Large-span composite string truss hoisting construction method under working condition of limited space
By adopting the whole truss hoisting method under limited space conditions and using the matching technology of tower and main boom crawler cranes to hoist large-span composite tension trusses group by group, the construction efficiency and safety problems in traditional installation methods are solved. , achieving an efficient and safe construction process.
Patent Information
- Application Number
- CN202410846044.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-27
- Publication Date
- 2024-10-01
AI Technical Summary
Under limited space conditions, the traditional high-altitude scattered installation method of long-span composite tension truss buildings has problems such as long installation cycles, many cross-cutting operations, and insufficient construction safety guarantees, making it difficult to adapt to the construction needs of such buildings.
The entire truss hoisting method is adopted. Multiple groups of assembled tire frames are set up on the ground, and the combined lifting technology of the tower-type crawler crane and the main arm crawler crane is used to hoist the composite tension truss group by group, reducing high-altitude operations and improving construction efficiency. Efficiency and safety.
This method effectively improves the installation efficiency of long-span composite tension trusses, reduces the risk of high-altitude operations, makes full use of ground operation space and hoisting equipment, simplifies the construction process, and improves construction safety and equipment utilization efficiency.
Smart Images

Figure CN118728093A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a large-span composite string truss hoisting construction method under space-constrained working conditions. Background Art
[0002] With the acceleration of industrial construction, large-span landmark buildings are increasingly widely used. At present, a composite chord truss (shuttle-shaped) has been widely used in such large-span building roofs. The support nodes are located at both ends of the upper chord, and both ends of the lower chord are connected to the support nodes. The prestressed cables arranged on both sides of the lower chord are also anchored to the support nodes. The composite truss structure has a small rise and good indoor effect.
[0003] Some exhibition buildings that use large-span composite tensioned trusses (shuttle-shaped) are affected by external factors such as aviation height restrictions and small work sites. If the traditional high-altitude scattered installation method is used, there are many technical difficulties such as long installation cycle, many cross-operations, and lack of construction safety. Therefore, the traditional lifting method is not suitable for large-span composite tensioned truss buildings under space-constrained conditions.
[0004] Therefore, providing a hoisting method that can make full use of ground operating space and hoisting equipment, using the method of hoisting the entire truss to ensure the assembly accuracy of the truss, speed up the construction progress, and reduce the risk of high-altitude operations has become an urgent problem to be solved by technical personnel in this field. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a method for hoisting and constructing a large-span composite tensioned truss under space-constrained working conditions, so as to at least solve some of the above-mentioned technical problems.
[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0007] The invention discloses a method for installing a large-span composite string truss under space-constrained working conditions, comprising the following steps:
[0008] Step 1: according to the width of the tire frame and along the length direction of the building, two sets of ground assembly tire frame groups are arranged and the composite string trusses are assembled thereon, each set of ground assembly tire frame group includes two ground assembly tire frames;
[0009] Step 2: After the composite chord truss is assembled, it is hoisted. One composite chord truss is hoisted each time. A tower working crawler crane and a main arm working crawler crane are used for hoisting.
[0010] Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles;
[0011] Step 4: After the installation of another set of composite tension-string trusses is completed, the two composite tension-string trusses on the outer edge of the building will be installed.
[0012] In some embodiments of the present invention, in step one, two groups of ground assembly cradles are offset by 15 to 25 m, preferably 20 m, in the length direction; four ground assembly cradles are equidistantly distributed and the distance between two adjacent ground assembly cradles is 3 to 5 m, preferably 4 m.
[0013] In some embodiments of the present invention, in step 2, when the composite chord truss is hoisted, the composite chord truss is first hoisted from the composite chord truss located inside the building, and then hoisted from the inside to the outside.
[0014] In some embodiments of the present invention, in step 2, when the composite chord truss is hoisted, the tower working crawler crane is located at the front end of the hoisted composite chord truss, and the main arm working crawler crane is located at the rear end of the hoisted composite chord truss, and the two crawler cranes jointly lift the hoisted composite chord truss away from the assembly frame.
[0015] In some embodiments of the present invention, in step 2, during the hoisting process of the composite chord truss, the tower working crawler crane moves in a direction perpendicular to the length of the building, and the main arm working crawler moves from the outside to the inside along the length of the building at the same time. The two crawler cranes cooperate to rotate the hoisted composite chord truss 90° and hoist it to just below the installation position. Thereafter, the two crawler cranes jointly hoist the hoisted composite chord truss to the installation height and fix both ends of the hoisted composite chord truss.
[0016] In some embodiments of the present invention, after the composite chord truss to be hoisted is hoisted to just below the installation position, two crawler cranes jointly hoist the composite chord truss to be hoisted to the installation height and fix both ends of the composite chord truss.
[0017] In some embodiments of the present invention, after both ends of the composite chord truss are fixed, a truck crane is used to hoist part of the roof steel structure rods and assemble them so that the composite chord truss obtains a stable support system; preferably, a 50t truck crane is used.
[0018] In some embodiments of the present invention, in step 2, during the composite chord truss hoisting process, after a group of composite chord trusses are hoisted, a truck crane is used to start installing the rods between the composite chord trusses; preferably, a 50t truck crane is used.
[0019] In some embodiments of the present invention, in step three, when the hoisting of the two sets of composite tensioned trusses is completed, a truck crane is used to start hoisting the outer roof structure of the building; preferably, a 160t truck crane is used to start hoisting the outer roof structure of the building.
[0020] In some implementation schemes of the present invention, in step 4, after the three sets of composite tensioned trusses are hoisted, the two crawler cranes jointly assist the truck crane in installing the remaining roof structure.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] The invention has a simple structure, a scientific and reasonable design, and is easy to use. The hoisting construction method of the invention fully utilizes the ground operating space and hoisting equipment, and adopts a whole-truss hoisting method to ensure the assembly accuracy of the truss, speed up the construction progress, and reduce the risk of high-altitude operations.
[0023] The present invention adopts a method of assembling the composite string truss on the ground first and then hoisting the whole truss, which greatly improves the installation efficiency of such large-span trusses. After the truss is removed by two cranes, the truss is rotated in coordination and then hoisted, which minimizes the ground space and clearance height required for the hoisting operation. The method of assembling and hoisting four trusses in sequence, and then shifting and assembling them alternately and hoisting them improves the installation efficiency of truck cranes and crawler cranes, effectively speeds up the construction progress, and reduces equipment rental costs. The present invention reduces high-altitude operations and ensures construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a flow chart of the hoisting construction method of the present invention;
[0025] Figure 2 This is a schematic diagram of the assembly construction of the composite string truss;
[0026] Figure 3 This is a schematic diagram of the double-machine lifting and debonding construction;
[0027] Figure 4 This is a schematic diagram of the construction of a double-machine lifting and rotating truss;
[0028] Figure 5 This is a schematic diagram of the truss in place construction;
[0029] Figure 6 This is a construction diagram of using a truck crane to hoist the steel structure rods of the roof;
[0030] Figure 7 This is a schematic diagram of the ground assembly work of trusses 5 and 6;
[0031] Figure 8 This is a schematic diagram of the hoisting construction of the second set of composite string trusses;
[0032] Fig. 9 This is a schematic diagram of the hoisting construction of two composite tension-string trusses on the outer edge of the building after the hoisting of the composite tension-string trusses is completed. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0034] Example 1
[0035] As attached Figure 1-9 As shown, the present invention discloses a method for hoisting and constructing a large-span composite string truss under space-constrained working conditions, comprising the following steps:
[0036] Step 1: according to the width of the tire frame and along the length direction of the building, two sets of ground assembly tire frame groups are arranged and the composite string trusses are assembled thereon, each set of ground assembly tire frame group includes two ground assembly tire frames;
[0037] Step 2: After the composite chord truss is assembled, it is hoisted. One composite chord truss is hoisted each time. A tower working crawler crane and a main arm working crawler crane are used for hoisting.
[0038] Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles;
[0039] Step 4: After the installation of another set of composite tension-string trusses is completed, the two composite tension-string trusses on the outer edge of the building will be installed.
[0040] Example 2
[0041] As attached Figure 1-9 As shown, the present invention discloses a method for hoisting and constructing a large-span composite string truss under space-constrained working conditions, comprising the following steps:
[0042] Step 1. According to the width of the tyre and along the length direction of the building, set up 2 groups of ground assembly tyre groups and assemble the composite tensioned trusses on them. Each group of ground assembly tyre groups includes 2 ground assembly tyres. For the convenience of lifting, the assembly tyres of 1-2 trusses need to be staggered with the assembly tyres of 3-4 trusses in the length direction by 15-25m, preferably 20m. A spacing of 3-5m, preferably 4m, needs to be reserved between the tyres. The crane travels on both sides of the 4 ground assembly tyres.
[0043] As attached Figure 2As shown in the figure, according to the width of the cradle, 4 ground assembly cradles are set along the length direction of the building. To facilitate hoisting, the assembly cradle of the 1-2 trusses needs to be offset by 20m in the length direction with the assembly cradle of the 3-4 trusses, and a 4m spacing needs to be reserved between the cradles. The crane travels on both sides of the 4 ground assembly cradles. The composite string truss is assembled in the order of 4→3→2→1.
[0044] Step 2: After the composite cable-stayed truss is assembled, the hoisting begins. One composite cable-stayed truss is hoisted each time. A tower-type crawler crane and a main-arm crawler crane are used to coordinate the hoisting.
[0045] Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles;
[0046] Step 4: After the installation of another set of composite string trusses is completed, the two composite string trusses on the outer edge of the building are then installed, as shown in the attached figure. Fig. 9 shown.
[0047] Example 3
[0048] As attached Figure 1-9 As shown, the present invention discloses a method for hoisting and constructing a large-span composite string truss under space-constrained working conditions, comprising the following steps:
[0049] Step 1. According to the width of the tyre and along the length direction of the building, set up 2 groups of ground assembly tyre groups and assemble the composite tensioned trusses on them. Each group of ground assembly tyre groups includes 2 ground assembly tyres. For the convenience of lifting, the assembly tyres of 1-2 trusses need to be staggered with the assembly tyres of 3-4 trusses in the length direction by 15-25m, preferably 20m. A spacing of 3-5m, preferably 4m, needs to be reserved between the tyres. The crane travels on both sides of the 4 ground assembly tyres.
[0050] As attached Figure 2 As shown in the figure, according to the width of the cradle, 4 ground assembly cradles are set along the length direction of the building. To facilitate hoisting, the assembly cradle of the 1-2 trusses needs to be offset by 20m in the length direction with the assembly cradle of the 3-4 trusses, and a 4m spacing needs to be reserved between the cradles. The crane travels on both sides of the 4 ground assembly cradles. The composite string truss is assembled in the order of 4→3→2→1.
[0051] Step 2: After the composite cable-stayed truss is assembled, the hoisting begins. One composite cable-stayed truss is hoisted each time. A tower-type crawler crane and a main-arm crawler crane are used to coordinate the hoisting.
[0052] When hoisting the composite string truss, start with the composite string truss located on the inside of the building, and then hoist from the inside to the outside. When hoisting the composite string truss, the tower working crawler crane is located at the front end of the composite string truss being hoisted, and the main arm working crawler crane is located at the rear end of the composite string truss being hoisted. The two crawler cranes lift together to separate the hoisted composite string truss from the assembly frame.
[0053] During the hoisting process of the composite tension-string truss, the tower working crawler crane moves in the direction perpendicular to the length of the building, and the main arm working crawler moves from the outside to the inside along the length of the building at the same time. The two crawler cranes cooperate to rotate the hoisted composite tension-string truss 90° and hoist it to the bottom of the installation position. After that, the two crawler cranes jointly hoist the hoisted composite tension-string truss to the installation height and fix both ends of the hoisted composite tension-string truss.
[0054] After the composite chord truss to be hoisted is lifted to the position just below the installation position, two crawler cranes jointly lift the composite chord truss to the installation height and fix both ends of the composite chord truss.
[0055] After both ends of the composite chord truss are fixed, a truck crane is used to hoist part of the roof steel structure rods and assemble them so that the composite chord truss obtains a stable support system; preferably, a 50t truck crane is used.
[0056] During the composite string-truss hoisting process, after a group of composite string-trusses is hoisted, a truck crane is used to start installing the rods between the composite string-trusses; preferably, a 50t truck crane is used.
[0057] As attached Figure 3-6 As shown, the trusses are hoisted in the order of 4→3→2→1. After the assembly of truss No. 4 is completed, two crawler cranes enter the site, the tower crawler crane stands at the front end of the truss, and the main arm crawler crane stands at the rear end of the truss, and jointly hoists the composite chord truss No. 4 to separate it from the assembly frame. The tower crawler crane moves in the direction of the green arrow, and the main arm crawler crane moves in the direction of the red arrow at the same time, and cooperates to rotate the composite chord truss No. 4 by 90° and hoist it to the bottom of the installation position. After the safety inspection, the two crawler cranes jointly hoist the composite chord truss No. 4 to the installation height and fix the two ends of the truss. When the double cranes hoist the truss No. 4 to the installation position, a small amount of roof steel structure rods (red) are used to hoist the composite chord truss. After the hoisting of truss No. 4 is completed, the two crawler cranes continue to hoist and fix truss No. 3 according to the above hoisting method. At this time, a 50t truck entered the site and began to install the rods between the No. 3-4 composite string trusses.
[0058] Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles;
[0059] Step 4: After the installation of another set of composite tension-string trusses is completed, the two composite tension-string trusses on the outer edge of the building will be installed.
[0060] Example 4
[0061] As attached Figure 1-9 As shown, the present invention discloses a method for hoisting and constructing a large-span composite string truss under space-constrained working conditions, comprising the following steps:
[0062] Step 1. According to the width of the tyre and along the length direction of the building, set up 2 groups of ground assembly tyre groups and assemble the composite tensioned trusses on them. Each group of ground assembly tyre groups includes 2 ground assembly tyres. For the convenience of lifting, the assembly tyres of 1-2 trusses need to be staggered with the assembly tyres of 3-4 trusses in the length direction by 15-25m, preferably 20m. A spacing of 3-5m, preferably 4m, needs to be reserved between the tyres. The crane travels on both sides of the 4 ground assembly tyres.
[0063] As attached Figure 2 As shown in the figure, according to the width of the cradle, 4 ground assembly cradles are set along the length direction of the building. To facilitate hoisting, the assembly cradle of the 1-2 trusses needs to be offset by 20m in the length direction with the assembly cradle of the 3-4 trusses, and a 4m spacing needs to be reserved between the cradles. The crane travels on both sides of the 4 ground assembly cradles. The composite string truss is assembled in the order of 4→3→2→1.
[0064] Step 2: After the composite cable-stayed truss is assembled, the hoisting begins. One composite cable-stayed truss is hoisted each time. A tower-type crawler crane and a main-arm crawler crane are used to coordinate the hoisting.
[0065] When hoisting the composite string truss, start with the composite string truss located on the inside of the building, and then hoist from the inside to the outside. When hoisting the composite string truss, the tower working crawler crane is located at the front end of the composite string truss being hoisted, and the main arm working crawler crane is located at the rear end of the composite string truss being hoisted. The two crawler cranes lift together to separate the hoisted composite string truss from the assembly frame.
[0066] During the hoisting process of the composite tension-string truss, the tower working crawler crane moves in the direction perpendicular to the length of the building, and the main arm working crawler moves from the outside to the inside along the length of the building at the same time. The two crawler cranes cooperate to rotate the hoisted composite tension-string truss 90° and hoist it to the bottom of the installation position. After that, the two crawler cranes jointly hoist the hoisted composite tension-string truss to the installation height and fix both ends of the hoisted composite tension-string truss.
[0067] After the composite chord truss to be hoisted is lifted to the position just below the installation position, two crawler cranes jointly lift the composite chord truss to the installation height and fix both ends of the composite chord truss.
[0068] After both ends of the composite chord truss are fixed, a truck crane is used to hoist part of the roof steel structure rods and assemble them so that the composite chord truss obtains a stable support system; preferably, a 50t truck crane is used.
[0069] During the composite string-truss hoisting process, after a group of composite string-trusses is hoisted, a truck crane is used to start installing the rods between the composite string-trusses; preferably, a 50t truck crane is used.
[0070] As attached Figure 3-6 As shown, the trusses are hoisted in the order of 4→3→2→1. After the assembly of truss No. 4 is completed, two crawler cranes enter the site, the tower crawler crane stands at the front end of the truss, and the main arm crawler crane stands at the rear end of the truss, and jointly hoists the composite chord truss No. 4 to separate it from the assembly frame. The tower crawler crane moves in the direction of the green arrow, and the main arm crawler crane moves in the direction of the red arrow at the same time, and cooperates to rotate the composite chord truss No. 4 by 90° and hoist it to the bottom of the installation position. After the safety inspection, the two crawler cranes jointly hoist the composite chord truss No. 4 to the installation height and fix the two ends of the truss. When the double cranes hoist the truss No. 4 to the installation position, a small amount of roof steel structure rods (red) are used to hoist the composite chord truss. After the hoisting of truss No. 4 is completed, the two crawler cranes continue to hoist and fix truss No. 3 according to the above hoisting method. At this time, a 50t truck entered the site and began to install the rods between the No. 3-4 composite string trusses.
[0071] Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles;
[0072] As attached Figure 7-8 As shown, a 50t truck crane is used to move the already empty No. 3 and No. 4 assembly frames to the rear end to the No. 5 and No. 6 positions, and then the No. 5 and No. 6 trusses are assembled on the ground. After the No. 1-4 composite string trusses are hoisted, two crawler cranes continue to install the above hoisting method, and the subsequent composite string trusses are hoisted in the order of 7→6→5. When the hoisting of the two sets of composite string trusses is completed, a 160t truck crane is used to start hoisting the outer roof structure of the building.
[0073] Step 4: After the installation of another set of composite string trusses is completed, the two composite string trusses on the outer edge of the building are then installed, as shown in the attached figure. Fig. 9 shown.
[0074] The hoisting construction method of the present invention fully utilizes the ground operating space and hoisting equipment, and adopts the method of hoisting the entire truss to ensure the assembly accuracy of the truss, speed up the construction progress, and reduce the risk of high-altitude operations.
[0075] The present invention adopts a method of assembling the composite string truss on the ground first and then hoisting the whole truss, which greatly improves the installation efficiency of such large-span trusses. After the truss is removed by two cranes, the truss is rotated in coordination and then hoisted, which minimizes the ground space and clearance height required for the hoisting operation. The method of assembling and hoisting four trusses in sequence, and then shifting and assembling them alternately and hoisting them improves the installation efficiency of truck cranes and crawler cranes, effectively speeds up the construction progress, and reduces equipment rental costs. The present invention reduces high-altitude operations and ensures construction safety.
[0076] Finally, it should be noted that the above embodiments are only preferred embodiments of the present invention to illustrate the technical solution of the present invention, but not to limit it, and certainly not to limit the patent scope of the present invention. Any changes or modifications that are made to the main design concept and spirit of the present invention without any substantial meaning, and the technical problems they solve are still consistent with the present invention, should be included in the protection scope of the present invention; in addition, the direct or indirect application of the technical solution of the present invention in other related technical fields is also included in the patent protection scope of the present invention.
Claims
1. A method for installing a large-span composite string truss under space-constrained working conditions, characterized in that: The following steps are involved: Step 1: according to the width of the tire frame and along the length direction of the building, two sets of ground assembly tire frame groups are arranged and the composite string trusses are assembled thereon, each set of ground assembly tire frame group includes two ground assembly tire frames; Step 2: After the composite chord truss is assembled, it is hoisted. One composite chord truss is hoisted each time. A tower working crawler crane and a main arm working crawler crane are used for hoisting. Step 3: After hoisting the composite truss string on one set of ground assembly cradles, move the ground assembly cradle to the outer edge of the building and start assembling the composite truss string thereon, while continuing to hoist the composite truss string on another set of ground assembly cradles; Step 4: After the installation of another set of composite tension-string trusses is completed, the two composite tension-string trusses on the outer edge of the building will be installed.
2. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In step one, the two groups of ground assembly frames are offset by 15 to 25 m, preferably 20 m, in the length direction; the four ground assembly frames are evenly distributed and the distance between two adjacent ground assembly frames is 3 to 5 m, preferably 4 m.
3. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In the step 2, when the composite chord truss is hoisted, the composite chord truss located inside the building is hoisted first, and then hoisted from the inside to the outside in sequence.
4. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In the step 2, when the composite chord truss is hoisted, the tower working crawler crane is located at the front end of the hoisted composite chord truss, and the main arm working crawler crane is located at the rear end of the hoisted composite chord truss. The two crawler cranes jointly lift the hoisted composite chord truss to separate it from the assembly frame.
5. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In the step 2, during the hoisting process of the composite chord truss, the tower working crawler crane moves in a direction perpendicular to the length of the building, and the main arm working crawler moves from the outside to the inside along the length of the building at the same time. The two crawler cranes cooperate to rotate the hoisted composite chord truss 90° and hoist it to just below the installation position. After that, the two crawler cranes jointly hoist the hoisted composite chord truss to the installation height and fix both ends of the hoisted composite chord truss.
6. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 5 is characterized in that: After the composite chord truss to be hoisted is lifted to the position just below the installation position, two crawler cranes jointly lift the composite chord truss to the installation height and fix both ends of the composite chord truss.
7. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 6 is characterized in that: After both ends of the composite chord truss are fixed, a truck crane is used to hoist part of the roof steel structure rods and assemble them so that the composite chord truss obtains a stable support system; preferably, a 50t truck crane is used.
8. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In the step 2, during the composite chord truss hoisting process, after a group of composite chord trusses are hoisted, a truck crane is used to start installing the rods between the composite chord trusses; preferably, a 50t truck crane is used.
9. The method for installing a large-span composite string truss under space-constrained working conditions according to claim 1 is characterized in that: In the step three, when the hoisting of the two sets of composite tensioned trusses is completed, a truck crane is used to start hoisting the outer roof structure of the building; preferably, a 160t truck crane is used to start hoisting the outer roof structure of the building.
10. The method for installing and constructing a large-span composite string truss under space-constrained working conditions according to claim 9 is characterized in that: In step 4, after the three sets of composite tensioned trusses are hoisted, the two crawler cranes assist the truck crane in installing the remaining roof structure.
Citation Information
Patent Citations
Erection method of large-span truss structure in limited space
CN105332515A
Installation method of large-span steel trusses
CN106869319A
Three-stage sliding construction method for ultra-large-span pipe truss in limited space
CN116220380A
Installation method of steel structure of column building
CN117328688A
Method for quickly realizing integral construction of high-altitude steel structure truss girder
CN117403895A