Construction method for preventing infilled wall from being separated from beam plate bottom

By pre-embedding connecting components and using mortar to fill gaps during construction, combined with the horse-drawn structure, the problem of cracking at the connection between the filling wall and the bottom of the beam plate was solved, the stability and seismic performance of the structure were improved, and the masonry efficiency and The overall strength of the wall.

CN118855232APending Publication Date: 2024-10-29GUANGZHOU PEARL RIVER CONSTR DEV CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411264345.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

During construction, the connection between the infill wall and the bottom of the beam plate often leads to cracking due to different linear expansion coefficients of the materials, affecting the structural stability and seismic performance.

Method used

The connecting components are pre-embedded at the bottom of the beam plate and a groove is reserved at the top of the filling wall. The connecting components extend into the groove. A gap is reserved between the bottom of the beam plate and the top of the filling wall. Fine stone concrete is poured and the gap is filled with mortar. Reinforcement materials The connection between the structural columns and the wall is made to reduce the risk of cracks, and a horse-shaped structure is used at the connection between the structural column and the wall to enhance the seismic performance.

Benefits of technology

It effectively reduces the risk of cracking at the connection between the infill wall and the bottom of the beam plate, improves the overall stability and seismic performance of the structure, and at the same time improves the masonry efficiency and the strength and durability of the wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118855232A_ABST
    Figure CN118855232A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for preventing an infilled wall from being separated from the bottom of a beam plate, which comprises the following steps: pre-burying a connecting component at the bottom of the beam plate, reserving a groove in the top of the infilled wall, extending the connecting component, and reserving a gap in the bottom of the beam plate and the top of the infilled wall, so that a wall body has enough space for settlement and contraction; the gap between the bottom of the beam slab and the top of the infilled wall is filled with mortar, and the connecting component is embedded in the mortar, so that effective transition is formed between the concrete structure and the masonry, connection between two materials with different linear expansion coefficients is enhanced, cracks generated due to the difference between the two materials are effectively reduced, and the service life of the concrete structure is prolonged. And the risk of cracking at the joint of the infilled wall and the beam plate bottom is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and in particular to a construction method in which a filling wall and a beam and slab bottom are not separated. Background Art

[0002] In modern buildings, infill walls are non-load-bearing walls. Although they do not directly bear the weight of the building, their connection method with the main structure (such as beams and slabs) has an important impact on the overall stability of the structure. The stable connection between the infill wall and the beams and slabs can enhance the integrity of the structure, improve the seismic performance of the building, and ensure that the building can remain relatively stable and reduce damage when natural disasters such as earthquakes occur.

[0003] In the related art, in order to ensure the stability of the structure, beam and slab construction is usually carried out first, and then the infill wall construction is carried out. After the wall is built, due to the different material selections between the beam and slab and the top of the infill wall, the linear expansion coefficients of the materials are different, and the wall often shrinks, resulting in cracks in the plaster at the junction with the bottom of the beam. Therefore, there is still room for improvement. Summary of the invention

[0004] In order to reduce the risk of cracking at the junction of the infill wall and the bottom of the beam and slab, the present application provides a construction method in which the infill wall and the bottom of the beam and slab are not separated.

[0005] The present application provides a construction method for the infill wall and the beam and slab bottom to be constructed without separation, which adopts the following technical solution: A construction method for a filling wall and a beam-slab bottom that are not separated comprises the following steps: S1: Beam-slab construction, pre-embed the connecting components at the bottom of the beam-slab; S2: Infill wall construction, a groove is reserved at the top of the infill wall, the lower end of the connecting member extends into the groove, and a gap is reserved between the bottom of the beam and the top of the infill wall; S3: Formwork construction, the formwork forms a casting cavity at the groove; S4: pour fine stone concrete into the casting cavity, bury the connecting member in the fine stone concrete in the groove, and then make mortar, and fill the mortar into the gap reserved between the bottom of the beam and the top of the filling wall; S5: Fix the wire mesh or mesh cloth at the joint of the filling wall and carry out the painting construction.

[0006] By adopting the above technical scheme, a connecting member is embedded at the bottom of the beam and a groove is reserved at the top of the infill wall. The connecting member extends into the groove, and a gap is reserved at the bottom of the beam and the top of the infill wall so that the wall has enough space for settlement and contraction. Fine stone concrete is poured into the casting cavity, and the connecting member is embedded in the fine stone concrete in the groove. Then, the gap between the bottom of the beam and the top of the infill wall is filled with mortar, so that an effective transition is formed between the concrete structure and the masonry, and the connection between the two materials with different linear expansion coefficients is enhanced, which effectively reduces the cracks caused by the difference between the two materials, which is beneficial to reducing the risk of cracking at the connection between the infill wall and the bottom of the beam.

[0007] Preferably, in the infill wall construction step of S2, structural column reinforcement is reserved, and structural column construction is carried out, and the masonry at the connection between the structural column and the infill wall is built into a tooth joint.

[0008] By adopting the above technical solution, in the connection between the structural column and the wall, the masonry at the connection between the structural column and the filling wall is built into a tooth joint, and the protruding part of the structural column forms a staggered connection with the wall, thereby enhancing the seismic performance of the structure.

[0009] Preferably, in the filling wall construction step of S2, a thin layer of mortar with a thickness of 3 to 5 mm is used between the blocks, and the filling wall is cured after completion of the construction.

[0010] By adopting the above technical solution, the use of thin-layer mortar can greatly reduce the amount of mortar used, and masonry workers can complete the application of mortar and the placement of bricks more quickly, thereby improving the overall masonry efficiency. In addition, the thin-layer mortar has better adhesion, making the bond between bricks tighter, which helps to improve the overall strength of the wall. Thin-layer mortar can also better disperse stress and improve the crack resistance and durability of the wall.

[0011] Preferably, in the formwork erection step of S3, formworks are arranged on both sides of the filling wall respectively, and are locked and fixed with tension screws, and grouting holes are reserved on one side of the formworks.

[0012] Preferably, in the formwork erection step of S3, a sleeve is sleeved on the outer circumference of the tension screw, the length of the sleeve is equal to the thickness of the filling wall, and both ends of the sleeve respectively abut against the inner sides of the two formworks.

[0013] By adopting the above technical scheme, the tension screws fix the formwork on the wall through the pulling action, which effectively prevents the formwork from shifting or deforming during the concrete pouring process. The mortar is poured into the grooves through the grouting holes of the formwork. During the grouting process, the tension screws can withstand the lateral pressure and other loads of the concrete, which is beneficial to ensure the stability of the formwork. In addition, a sleeve is sleeved on the outer periphery of the tension screws, and the sleeve serves as a top-up mechanism. When the tension screws pull and lock the two formworks, the sleeve generates a reaction force on the inner side of the formwork, which prevents the deformation of the middle part of the formwork caused by the pulling, and is beneficial to the fixation of the formwork.

[0014] Preferably, in the grouting step of S4, a mortar gun is used to fill the gap between the top of the filling wall and the bottom of the beam and slab. The mortar gun muzzle is inserted into the gap and the mortar is moved at a uniform speed from one end to the other end of the gap until the mortar overflows. The mortar is cured after initial setting.

[0015] By adopting the above technical solution, using a mortar gun for sealing can quickly inject mortar into the gap, improving construction efficiency. The mortar gun can penetrate deep into the gap to ensure that the mortar can be evenly filled into the entire gap. The construction is carried out by moving at a uniform speed from one end to the other end of the gap until the mortar overflows, thereby achieving complete closure of the gap and reducing the risk of hollowing and cracking. Proper maintenance after the mortar is initially set can further improve the connection strength between the filling wall and the beam slab.

[0016] Preferably, in the grouting step of S4, the mortar gun is inserted into the gap at an angle of 15° to 25°.

[0017] By adopting the above technical solution, since the edges of the gaps are often not completely straight or regular, the slope design can reduce the friction between the mortar gun and the edges of the gaps, allowing the mortar to enter the gaps more smoothly to adapt to gaps of different shapes and sizes, which is conducive to improving the uniformity and completeness of the filling.

[0018] Preferably, in the mortar making step of S4, cement mortar is used as the mortar, the ratio of cement to sand in the mortar is 1:3, and 6% to 8% of an expansion agent is added to the mortar.

[0019] By adopting the above technical solution, a dry hard mortar is configured, which has low slump and high dry hardness, which is conducive to improving the overall strength and stability of the mortar structure in the gap. The expansion agent can generate stronger electrostatic effects between the cement particles and sand particles in the mortar, thereby enhancing the bonding force between the mortar and the base materials such as the filling wall, beam and slab, and improving the stability of the overall structure.

[0020] Preferably, in the filling wall construction step of S2, the overlap between the upper and lower skins of the blocks is not less than one third of the length of the blocks, and the length is less than 150 mm, and the thickness of the mortar joint is controlled within the range of 3 to 5 mm.

[0021] By adopting the above technical solution, effective overlap between the upper and lower skins of the building blocks can be achieved, thereby increasing the overall structural strength of the wall, and helping to tightly connect the building blocks together to form a more stable overall structure.

[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. By pre-embedding the connecting components at the bottom of the beam slab and reserving a groove at the top of the infill wall, the connecting components extend into it, and reserving a gap at the bottom of the beam slab and the top of the infill wall, so that the wall has enough space for settlement and shrinkage, and the gap between the bottom of the beam slab and the top of the infill wall is filled with mortar, and the connecting components are buried in the mortar, so that an effective transition is formed between the concrete structure and the masonry, and the connection between the two materials with different linear expansion coefficients is enhanced, effectively reducing the cracks caused by the difference between the two materials, which is conducive to reducing the risk of cracking at the junction of the infill wall and the bottom of the beam slab; 2. In the connection between the structural column and the wall, the masonry at the connection between the structural column and the filling wall is built into a tooth joint, and the protruding part of the structural column forms a staggered connection with the wall to enhance the seismic performance of the structure; 3. The tension screws fix the formwork to the wall through the tensioning action, effectively preventing the formwork from shifting or deforming during the concrete pouring process. The mortar is poured into the groove through the grouting holes of the formwork. During the grouting process, the tension screws can withstand the lateral pressure and other loads of the concrete, which is conducive to ensuring the stability of the formwork. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is an overall view of a construction method in which a filling wall and a beam and slab bottom are not separated, which is disclosed in an embodiment of the present application.

[0024] Figure 2 It is a partial view of a construction method in which a filling wall and a beam and slab bottom are not separated, which is disclosed in an embodiment of the present application.

[0025] Figure 3 yes Figure 2 Cross-sectional view along the A-A direction.

[0026] Figure 4 This is a view of the position of grouting holes in a construction method in which a filling wall and a beam and slab bottom are not separated, which is disclosed in an embodiment of the present application.

[0027] Figure 5 The present application discloses a schematic diagram of the state of caulking in a construction method in which a filling wall and a beam and slab bottom are not separated.

[0028] Explanation of the accompanying reference numerals: 1. Beam and slab; 2. Infill wall; 3. Structural column; 4. Groove; 5. Formwork; 6. Gap; 7. Connecting member; 8. Mortar gun; 9. Grouting hole; 10. Tension screw; 11. Casing. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1-5 This application is described in further detail.

[0030] The present application embodiment discloses a construction method in which the filling wall and the beam and slab bottom are not separated. Figure 1 and Figure 2 , including the following steps: S1: Construction of beam and slab 1. Pre-embed the connection member 7 at the bottom of the beam and slab 1, wherein the connection member 7 is specifically a U-shaped tie bar or a planted tie bar. Before pouring concrete on the beam and slab 1, accurately determine the position and quantity of the connection member 7 (U-shaped tie bar or planted tie bar) according to the design drawings (refer to Figure 2 and Figure 3 ,). The U-shaped tie bars need to be bent and formed in advance to ensure that the size meets the design requirements; the embedded tie bars need to be completed through drilling, hole cleaning, glue injection, and embedded reinforcement to ensure that the depth, direction, and verticality of the embedded reinforcement meet the requirements of the specifications. The connecting member 7 is located directly below the construction position of the filling wall 2 and is arranged at intervals along the extension direction of the filling wall 2 to ensure the effective connection between the filling wall 2 and the beam slab 1. The connecting member 7 is the basis for the connection between the filling wall 2 and the beam slab 1. By pre-embedding the connecting member 7, it helps to improve the stability and safety of the overall structure.

[0031] S2: Laying down of filling wall 2. Before laying down filling wall 2, the blocks need to be moistened to improve their water absorption and adhesion. In the laying step of filling wall 2, a thin layer of mortar is used between blocks, and the thickness of the mortar layer and the thickness of the mortar joints are strictly controlled. The thickness of the mortar layer is 3 to 5 mm to ensure that the blocks are firmly bonded. The thickness of the mortar joints is controlled within the range of 3 to 5 mm. The upper and lower skins of the blocks overlap by no less than one-third of the length of the blocks, and the length dimension is less than 150 mm to achieve effective overlap between the upper and lower skins of the blocks, and to connect the blocks tightly together to form a more stable overall structure, thereby increasing the overall structural strength of the wall, and improving the integrity and shear strength of the wall. During the laying process, attention should also be paid to the staggered overlap between the blocks to avoid the formation of through seams.

[0032] A plurality of grooves 4 are reserved at the top of the filling wall 2, and the grooves 4 are spaced apart along the extension direction of the filling wall 2. The width of the groove 4 is 120 mm and the height is 300 mm. The groove 4 is connected to both sides of the filling wall 2, and the lower end of the connecting member 7 extends into the groove 4. A gap 6 of 20 to 30 mm is reserved between the bottom of the beam slab 1 and the top of the filling wall 2, so that the wall has enough space for settlement and contraction.

[0033] During the construction of the filling wall 2, steel bars for the structural column 3 are reserved and the structural column 3 is constructed. The masonry at the connection between the structural column 3 and the filling wall 2 is built into a tooth joint. The protruding part of the structural column 3 is staggered with the wall to enhance the seismic performance of the structure. After the wall of the filling wall 2 is completed, it is maintained.

[0034] S3: Template 5 construction. Figure 4 and Figure 5 In the step of building the template 5, the templates 5 are arranged on both sides of the filling wall 2. The templates 5 need to be accurately cut and assembled according to the position and size of the groove 4. The templates 5 are made of flat, smooth, and non-deformed plates to ensure that the surface of the poured mortar is flat and beautiful. The template 5 forms a pouring cavity at the groove 4 for the subsequent pouring of fine stone concrete. It should be noted that the covering area of ​​the template 5 is larger than the side opening area of ​​the groove 4. When the template 5 blocks the side opening of the groove 4, there is an overlapping area between the edge of the template 5 and the masonry of the filling wall 2.

[0035] When the template 5 is installed, the templates 5 on both sides of the filling wall 2 are locked and fixed with the tension screws 10 to ensure the stability and sealing of the template 5. In addition, a sleeve 11 is sleeved on the outer circumference of the tension screw 10. The length of the sleeve 11 is equal to the thickness of the filling wall 2, and the two ends of the sleeve 11 are respectively against the inner sides of the two templates 5. This prevents the middle part of the template 5 from being deformed when the template 5 is pulled against each other, and is conducive to fixing the template 5.

[0036] In addition, a grouting hole 9 is reserved on the top of one side of the template 5 for pouring fine stone concrete. The precise construction of the template 5 provides a good space guarantee for the filling of fine stone concrete, ensuring that the fine stone concrete can be fully filled into the groove 4 and tightly combined with the connecting member 7. At the same time, the reserved grouting hole 9 and gap also provide convenience for subsequent construction and improve construction efficiency.

[0037] In this embodiment, the top of the template 5 on one side of the infill wall 2 is against the bottom of the beam slab 1, and there is a gap between the top of the template 5 on the other side and the bottom of the beam slab 1 to facilitate the subsequent caulking operation. After the template 5 is built, an acceptance inspection is required to ensure that the template 5 is accurately positioned, the size meets the requirements, and it is firmly fixed without looseness.

[0038] S4: The groove 4 is filled with fine stone concrete by grouting. When filling, the fine stone concrete is first poured into the groove 4 through the grouting hole 9 until it is filled, and the flow of the fine stone concrete is observed to avoid bubbles and voids, and the connecting member 7 is buried in the fine stone concrete in the groove 4. After the filling is completed, it is necessary to wait for the fine stone concrete to initially set before the subsequent caulking treatment.

[0039] Prepare mortar. The mortar adopts cement mortar, the ratio of cement to sand in the mortar is 1:3, and 6% to 8% of expansion agent is added to the mortar. After the preparation is completed, the mortar is stuffed into the gap 6 between the top of the filling wall 2 and the bottom of the beam slab 1 through the mortar gun 8 to perform the filling treatment. This forms an effective transition between the concrete structure and the masonry, strengthens the connection between the two materials with different linear expansion coefficients, effectively reduces the cracks caused by the difference between the two materials, and is conducive to reducing the risk of cracking at the joint between the filling wall 2 and the bottom of the beam slab 1.

[0040] Since the edge of the gap 6 is often not completely straight or regular, the mortar gun 8 is inserted into the gap 6 at an angle of 15° to 25°. The mortar gun 8 moves along the gap 6 from one end to the other end at a uniform speed and performs the filling construction until the mortar overflows, and the mortar is cured after the initial setting.

[0041] S5: Fix a steel mesh or mesh cloth at the junction of the filling wall 2 to enhance the crack resistance. The steel mesh or mesh cloth needs to be firmly bonded to the filling wall 2 without hollowing. Then, the painting construction is carried out. First, the interface agent is applied to enhance the bonding strength between the filling wall 2 and the painting layer, then the putty is applied in layers and polished flat, and finally the paint is applied to complete the painting work. Fixing the steel mesh or mesh cloth at the junction effectively prevents the crack problem caused by stress concentration and improves the overall durability and aesthetics of the filling wall 2. The painting construction further beautifies the wall surface and provides the necessary protection and decorative functions.

[0042] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A construction method in which the filling wall and the bottom of the beam and slab are not separated, characterized in that: The following steps are involved: S1: Construction of the beam and slab (1), pre-embedding the connecting member (7) at the bottom of the beam and slab (1); S2: The infill wall (2) is built, a groove (4) is reserved at the top of the infill wall (2), the lower end of the connecting member (7) extends into the groove (4), and a gap (6) is reserved between the bottom of the beam slab (1) and the top of the infill wall (2); S3: The template (5) is constructed, and the template (5) forms a casting cavity at the groove (4); S4: pouring fine stone concrete into the casting cavity, embedding the connecting member (7) in the fine stone concrete in the groove (4), and then preparing mortar, and filling the mortar into the gap (6) reserved between the bottom of the beam plate (1) and the top of the filling wall (2); S5: Fix the steel wire mesh or mesh cloth at the joint of the filling wall (2) and carry out the painting construction.

2. A construction method for the infill wall and the beam and slab bottom not to be separated according to claim 1, characterized in that: In the step of building the filling wall (2) of S2, steel bars for the structural columns (3) are reserved, and the structural columns (3) are constructed. The masonry at the connection between the structural columns (3) and the filling wall (2) is built into tooth joints.

3. The method for construction of a filling wall and a beam-slab bottom that are not separated according to claim 1, characterized in that: In the step of building the filling wall (2) of S2, a thin layer of mortar is used between the blocks, with a thickness of 3 to 5 mm. After the wall of the filling wall (2) is built, it is cured.

4. The construction method of the infill wall and the beam and slab bottom not being separated according to claim 1 is characterized in that: In the template (5) construction step of S3, the templates (5) are arranged on both sides of the filling wall (2), and are locked and fixed with tension screws (10), and grouting holes (9) are reserved on one side of the template (5).

5. The construction method of the infill wall and the beam and slab bottom not being separated according to claim 4 is characterized in that: In the template (5) construction step of S3, a sleeve (11) is sleeved on the outer circumference of the tension screw (10), the length of the sleeve (11) is equal to the thickness of the filling wall (2), and the two ends of the sleeve (11) respectively abut against the inner sides of the two templates (5).

6. The method for constructing a filling wall without separation from the bottom of a beam and slab according to claim 1, characterized in that: In the grouting step of S4, a mortar gun (8) is used to seal the gap (6) between the top of the filling wall (2) and the bottom of the beam and slab (1). The mouth of the mortar gun (8) is inserted into the gap (6), and the mortar gun (8) is moved at a uniform speed from one end to the other end of the gap (6) until the mortar overflows. After the mortar has initially set, it is cured.

7. A construction method for the infill wall and the beam and slab bottom not to be separated according to claim 6, characterized in that: In the grouting step of S4, the mortar gun (8) is inserted into the gap (6) at an angle of 15° to 25°.

8. The method for constructing a filling wall without separation from the bottom of a beam and slab according to claim 1, characterized in that: In the mortar making step of S4, cement mortar is used as the mortar, the ratio of cement to sand in the mortar is 1:3, and 6% to 8% of an expansion agent is added into the mortar.

9. The method for construction of a filling wall and a beam-slab bottom that are not separated according to claim 1, characterized in that: In the step of building the filling wall (2) of S2, the overlap between the upper and lower skins of the blocks is not less than one third of the length of the blocks, and the length is less than 150 mm, and the thickness of the mortar joint is controlled within the range of 3 to 5 mm.

Citation Information

Patent Citations

  • Novel light connecting structure of block filling wall and frame structure and construction technique

    CN105804274A

  • Construction method aiming at subsequently built filling wall beam bottom seam plugging

    CN106049869A

  • Embedded steel bar anchoring method for tying wall top of infilled wall and beam or plate

    CN112962830A

  • Anti-crack connecting joint of steel beam and infilled wall

    CN211172416U

  • Ceramsite concrete partition wall mounting structure

    CN211447356U