Supporting structure of underneath penetrating uplift pile and construction method of supporting structure
The tube curtain method is used to connect the tunnel segments and the upper building structure to form an overall anti-floating structure, which solves the anti-floating failure and construction difficulty problems caused by underground excavation and penetration of anti-outlift piles, and realizes safe and efficient construction of deep underground tunnels, widening The scope of application of the mechanical undercover excavation method has been expanded.
Patent Information
- Application Number
- CN202411065740.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-08-05
AI Technical Summary
The existing technology breaks the anti-uplift piles when digging underground structures, resulting in the failure of the anti-floating effect. The construction is difficult, and the steel bars cannot be removed and welded to the steel arch frame during mechanical excavation, which poses safety risks. Moreover, the existing method is suitable for shallow burials. Tunnels and water-rich layers are not suitable for construction deep underground and under dense buildings.
The pipe curtain method is used to connect the existing building structure and the connecting steel pipe of the tunnel segment. The overall structure is formed through the curved beam plate and the reinforced ring beam. The upper building structure is connected first to avoid the risk of anti-floating failure caused by the connection after breaking the anti-lift pile. In addition, reinforcement reinforcement and grouting treatment are provided at the machinable openings to form a stable connection.
It achieves safe and efficient penetration of deep underground tunnel construction, avoids anti-floating failure and structural cracking problems, broadens the scope of application of mechanical undercover excavation methods in deep and dense buildings, and improves construction safety and efficiency.
Smart Images

Figure CN118855501A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, in particular to a supporting structure for underpass anti-pulling piles and a construction method thereof. Background Art
[0002] With the advancement of urbanization, more and more cities are building subways to relieve the pressure of ground transportation. Since the line planning lags behind the urban development, subway excavation inevitably needs to pass under existing buildings. In the process of underground space development, when using the dark excavation method to pass through existing tunnels and / or buildings, it is usually necessary to break the retaining piles, anti-pulling piles, etc., which will have a great impact on the existing buildings and affect the anti-floating effect of the original structure. Especially under poor geological conditions, the construction is difficult and there are technical risks.
[0003] The existing anti-floating method adopts the method of cutting the original anti-pull pile and connecting it with the existing underground structure. For example, the patent with the publication number of CN 113062750 A discloses a construction method of a tunnel structure under the underground structure anti-pull pile. When the anti-pull pile is encountered during the excavation process, the main reinforcement of the anti-pull pile is chiseled out, and steel arch frames are erected on the left and right sides of the anti-pull pile concrete, and the steel arch frames are densely arranged around and welded with the anti-pull pile main reinforcement of the anti-pull pile, and then concrete is sprayed to close the initial support. Finally, after the initial support reaches the design strength and the deformation is stable, the secondary lining is poured to complete the construction of the tunnel structure under the underground structure anti-pull pile. However, this method first breaks the anti-pull pile, and then connects the anti-pull pile with the later built building structure, which destroys the original anti-floating stability; at the same time, when mechanical excavation is adopted, it is impossible to cut off the exposed steel bars and steel arch frames for welding, and at the same time, the anti-pull piles after cutting are difficult to form a whole with the tunnel segments, which destroys the stability of the original structure and has a large safety hazard. Therefore, this method is not suitable for mechanical excavation.
[0004] In order to solve this problem, the patent with publication number CN 113803073 A discloses a construction method for a tunnel structure with artificial obstacle removal in a water-rich sand layer, and provides a solution for the shield tunneling encountering a pile foundation. First, the area around the anti-pull pile is frozen, and then the cutting and lining are completed, and then the concrete is backfilled, and finally the mechanical excavation is carried out. This method expands the application scope of mechanical excavation, but the freeze-thaw process and concrete backfilling process of this method are complicated, the cost is high, and it is only applicable to shallow buried conditions. The freezing method is applicable to water-rich layers. When the groundwater is less, construction will lead to risks such as landslides. The patent with publication number CN 116291552 A discloses a shallow buried tunnel anti-floating structure, which provides a tunnel structure for anti-pull piles under the underground structure. It achieves a good anti-floating effect of the shallow buried tunnel by setting an anti-floating longitudinal beam in the hole and connecting it with the anti-pull pile below. However, this method does not consider the situation where there are dense buildings above the construction structure that need to pass through the anti-pull piles, and this method is also only applicable to the construction of shallow buried tunnels, and does not consider the situation of passing under the existing buildings.
[0005] In order to solve the above problems, it is necessary to design a structural form and construction method of pull-out piles for mechanical underground excavation to solve the problem of damage to anti-floating safety caused by the need to remove pull-out piles under underground structures during underground excavation of existing tunnels and / or buildings. Summary of the invention
[0006] In view of the deficiencies in the above-mentioned background technology, the present invention proposes a support structure for underpass anti-pullout piles and a construction method thereof, which solves the problems in the prior art of destroying the anti-floating safety and high construction difficulty coefficient caused by the need to remove anti-pullout piles during dark excavation under existing tunnels and / or buildings.
[0007] The technical solution of the present invention is implemented as follows: a support structure for underpass anti-pullout piles, including a connecting steel pipe that connects an existing building structure and a tunnel segment by a pipe curtain method, a curved beam plate is provided on the side of the tunnel segment corresponding to the connecting steel pipe, a reinforcing ring beam is provided on the side of the existing building structure corresponding to the connecting steel pipe, one end of the connecting steel pipe passes through the tunnel segment and is connected to the curved beam plate, and the other end passes through the existing building structure and is connected to the reinforcing ring beam and / or the existing building structure; after one side of the existing building structure is connected to the tunnel segment by the connecting steel pipe, the existing anti-pullout pile is cut off, and then the other side of the existing building structure is connected to the tunnel segment by the connecting steel pipe. The above structure avoids the risk of temporary failure of the anti-floating effect caused by first breaking the anti-pullout pile and then connecting it in the conventional method of underpass anti-pullout piles.
[0008] Further preferably, a cuttable hole is provided on the tunnel segment at the connection corresponding to the connecting steel pipe, the curved beam plate is fitted with the inner wall of the tunnel segment, the connecting steel pipe passes through the cuttable hole and the curved beam plate and is fixedly connected to the curved beam plate through a second connecting end plate.
[0009] Further preferably, after the cuttable opening is cut, a segment door is formed for the connecting steel pipe to pass through, the cuttable opening is reinforced with steel bars and a steel lining is provided on the inside of the cuttable opening, the curved beam plate can seal the inside of the cuttable opening, the curved beam plate is fixedly connected to the tunnel segment, and the outside of the cuttable opening is grouting treated.
[0010] As a preferred solution, the curved beam plate is a curved steel beam, which includes a plurality of annular curved steel sheets, two adjacent curved steel sheets are fixed by welding, and the curved steel sheets and the segment rings of the tunnel segments are staggered. The axial length of the curved steel sheets along the tunnel segment is twice the segment ring width.
[0011] As another preferred solution, the curved beam-slab is a concrete lining beam-slab, and the concrete lining beam-slab is fixed on the inner wall of the tunnel segment; this structure can be applied to the case of passing under the existing structure anti-pulling piles by the mining method.
[0012] Further preferably, a construction portal is provided on the side of the existing building structure corresponding to the connecting steel pipe, a reinforcing ring beam is provided on the inner side of the construction portal, grouting reinforcement is performed on the outer side of the construction portal, and the connecting steel pipe passes through the construction portal and is connected to the existing building structure through a first connecting end plate.
[0013] Further preferably, a support structure is provided in the area to be excavated in the existing building structure. The connecting steel pipe is an oblique straight pipe or an arc-shaped pipe; and a drill hole for fixing the pull-out pile is reserved at the lower part of the tunnel segment.
[0014] A construction method of a support structure under a pull-out pile, comprising the following steps: S1: Determine the size and model of the connecting steel pipe and the curved beam plate, and determine the position of the segment ring with the cuttable opening based on the position relationship.
[0015] S2: Set up a support structure in the area to be excavated in the existing building structure, set up a reinforcing ring beam on the inner side of the construction portal, and perform grouting reinforcement on the outer side of the construction portal to form soil reinforcement on the outer side of the existing building; simultaneously carry out tunnel excavation and assemble the tunnel segments, and after the segment ring carrying the cuttable opening in the tunnel segment is assembled to the first predetermined position, perform grouting reinforcement on the outer side of the cuttable opening to form soil reinforcement on the outer side of the segment, and then use the curved pipe curtain technology to connect the steel pipes between one side of the existing building structure and the tunnel segment. It should be pointed out that the connecting steel pipes for connecting steel pipes constructed using the curved pipe curtain technology can be started from the existing building structure and received by the tunnel segment; or, the connecting steel pipes can be started from the tunnel segment and received by the existing building structure. Make a reasonable choice according to the working conditions.
[0016] S3: Fix one end of the connecting steel pipe to the existing building structure through the first connecting end plate; fix the other end of the connecting steel pipe to the tunnel segment through the second connecting end plate and the curved beam plate.
[0017] S4: Continue to excavate the proposed tunnel and directly remove the pull-out piles by mechanical excavation when encountering them.
[0018] S5: After the proposed tunnel passes through the existing building structure and the segment rings carrying the cuttable openings in the tunnel segments are assembled to the second predetermined position, the curved pipe curtain technology is used to connect the steel pipes between the other side of the existing building structure and the tunnel segments.
[0019] S6: Repeat step S3 to complete the connection of the left and right sides of the existing building structure with the connecting steel pipes of the tunnel segments, and connect the curved beam and slab with the existing building structure through the connecting steel pipes to form an integral common anti-floating structure.
[0020] When the overall common anti-floating structure does not meet the anti-floating requirements, the reserved drilled holes at the bottom of the tunnel segments are fixed with newly constructed anti-pullout piles to increase the overall anti-floating performance.
[0021] The beneficial effects of the present invention are as follows: the present invention uses the pipe curtain method to construct the connecting pipe, and connects the tunnel segments and the internal curved steel beams with the upper existing building structure through the connecting steel pipe to form a whole, so that the tunnel segments and the upper structure play a common anti-floating effect, and can safely and efficiently realize the safe construction of tunnels under existing buildings. When the construction scope encounters pull-out piles, the present invention adopts the method of connecting steel pipes to fix the tunnel segments and the upper structure, so that both participate in the anti-floating at the same time, which can effectively solve the problems of the upper structure anti-floating failure and structural cracking caused by the need to break the pull-out piles of the upper structure during the construction of deep underground tunnels, and greatly improve the construction safety and construction efficiency.
[0022] Compared with the prior art, the present invention proposes a structural form and construction method of underpass anti-pullout piles, which, by setting an anti-floating structure pre-connected to the upper building structure, avoids the risk of temporary failure of the anti-floating effect caused by first breaking the anti-pullout piles and then reconnecting them in the conventional underpass anti-pullout pile method. At the same time, this method changes the defect of the prior art that only the mining method can be used to break the anti-pullout piles, and broadens the scope of application of the mechanical excavation method to construct underground projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0024] Figure 1 The figure is a schematic diagram of one side of the supporting structure of the present invention.
[0025] Figure 2 It is a schematic side view of the supporting structure of the present invention.
[0026] Figure 3 This is a schematic diagram of the arc-shaped pipe structure used in the supporting structure of the present invention.
[0027] Figure 4 This is a schematic diagram of the curved beam-slab connection state in Example 1.
[0028] Figure 5 This is a schematic diagram of the support structure of the present invention using oblique straight pipes.
[0029] Figure 6 Schematic diagram of the side view of the construction of new pull-out piles.
[0030] Figure 7 This is a schematic diagram of the main view of the construction of new pull-out piles.
[0031] In the figure: 1: existing building or underground station, 2: connecting steel pipe, 3: tunnel segment, 4: pull-out pile, 41: new pull-out pile, 5: curved beam and slab, 51: front section small curved steel beam, 52: rear section small curved steel beam, 53: weld, 54: reinforcement layer, 55: bolt connection, 61: soil reinforcement outside existing building, 62: soil reinforcement outside segment, 71: first connection end plate, 72: second connection end plate, 8: supporting structure, 9: reinforced ring beam, 10: cuttable opening. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] like Figure 1 , 2 As shown, in Example 1, a support structure for underpassing anti-pull piles includes a connecting steel pipe 2 that connects an existing building structure 1 and a tunnel segment 3 by a pipe curtain method; that is, the corresponding connecting steel pipe is constructed by a pipe curtain. The existing building structure 1 can also be an underground station structure, and a curved beam plate 5 is provided on the side corresponding to the connecting steel pipe 2 in the tunnel segment 3, and a reinforcing ring beam 9 is provided on the side corresponding to the connecting steel pipe 2 in the existing building structure 1. One end of the connecting steel pipe 2 passes through the tunnel segment 3 and is connected to the curved beam plate 5, and the other end passes through the existing building structure 1 and is connected to the reinforcing ring beam 9 and / or the existing building structure 1. The above structure is suitable for a newly built subway station or tunnel underpassing an existing building. When the construction scope encounters anti-pull piles, the fixed segment and the upper existing building structure are used to make the two participate in anti-floating at the same time, which can effectively solve the problems of anti-floating failure of the upper structure and structural cracking caused by the need to break the anti-pull piles of the upper structure during the construction of deep underground tunnels, and achieve the effect of safe and convenient construction.
[0034] After one side of the existing building structure 1 is connected to the tunnel segment 3 through the connecting steel pipe 2, the existing anti-pullout pile 4 is cut off, and then the other side of the existing building structure 1 is connected to the tunnel segment 3 through the connecting steel pipe 2. The above structure can be applied to the case where there are anti-pullout piles on the predetermined construction route when the dark excavation method is used for construction, and the new anti-floating structure is constructed, and then the original anti-pullout piles are removed; thereby avoiding the risk of temporary failure of the anti-floating effect caused by first breaking the anti-pullout piles and then connecting them in the conventional method of passing under the anti-pullout piles.
[0035] As an implementation method, a cuttable hole 10 is provided at the connection point corresponding to the connecting steel pipe 2 on the tunnel segment 3; the tunnel segment 3 is the same as the existing structure, that is, it is composed of a number of segment rings spliced together, and the cuttable hole 10 is provided on the corresponding segment ring, and the cuttable hole 10 is chiseled out to form the corresponding segment door. When the prefabricated segment is processed, a cuttable hole is provided at the corresponding position, and the steel bars around the hole are reinforced. The curved beam plate 5 is fitted and fixed to the inner wall of the tunnel segment 3, and the connecting steel pipe 2 passes through the cuttable hole 10 and the curved beam plate 5 and is fixedly connected to the curved beam plate 5 through the second connecting end plate 72, and the fixing method can be welding or bolting.
[0036] As an implementation method, the cuttable opening 10 is cut to form a segment opening for the connecting steel pipe 2 to pass through. The cuttable opening 10 is surrounded by reinforced steel bars and a steel lining is provided inside the cuttable opening 10 to further improve the firmness of the opening. The curved beam 5 can seal the inside of the cuttable opening 10 and provide a connection with the connecting steel pipe. The curved beam 5 is fixedly connected to the tunnel segment 3, and the outside of the cuttable opening 10 is grouting-treated; the outside of the cuttable opening 10 forms a segment outer soil reinforcement 62 to ensure its sealing.
[0037] As an implementation method in this embodiment, the arc beam plate 5 is an arc steel beam, which includes several sections of small arc steel beams. Two adjacent sections of small arc steel beams are fixed by welding, and the small arc steel beams and the segment ring of the tunnel segment 3 are staggered. In the specific construction, the axial length of the small arc steel beam along the tunnel segment 3 is twice the segment ring width. The front section of the small arc steel beam 51 corresponds to the first predetermined position of the cuttable opening, and is welded with the rear section of the small arc steel beam 52 to form an intermediate weld 53. The subsequent small arc steel beams are connected in sequence until the small arc steel beam is welded to the second predetermined position to form an integral arc steel beam 5. The connecting end plate is fixedly connected to the arc steel beam by bolts 54, and the arc steel beam and the tunnel segment 3 are poured and reinforced to form a reinforcement layer 54, while ensuring the stability of the arc steel beam. The arc steel plate can be pre-opened, and the connection method with the segment can be replaced by planting or bolting. This structure is suitable for tunnels that are mechanically excavated and pass through existing buildings.
[0038] During the specific construction, the proposed tunnel is first excavated. After the prefabricated segments for cutting holes are reserved in the proposed tunnel to the predetermined position, the curved pipe curtain technology is used to connect the steel pipes between the existing superstructure and the tunnel segments that have been excavated. The existing superstructure and the tunnel segments that have been excavated are connected by connecting steel pipes, so that the tunnel segments that have been excavated can provide anti-buoyancy to the existing superstructure through the connecting steel pipes. Then the proposed tunnel is continued to be constructed. When anti-pullout piles are encountered, they can be directly mechanically excavated and broken without worrying about the problem of insufficient anti-buoyancy of the existing superstructure. After the proposed tunnel passes through the existing superstructure, the curved pipe curtain technology can still be used here to connect the existing superstructure and the proposed tunnel. Furthermore, the curved steel beam can be set on the inner surface of the tunnel and connected to the connecting steel pipes on the left and right sides, so that the tunnel segments and the superstructure can have a common anti-buoyancy effect.
[0039] The curved pipe curtain technology is used to connect the steel pipes between the existing superstructure and the pre-excavated pipeline, and the pipeline is excavated at the same time. After the prefabricated pipe segments with cuttable holes are installed in the corresponding positions, a section of curved steel beam is placed in the tunnel, one end of the connecting steel beam is fixed to the superstructure, and the other end is passed through the pipe segment door and fixed to the curved steel beam and the curved steel beam is fixed to the pipe segment. As the tunnel is excavated, the curved steel beams are repeatedly placed in the tunnel, and the curved steel beams are connected by welding until the other end of the tunnel is completed. The curved steel beam is connected to the superstructure through steel pipes to form a whole, so that the tunnel segments and the superstructure have a common anti-floating effect.
[0040] Embodiment 2, a support structure for underpassing pull-out piles, this embodiment is different from embodiment 1 in that the arc-surface beam 5 in this embodiment is a concrete lining beam, which is fixed to the inner wall of the tunnel segment 3. The arc-surface steel plate is replaced with a reinforced concrete structure, which can also be applied to the case of underpassing pull-out piles of existing structures by mining method.
[0041] like Figure 3 As shown, on the basis of Example 1 or 2, the existing building structure 1 is provided with a construction portal on the side corresponding to the connecting steel pipe 2, a reinforcing ring beam 9 is provided inside the construction portal, and grouting reinforcement is performed on the outside of the construction portal, the connecting steel pipe 2 passes through the construction portal and is connected to the existing building structure 1 through the first connecting end plate 71; the connection method can be welding or bolt connection. In order to improve the stability of the existing building structure during use, a support structure 8 can be set in the area to be excavated in the existing building structure 1.
[0042] As a preferred solution, the connecting steel pipe 2 is an oblique straight pipe or an arc-shaped pipe. The steel pipe line shape used in the pipe curtain construction can be a straight line. The straight line form can make full use of the stress performance of steel and save steel; concrete can be poured into the steel pipe to improve the stress performance of the connecting steel pipe. When the above structure does not meet the anti-floating requirements, anti-pullout piles can be installed at the drilled holes reserved for fixing the anti-pullout piles 4 at the bottom of the tunnel segment 3 to increase the overall anti-floating performance.
[0043] Embodiment 3: A construction method of a support structure under the anti-pulling pile as described in Embodiment 1 or 2, the steps are as follows: S1: According to the construction plan and the force calculation results, the size and model of the connecting steel pipe 2 and the curved beam slab 5 are determined, and according to the position relationship, the position of the pipe segment ring with the cuttable opening 10 is determined; the pipe segment ring with the cuttable opening 10 has two predetermined positions corresponding to both sides of the existing building structure 1; when the prefabricated pipe segment is processed, the cuttable opening is set at the corresponding position, the steel bars around the opening are reinforced, and the steel lining is set inside the opening.
[0044] S2: A support structure 8 is set in the area to be excavated of the existing building structure 1, a reinforcing ring beam 9 is set on the inner side of the construction portal, and grouting reinforcement is performed on the outer side of the construction portal to form the soil reinforcement 61 on the outer side of the existing building to ensure sealing; the proposed tunnel is excavated simultaneously, and the tunnel segments 3 are assembled simultaneously. After the segment ring carrying the cuttable opening 10 in the tunnel segment 3 is assembled to the first predetermined position, the curved pipe curtain technology is used to construct the connecting steel pipe 2 between one side of the existing building structure 1 and the tunnel segment 3. The connecting steel pipe 2 can be an arc pipe fitting or an oblique straight pipe fitting. The straight form can make full use of the stress performance of steel and save steel; concrete can be poured into the steel pipe to improve the stress performance of the connecting steel pipe. It should be pointed out that the connecting steel pipe constructed by the curved pipe curtain technology can be started from the existing building structure and received by the tunnel segment; or, the connecting steel pipe can be started from the tunnel segment and received by the existing building structure. Reasonable selection is made according to the working conditions.
[0045] S3: Fix one end of the connecting steel pipe 2 to the existing building structure 1 through the first connecting end plate 71; the fixing method can be welding, bolt connection, etc. to ensure the firmness of the connection. Fix the other end of the connecting steel pipe 2 to the tunnel segment 3 through the second connecting end plate 72 and the curved beam plate 5; specifically: construct the curved beam plate 5 in the tunnel segment 3 corresponding to the cuttable opening 10, then chisel the cuttable opening 10 to form the segment opening, the connecting steel pipe 2 passes through the segment opening and the curved beam plate 5 and is fixed on the curved beam plate 5 through the second connecting end plate 72, and grouting is performed between the curved beam plate 5 and the tunnel segment 3 and outside the segment opening.
[0046] S4: Continue to excavate the proposed tunnel, and directly remove the pull-out pile 4 by mechanical dark excavation when encountering it. This avoids the risk of temporary failure of the anti-floating effect caused by first removing the pull-out pile and then connecting it in the conventional method of underpassing the pull-out pile.
[0047] S5: After the proposed tunnel passes through the existing building structure 1 and the segment rings carrying the cuttable openings 10 in the tunnel segments 3 are assembled to the second predetermined position, the curved pipe curtain technology is used to connect the steel pipes 2 between the other side of the existing building structure 1 and the tunnel segments 3.
[0048] S6: Repeat step S3 to complete the connection of the connecting steel pipes 2 between the left and right sides of the existing building structure 1 and the tunnel segment 3, and connect the curved beam slab 5 to the existing building structure 1 through the connecting steel pipes 2 to form an integral common anti-floating structure.
[0049] like Figure 6 , 7As shown, when the overall common anti-floating structure does not meet the anti-floating requirements, the overall anti-floating performance is increased by drilling holes reserved at the bottom of the tunnel segment 3 and constructing new anti-pullout piles 4. In the specific construction, the curved steel plate can be replaced with a concrete lining structure, which changes the defect of the existing technology that only the mining method can be used to remove the anti-pullout piles, and broadens the scope of application of the mechanical dark excavation method to build underground projects.
[0050] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A support structure under the anti-pulling pile, Features: It comprises a connecting steel pipe (2) for connecting an existing building structure (1) and a tunnel segment (3) by using a pipe curtain method, wherein a curved beam plate (5) is provided on the side of the tunnel segment (3) corresponding to the connecting steel pipe (2), and a reinforcing ring beam (9) is provided on the side of the existing building structure (1) corresponding to the connecting steel pipe (2); one end of the connecting steel pipe (2) passes through the tunnel segment (3) and is connected to the curved beam plate (5), and the other end passes through the existing building structure (1) and is connected to the reinforcing ring beam (9) and / or the existing building structure (1); After one side of the existing building structure (1) is connected to the tunnel segment (3) via the connecting steel pipe (2), the existing pull-out piles (4) are removed, and then the other side of the existing building structure (1) is connected to the tunnel segment (3) via the connecting steel pipe (2).
2. The support structure for underpass anti-pulling piles according to claim 1, Features: A cuttable hole (10) is provided at a connection point on the tunnel segment (3) corresponding to the connecting steel pipe (2); the curved beam plate (5) is fitted with the inner wall of the tunnel segment (3); the connecting steel pipe (2) passes through the cuttable hole (10) and the curved beam plate (5) and is fixedly connected to the curved beam plate (5) via a second connecting end plate (72).
3. The support structure for underpass anti-pulling piles according to claim 2, Features: After the cuttable opening (10) is cut, a segment opening is formed for the connecting steel pipe (2) to pass through. The cuttable opening (10) is reinforced with steel bars and a steel lining is provided inside the cuttable opening (10). The curved beam plate (5) can seal the inside of the cuttable opening (10). The curved beam plate (5) is fixedly connected to the tunnel segment (3), and the outside of the cuttable opening (10) is grouting-treated.
4. The support structure for underpass anti-pulling piles according to any one of claims 1 to 3, Features: The curved beam plate (5) is a curved steel beam, which comprises a plurality of annular curved steel sheets, two adjacent curved steel sheets are fixed by welding, and the curved steel sheets and the tunnel segments (3) are arranged in staggered seams.
5. The support structure for underpass anti-pulling piles according to any one of claims 1 to 3, Features: The curved beam slab (5) is a concrete lining beam slab, and the concrete lining beam slab is fixed on the inner wall of the tunnel segment (3).
6. The support structure for underpass anti-pulling piles according to claim 1, Features: A construction portal is provided on the side of the existing building structure (1) corresponding to the connecting steel pipe (2), a reinforcing ring beam (9) is provided on the inner side of the construction portal, and grouting reinforcement is performed on the outer side of the construction portal. The connecting steel pipe (2) passes through the construction portal and is connected to the existing building structure (1) via a first connecting end plate (71).
7. The support structure for underpass anti-pulling piles according to claim 6, Features: A support structure (8) is provided in the area to be excavated within the existing building structure (1).
8. The support structure for underpass anti-pulling piles according to claim 1, Features: The connecting steel pipe (2) is an oblique straight pipe or an arc-shaped pipe; a drill hole for fixing the pull-out pile (4) is reserved at the lower part of the tunnel segment (3).
9. A construction method for a support structure under a pull-out pile as claimed in claim 1, Features: Here are the steps: S1: Determine the size and model of the connecting steel pipe (2) and the curved beam plate (5), and determine the position of the segment ring with the cuttable hole (10) according to the positional relationship; S2: a support structure (8) is provided in the area to be excavated of the existing building structure (1), a reinforcing ring beam (9) is provided on the inner side of the construction tunnel portal, and grouting reinforcement is performed on the outer side of the construction tunnel portal to form soil reinforcement (61) on the outer side of the existing building; the proposed tunnel is excavated simultaneously, and the tunnel segments (3) are assembled; after the segment ring carrying the cuttable opening (10) in the tunnel segment (3) is assembled to the first predetermined position, grouting reinforcement is performed on the outer side of the cuttable opening (10) to form soil reinforcement (62) on the outer side of the segment; and then a curved pipe curtain technology is used to connect the steel pipe (2) between one side of the existing building structure (1) and the tunnel segment (3); S3: fixing one end of the connecting steel pipe (2) to the existing building structure (1) via a first connecting end plate (71); fixing the other end of the connecting steel pipe (2) to the tunnel segment (3) via a second connecting end plate (72) and a curved beam plate (5); S4: Continue to excavate the proposed tunnel, and when encountering the pull-out pile (4), directly remove it by mechanical dark excavation; S5: After the proposed tunnel passes through the existing building structure (1), and the segment ring with the cuttable opening (10) in the tunnel segment (3) is assembled to the second predetermined position, the curved pipe curtain technology is used to connect the steel pipe (2) between the other side of the existing building structure (1) and the tunnel segment (3); S6: Repeat step S3 to complete the connection of the connecting steel pipes (2) of the left and right sides of the existing building structure (1) and the tunnel segments (3), and connect the curved beam plate (5) and the existing building structure (1) through the connecting steel pipes (2) to form an integral common anti-floating structure.
10. The construction method of the support structure under the anti-pulling pile according to claim 9, Features: When the overall common anti-floating structure does not meet the anti-floating requirements, new anti-pullout piles (41) are constructed through the reserved drilled holes at the bottom of the tunnel segments (3) to increase the overall anti-floating performance.
Citation Information
Patent Citations
Structure and method of tunnel construction
CN108222949A
Construction method of tunnel structure of uplift pile penetrating underground structure
CN113062750A
Wear tunnel supporting structure of existing pile foundation building down
CN208702421U
Tunnel heave-preventing reinforcing structure tensioned by steel strands
CN210564550U
The structure that pre-stressed uplift piles control floating of foundation pit across existing tunnel is adopted
CN211948395U