Tunnel construction process automatic identification and recording system based on passive seismic wave monitoring

Through an automated identification and recording system based on passive seismic wave monitoring, machine learning algorithms are used to automatically identify and record passive seismic wave signals at the tunnel construction site, which solves the efficiency and accuracy problems of traditional manual recording methods and improves construction safety and optimization efficiency.

CN118732017APending Publication Date: 2024-10-01SICHUAN JIAOTOU CONSTR ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410716326.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

During the tunnel construction process, the traditional manual recording method is time-consuming and labor-intensive, prone to recording errors, and affects construction safety and efficiency.

Method used

The automatic identification and recording system based on passive seismic wave monitoring uses the signal transmission module, signal acquisition module, data processing classification module and data storage module to perform kurtosis calculation and event classification on the passive seismic wave signal through the machine learning algorithm (SVM classifier). Automatic identification and recording.

Benefits of technology

It improves the accuracy and efficiency of data recording, provides technical support for safety monitoring and process optimization of tunnel construction, and reduces human errors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118732017A_ABST
    Figure CN118732017A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel construction monitoring, in particular to a tunnel construction process automatic identification and recording system based on passive seismic wave monitoring, which comprises a signal transmission module, a signal acquisition module, a data processing and classification module and a data storage module which are connected in sequence, the signal transmission module is used for acquiring a passive seismic wave signal of a tunnel construction site; the signal acquisition module receives and uploads a passive seismic wave signal of a tunnel construction site; the data processing and classifying module is used for distinguishing passive seismic wave signals of a tunnel construction site according to time intervals, performing kurtosis calculation on signals of each partition interval, and performing event classification on kurtosis data of each partition interval through an SVM classifier; and the data storage module is used for storing the passive seismic wave signals of the tunnel construction site and the classified data output by the data processing and classifying module.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel construction monitoring, and in particular to an automatic identification and recording system for a tunnel construction process based on passive seismic wave monitoring. Background Art

[0002] The tunnel construction process usually includes drilling, blasting, loading and transporting slag, and primary support construction. During the construction process, each step will generate a unique passive seismic wave signal. At present, in order to ensure the safe and effective construction and optimize the construction process, the staff usually monitors each construction step, and each construction process and its construction time are entered into the daily worksheet for storage. So far, the construction steps of these steps have been manually recorded and stored by on-site staff, which is not only time-consuming and labor-intensive, but also prone to erroneous data recording due to human factors. Based on this, in order to overcome the above shortcomings, there is an urgent need for a system that can automatically identify and record the tunnel construction process to improve monitoring efficiency and data accuracy. Summary of the invention

[0003] The purpose of the present invention is to provide an automatic identification and recording system for the tunnel construction process based on passive seismic wave monitoring. It utilizes the characteristics of passive seismic wave signals and combines machine learning algorithms to realize automatic identification and recording of the tunnel construction process, overcomes the defects of traditional manual recording methods, improves the accuracy and efficiency of data recording, and provides strong technical support for safety monitoring and process optimization of tunnel construction.

[0004] The embodiments of the present invention are implemented by the following technical solutions:

[0005] An automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring includes: a signal transmission module, a signal acquisition module, a data processing and classification module, and a data storage module connected in sequence;

[0006] The signal transmission module acquires the passive seismic wave signal at the tunnel construction site;

[0007] The signal acquisition module receives and uploads the passive seismic wave signal at the tunnel construction site;

[0008] The data processing and classification module distinguishes the passive seismic wave signals at the tunnel construction site according to time intervals, calculates the kurtosis of the signals in each compartment, and classifies the kurtosis data of each compartment by using a SVM classifier;

[0009] The data storage module stores the passive seismic wave signals at the tunnel construction site and the classified data output by the data processing and classification module.

[0010] Optionally, the signal transmission module is specifically composed of multiple horizontal detectors, multiple vertical detectors and multi-conductor detector cables, the horizontal detectors and vertical detectors are respectively connected to the multi-conductor detector cables, the multi-conductor detector cables are connected to the signal acquisition module, the horizontal detectors and vertical detectors are respectively arranged in the cross section and longitudinal section of the tunnel, wherein the horizontal detectors and vertical detectors are specifically fixedly installed in the lining after the initial support of each excavation step of the tunnel is completed.

[0011] Optionally, before calculating the kurtosis of each separated interval signal, a denoising calculation is also included, and the specific process is as follows:

[0012] Determine the wavelet basis and the number of decomposition layers according to the characteristics of the signals in each separation interval;

[0013] Perform multi-layer wavelet decomposition on the separated interval signal to obtain multiple levels of approximate coefficients and detail coefficients;

[0014] The detail coefficients are subjected to threshold processing, and the detail coefficients and approximate coefficients after threshold processing are subjected to wavelet reconstruction to obtain the denoised separation interval signal.

[0015] Optionally, the kurtosis of each separated interval signal is calculated, and the specific calculation formula is:

[0016]

[0017] Among them, K is the kurtosis value, n is the sample size, and x i is the value of the ith data point, x is the sample mean, and s is the sample standard deviation.

[0018] Optionally, the event classification is performed on the kurtosis data of each separation interval by using an SVM classifier, and the specific process is as follows:

[0019] Extract the kurtosis data of each separation interval and generate corresponding eigenvectors;

[0020] Assign event category labels to each feature vector, aggregate them to form a data set, and divide the data set into a training set and a test set;

[0021] Determine the kernel function, train the SVM classifier using the training set, and evaluate the trained SVM classifier using the test set;

[0022] According to the evaluation results, the parameters of the SVM classifier are updated until the maximum number of updates is reached, and the trained SVM classifier is output. The kurtosis data of each separation interval is classified by the trained SVM classifier to predict the corresponding event type.

[0023] Optionally, the SVM classifier specifically aims to maximize the classification interval and minimize the classification error, and the calculation formula of its objective function is:

[0024]

[0025] Among them, α is the Lagrange multiplier, C is the regularization parameter, and z i is the feature vector of the i-th training sample, y i For z i The class label, y j is the true label of the jth training sample, K(z i ,z j ) is the kernel function, and m is the number of training samples.

[0026] Optionally, the decision function of the trained SVM classifier is:

[0027]

[0028] Among them, z is the new input sample, b is the threshold, K(z i ,z) is the kernel function.

[0029] Optionally, a human-computer interaction module is also included, and the human-computer interaction module is connected to the data processing classification module to display and interact with the classification data output by the data processing classification module.

[0030] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects:

[0031] The embodiment of the present invention utilizes the characteristics of passive seismic wave signals and combines them with machine learning algorithms to realize automatic identification and recording of the tunnel construction process, overcomes the defects of traditional manual recording methods, improves the accuracy and efficiency of data recording, and provides strong technical support for safety monitoring and process optimization of tunnel construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 A schematic diagram of the principle of an automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring provided by an embodiment of the present invention;

[0033] Figure 2 A schematic diagram of the arrangement of horizontal and vertical geophones for earthquakes in a tunnel cross section provided by an embodiment of the present invention;

[0034] Figure 3 A schematic diagram of the arrangement of the tunnel longitudinal section seismic horizontal geophone and vertical geophone provided by an embodiment of the present invention;

[0035] Legend: 1. Horizontal detector; 2. Vertical detector; 3. Initial branch of tunnel; 4. Completed excavation step of tunnel; 5. Next unfinished excavation step of tunnel; 6. Multi-conductor detector cable. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0037] like Figure 1 As shown, the present invention provides one embodiment: an automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring, comprising: a signal transmission module, a signal acquisition module, a data processing and classification module and a data storage module connected in sequence;

[0038] The signal transmission module acquires the passive seismic wave signal at the tunnel construction site;

[0039] The signal acquisition module receives and uploads the passive seismic wave signal at the tunnel construction site;

[0040] The data processing and classification module distinguishes the passive seismic wave signals at the tunnel construction site according to time intervals, calculates the kurtosis of the signals in each compartment, and classifies the kurtosis data of each compartment by using a SVM classifier;

[0041] The data storage module stores the passive seismic wave signals at the tunnel construction site and the classified data output by the data processing and classification module.

[0042] In this embodiment, the signal transmission module is specifically composed of multiple horizontal detectors, multiple vertical detectors and multi-conductor detector cables. The horizontal detectors and vertical detectors are respectively connected to the multi-conductor detector cables, and the multi-conductor detector cables are connected to the signal acquisition module. The horizontal detectors and vertical detectors are respectively arranged in the cross section and longitudinal section of the tunnel, wherein the horizontal detectors and vertical detectors are specifically fixedly installed in the lining after the initial support of each excavation step of the tunnel is completed.

[0043] Specifically, the signal transmission module is used to transmit the passive seismic wave signal collected at the construction site. When the horizontal detector and the vertical detector detect the signal, it is transmitted to the signal acquisition module through the I / Q module, i.e., the multi-conductor detector cable 6. The arrangement of the horizontal detector and the vertical detector is as follows: Figure 2 and 3As shown, the horizontal geophone 1 and the vertical geophone 2 are arranged on the lining after the initial support of each excavation step is completed, and can collect the construction seismic wave signal data of the next excavation step in front that has not completed the initial support in real time, and transmit the data through the multi-conductor geophone cable 6.

[0044] In this embodiment, before calculating the kurtosis of each separated interval signal, a denoising calculation is also included, and the specific process is as follows:

[0045] Determine the wavelet basis and the number of decomposition layers according to the characteristics of the signals in each separation interval;

[0046] Perform multi-layer wavelet decomposition on the separated interval signal to obtain multiple levels of approximate coefficients and detail coefficients;

[0047] The detail coefficients are subjected to threshold processing, and the detail coefficients and approximate coefficients after threshold processing are subjected to wavelet reconstruction to obtain the denoised separation interval signal.

[0048] Specifically, the kurtosis of each separation interval signal is calculated, and the specific calculation formula is:

[0049]

[0050] Among them, K is the kurtosis value, n is the sample size, and x i is the value of the ith data point, x is the sample mean, and s is the sample standard deviation.

[0051] In this embodiment, the kurtosis data of each partition interval is classified into events by using the SVM classifier, and the specific process is as follows:

[0052] Extract the kurtosis data of each separation interval and generate corresponding eigenvectors;

[0053] Assign event category labels to each feature vector, aggregate them to form a data set, and divide the data set into a training set and a test set;

[0054] Determine the kernel function, train the SVM classifier using the training set, and evaluate the trained SVM classifier using the test set;

[0055] According to the evaluation results, the parameters of the SVM classifier are updated until the maximum number of updates is reached, and the trained SVM classifier is output. The kurtosis data of each separation interval is classified by the trained SVM classifier to predict the corresponding event type.

[0056] Specifically, the event category label, i.e., the class label vector y, represents the event type corresponding to each time period (for example, 0 represents a non-rupture event, and 1 represents a rupture event). The determination of the class label usually requires the event type of each time period to be labeled based on the actual situation, using expert knowledge or prior information.

[0057] More specifically, the SVM classifier aims to maximize the classification interval and minimize the classification error. The calculation formula of its objective function is:

[0058]

[0059] Among them, α is the Lagrange multiplier, C is the regularization parameter, and z i is the feature vector of the i-th training sample, y i For z i The class label, y j is the true label of the jth training sample, K(z i ,z j ) is the kernel function, and m is the number of training samples.

[0060] Furthermore, the decision function of the trained SVM classifier is:

[0061]

[0062] Among them, z is the new input sample, b is the threshold, K(z i ,z) is the kernel function.

[0063] In a specific application of this embodiment, a human-computer interaction module is also included. The human-computer interaction module is connected to the data processing classification module to display and interact with the classification data output by the data processing classification module.

[0064] During implementation, Python can be used to visualize the classified data files, generate work views of the start and end times of different construction phases, and generate EXCEL tables for viewing and editing.

[0065] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring, characterized in that: include: A signal transmission module, a signal acquisition module, a data processing and classification module and a data storage module connected in sequence; The signal transmission module acquires the passive seismic wave signal at the tunnel construction site; The signal acquisition module receives and uploads the passive seismic wave signal at the tunnel construction site; The data processing and classification module distinguishes the passive seismic wave signals at the tunnel construction site according to time intervals, calculates the kurtosis of the signals in each compartment, and classifies the kurtosis data of each compartment by using a SVM classifier; The data storage module stores the passive seismic wave signals at the tunnel construction site and the classified data output by the data processing and classification module.

2. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 1 is characterized in that: The signal transmission module is specifically composed of multiple horizontal detectors, multiple vertical detectors and multi-conductor detector cables. The horizontal detectors and vertical detectors are respectively connected to the multi-conductor detector cables, and the multi-conductor detector cables are connected to the signal acquisition module. The horizontal detectors and vertical detectors are respectively arranged in the cross section and longitudinal section of the tunnel, wherein the horizontal detectors and vertical detectors are specifically fixedly installed at the lining after the initial support of each excavation step of the tunnel is completed.

3. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 2 is characterized in that: Before calculating the kurtosis of each separated interval signal, a denoising calculation is also included, and the specific process is as follows: Determine the wavelet basis and the number of decomposition layers according to the characteristics of the signals in each separation interval; Perform multi-layer wavelet decomposition on the separated interval signal to obtain multiple levels of approximate coefficients and detail coefficients; The detail coefficients are subjected to threshold processing, and the detail coefficients and approximate coefficients after threshold processing are subjected to wavelet reconstruction to obtain the denoised separation interval signal.

4. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 3 is characterized in that: The kurtosis of each separation interval signal is calculated, and the specific calculation formula is: Among them, K is the kurtosis value, n is the sample size, and x i is the value of the ith data point, is the sample mean, and s is the sample standard deviation.

5. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 4 is characterized in that: The event classification is performed on the kurtosis data of each separation interval by using the SVM classifier, and the specific process is as follows: Extract the kurtosis data of each separation interval and generate corresponding eigenvectors; Assign event category labels to each feature vector, aggregate them to form a data set, and divide the data set into a training set and a test set; Determine the kernel function, train the SVM classifier using the training set, and evaluate the trained SVM classifier using the test set; According to the evaluation results, the parameters of the SVM classifier are updated until the maximum number of updates is reached, and the trained SVM classifier is output. The kurtosis data of each separation interval is classified by the trained SVM classifier to predict the corresponding event type.

6. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 5 is characterized in that: The SVM classifier specifically aims to maximize the classification interval and minimize the classification error. The calculation formula of its objective function is: Among them, α is the Lagrange multiplier, C is the regularization parameter, and z i is the feature vector of the i-th training sample, y i For z i The class label, y j is the true label of the jth training sample, K(z i ,z j ) is the kernel function, and m is the number of training samples.

7. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 6 is characterized in that: The decision function of the trained SVM classifier is: Among them, z is the new input sample, b is the threshold, K(z i ,z) is the kernel function.

8. The automatic identification and recording system for tunnel construction process based on passive seismic wave monitoring according to claim 1 is characterized in that: It also includes a human-computer interaction module, which is connected to the data processing classification module and is used to display and interact with the classification data output by the data processing classification module.