Indoor alternating-current high-voltage gas insulated metal-enclosed switchgear

By designing a sampling and processing system in indoor AC high-voltage gas-insulated metal-enclosed switchgear, the problem of harm to the human body from insulation gas leakage is solved, the rapid discharge of gas and the reduction of harmfulness are achieved, and the safety of equipment maintenance is ensured.

CN118739103AInactive Publication Date: 2024-10-01LANGZHOU ELECTRIC TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410916300.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When insulation gas leaks from indoor AC high-voltage gas-insulated metal-enclosed switchgear, it is difficult to effectively guide the leaked gas, causing harm to the human body, and the leaked gas is difficult to quickly remove, affecting maintenance safety.

Method used

A device including a closed box, a sealed box, a sampling box, a traction control component, a gas transport component and a gas processing mechanism is designed. The traction control component drives the sampling box to move for gas sampling, and the gas transport component and processing are used The mechanism dilutes and absorbs the leaked gas to ensure that the gas is quickly discharged and reduces its harmfulness.

Benefits of technology

It effectively avoids the risk of insulation gas leakage, quickly discharges the leaked gas, reduces its harm to the human body, ensures the safety of maintenance personnel, and facilitates equipment maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118739103A_ABST
    Figure CN118739103A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of gas-insulated enclosed switches, and provides an indoor alternating-current high-pressure gas-insulated metal-enclosed switchgear, which comprises an enclosed box body, a sealed box body, a sampling box body and a traction control assembly, the enclosed box body is internally provided with a gas box and a plurality of installation box bodies, and the sealed box body is fixedly connected in the enclosed box body. The gas box is fixedly connected in the sealed box body, a port is communicated between the sealed box body and the top of the closed box body, the sampling box body is arranged in the sealed box body in a sliding manner through the sliding control assembly, and the two traction control assemblies are respectively arranged at the top and the bottom of the closed box body. Through the above technical scheme, the problem that in the prior art, when high-insulation gas leakage occurs in the enclosed switchgear, the leaked high-insulation gas cannot be guided easily, so that the high-insulation gas is prone to hurting people is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of gas-insulated enclosed switches, and in particular to an indoor alternating current high-voltage gas-insulated metal-enclosed switchgear. Background Art

[0002] Indoor AC high-voltage gas-insulated metal-enclosed switchgear is a high-voltage power equipment, mainly used in power transmission and distribution networks, and is a switchgear with a higher safety factor in the prior art. The main structure of the AC high-voltage gas-insulated metal-enclosed switchgear is composed of a circuit breaker, a disconnector, a grounding switch and a mutual inductor. The rest is also provided with a cable power supply system and a relay control system matching the above-mentioned device. By cooperating with the circuit breaker and the disconnector, the current transmitted in the power grid can be isolated when a circuit fault occurs. The difference between the AC high-voltage gas-insulated metal-enclosed switchgear and the ordinary current-enclosed switchgear is that after the circuit breaker, disconnector and other equipment are installed in the gas box inside the enclosed switchgear, a high-insulation gas is added to the gas box to ensure the insulation performance of various metal conductors inside the enclosed switchgear through the high-insulation gas, so that the high-insulation gas prevents leakage inside the enclosed switchgear.

[0003] After adding high-insulating gas to the closed switchgear, a large air pressure will be generated inside the closed switchgear. Although the closed switchgear has sufficient airtightness, so that the high-insulating gas in the closed switchgear is not easy to leak, due to the low density of the gas and the long-term use of the closed switchgear, it is inevitable that the high-insulating gas in the closed switchgear will leak. High-insulating gas will cause great harm to the human body. Because high-insulating gas has a high concentration, after the high-insulating gas leaks, the high-insulating gas will escape in the closed switchgear and the air. In order to prevent the high-insulating gas from causing harm to the maintenance personnel, it is necessary to clear all the high-insulating gas before the maintenance personnel can repair the inside of the closed switchgear. In addition, when the closed switchgear leaks, if there are people around the closed switchgear, it is easy to cause great harm to people. Summary of the invention

[0004] The present invention proposes an indoor AC high-voltage gas-insulated metal-enclosed switchgear, which solves the problem that when high-insulation gas leaks, the enclosed switchgear in the related art is not conducive to guiding the leaked high-insulation gas, making it easy for the high-insulation gas to cause harm to people.

[0005] The technical solution of the present invention is as follows: an indoor AC high-voltage gas-insulated metal-enclosed switchgear comprises a closed box, wherein a gas box and a plurality of mounting boxes are arranged inside the closed box, and further comprises: A sealed box body, wherein the sealed box body is fixedly connected to the closed box body, the air box is fixedly connected to the sealed box body, and a through opening is communicated between the sealed box body and the top of the closed box body; A sampling box, wherein the sampling box is slidably disposed in the sealed box via a sliding control assembly; A traction control assembly, wherein the number of the traction control assemblies is set to two, and the two traction control assemblies are respectively arranged at the top and the bottom of the closed box, and the traction control assembly is used to move the sampling box in the sealed box; An air extraction device, the air extraction device being arranged on the top of the closed box; A gas delivery assembly, the gas delivery assembly being arranged between the gas extraction device and the sampling box, and the gas delivery assembly being used to discharge the high-insulation gas from the sealed box; A gas processing mechanism, a processing chamber is arranged between the interior of the closed box and the plurality of installation boxes, the gas processing mechanism is arranged in the processing chamber, and the gas processing mechanism is used to process the insulating gas flowing in the sealed box.

[0006] In order to add gas into the sealed box and sample the gas in the sealed box, it is preferred that an air supply fan and a sampling tube are also included, an installation port is provided between the closed box and the sealed box, the air supply fan is arranged in the installation port, an installation groove is provided on the sampling box, an air outlet pipe is connected in the installation groove, the sampling tube is arranged in the installation groove, and the sampling tube is sealed and connected to the air outlet pipe.

[0007] In order to make the sampling box move in the sealed box, the sliding control component further includes an L-shaped slide rail, a rotating ball and a rotating wheel. The L-shaped slide rails are fixedly connected to both sides of the inner wall of the sealed box. The rotating ball is provided in each of the L-shaped slide rails. The ball joint on the rotating ball is connected to a rotating rod, and the rotating rod is fixedly connected to the sampling box. The rotating wheel is rotatably connected to the rotating rod, and a shock-absorbing ring is provided on the rotating wheel.

[0008] In order to drive the sampling box to move in the sealed box, further, the traction control assembly includes a rotating seat, a winding drum, a driving motor, a fixed frame, a rotating member and a traction rope, the number of the rotating seats is set to two, the two rotating seats are fixedly connected to the closed box, the winding drum is rotatably connected between the two rotating seats, the driving motor is arranged on the rotating seat, the output end of the driving motor is fixedly connected to the winding drum, the fixed frame is fixedly connected to the closed box, both sides of the interior of the fixed frame are rotatably connected to fixed wheels, the rotating member is fixedly connected to the sampling box, and the rotating member is rotatably connected to a rotating block, one end of the traction rope is fixedly connected to the winding drum, the traction rope is wound around the winding drum, and the traction rope passes through the fixed frame, and the other end of the traction rope is fixedly connected to the rotating block.

[0009] In order to extract the insulating gas when the insulating gas leaks in the gas box, further, the gas delivery assembly includes a connecting cylinder, an air collecting hopper, an exhaust port, a connecting cylinder and a first electric cylinder. The bottom of the sampling box is fixedly connected to the connecting cylinder, the bottom of the connecting cylinder is connected to the air collecting hopper, the side wall of the connecting cylinder is connected to the exhaust port, the connecting cylinder is slidably connected to the top of the closed box, the connecting cylinder is connected to a sealing port, the first electric cylinder is arranged on the top of the closed box, and the output end of the first electric cylinder is fixedly connected to the connecting cylinder.

[0010] In order to dilute the leaked gas and reduce the destructiveness of the insulating gas, on the basis of the present solution, the gas processing mechanism includes a cooling cylinder, a fixed box, a water supply box, a cooling water circulation component and a gas dilution component. The sealed box is provided with an opening, and the cooling cylinder is arranged in the opening. The fixed box is connected to the closed box, and the water supply box is fixedly connected to the fixed box. The cooling water circulation component is arranged between the cooling cylinder and the water supply box, and the gas dilution component is arranged on the cooling water circulation component.

[0011] In order to transport water, on the basis of the present scheme, further, the cooling water circulation component includes a serpentine connecting pipe, a return pipeline, a water delivery pump, a sliding pipe sleeve, a connecting pipeline and a second electric cylinder, the number of the serpentine connecting pipes is multiple, one end of the multiple serpentine connecting pipes is connected to the cooling cylinder, the other ends of the multiple serpentine connecting pipes are connected to a fixed cylinder, the cooling cylinder and the water supply box are connected by multiple return pipelines, the water delivery pump is arranged on the water supply box, the input end of the water delivery pump is connected to the water supply box, the sliding pipe sleeve is fixedly connected in the processing chamber, the output end of the water delivery pump is connected to the sliding pipe sleeve, the connecting pipeline is slidingly sealed and connected in the sliding pipe sleeve, the connecting pipeline is connected to the fixed cylinder, the second electric cylinder is arranged on the water supply box, and the output end of the second electric cylinder is fixedly connected to the fixed cylinder.

[0012] In order to reduce the harmfulness of leaked insulating gas, on the basis of the present scheme, further, the gas dilution component includes a water supply cylinder, a spray cylinder, an adsorption layer, a baffle and a drain pipe, the tops of the multiple serpentine connecting pipes are connected to the water supply pipe, the water supply pipe is provided with a valve, the water supply cylinder is connected between the multiple water supply pipes, both ends of the water supply cylinder are connected to the spray cylinder, the bottom of the spray cylinder is connected to multiple spray heads, the adsorption layer is provided between the multiple serpentine connecting pipes, the baffle is fixedly connected between the tops of the multiple serpentine connecting pipes, the drain pipe is provided in the processing chamber, and the drain pipe is connected to the closed box.

[0013] In order to transport the diluted insulating gas to the exhaust device, on the basis of the present solution, further, a gas collecting hopper is included, the gas collecting hopper is connected to the top of the fixed box, and the gas collecting hopper is connected to the exhaust device.

[0014] The working principle and beneficial effects of the present invention are: 1. In the present invention, in order to avoid the risk of insulating gas leakage in the gas box, two traction control components are used to drive the sampling box to move along the L-shaped slide rail in the sealed box, so that the sampling box cooperates with the sampling tube to complete the gas sampling work in various areas of the sealed box, and judge whether there is a problem of insulating gas leakage in the sealed box. Because the sampling box moves in an L-shaped path in the sealed box, in order to prevent the sampling box from colliding with the sealed box and the gas box, firstly, by rotating the ball, the sampling box can be turned over in the sealed box to the greatest extent, and by setting the rotating wheel, the rotating wheel will always be in contact with the inner wall of the sealed box and the outer wall of the gas box, ensuring that the sampling box does not contact the inner wall of the sealed box and the outer wall of the gas box, effectively protecting the sampling box; 2. In the present invention, when there is a problem of insulating gas leakage in the air box, gas is added to the sealed box through the air supply fan, so that the gas dilutes the insulating gas leaked in the air box, and after the sampling box moves to the top of the closed box and the sealed box, the first electric cylinder is started to push the connecting cylinder to move in the direction of the connecting cylinder, so that the sealing port enters the exhaust port, and the insulating gas in the sealed box is discharged to the designated area through the gas collecting hopper, the connecting cylinder and the connecting cylinder by starting the air extraction device, and the harmfulness of the insulating gas is reduced by mixing the ordinary gas with the insulating gas, the speed of discharging the insulating gas in the air box is increased, and the residual amount of the insulating gas in the sealed box is reduced, so that the insulating gas in the air box can be discharged more quickly; 3. In the present invention, after the insulating gas leaks into the sealed box, in order to reduce the harmfulness of the insulating gas, the second electric cylinder is started to move the cooling cylinder, multiple serpentine connecting pipes and multiple adsorption layers into the sealed box, so that when the insulating gas is discharged through the gas collecting bucket, the harmful components in the insulating gas are adsorbed by the adsorption layer, and in order to increase the discharge speed of the insulating gas from the sealed box, part of the insulating gas can also be discharged through the processing chamber, and after the insulating gas is mixed with ordinary gas and passes through the processing chamber, water is transported to the water supply cylinder through multiple water supply pipes on the serpentine connecting pipe, and then the insulating gas passing through the processing chamber is sprayed through the spray cylinder, which can not only greatly reduce the harmful parts of the discharged insulating gas, but also avoid the problem of more residual insulating gas in the sealed box; 4. In the present invention, since a variety of electrical equipment is installed in the air box, a certain temperature will be generated in the air box when the multiple electronic equipment are working. The air supply fan is used to transport ordinary gas into the sealed box, so that the ordinary gas can cool and dissipate heat inside the air box. Since the internal space of the sealed box is large, in order to ensure that the ordinary gas has a good cooling effect on the inside of the air box, the ordinary gas is effectively cooled after passing through the cooling cylinder, ensuring a good cooling effect of the ordinary gas on the air box. 5. Therefore, when the indoor AC high-voltage gas-insulated metal-enclosed switchgear has a leakage problem, it can speed up the discharge of the insulating gas from the closed box and reduce the harmfulness of the discharged insulating gas. It can also avoid excessive residual insulating gas in the closed box, making it easier for maintenance personnel to repair the leakage in the closed box as soon as possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0016] Figure 1 It is a schematic diagram of the structure of a partial cross-section of the present invention; Figure 2 It is a schematic diagram of the overall structure of the present invention; Figure 3 It is a schematic diagram of a partial cross-section of the structure of the air box, the sealed box body, the air supply fan and the L-shaped slide rail in the present invention; Figure 4 It is a schematic diagram of a partial cross-section of the structure of the sampling box, the sliding control assembly and the traction control assembly in the present invention; Figure 5 For the present invention Figure 4 A schematic diagram of the local enlarged structure at point A in the middle; Figure 6 It is a schematic diagram of the structure of the sampling box, the rotating rod and the connecting cylinder in the present invention; Figure 7 For the present invention Figure 6 A schematic diagram of the local enlarged structure at B in the middle; Figure 8 It is a partial cross-sectional structural schematic diagram of the sampling box, the rotating rod, the sampling tube and the connecting cylinder of the present invention; Fig. 9 is a schematic diagram of the structure of the traction control component of the present invention; Fig.10 It is a schematic diagram of the structure of the connecting cylinder and the air collecting hopper in the present invention; Fig.11 It is a schematic diagram of the structure of the connection cylinder, the sealing port and the first electric cylinder in the present invention; Fig.12 It is a structural schematic diagram of the gas processing mechanism in the present invention; Fig.13 It is a schematic diagram of the structure of the cooling cylinder, the fixed box and the water supply box in the present invention; Fig.14 It is a schematic diagram of the structure of the coordination of the serpentine connecting pipe, the fixed cylinder, the water supply cylinder and the spray cylinder in the present invention.

[0017] In the figure: 100, sliding control assembly; 200, traction control assembly; 300, gas delivery assembly; 400, gas processing mechanism; 1. Enclosed box; 2. Air box; 3. Mounting box; 4. Sealed box; 5. Sampling box; 6. Air extraction equipment; 7. Air supply fan; 8. Sampling tube; 9. L-shaped slide rail; 10. Rotating ball; 11. Rotating rod; 12. Rotating wheel; 13. Rotating seat; 14. Winding drum; 15. Driving motor; 16. Fixed frame; 17. Fixed wheel; 18. Rotating part; 19. Rotating block; 20. Traction rope; 21. Connecting cylinder; 22. Air collecting bucket; 2 3. Connecting cylinder; 24. Sealing port; 25. First electric cylinder; 26. Cooling cylinder; 27. Fixed box; 28. Water supply box; 29. ​​Serpentine connecting pipe; 30. Fixed cylinder; 31. Return pipeline; 32. Water delivery pump; 33. Sliding pipe sleeve; 34. Connecting pipeline; 35. Second electric cylinder; 36. Water supply cylinder; 37. Spray cylinder; 38. Adsorption layer; 39. Baffle; 40. Drain pipe; 41. Air collecting hopper; 42. Closed tank. DETAILED DESCRIPTION

[0018] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] like Figures 1 to 14As shown, this embodiment proposes an indoor AC high-voltage gas-insulated metal-enclosed switchgear, comprising a closed box 1, a gas box 2 and a plurality of mounting boxes 3 are arranged inside the closed box 1, and a sealed box 4 is also included. The sealed box 4 is fixedly connected to the closed box 1, and the gas box 2 is fixedly connected to the sealed box 4. A through hole is communicated between the sealed box 4 and the top of the closed box 1. The gas box 2 arranged in the closed box 1 is used to install various components for controlling the closed switch of the circuit, and a gas filling device is arranged on the closed box 1, and insulating gas is filled into the gas box 2 through the gas filling device, and the plurality of mounting boxes 3 are used to install auxiliary components such as cables and relays, so that various electronic components cooperate with each other to realize the switch control of the current. Industry, and after the sampling box 5 and the connecting cylinder 21 are moved out of the through port, a closed groove body 42 is connected on the upper side of the through port, and the sampling box 5 will enter the closed groove body 42, and the closed groove body 42 is provided with an entrance at one end close to the sealing port 24. The closed groove body 42 can prevent the leaked insulating gas from being discharged through the through port. Because the gas box 2 itself is also made of metal bending technology during the production process, there are not many splicing seams on the gas box 2. Therefore, when the gas box 2 is actually monitored for gas leakage risk, most of the insulating gas in the gas box 2 will only leak through the gaps processed by the gas box 2. Therefore, the end face of the gas box 2 without seams can fit with the inner wall of the sealed box body 4, and the leakage risk of the gas box 2 is reduced by the sealed box body 4.

[0020] The invention also includes an air supply fan 7 and a sampling tube 8. An installation port is provided between the closed box 1 and the sealed box 4. The air supply fan 7 is provided in the installation port. An installation slot is provided on the sampling box 5. The installation slot is connected with an air outlet pipe. The sampling tube 8 is provided in the installation slot. The sampling tube 8 is sealed and connected with the air outlet pipe. Ordinary gas outside the closed box 1 is filled into the sealed box 4 through the air supply fan 7, so as to cool various electronic components in the air box 2. When the insulating gas in the air box 2 leaks, the ordinary gas is mixed with the insulating gas, so as to dilute the insulating gas and accelerate the insulating gas from the sealed box 2. The exhaust speed of the box 4 is determined, and a special sampling pump will be arranged in the sampling box 5. The air in the sealed box 4 is sampled by the sampling pump, and the collected gas is added to the sampling tube 8 in the installation groove through the air outlet pipe. The sampling box 5 and the sampling tube 8 cooperate with each other, which can not only meet the daily sampling of the gas in the sealed box 4, but also can sample the residual insulating gas content in the sealed box 4 after the insulating gas leaks in the air box 2 and the insulating gas is discharged. The user can detect the sampled gas in the sampling tube 8, thereby detecting the gas condition in the sealed box 4.

[0021] The sampling box 5 is slidably arranged in the sealed box 4 through a sliding control component 100. The sliding control component 100 includes an L-shaped slide rail 9, a rotating ball 10 and a rotating wheel 12. The inner wall of the sealed box 4 is fixedly connected with the L-shaped slide rail 9 on both sides. A rotating ball 10 is arranged in each L-shaped slide rail 9. The rotating ball 10 is connected with a rotating rod 11 on a ball joint. The rotating rod 11 is fixedly connected to the sampling box 5. The rotating wheel 12 is rotatably connected to the rotating rod 11. A shock-absorbing ring is arranged on the rotating wheel 12. In order to make the sampling box 5 in the sealed box 4, firstly, during the movement of the sampling box 5, the rotating ball 10 can realize the circumferential movement on the L-shaped slide rail 9, so that during the movement of the sampling box 5 and the rotating ball 10, the sampling box 5 and the rotating rod 11 are not affected from turning over along the rotating ball 10, and during the movement of the sampling box 5, the rotating wheel 12 is always fitted between the inner wall of the sealed box 4 and the outer wall of the air box 2, and the shock-absorbing ring provided on the rotating wheel 12 can effectively avoid the collision between the sampling box 5 and the sealed box 4 or the air box 2.

[0022] The number of traction control components 200 is set to two, and the two traction control components 200 are respectively arranged at the top and bottom of the closed box 1. The traction control component 200 is used to move the sampling box 5 in the sealed box 4. The traction control component 200 includes a rotating seat 13, a winding drum 14, a driving motor 15, a fixed frame 16, a rotating member 18 and a traction rope 20. The number of rotating seats 13 is set to two, and the two rotating seats 13 are fixedly connected to the closed box 1. The winding drum 14 is rotatably connected between the two rotating seats 13. The driving motor 15 is arranged on the rotating seat 13, and the output end of the driving motor 15 is fixedly connected to the winding drum 14. The fixed frame 16 is fixedly connected to the closed box 1, and both sides of the interior of the fixed frame 16 are rotatably connected to fixed wheels 17. The sampling box 5 is fixedly connected to the rotating member 18. 8. A rotating block 19 is rotatably connected to the rotating member 18, one end of the traction rope 20 is fixedly connected to the winding drum 14, the traction rope 20 is wound around the winding drum 14, and the traction rope 20 passes through the fixed frame 16, and the other end of the traction rope 20 is fixedly connected to the rotating block 19. When it is necessary to drive the sampling box 5 to move in the sealed box 4, the two driving motors 15 are started to drive the corresponding winding drum 14 to rotate, so as to complete the winding or unwinding operation of the traction rope 20. Through the mutual cooperation between the two winding drums 14, the purpose of moving the sampling box 5 in the sealed box 4 is completed. Because the moving path of the sampling box 5 in the sealed box 4 is L-shaped, the rotating block 19 and the rotating member 18 are in a rotatable connection relationship, so that when the traction rope 20 drives the sampling box 5 to flip, it does not affect the flipping of the sampling box 5 itself.

[0023] The exhaust device 6 is arranged at the top of the closed box 1, and the gas delivery component 300 is arranged between the exhaust device 6 and the sampling box 5. The gas delivery component 300 is used to discharge the high-insulation gas from the sealed box 4. The gas delivery component 300 includes a connecting cylinder 21, an air collecting bucket 22, an exhaust port, a connecting cylinder 23 and a first electric cylinder 25. The bottom of the sampling box 5 is fixedly connected with the connecting cylinder 21, the bottom of the connecting cylinder 21 is connected with the air collecting bucket 22, the side wall of the connecting cylinder 21 is connected with the exhaust port, the connecting cylinder 23 is slidably connected to the top of the closed box 1, and the connecting cylinder 23 is connected with the sealing port 24. The first electric cylinder 25 is arranged at the top of the closed box 1, and the output end of the first electric cylinder 25 is connected to the connecting cylinder 21. The connecting cylinder 23 is fixedly connected. When the insulating gas in the air box 2 leaks, ordinary gas is discharged into the sealed box 4 through the air supply fan 7. The ordinary gas mixed with the insulating gas will flow in the sealed box 4. After the sampling box 5 is moved into the closed slot 42, the first electric cylinder 25 is started to move the connecting cylinder 23, so that the sealing port 24 connected on the connecting cylinder 23 enters the exhaust port, and the gas in the sealed box 4 is extracted and transported to the designated position by driving the exhaust device 6. The insulating gas leaked in the air box 2 is discharged from the sealed box 4 more quickly through the cooperation of the air supply fan 7 and the exhaust device 6. The above method is mainly used when the leakage of insulating gas in the air box 2 is small.

[0024] A processing chamber is arranged between the interior of the closed box 1 and the plurality of mounting boxes 3, a gas processing mechanism 400 is arranged in the processing chamber, the gas processing mechanism 400 is used to process the insulating gas circulating in the sealed box 4, the gas processing mechanism 400 includes a cooling cylinder 26, a fixed box 27, a water supply box 28, a cooling water circulation component and a gas dilution component, an opening is opened on the sealed box 4, a cooling cylinder 26 is arranged in the opening, the fixed box 27 is connected to the closed box 1, the water supply box 28 is fixedly connected to the fixed box 27, a water injection pipe is connected to the water supply box 28, the cooling water circulation component is arranged between the cooling cylinder 26 and the water supply box 28, the gas dilution component is arranged on the cooling water circulation component, and also includes a gas collecting hopper 41, the gas collecting hopper 41 is connected to the top of the fixed box 27, and the gas collecting hopper 41 is connected to the exhaust device The air box 2 is connected to the air supply box 6. Because the temperature of the air box 2 needs to be strictly controlled during the use of various electronic components inside the air box 2, ordinary gas is added into the sealed box 4 through the air supply fan 7 to make the gas cool the air box 2. In order to improve the cooling effect of the gas on the air box 2, cooling water is added into the water supply box 28 so that the cooling water in the water supply box 28 enters the cooling cylinder 26. The surface of the cooling cylinder 26 is set to be concave and convex, which increases the contact area between the ordinary gas and the surface of the cooling cylinder 26, so that the ordinary gas continues to cool after passing through the cooling cylinder 26 area, thereby improving the cooling effect of the ordinary gas on the air box 2. After spraying the insulating gas, the insulating gas in the fixed box 27 is extracted and transported through the gas collecting hopper 41 and the exhaust device 6. The exhaust device 6 is a conventional exhaust device in the prior art. The cooling water circulation component includes a serpentine connecting pipe 29, a return pipe 31, a water delivery pump 32, a sliding pipe sleeve 33, a connecting pipe 34 and a second electric cylinder 35. The number of the serpentine connecting pipes 29 is multiple, one end of the multiple serpentine connecting pipes 29 is connected to the cooling cylinder 26, and the other ends of the multiple serpentine connecting pipes 29 are connected to a fixed cylinder 30. The cooling cylinder 26 and the water supply box 28 are connected by multiple return pipes 31. The water delivery pump 32 is arranged on the water supply box 28, and the input end of the water delivery pump 32 is connected to the water supply box 28. The sliding pipe sleeve 33 is fixedly connected in the processing chamber, and the output end of the water delivery pump 32 is connected to the sliding pipe sleeve 33. The connecting pipe 34 is slidingly sealed and connected in the sliding pipe sleeve 33. The connecting pipe 34 is connected to the fixed cylinder 30. The second electric cylinder 35 is arranged on the water supply box 28. The output end of the cylinder 35 is fixedly connected to the fixed cylinder 30. When it is necessary to add cooling water to the cooling cylinder 26, the water delivery pump 32 is started to discharge the cooling water in the water supply box 28 into the fixed cylinder 30. Then, the cooling water in the fixed cylinder 30 enters the cooling cylinder 26 through a plurality of serpentine connecting pipes 29, and the heated cooling water in the cooling cylinder 26 flows back to the water supply box 28 through the return pipe 31, so that the heated cooling water continues to cool. By setting a sliding sleeve 33 and a connecting pipe 34, when the second electric cylinder 35 drives the serpentine connecting pipe 29 and the fixed cylinder 30 to move, the connecting pipe 34 slides in the sliding sleeve 33, so that after the cooling cylinder 26, the serpentine connecting pipe 29 and the fixed cylinder 30 move, the cooling water in the water supply box 28 can also enter the serpentine connecting pipe 29 and other components. The gas dilution component includes a water supply cylinder 36, a spray cylinder 37, an adsorption layer 38, a baffle 39 and a drain pipe 40. The tops of the multiple serpentine connecting pipes 29 are connected to the water supply pipes, and the water supply pipes are provided with valves. The water supply cylinder 36 is connected between the multiple water supply pipes, and both ends of the water supply cylinder 36 are connected to the spray cylinder 37. The bottom of the spray cylinder 37 is connected to multiple spray heads. An adsorption layer 38 is provided between the multiple serpentine connecting pipes 29. The baffles 39 are fixedly connected between the tops of the multiple serpentine connecting pipes 29. A drain pipe 40 is provided in the processing chamber, and the drain pipe 40 is connected to the closed box 1. Because the concentration of the insulating gas is high and it is easy to cause harm to people, it is necessary to reduce the concentration of the insulating gas in the process of discharging the leaked insulating gas. When the second electric cylinder 35 is started to push the fixed cylinder 30 to move, the cooling cylinder 26 enters the sealed box 4, and part of it passes through the ordinary After the gas-diluted insulating gas enters the processing chamber, the valve is opened to allow cooling water to enter the water supply cylinder 36 through the water supply pipe, and finally the cooling water is sprayed out through the multiple spray heads of the spray cylinder 37 to spray the insulating gas entering the processing chamber, so that the cooling water reduces the harmful parts in the insulating gas, and finally the sprayed water is discharged through the drain pipe 40. After the insulating gas enters the processing chamber, various substances in the insulating gas can also be adsorbed by multiple adsorption layers 38, and the baffle 39 is set to prevent the sprayed cooling water from affecting the adsorption layer 38, causing water immersion on the adsorption layer 38, and affecting the purpose of the adsorption layer 38 to adsorb harmful substances in the insulating gas. The adsorption layer 38 is a type of activated carbon adsorption layer 38 in the prior art, and is a common item used to filter and adsorb harmful parts in the gas.

[0025] The working principle of the indoor AC high-voltage gas-insulated metal-enclosed switchgear is as follows: during the normal working process in the gas box 2, when a small amount of insulating gas leaks inside the gas box 2, the two driving motors 15 are started to drive the two winding drums 14 to rotate, so that the two traction ropes 20 drive the sampling box 5 to move in the L-shaped slide rail 9, so that the sampling box 5 performs sampling operations on multiple areas in the sealed box 4 to determine the insulating gas leakage position and leakage amount, and then the air supply fan 7 is started to transport ordinary gas to the inside of the sealed box 4, and the sampling box 5 is moved to the closed slot 42 in advance, and the first electric cylinder 25 is started to move the connecting cylinder 23, so that the sealing port 24 connected to the connecting cylinder 23 enters the exhaust port, and the gas in the sealed box 4 is extracted and transported to the designated position by driving the exhaust device 6, and the leaked insulating gas in the gas box 2 is discharged from the sealed box 4 more quickly through the cooperation between the air supply fan 7 and the exhaust device 6; When there is a lot of insulating gas leaking in the air box 2, the second electric cylinder 35 is started to push the fixed cylinder 30 to move, so that the cooling cylinder 26 enters the sealed box 4. After part of the insulating gas diluted by ordinary gas enters the processing chamber, the valve is opened to allow cooling water to enter the water supply cylinder 36 through the water supply pipe, and finally the cooling water is sprayed through the multiple spray heads of the spray cylinder 37 to spray the insulating gas entering the processing chamber, so that the cooling book reduces the harmful parts in the insulating gas, and finally the sprayed water is discharged through the drain pipe 40. After the insulating gas enters the processing chamber, various substances in the insulating gas can also be adsorbed by multiple adsorption layers 38, and then the insulating gas in the fixed box 27 is extracted and transported through the gas collecting hopper 41 and the exhaust equipment 6.

[0026] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An indoor AC high-voltage gas-insulated metal-enclosed switchgear, comprising a closed box (1), wherein a gas box (2) and a plurality of mounting boxes (3) are arranged inside the closed box (1), characterized in that: Also includes: A sealed box (4), the sealed box (4) being fixedly connected inside the closed box (1), the air box (2) being fixedly connected inside the sealed box (4), and a through opening being communicated between the tops of the sealed box (4) and the closed box (1); A sampling box (5), the sampling box (5) being slidably disposed in the sealed box (4) via a sliding control assembly (100); A traction control assembly (200), wherein the number of the traction control assemblies (200) is set to two, and the two traction control assemblies (200) are respectively arranged at the top and the bottom of the closed box (1), and the traction control assembly (200) is used to enable the sampling box (5) to move within the sealed box (4); An air extraction device (6), the air extraction device (6) being arranged on the top of the closed box (1); A gas delivery component (300), the gas delivery component (300) being arranged between the gas extraction device (6) and the sampling box (5), the gas delivery component (300) being used to discharge high-insulation gas from the sealed box (4); A gas processing mechanism (400), wherein a processing chamber is provided between the interior of the closed box (1) and the plurality of mounting boxes (3), and the gas processing mechanism (400) is provided in the processing chamber, and the gas processing mechanism (400) is used to process the insulating gas flowing in the sealed box (4).

2. An indoor AC high voltage gas insulated metal enclosed switchgear according to claim 1, characterized in that: Also includes: An air supply fan (7), wherein an installation opening is provided between the closed box body (1) and the sealed box body (4), and the air supply fan (7) is arranged in the installation opening; A sampling tube (8), wherein a mounting groove is provided on the sampling box (5), an air outlet pipe is connected in the mounting groove, the sampling tube (8) is arranged in the mounting groove, and the sampling tube (8) is connected to the air outlet pipe in a sealed manner.

3. An indoor AC high voltage gas insulated metal enclosed switchgear according to claim 2, characterized in that: The sliding control assembly (100) comprises: L-shaped slide rails (9), both sides of the inner wall of the sealed box body (4) being fixedly connected to the L-shaped slide rails (9); A rotating ball (10), wherein each of the L-shaped slide rails (9) is provided with the rotating ball (10), a rotating rod (11) is connected to the rotating ball (10) by a ball joint, and the rotating rod (11) is fixedly connected to the sampling box (5); A rotating wheel (12), the rotating wheel (12) being rotatably connected to the rotating rod (11), and a shock absorbing ring is provided on the rotating wheel (12).

4. The indoor AC high voltage gas insulated metal enclosed switchgear according to claim 3, characterized in that: The traction control assembly (200) comprises: A rotating seat (13), wherein the number of the rotating seats (13) is set to two, and the two rotating seats (13) are fixedly connected to the closed box body (1); A winding drum (14), the winding drum (14) being rotatably connected between the two rotating seats (13); a driving motor (15), the driving motor (15) being arranged on the rotating seat (13), and the output end of the driving motor (15) being fixedly connected to the winding drum (14); A fixed frame (16), the fixed frame (16) being fixedly connected to the closed box (1), and both sides of the interior of the fixed frame (16) being rotatably connected to fixed wheels (17); A rotating member (18), the sampling box (5) is fixedly connected to the rotating member (18), and a rotating block (19) is rotatably connected to the rotating member (18); A traction rope (20), one end of the traction rope (20) being fixedly connected to the winding drum (14), the traction rope (20) being wound around the winding drum (14), and the traction rope (20) passing through the fixed frame (16), and the other end of the traction rope (20) being fixedly connected to the rotating block (19).

5. The indoor AC high voltage gas insulated metal enclosed switchgear according to claim 4, characterized in that: The gas delivery assembly (300) comprises: A connecting cylinder (21), the bottom of the sampling box (5) being fixedly connected to the connecting cylinder (21); An air collecting hopper (22), the bottom of the communicating cylinder (21) being connected to the air collecting hopper (22); An exhaust port, the exhaust port being connected to the side wall of the communicating cylinder (21); A connecting cylinder (23), the connecting cylinder (23) being slidably connected to the top of the closed box (1), and the connecting cylinder (23) being connected to a sealing port (24); A first electric cylinder (25), wherein the first electric cylinder (25) is arranged on the top of the closed box (1), and an output end of the first electric cylinder (25) is fixedly connected to the connecting cylinder (23).

6. The indoor AC high voltage gas insulated metal enclosed switchgear according to claim 5, characterized in that: The gas processing mechanism (400) comprises: A cooling cylinder (26), wherein the sealed box (4) is provided with an opening, and the cooling cylinder (26) is arranged in the opening; A fixed box (27), the fixed box (27) being connected to the closed box (1); A water supply box (28), the water supply box (28) being fixedly connected inside the fixed box (27); A cooling water circulation component, the cooling water circulation component being arranged between the cooling cylinder (26) and the water supply box (28); A gas dilution component is arranged on the cooling water circulation component.

7. An indoor AC high voltage gas insulated metal enclosed switchgear according to claim 6, characterized in that: The cooling water circulation assembly comprises: a serpentine connecting tube (29), wherein the number of the serpentine connecting tubes (29) is multiple, one end of the multiple serpentine connecting tubes (29) is connected to the cooling cylinder (26), and the other ends of the multiple serpentine connecting tubes (29) are connected to a fixed cylinder (30); A return pipeline (31), wherein a plurality of return pipelines (31) are connected between the cooling cylinder (26) and the water supply box (28); a water delivery pump (32), the water delivery pump (32) being arranged on the water supply box (28), the input end of the water delivery pump (32) being in communication with the water supply box (28); A sliding pipe sleeve (33), the sliding pipe sleeve (33) being fixedly connected in the processing chamber, and the output end of the water delivery pump (32) being in communication with the sliding pipe sleeve (33); a connecting pipeline (34), the connecting pipeline (34) being slidably sealed and connected in the sliding sleeve (33), and the connecting pipeline (34) being connected to the fixed cylinder (30); A second electric cylinder (35), wherein the second electric cylinder (35) is arranged on the water supply box (28), and an output end of the second electric cylinder (35) is fixedly connected to the fixed cylinder (30).

8. The indoor AC high voltage gas insulated metal enclosed switchgear according to claim 7, characterized in that: The gas dilution assembly comprises: A water supply cylinder (36), the tops of the plurality of serpentine connecting pipes (29) are all connected to a water supply pipe, a valve is provided on the water supply pipe, and the water supply cylinder (36) is connected between the plurality of water supply pipes; A spray cylinder (37), wherein both ends of the water supply cylinder (36) are connected to the spray cylinder (37), and the bottom of the spray cylinder (37) is connected to a plurality of spray heads; an adsorption layer (38), wherein the adsorption layer (38) is disposed between the plurality of serpentine connecting tubes (29); a baffle (39), wherein the baffle (39) is fixedly connected between the tops of the plurality of serpentine connecting pipes (29); A drainage pipe (40), wherein the treatment chamber is provided with the drainage pipe (40), and the drainage pipe (40) is connected to the closed box (1).

9. The indoor AC high voltage gas insulated metal enclosed switchgear according to claim 8, characterized in that: Also includes: An air collecting hopper (41), the air collecting hopper (41) being connected to the top of the fixed box (27), and the air collecting hopper (41) being connected to the air extraction device (6).