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 1 is characterized in that: The hanging basket is divided into an upper hanging basket and a lower hanging basket; both the upper hanging basket and the lower hanging basket include a traveling system, a main truss system, a suspension system and a bottom basket system. The traveling system is installed on the upper surface of the upper chord beam or the lower chord arch, the main truss system is installed on the traveling system and extends toward the cantilever end, the upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load; In step 1, the specific construction method of the upper chord beam and the lower chord arch and pier column connection position is: Step 1.1, complete the construction of the bridge pier, cast the 0# section of the upper chord beam on the top of the bridge pier, install the upper chord hanging basket on the 0# section of the upper chord beam, use the upper chord hanging basket to cast the 1# section of the upper chord beam, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system; Step 1.2, the lifting system drives the bottom basket system to move downward to the arch foot position of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support; Step 1.3, the walking system of the upper chord hanging basket drives the main truss system, lifting system, suspension system and bottom basket system to move forward together, and the bottom basket system is used as a support to cast the lower chord arch 2# section; Step 1.4, install the walking system and main truss system of the lower chord hanging basket on the lower chord arch section 1# and section 2#, connect the main truss system of the lower chord hanging basket with the upper end of the suspension system of the upper chord hanging basket, and convert the suspension system and bottom basket system of the upper chord hanging basket into the suspension system and bottom basket system of the lower chord hanging basket; Step 1.5, cast the lower chord arch section 3#, remove the upper chord hanging basket, set up brackets on the lower chord arch sections 1# and 2# as support for the upper chord formwork, and cast the upper chord beam section 2#.
5. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of the arch-beam composite bridge according to claim 4 is characterized in that: The lifting system includes several electric hoists; In step 1.1, during the construction of the bridge pier, the horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system; In step 1.2, when the electric hoist drives the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, the template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#.
6. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 5 is characterized in that: The suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod. The upper and lower ends of the suspension rod are respectively provided with an upper connecting piece and a lower connecting piece. The upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece. The upper connecting piece is supported on the main truss system. In step 1.2, remove the upper connector, temporarily fix the steel cables of the boom and the electric hoist with iron wire, drive the bottom basket system downward with the electric hoist, and pass the upper end of the extension rod through the main truss system of the upper chord hanging basket and threadedly connect with the upper connector. The upper connector is supported on the main truss system, and the extension rod is threadedly connected with the extension connector at the lower end of the extension rod. The lower end of the extension connector is threadedly connected with the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed.
7. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 6 is characterized in that: The thread directions of the suspension rod and the extension rod are the same, and a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the main truss system of the upper chord hanging basket and the lower chord hanging basket both include a main truss, and the main truss is provided with a front crossbeam and a rear crossbeam, and the front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad; the bottom basket system of the upper chord hanging basket includes a front cantilever beam and a rear cantilever beam, and a plurality of longitudinal beams are provided between the front cantilever beam and the rear cantilever beam; In step 1.4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is: Step 1.4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam; Step 1.4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.
8. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 7 is characterized in that: One ends of the plurality of longitudinal beams are hinged to the front cantilever beam, and the rear cantilever beam is provided with a plurality of horizontally arranged support tubes, and the other ends of the longitudinal beams are supported on the support tubes, and the other ends of the longitudinal beams can slide on the support tubes.
9. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 8 is characterized in that: There are four strip-shaped bolt holes on the conversion pad, and a limit bolt can be installed in each bolt hole; In step 1.4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.
10. The method for integrally moving the bottom formwork of the cast-in-place segmental beam of an arch-beam composite bridge according to claim 9, characterized in that: In step 1.1, a temporary longitudinal prestress is applied to the upper side of the upper chord beam 1# segment; In step 1.5, after the support is erected, the temporary prestress applied to the upper chord beam section 1# is removed.
