Construction method of building steel reinforced concrete combined joint structure and joint structure
In the construction of a steel-shaped concrete composite structure, the frame structure is pre-assembled and hoisted to the outside of the top surface of the wall, and the support mechanism is used to cooperate with the construction joints to synchronize concrete pouring and floor panel steel bar construction, which solves the difficulty of steel bar binding in the existing technology. The problem has achieved improvement in construction efficiency and time saving.
Patent Information
- Application Number
- CN202411151479.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-05
AI Technical Summary
During the construction of existing steel-concrete composite structures, it is difficult to cross-bind the steel bars and steel beams, and it is difficult to tie the stirrups of the steel columns. The collision between the steel bars and steel columns at the junction of the walls leads to high construction difficulty and low efficiency, which affects the progress.
The pre-assembled frame structure is hoisted to the outside of the top surface of the wall, and the support mechanism is used to cooperate with the construction joints to simultaneously carry out the wall concrete pouring and the floor panel steel bar structure construction to reduce the mutual influence of the steel bar structure and improve the binding efficiency.
The construction cycle is shortened, the construction efficiency is improved, and the difficulty of binding the steel bar structure in the concrete wall is reduced, and the maximum decoupling between the concrete wall and the floor panel steel structure is achieved, greatly saving construction time.
Smart Images

Figure CN118895822A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building engineering, and in particular to a construction method and a node structure of a building steel-concrete composite node structure. Background Art
[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] The current structure of some buildings is a steel-concrete composite structure, and steel beams and columns are required inside the thick walls. The original intention of this structure is to first construct the steel structure and quickly form a frame structure from the perspective of construction logic; then pour concrete on the wall to wrap part of the steel structure frame, and during this period, steel bars need to be tied around the steel structure. This construction logic has caused many problems in the construction of concrete walls. For example, the steel bars of the concrete wall cross the steel beams, making it difficult to tie; the problem of difficulty in tying stirrups around the steel columns; and the problem of collision between the steel bars and the steel columns at the junction of the wall. This situation increases the difficulty of construction and affects the construction efficiency. In addition, during the current construction, the steel structure of the floor panel is constructed first, and then the concrete of the wall is poured after the construction is completed. The construction time is long, which affects the construction progress. Summary of the invention
[0004] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a construction method and a node structure of a building steel-concrete composite node structure, which shortens the construction period and speeds up the construction progress.
[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0006] In a first aspect, an embodiment of the present invention provides a construction method for a building steel-concrete composite node structure, comprising the following steps:
[0007] Tie up the steel reinforcement structure of the wall;
[0008] The pre-assembled frame structure is hoisted, and the frame structure includes side beams and main beams and secondary beams vertically fixed to the side beams. The side beams are hoisted to a position on one side above the construction joint on the top surface of the constructed wall, and the support mechanism arranged on the back of the side beams cooperates with the construction joint to support the entire frame structure;
[0009] The concrete pouring of the wall and the construction of the floor slab reinforcement structure are carried out simultaneously.
[0010] Optionally, the support mechanism includes a shear key fixed to the back of the edge beam, and the shear member includes an I-beam perpendicular to the back of the edge beam, and the I-beam is vertically welded with a channel steel, and the bottom end of the channel steel is matched with the construction joint;
[0011] Furthermore, a plurality of anchor bars are provided on the back side of the side beam.
[0012] Optionally, when frame structures are provided on both sides of the wall, the shear keys of the corresponding support mechanisms on the back sides of the side beams on both sides of the wall are welded and fixed;
[0013] Furthermore, when frame structures are arranged on both sides of the wall, the anchor bars on the back sides of the side beams are arranged staggered.
[0014] In a second aspect, an embodiment of the present invention provides a construction method of a building steel-concrete composite structure, comprising the following steps:
[0015] Tie up the steel reinforcement structure of the wall;
[0016] The pre-assembled frame structure is hoisted, the frame structure includes a plurality of main beams, wherein the main beam is hoisted to a position where the end is located above the construction joint on the top surface of the constructed wall, and the support mechanism arranged at the end of the main beam cooperates with the construction joint to support the main beam;
[0017] The concrete pouring of the wall and the construction of the floor slab reinforcement structure are carried out simultaneously.
[0018] Optionally, the support mechanism includes a shear key fixed to the end of the main beam, and the shear member includes an I-beam perpendicular to the end face of the main beam, and the I-beam is vertically welded with a channel steel, and the bottom end of the channel steel is matched with the construction joint;
[0019] Furthermore, the end surface of the main beam is also provided with a plurality of anchor bars.
[0020] Optionally, when frame structures are provided on both sides of the wall, corresponding support mechanisms of the main beams on both sides of the wall are welded and fixed;
[0021] Furthermore, when frame structures are arranged on both sides of the wall, the anchor bars on the back sides of the side beams are arranged staggered.
[0022] Optionally, the frame structure has the support mechanism fixed in advance;
[0023] or,
[0024] After the frame structure is hoisted into place, the supporting mechanism is then welded and fixed. The supporting mechanism cooperates with the construction joint, and the welding position of the supporting mechanism enables the frame structure to maintain a horizontal posture.
[0025] Optionally, during the process of binding the steel bar structure of the wall, an operating space is reserved for welding the supporting mechanism, and a mechanical sleeve is reserved at the end of the steel bar outside the operating space. After the welding of the supporting mechanism is completed, steel bars are constructed on the mechanical sleeve to form a complete steel bar structure of the wall.
[0026] Optionally, during the welding of the support structure, a lifting device is used to support the entire frame structure.
[0027] or;
[0028] The entire frame structure is supported by temporary pillars set on the floor or ground one level below.
[0029] In a third aspect, an embodiment of the present invention provides a building steel-concrete composite node structure, which is constructed using the building steel-concrete composite node structure construction method described in the first aspect or the second aspect.
[0030] The beneficial effects of the present invention are as follows:
[0031] 1. The construction method of the present invention is that when the frame structure is hoisted, it is hoisted to a side above the construction joint on the top surface of the constructed wall, so that the frame structure is located on the outside of the wall, and the frame mechanism uses the cooperation of the support mechanism and the construction joint to achieve support. The construction of the floor steel structure and the concrete pouring of the wall can be carried out simultaneously without waiting for the completion of the construction of the floor steel structure, thereby reducing the mutual influence between the floor steel structure construction and the wall concrete pouring, shortening the construction period, accelerating the construction progress, improving the construction efficiency, and greatly saving the construction period.
[0032] 2. In the construction method of the present invention, the frame structure is located on the outside of the wall, which greatly reduces the steel structure in the concrete wall, realizes the maximum decoupling of the binding of the concrete wall steel structure and the floor panel steel structure, greatly reduces the difficulty of binding the steel structure in the wall, improves construction efficiency, and shortens the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0034] Figure 1 is a flow chart of the construction method of embodiment 1 of the present invention;
[0035] Figure 2 This is a construction elevation drawing of Embodiment 1 of the present invention;
[0036] Figure 3 This is a construction plan view of Embodiment 1 of the present invention;
[0037] Figure 4 is a flow chart of the construction method of embodiment 2 of the present invention;
[0038] Among them, 1. constructed walls, 2. side beams, 3. main beams, 4. secondary beams, 5. wall reinforcement structure, 6. steel pipe supports, 7. shear keys, 8. anchor bars, 9. inner formwork, 10. outer formwork. DETAILED DESCRIPTION
[0039] Example 1
[0040] This embodiment provides a construction method for a building steel-concrete composite node structure. Figure 1-Figure 3 As shown, the frame structure of the pre-processed floor panel is hoisted to the side above the construction joint at the top of the constructed wall 1, and the supporting mechanism of the frame structure cooperates with the construction joint to support the frame structure, and then the steel structure of the floor panel and the concrete pouring of the wall to be constructed are synchronously constructed.
[0041] In this embodiment, the frame structure includes a side beam 2 and a main beam 3 and a secondary beam 4 vertically fixed to the side beam 2, wherein the side beam 2 is used to be arranged along the edge of the wall, and both ends of the main beam 3 and the secondary beam 4 are connected and fixed with the side beam 2, and the side beam 2 plays a role of sealing the main beam 3 and the secondary beam 4, and a supporting mechanism is arranged on the back of the side beam 2. In this embodiment, the side beam 2 adopts a channel steel, and the channel steel is welded with a connecting plate at the connecting position of the main beam 2 and the secondary beam 3, and is fixed to the main beam 2 and the secondary beam 3 by bolts. The main beam 2 and the secondary beam 3 can adopt an I-beam, and the web end of the I-beam is fixed to the connecting plate by bolts. The construction method specifically includes the following steps:
[0042] Step 1: Tie up the wall reinforcement structure 5.
[0043] The binding of the wall reinforcement structure 5 can be done by using the existing technology, which will not be described in detail here. In this embodiment, it is necessary to leave space at the placement position of the support mechanism so that the construction personnel can conveniently weld and fix the support mechanism to the back of the side beam 2. A mechanical sleeve is reserved at the end of the reinforcement outside the reserved space, so that after the support mechanism is welded, the reinforcement can be connected at the mechanical sleeve to form a complete wall reinforcement structure 5 of the wall.
[0044] Step 2: Hoist the frame structure.
[0045] In this embodiment, the frame structure is hoisted to one side of the space above the construction joint on the top surface of the constructed wall 1 by the side beam 2, so that the frame structure is located on the outside of the wall to be constructed. After the frame structure is hoisted into place, a plurality of supporting mechanisms are welded on the back side of the side beam 2, and the plurality of supporting mechanisms are matched with the construction joint on the top surface of the constructed wall 1, and the entire frame structure is supported by the supporting mechanisms.
[0046] In this embodiment, a plurality of support mechanisms are distributed along the length direction of the side beam.
[0047] When the supporting mechanism is welded, the welding position of the supporting mechanism should be adjusted so that the side beam 2 can maintain a horizontal posture after being supported by the supporting mechanism.
[0048] In this embodiment, during the welding process of the support mechanism, it is necessary to use a lifting device to lift the frame structure to maintain the position and posture of the frame structure. After the frame structure is supported, it can be separated from the lifting device.
[0049] It is understandable that if the construction load of the frame structure is large, temporary supports can also be set on the floor slab or the ground of the lower layer. The top of the temporary support is in contact with the main beam, secondary beam or side beam to support the frame structure. The side beam can be removed after the wall strength meets the standard through the support mechanism and anchor bars.
[0050] Preferably, the temporary support can be a steel pipe support 6 .
[0051] In another embodiment, the support mechanism is pre-welded to the back of the edge beam 2 , and during construction, the support mechanism is directly hoisted to cooperate with the construction joint at the top of the constructed wall 1 .
[0052] In this embodiment, the support mechanism adopts a shear key 7, which includes a horizontally arranged I-beam, one end of which is welded and fixed to the middle position of the back side beam 2, and the I-beam is vertically welded with a channel steel. The bottom end of the channel steel is used to be placed on the construction joint surface of the top surface of the constructed wall 1, thereby supporting the entire frame structure.
[0053] After the supporting mechanism is welded, multiple anchor bars 8 are welded on the back of the side beam. The anchor bars 8 adopt an L-shaped structure, including a first anchoring section and a second anchoring section vertically arranged at one end of the first anchoring section. One end of the first anchoring section is welded and fixed to the back of the side beam 2.
[0054] It is understandable that the anchor bar 8 can also be welded and fixed to the back side of the side beam 2 in advance.
[0055] In this embodiment, two rows of anchor bars 8 are arranged on the back side of the side beam 2. The second anchoring sections of the anchor bars 8 in the upper row extend upward or horizontally, or among the multiple anchor bars, there are anchor bars with the second anchoring sections extending upward and anchor bars with the second anchoring sections extending horizontally. The second anchoring sections of the anchor bars 8 in the lower row extend horizontally to avoid the construction joints.
[0056] In this embodiment, if both sides of the wall have frame structures, the shear keys 7 of the side beams on both sides are welded and fixed, and the anchor bars 8 on the back of the side beams 2 on both sides are staggered.
[0057] After the shear key 7 and the anchor bar 8 are welded, the mechanical sleeve outside the space reserved for the wall reinforcement structure 5 is connected to the reinforcement to complete the construction of the complete wall reinforcement structure 5 of the wall.
[0058] Step 3: Simultaneously pour the wall concrete and construct the floor slab reinforcement structure.
[0059] When pouring wall concrete, first set up the formwork, wherein the inner formwork 9 is set up on the top surface of the side beam 2, and the outer formwork 10 can be set up using existing technology. After the formwork is set up, the concrete of the wall is poured. While the concrete is being poured, the steel structure of the floor panel can be constructed. The construction method of the steel structure of the floor panel can use existing technology and will not be described in detail here.
[0060] By adopting the construction method of this embodiment, the construction of the floor panel steel structure and the concrete pouring of the wall can be carried out simultaneously without waiting for the completion of the floor panel steel structure construction, thereby reducing the mutual influence of the floor panel steel structure construction and the wall concrete pouring, shortening the construction period, speeding up the construction progress, improving the construction efficiency, and greatly saving the construction period. Moreover, the steel structure in the concrete wall is greatly reduced, and the maximum decoupling of the binding of the concrete wall steel structure and the floor panel steel structure is achieved, which greatly reduces the difficulty of binding the steel structure in the wall, improves the construction efficiency, and shortens the construction period.
[0061] Example 2
[0062] This embodiment provides a construction method for a steel-concrete composite structure. Figure 4 As shown, compared with embodiment 1, the frame structure includes multiple main beams 3, and no secondary beams and side beams are provided, and includes the following steps:
[0063] Step a: Tie up the wall reinforcement structure 5.
[0064] The binding of the wall reinforcement structure 5 can be done by using the existing technology, which will not be described in detail here. In this embodiment, it is necessary to leave space at the placement position of the support mechanism so that the construction personnel can conveniently weld and fix the support mechanism to the end of the main beam. A mechanical sleeve is reserved at the end of the reinforcement outside the reserved space, so that after the support mechanism is welded, the reinforcement can be connected to the mechanical sleeve to form a complete reinforcement structure of the wall.
[0065] Step b: Hoist the frame structure.
[0066] In this embodiment, the frame structure is hoisted to the end of the main beam at one side of the space above the construction joint on the top surface of the constructed wall, so that the frame structure is located on the outside of the wall to be constructed. After the main beam 3 is hoisted into place, a supporting mechanism is welded to the end of the main beam 3, and the supporting mechanism is matched with the construction joint on the top surface of the constructed wall. The main beam is supported by the supporting mechanism. After the welding of the supporting mechanism is completed, multiple anchor bars are welded on the back of the side beam.
[0067] When the supporting mechanism is welded, the welding position of the supporting mechanism should be adjusted so that the plurality of main beams 3 remain flush in the horizontal direction.
[0068] In this embodiment, during the welding process of the support mechanism, it is necessary to use a lifting device to lift the main beam 3 to maintain the position and posture of the main beam. After the main beam is supported, it can be separated from the lifting device.
[0069] It is understandable that if the construction load of the main beam 3 is large, temporary supports can also be set on the floor panel or the ground of the lower layer. The top of the temporary support is in contact with the main beam, secondary beam or side beam to support the frame structure. The main beam can be removed after the wall strength meets the standard through the support mechanism and anchor bars.
[0070] In this preferred embodiment, the temporary support can be a steel pipe support 6.
[0071] After the support structure is welded, the anchor bars 8 are welded and fixed at the ends of the main beam 3 .
[0072] In this embodiment, the supporting mechanism adopts the shear key 7, and the structure of the shear key 7 and the anchor bar 8 is the same as that in the embodiment 1, and will not be described repeatedly here.
[0073] In this embodiment, if both sides of the wall have frame structures, the shear keys 7 corresponding to the main beams 3 on both sides are welded and fixed, and the anchor bars 8 at the ends of the main beams 3 on both sides are staggered.
[0074] After the shear key 7 and the anchor bar 8 are welded, the mechanical sleeve outside the space reserved for the steel bar structure of the wall is connected to the steel bar to complete the construction of the complete wall steel bar structure 5 of the wall.
[0075] Step c: Simultaneously carry out the pouring of wall concrete and the construction of the floor slab reinforcement structure.
[0076] Step c of this embodiment is the same as step 3 in embodiment 1, the only difference being that when pouring the wall concrete, the inner formwork is set up on the top surface of the main beam end, and the specific construction method is not described in detail here.
[0077] Example 3
[0078] This embodiment provides a building steel-concrete composite node structure, which is constructed by the construction method of the building steel-concrete component node structure described in Example 1. It includes a concrete wall, a steel bar structure 5 is arranged inside the wall, a side beam 2 is arranged on one side of the wall, a shear key 7 and an anchor bar 8 on the back of the side beam 2 are embedded in the wall, and the side beam is vertically fixed to the main beam 3 and the secondary beam.
[0079] Example 4
[0080] This embodiment provides a building steel-concrete composite node structure, which is constructed using the building steel-concrete component node structure construction method described in Example 2, and includes a concrete wall with a steel structure 5 inside the wall. A main beam is provided on one side of the wall, and the shear keys 7 and anchor bars 8 at the ends of the main beam are buried inside the wall.
[0081] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A construction method for a building steel-concrete composite node structure, characterized in that: The following steps are involved: Steel reinforcement structure for tying up the wall; The pre-assembled frame structure is hoisted, and the frame structure includes side beams and main beams and secondary beams vertically fixed to the side beams. The side beams are hoisted to a position on one side above the construction joint on the top surface of the constructed wall, and the support mechanism arranged on the back of the side beams cooperates with the construction joint to support the entire frame structure; The concrete pouring of the wall and the construction of the floor slab reinforcement structure are carried out simultaneously.
2. A construction method for a building steel-concrete composite node structure as claimed in claim 1, characterized in that: The support mechanism includes a shear key fixed to the back of the edge beam, and the shear member includes an I-beam perpendicular to the back of the edge beam, and the I-beam is vertically welded with a channel steel, and the bottom end of the channel steel is matched with the construction joint; Furthermore, a plurality of anchor bars are provided on the back side of the side beam.
3. A construction method for a building steel-concrete composite node structure as claimed in claim 2, characterized in that: When frame structures are provided on both sides of the wall, the shear keys of the corresponding support mechanisms on the back of the side beams on both sides of the wall are welded and fixed; Furthermore, when frame structures are arranged on both sides of the wall, the anchor bars on the back sides of the side beams are arranged staggered.
4. A construction method for a building steel-concrete composite node structure, characterized in that: The following steps are involved: Steel reinforcement structure for tying up the wall; The pre-assembled frame structure is hoisted, the frame structure includes a plurality of main beams, wherein the main beam is hoisted to a position where the end is located above the construction joint on the top surface of the constructed wall, and the support mechanism arranged at the end of the main beam cooperates with the construction joint to support the main beam; The concrete pouring of the wall and the construction of the floor slab reinforcement structure are carried out simultaneously.
5. A construction method for a building steel-concrete composite node structure as claimed in claim 4, characterized in that: The support mechanism includes a shear key fixed to the end of the main beam, and the shear member includes an I-beam perpendicular to the end face of the main beam, and the I-beam is vertically welded with a channel steel, and the bottom end of the channel steel is matched with the construction joint; Furthermore, the end surface of the main beam is also provided with a plurality of anchor bars.
6. A construction method for a building steel-concrete composite node structure as claimed in claim 5, characterized in that: When frame structures are set on both sides of the wall, the corresponding shear keys of the main beams on both sides of the wall are welded and fixed; Furthermore, when frame structures are arranged on both sides of the wall, the anchor bars on the back sides of the side beams are arranged staggered.
7. A construction method for a building steel-concrete composite node structure as claimed in claim 1 or 4, characterized in that: The frame structure has the supporting mechanism fixed in advance; or, After the frame structure is hoisted into place, the supporting mechanism is then welded and fixed. The supporting mechanism cooperates with the construction joint, and the welding position of the supporting mechanism enables the frame structure to maintain a horizontal posture.
8. A construction method for a building steel-concrete composite node structure as claimed in claim 1 or 4, characterized in that: During the process of binding the steel bar structure of the wall, an operating space is reserved for welding the supporting mechanism, and a mechanical sleeve is reserved at the end of the steel bar outside the operating space. After the welding of the supporting mechanism is completed, steel bars are constructed on the mechanical sleeve to form a complete steel bar structure of the wall.
9. A construction method for a building steel-concrete composite node structure as claimed in claim 1 or 4, characterized in that: During the welding of the supporting mechanism, the entire frame structure is supported by lifting equipment; or; The entire frame structure is supported by temporary pillars set on the floor or ground one level below.
10. A building steel-concrete composite node structure, characterized in that: The structural steel-concrete composite node structure is constructed by the construction method of claim 1 or claim 4.