Pier beam connecting device capable of horizontally moving and vertically limiting and construction method of pier beam connecting device

By designing horizontally movable and vertically limited pier-beam connecting devices, and using sliding bearings and flexible cables to achieve vertical and horizontal displacements, the problem of limited seismic resistance in the existing technology is solved and the seismic performance of the bridge is enhanced.

CN118774035APending Publication Date: 2024-10-15CHINA RAILWAY FIRST SURVEY & DESIGN INST GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411051212.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing pier-beam connection device cannot realize horizontal movement and vertical limitation at the same time, resulting in a decrease in seismic resistance.

Method used

A horizontally movable and vertically limited pier-beam connection device is designed, which includes a base plate, a limit plate, a sliding bearing and a flexible cable. The sliding bearing is perpendicular to the limit hole, and the bottom end of the flexible cable is along the length of the sliding bearing. Sliding, the sliding bearing slides along the length direction of the limit hole to achieve displacement release in both vertical and horizontal directions.

Benefits of technology

This device can allow relative displacement between piers and beams while vertically limiting, enhance earthquake resistance, and overcome the problem of mutual interaction between horizontal movement and vertical limiting functions in the prior art.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774035A_ABST
    Figure CN118774035A_ABST
Patent Text Reader

Abstract

The invention relates to a pier beam connecting device capable of horizontally moving and vertically limiting and a construction method of the pier beam connecting device. The device is vertically arranged between a box girder bottom plate and a pier top and comprises a base plate, a limiting plate, a sliding bearing and a flexible inhaul cable from bottom to top. The base plate is horizontally arranged and fixed to the top of a pier. The two limiting plates are vertically arranged and symmetrically fixed to the top face of the base plate, and horizontal strip-shaped limiting holes are formed in the limiting plates. Two ends of the sliding bearing are inserted into the limiting holes; the top end of the flexible inhaul cable upwards penetrates through the box girder bottom plate and is anchored above the box girder bottom plate, and the bottom end of the flexible inhaul cable surrounds and is connected to the periphery of the sliding bearing; the length direction of the sliding bearing is perpendicular to the length direction of the limiting hole, the bottom end of the flexible inhaul cable can slide in the length direction of the sliding bearing, and the sliding bearing can slide in the length direction of the limiting hole. The device is compatible with relative displacement between piers and beams while serving as a vertical limiting device, and is compact in structure and high in shock resistance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a horizontally movable and vertically limited pier-beam connecting device and a construction method thereof. Background Art

[0002] Near-fault earthquakes have the significant characteristics of high seismic intensity and strong vertical components. In the seismic design of near-fault bridges, the seismic force needs to be reduced horizontally by dissipating the displacement energy of the seismic isolation bearings, and limit devices need to be set vertically to prevent the beams from falling.

[0003] However, the seismic design of conventional bridges is mainly to resist horizontal earthquake motion. The conventional seismic isolation bearings and steel beam stoppers widely used in railway bridges do not have vertical limit functions, and vertical limit devices need to be set separately. However, some existing bridge vertical limit devices are directly connected to the beam and the pier during installation. While limiting the vertical position, they also limit the horizontal relative displacement of the beam and the pier, hindering the horizontal displacement energy dissipation of the seismic isolation bearings, which is not conducive to the seismic resistance of the structure.

[0004] Therefore, it is necessary to propose new measures to overcome the above-mentioned defects. Summary of the invention

[0005] The purpose of the present invention is to provide a horizontally movable and vertically limited pier-beam connection device and a construction method thereof, so as to solve the problem that the current pier-beam connection device cannot achieve horizontal movement and vertical limitation at the same time.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A horizontally movable vertically limited pier-beam connection device, which is vertically arranged between the box beam bottom plate and the pier top, and comprises a base plate, a limit plate, a sliding bearing and a flexible cable from bottom to top;

[0008] The base plate is horizontally arranged and fixed to the top of the pier;

[0009] The limiting plates are provided with two, which are vertically arranged and symmetrically fixed to the top surface of the base plate, and the limiting plates are provided with horizontal and strip-shaped limiting holes;

[0010] The sliding bearing is arranged horizontally, and both ends are inserted into the limiting holes;

[0011] The top end of the flexible cable passes through the bottom plate of the box beam upwards and is anchored above the bottom plate of the box beam, and the bottom end of the flexible cable surrounds and is connected to the outer periphery of the sliding bearing;

[0012] The length direction of the sliding bearing is perpendicular to the length direction of the limiting hole, the bottom end of the flexible cable can slide along the length direction of the sliding bearing, and the sliding bearing can slide along the length direction of the limiting hole.

[0013] Furthermore, the top end of the flexible cable is anchored above the bottom plate of the box beam through a cable anchoring head.

[0014] Furthermore, the cable anchoring head comprises a protective cover, wherein a horizontal anchor gasket and a horizontal spring force transmission ring type open hole gasket are arranged from top to bottom in the protective cover, an opening is arranged at the center of each of the anchor gasket and the spring force transmission ring type open hole gasket, and a vertical buffer spring is arranged between the anchor gasket and the spring force transmission ring type open hole gasket;

[0015] The top end of the flexible cable passes through the opening of the spring force transmission ring-type open hole gasket, the buffer spring and the opening of the anchor gasket in sequence, and is connected to the anchor head. The anchor head is located above the anchor gasket, and the diameter of the anchor head is larger than the opening diameter of the anchor gasket.

[0016] Furthermore, a damping energy dissipation filling sheet is provided at the bottom of the spring force transmission ring type perforated gasket, an opening is provided at the center of the damping energy dissipation filling sheet, and the flexible cable passes through the opening of the damping energy dissipation filling sheet.

[0017] Furthermore, the device also includes a beam-embedded protective wall, which is vertically preset in the box beam bottom plate, and the flexible cable passes through the beam-embedded protective wall and through the box beam bottom plate.

[0018] Furthermore, the beam pre-embedded protective wall comprises, from top to bottom, a first annular sheet, a pipe and a second annular sheet;

[0019] The first annular sheet is horizontally arranged and located on the top surface of the box beam bottom plate, the second annular sheet is horizontally arranged and located on the bottom surface of the box beam bottom plate, and the pipeline is vertically connected between the first annular sheet and the second annular sheet and inserted in the box beam bottom plate.

[0020] Furthermore, the bottom end of the flexible cable surrounds the outer circumference of the sliding bearing and is fixed by a fastener, and the fastener is located above the sliding bearing and is tightly sleeved on the outside of the flexible cable and its end.

[0021] Further, the base plate is fixed to the top of the pier by means of bolt sleeves and bolts;

[0022] The bolt sleeve is vertically preset on the top of the pier, and a vertical through hole is provided on the base plate. The bolt is inserted into the bolt sleeve through the vertical through hole and fixed.

[0023] On the other hand, a construction method of the horizontally movable vertically limited pier-beam connection device as described above is provided, the method comprising:

[0024] During the construction of bridge piers, bolt sleeves are preset on the top of the piers;

[0025] During the construction of the box girder, a pre-buried retaining wall is pre-installed on the bottom plate of the box girder;

[0026] Determining structural parameters of the device;

[0027] Insert the bolts into the vertical through holes of the base plate and insert the bolt sleeves to fix the base plate to the top of the pier;

[0028] Fix the bottom of the limit plate to the base plate;

[0029] Insert both ends of the sliding bearing into the limiting holes on the limiting plate;

[0030] Pass the top end of the flexible cable upward through the embedded guard wall of the beam, and install the cable anchor head for anchoring; pass the bottom end of the flexible cable through the gap between the sliding bearing and the base plate, circle the outer diameter of the sliding bearing, align it with the front end cable body, and use fasteners to fix and lock it.

[0031] Further, determining the device structure parameters includes:

[0032] Determine the cross-sectional area A of the core material of the flexible cable s :

[0033]

[0034] Then determine the core cross-sectional diameter D of the flexible cable s ;

[0035] in:

[0036] F is the vertical tensile bearing capacity;

[0037] [σ t ] is the allowable tensile stress of the core material;

[0038] Determine the length of the middle section of the sliding bearing, that is, the clear distance L1 between the two limit plates:

[0039] L1=2ΔY+D s ;

[0040] in:

[0041] ΔY is the lateral displacement stroke;

[0042] Determine the cross-sectional radius R of the middle section of the sliding bearing:

[0043]

[0044] in:

[0045] [σ w ] is the allowable bending stress of the bearing material;

[0046] Determine the cross-sectional diameter r of the end of the sliding bearing:

[0047]

[0048] in:

[0049] [τ] is the allowable shear stress of the bearing material;

[0050] Determine the length B of the upper limit hole of the limit plate:

[0051] B = 2ΔX + 2r;

[0052] in:

[0053] ΔX is the longitudinal horizontal displacement;

[0054] Determine the height h range of the upper limit hole of the limit plate:

[0055] r≤h <R;

[0056] Determine the number of bolt sleeves N:

[0057]

[0058] in:

[0059] [f] is the allowable pull-out resistance of a single set of bolt sleeves.

[0060] Compared with the prior art, the present invention has the following beneficial effects:

[0061] The present invention provides a horizontally movable vertically limited pier-beam connecting device and a construction method thereof. The device serves as a vertical limiting device and is compatible with the relative displacement between the pier and the beam. The bottom end of the flexible cable is slidably connected to the outer periphery of the sliding bearing and can slide along the length direction of the sliding bearing. Moreover, the sliding bearing can slide along the length direction of the limiting hole of the limiting plate, thereby realizing the displacement release in both the vertical and horizontal directions and effectively enhancing the earthquake resistance. BRIEF DESCRIPTION OF THE DRAWINGS

[0062] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.

[0063] Figure 1 It is a three-dimensional structural diagram of the device of the present invention.

[0064] Figure 2 It is a cross-sectional view of the device of the present invention.

[0065] Figure 3 It is a longitudinal cross-sectional view of the device of the present invention.

[0066] Figure 4 It is a plan view of the pier top of the device of the present invention.

[0067] Figure 5 It is a cross-sectional view of the cable anchoring head of the device of the present invention.

[0068] Figure 6 It is an axial view of the pre-embedded protective wall of the beam portion of the device of the present invention.

[0069] Figure 7 It is an axial view of the sliding bearing of the device of the present invention.

[0070] Figure 8 It is an axonometric view of the limit plate of the device of the present invention.

[0071] Fig. 9 It is an assembly diagram of the pier top components of the device of the present invention.

[0072] Fig.10 It is a schematic diagram of the assembly relationship between the flexible cable and the sliding bearing in the present invention.

[0073] The symbols in the figure are:

[0074] 1 is a flexible cable, 2 is a cable anchor head, 3 is a beam embedded wall, 4 is a sliding bearing, 5 is a limit plate, 6 is a base plate, 7 is a bolt sleeve, 8 is a bolt, and 9 is a fastener;

[0075] 2-1 is an anchor head, 2-2 is an anchor gasket, 2-3 is a buffer spring, 2-4 is a spring force transmission ring type open hole gasket, 2-5 is a damping energy dissipation filling sheet, and 2-6 is a protective cover;

[0076] 3-1 is the first annular sheet, 3-2 is the pipe, and 3-3 is the second annular sheet. DETAILED DESCRIPTION

[0077] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. The preferred embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly understood.

[0078] In the description of the present invention, it is necessary to understand that the terms "center", "upper", "lower", "vertical", "horizontal", "top", "bottom", "inside", "outside", "lateral", "longitudinal" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0079] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection", "setting" and the like should be understood in a broad sense, for example, it can be fixedly connected or set, or detachably connected or set, or integrally connected or set. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0080] Meanwhile, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance. Of course, such objects can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.

[0081] It should also be noted that although the order of steps is mentioned in the method description, in some cases, they may be performed in an order different from that shown here, and this should not be construed as a limitation on the order of the steps.

[0082] In a specific implementation, Figure 1 The length direction of the middle sliding bearing 4 is defined as the transverse direction, and the length direction of the upper limit hole of the limit plate 5 is defined as the longitudinal direction.

[0083] The existing pier-beam connection device cannot take into account both horizontal movement and vertical limitation. Generally, two structural devices are set to realize the above two functions, which will affect each other and lead to reduced seismic resistance. The present invention provides a pier-beam connection device with horizontal movement and vertical limitation, which can vertically limit the distance between the bottom plate of the box beam and the top of the pier, and horizontally realize sliding relative movement in both the horizontal and vertical directions, thus overcoming the defects of the existing device.

[0084] like Figure 1-Figure 3 The device is vertically arranged between the bottom plate of the box beam and the top of the pier, and includes a base plate 6, a limit plate 5, a sliding bearing 4 and a flexible cable 1 from bottom to top.

[0085] like Figure 4, the base plate 6 is horizontally arranged and fixed to the top of the pier. Specifically, the base plate 6 is fixed to the top of the pier by means of a bolt sleeve 7 and a bolt 8. The bolt sleeve 7 is vertically preset on the top of the pier, and a vertical through hole is arranged on the base plate 6. The bolt 8 is inserted into the bolt sleeve 7 through the vertical through hole and fixed. The base plate 6 can be a plate made of metal, alloy or other materials.

[0086] like Figure 8 and Fig. 9 , two limit plates 5 are provided, which are arranged vertically and symmetrically fixed to the top surface of the base plate 6. In order to enhance the stability of the structure, stiffening ribs can also be provided on one or both sides of the limit plate 5. The limit plate 5 is provided with horizontal and strip-shaped limit holes. Figure 7 , the sliding bearing 4 is arranged horizontally, and the two ends are inserted into the limiting holes. The sliding bearing 4 includes a middle section and an end. The middle section is located between the two limiting plates 5, and the end is located in the limiting hole. The diameter of the end is smaller than the diameter of the middle section, and it can move along the length direction of the limiting hole to realize the longitudinal activity function of the device. In order to prevent the sliding bearing 4 from slipping out of the limiting hole, an enlarged end or a limiting plug can be installed at the end of the sliding bearing 4. The limiting plate 5 can be a plate made of metal, alloy or other materials, which has been treated with corrosion protection. It can be an integrally formed structure with the base plate 6, or it can be fixedly connected to each other. If both are made of metal materials, they can be welded and fixed to each other. The strip-shaped limiting hole is the track for its horizontal activity. The height of the limiting hole can be slightly larger than the diameter of the end of the sliding bearing 4, allowing the sliding bearing 4 to undergo a small vertical displacement, and is compatible with the small vertical displacement of the ball steel type seismic isolation bearing during operation. The sliding bearing 4 can be a circular cross-section rod made of metal, alloy or other materials, which has been treated with corrosion protection.

[0087] The top end of the flexible cable 1 passes through the bottom plate of the box beam upward and is anchored above the bottom plate of the box beam, and the bottom end of the flexible cable 1 surrounds and is connected to the outer periphery of the sliding bearing 4. Specifically, Figure 5The top of the flexible cable 1 is anchored above the bottom plate of the box girder through the cable anchor head 2. The cable anchor head 2 includes a protective cover 2-6, in which a horizontal anchor gasket 2-2 and a horizontal spring force transmission ring-type perforated gasket 2-4 are arranged from top to bottom. The anchor gasket 2-2 and the spring force transmission ring-type perforated gasket 2-4 are both provided with openings in the center, and a vertical buffer spring 2-3 is provided between the anchor gasket 2-2 and the spring force transmission ring-type perforated gasket 2-4. The outer periphery of the anchor gasket 2-2 and the spring force transmission ring-type perforated gasket 2-4 slightly rubs against the inner wall of the protective cover 2-6. The top end of the flexible cable 1 passes through the opening of the spring force transmission ring-type perforated gasket 2-4, the buffer spring 2-3 and the opening of the anchor gasket 2-2 in sequence, and is connected to the anchor head 2-1. The anchor head 2-1 is located above the anchor gasket 2-2, and the diameter of the anchor head 2-1 is larger than the diameter of the opening of the anchor gasket 2-2. A damping energy dissipation filling sheet 2-5 is provided at the bottom of the spring force transmission ring-type perforated gasket 2-4, and an opening is provided in the center of the damping energy dissipation filling sheet 2-5. The flexible cable 1 passes through the opening of the damping energy dissipation filling sheet 2-5. The damping energy dissipation filling sheet 2-5 can be made of rubber or other materials. Fig.10 The bottom end of the flexible cable 1 is wrapped around the outer periphery of the sliding bearing 4 and fixed by a fastener 9. The fastener 9 is located above the sliding bearing 4 and is tightly sleeved on the flexible cable 1 and its end. The flexible cable 1 can slide along the length direction of the sliding bearing 4 to realize the lateral activity function of the device.

[0088] In some embodiments, in order to further improve the structural stability of the device, a force transmission rod or other structures may be installed on the upper part of the flexible cable 1. In addition, after the top of the force transmission rod is provided with an external thread, the cable anchoring head 2 may be replaced with a nut for end anchoring, and an anti-falling device may be provided under the nut, such as a force transmission cone with a small top and a large bottom.

[0089] In addition, the device also includes a beam embedded protective wall 3, which is vertically preset in the box beam bottom plate, and the flexible cable 1 passes through the box beam bottom plate through the beam embedded protective wall 3. The beam embedded protective wall 3 is a channel for the flexible cable 1 to pass through the box beam bottom plate. Figure 6 The beam embedded protective wall 3 includes a first annular sheet 3-1, a pipe 3-2, and a second annular sheet 3-3 from top to bottom. The first annular sheet 3-1 is horizontally arranged and located on the top surface of the box beam bottom plate, the second annular sheet 3-3 is horizontally arranged and located on the bottom surface of the box beam bottom plate, the pipe 3-2 is vertically connected between the first annular sheet 3-1 and the second annular sheet 3-3, and inserted in the box beam bottom plate, and the inner diameter of the pipe 3-2 matches the outer diameter of the flexible cable 1. The beam embedded protective wall 3 is made of metal, alloy or other materials and is treated with anti-corrosion. The pipe 3-2 and the second annular sheet 3-3 can be transitioned through a trumpet-shaped structure to protect the flexible cable 1 and prevent it from being cut.

[0090] In the above structure, the length direction of the sliding bearing 4 is perpendicular to the length direction of the limiting hole, the bottom end of the flexible cable 1 can slide along the length direction of the sliding bearing 4, and the sliding bearing 4 can slide along the length direction of the limiting hole, so that the bridge pier can be displaced in both the horizontal and longitudinal directions under the box girder.

[0091] The construction method of the above device specifically comprises the following steps:

[0092] S1: During the construction of the bridge pier, a bolt sleeve 7 is preset on the top of the bridge pier. The bolt sleeve 7 is made of metal, alloy or other materials and is treated with anti-corrosion.

[0093] S2: During the construction of the box girder, a pre-embedded protective wall 3 is provided on the bottom plate of the box girder.

[0094] S3: Determine the device structure parameters;

[0095] S4: inserting the bolt 8 into the vertical through hole of the base plate 6 and inserting the bolt sleeve 7, thereby fixing the base plate 6 to the top of the pier;

[0096] S5: Fix the bottom of the limiting plate 5 to the base plate 6;

[0097] S6: Insert both ends of the sliding bearing 4 into the limiting holes on the limiting plate 5;

[0098] S7: The top end of the flexible cable 1 is passed upward through the embedded beam wall 3, and the cable anchor head 2 is installed for anchoring. The bottom end of the flexible cable 1 is passed through the gap between the sliding bearing 4 and the base plate 6, and after a circle around the outer diameter of the sliding bearing 4, it is aligned with the front end of the cable body and fixed and locked with the fastener 9. The fastener 9 is made of metal, alloy or other materials, and is treated with corrosion resistance. One or more fasteners are provided. The end of the flexible cable 1 after being hooped on the sliding bearing 4 is locked together with the front end to achieve a closed-loop connection between the flexible cable 1 and the sliding bearing 4. In order to reduce the friction between the flexible cable 1 and the sliding bearing 4 and avoid damage to the flexible cable 1, an inner ring or other structure can be installed outside the sliding bearing 4 to achieve the purpose of reducing friction.

[0099] The process of determining the device structure parameters is specifically as follows:

[0100] S301: Determine the cross-sectional area A of the core material of the flexible cable 1 according to the tensile calculation s :

[0101]

[0102] Considering the protective layer process, the core material cross-sectional diameter D of the flexible cable 1 is determined. s ;

[0103] in:

[0104] F is the vertical tensile bearing capacity;

[0105] [σ t ] is the allowable tensile stress of the core material;

[0106] S302: According to the lateral displacement travel requirement, determine the length of the middle section of the sliding bearing 4, that is, the clear distance L1 between the two limit plates 5:

[0107] L1=2ΔY+D s ;

[0108] in:

[0109] ΔY is the lateral displacement stroke;

[0110] S303: According to the bending calculation, determine the cross-sectional radius R of the middle section of the sliding bearing 4:

[0111]

[0112] in:

[0113] [σ w ] is the allowable bending stress of the bearing material;

[0114] S304: According to the shear calculation, determine the cross-sectional diameter r of the end of the sliding bearing 4:

[0115]

[0116] in:

[0117] [τ] is the allowable shear stress of the bearing material;

[0118] S305: Determine the length B of the upper limit hole of the limit plate 5 according to the longitudinal displacement stroke requirement:

[0119] B = 2ΔX + 2r;

[0120] in:

[0121] ΔX is the longitudinal horizontal displacement;

[0122] S306: Determine the height h range of the upper limit hole of the limit plate 5 according to the limit relationship:

[0123] r≤h <R;

[0124] S307: According to the pull-out calculation, the number N of bolt sleeves 7 is determined:

[0125]

[0126] in:

[0127] [f] is the allowable pull-out resistance of a single set of bolt sleeves.

[0128] This device can realize horizontal activity and vertical limit, and also has the following characteristics:

[0129] 1. This device only needs to embed small-diameter reinforcement pipes in the beam part. The opening of the beam part is small, which has little impact on the beam structure. It can be installed, disassembled and replaced later, which is more flexible.

[0130] 2. This device only needs to embed bolt sleeves on the pier top, and the other pier top parts are installed by bolts. The pier construction is convenient, and the device can be installed, disassembled and replaced later, which is more flexible;

[0131] 3. The mechanism of this device is simple and clear, and it is easy to process, install and replace. The materials are conventional and the cost is low.

[0132] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.

Claims

1. A horizontally movable and vertically limited pier-beam connection device, characterized in that: The device is vertically arranged between the bottom plate of the box beam and the top of the pier, and comprises, from bottom to top, a base plate (6), a limit plate (5), a sliding bearing (4) and a flexible cable (1); The base plate (6) is horizontally arranged and fixed to the top of the pier; The limiting plates (5) are provided with two, which are vertically arranged and symmetrically fixed to the top surface of the base plate (6), and the limiting plates (5) are provided with horizontal and strip-shaped limiting holes; The sliding bearing (4) is arranged horizontally, with both ends inserted into the limiting holes; The top end of the flexible cable (1) passes through the box beam bottom plate upwards and is anchored above the box beam bottom plate, and the bottom end of the flexible cable (1) surrounds and is connected to the outer periphery of the sliding bearing (4); The length direction of the sliding bearing (4) is perpendicular to the length direction of the limiting hole, the bottom end of the flexible cable (1) can slide along the length direction of the sliding bearing (4), and the sliding bearing (4) can slide along the length direction of the limiting hole.

2. The horizontally movable and vertically limited pier-beam connection device according to claim 1 is characterized in that: The top end of the flexible cable (1) is anchored above the bottom plate of the box beam via a cable anchoring head (2).

3. The horizontally movable and vertically limited pier-beam connection device according to claim 2 is characterized in that: The cable anchor head (2) comprises a protective cover (2-6), wherein a horizontal anchor gasket (2-2) and a horizontal spring force transmission ring-type perforated gasket (2-4) are arranged from top to bottom in the protective cover (2-6), an opening is arranged at the center of each of the anchor gasket (2-2) and the spring force transmission ring-type perforated gasket (2-4), and a vertical buffer spring (2-3) is arranged between the anchor gasket (2-2) and the spring force transmission ring-type perforated gasket (2-4); The top end of the flexible cable (1) passes through the opening of the spring force transmission ring-shaped open hole gasket (2-4), the buffer spring (2-3) and the opening of the anchor gasket (2-2) in sequence, and is connected to the anchor head (2-1). The anchor head (2-1) is located above the anchor gasket (2-2), and the diameter of the anchor head (2-1) is larger than the opening diameter of the anchor gasket (2-2).

4. The horizontally movable and vertically limited pier-beam connection device according to claim 3 is characterized in that: A damping energy dissipation filling sheet (2-5) is arranged at the bottom of the spring force transmission ring-shaped perforated gasket (2-4), an opening is arranged at the center of the damping energy dissipation filling sheet (2-5), and the flexible cable (1) passes through the opening of the damping energy dissipation filling sheet (2-5).

5. The horizontally movable and vertically limited pier-beam connection device according to claim 1 is characterized in that: The device also includes a beam pre-embedded protective wall (3), which is vertically preset in the box beam bottom plate, and the flexible cable (1) passes through the beam pre-embedded protective wall (3) and through the box beam bottom plate.

6. The horizontally movable and vertically limited pier-beam connection device according to claim 5 is characterized in that: The embedded retaining wall (3) of the beam part includes a first annular thin sheet (3-1), a pipe (3-2), and a second annular thin sheet (3-3) from top to bottom; The first annular thin sheet (3-1) is horizontally arranged and located on the top surface of the box girder bottom plate, the second annular thin sheet (3-3) is horizontally arranged and located on the bottom surface of the box girder bottom plate, and the pipe (3-2) is vertically connected between the first annular thin sheet (3-1) and the second annular thin sheet (3-3) and is inserted into the box girder bottom plate.

7. The pier-beam connection device with horizontal movement and vertical limit according to claim 1, characterized in that: The bottom end of the flexible cable (1) is wound around the outer periphery of the sliding bearing (4) and fixed by a fastener (9), and the fastener (9) is located above the sliding bearing (4) and sleeved tightly outside the flexible cable (1) and its end.

8. The pier-beam connection device with horizontal movement and vertical limit according to claim 1, characterized in that: The base plate (6) is fixed to the top of the pier by a bolt sleeve (7) and a bolt (8); The bolt sleeve (7) is vertically preset at the top of the pier, the base plate (6) is provided with a vertical through hole, and the bolt (8) passes through the vertical through hole and is inserted into the bolt sleeve (7) and fixed.

9. The construction method of the pier-beam connection device with horizontal movement and vertical limit as claimed in claim 1, characterized in that: The method includes: When constructing the pier, preset the bolt sleeve (7) at the top of the pier; When constructing the box girder, preset the embedded retaining wall (3) of the beam part at the bottom plate of the box girder; Determine the structural parameters of the device; Insert the bolt (8) into the vertical through hole of the base plate (6) and insert it into the bolt sleeve (7), so as to fix the base plate (6) to the top of the pier; Fix the bottom of the limit plate (5) to the base plate (6); Insert both ends of the sliding bearing (4) into the limit holes on the limit plate (5); Pull the top end of the flexible cable (1) upward through the embedded retaining wall (3) of the beam part, install the cable anchor head (2) for anchoring, pass the bottom end of the flexible cable (1) through the gap between the sliding bearing (4) and the base plate (6), wind around the outer diameter of the sliding bearing (4) for one week, align with the front cable body, and fix and lock it with a fastener (9).

10. The construction method of the pier-beam connection device with horizontal movement and vertical limit according to claim 9, characterized in that: Determining the structural parameters of the device includes: Determine the cross-sectional area A of the core material of the flexible cable (1) s : Then determine the core cross-sectional diameter D of the flexible cable (1) s ; Wherein: F is the vertical tensile bearing capacity; [σ t ] is the allowable tensile stress of the core material; Determine the length of the middle section of the sliding bearing (4), that is, the net distance L1 between the two limit plates (5): L1=2ΔY+D s ; Wherein: ΔY is the lateral displacement stroke; Determine the cross-sectional radius R of the middle section of the sliding bearing (4): Wherein: [σ w ] is the allowable bending stress of the bearing material; Determine the cross-sectional diameter r of the end of the sliding bearing (4): Wherein: [τ] is the allowable shear stress of the bearing material; Determine the length B of the limit hole on the limit plate (5): B = 2ΔX + 2r; wherein: ΔX is the longitudinal horizontal displacement stroke; Determine the height h range of the limit hole on the limit plate (5): r ≤ h < R; Determine the number N of bolt sleeves (7): Wherein: [f] is the allowable uplift force of a single bolt sleeve.