Impurity removing and cleaning complete equipment for building solid waste recycled concrete mortar

By designing a complete set of clean equipment for decomposing and removing impurities of building solid waste recycled concrete mortar, crushing motors and soaking and floating technology to remove light debris in concrete blocks, the problem of direct discarding waste concrete blocks and different particle sizes is solved, and the filling is improved Stability and regeneration efficiency.

CN118904440AInactive Publication Date: 2024-11-08YISHUI JINTAN CONCRETE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411103087.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Waste concrete blocks are often discarded directly, resulting in environmental pollution and waste of resources. The particles are of varying sizes after crushing, and the lightweight debris on the inside are difficult to remove, which affects the stability of filler usage and regeneration efficiency.

Method used

A complete set of equipment for removing impurities of recycled concrete mortar for construction solid waste is designed, including bearing support frames, push support frames, closed support frames, separation support frames, closed connection frames, decompression support frames and load-bearing base frames. The crushing motor and The clamping force performs concrete block crushing, combining soaking and floating separation techniques to remove light debris, and separation and recycling of particles and fragments are performed by separation and recycling of the bundle.

Benefits of technology

The effective crushing of concrete blocks and the removal of light debris are achieved, the stability and regeneration efficiency of fillers are ensured, the demand for manual cleaning is reduced, and the secondary utilization rate of resources is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118904440A_ABST
    Figure CN118904440A_ABST
Patent Text Reader

Abstract

The invention provides building solid waste recycled concrete mortar impurity removal and cleaning complete equipment, and relates to the technical field of structures for crushing and recycling waste concrete, the building solid waste recycled concrete mortar impurity removal and cleaning complete equipment comprises a bearing support frame, a pushing support frame, a closed support frame, a separation support frame, a closed connecting frame, an impurity removal support frame and a bearing bottom frame; two groups of climbing ladders are fixedly mounted on the side surface of the bearing support frame; the pushing support frame is fixedly mounted on the inner side of the bearing support frame through the mounting support groove; the closed support frame is mounted on the inner side of one end of the pushing support frame through a rotating shaft; the separating support frame is fixedly mounted at the top of the bearing support frame; broken concrete blocks are soaked through a borne cleaning water body, floating light impurities are supported and recycled through a subsequent impurity removal pore plate, and broken materials of different sizes are separated and recycled through cooperation of a separation screw rod and a bearing pore frame; the problems that most recycling treatment devices are different in size, most padding is directly mixed and recycled, and meanwhile light impurities mixed on the inner sides of waste concrete blocks are difficult to remove synchronously are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of structures for crushing and recycling waste concrete, and in particular to a complete set of equipment for removing impurities and cleaning concrete mortar recycled from construction solid waste. Background Art

[0002] Construction site waste refers to the general term for slag, waste concrete blocks and other wastes generated during the construction, laying, demolition and repair of various buildings, structures, pipelines, etc. by construction units or individuals. Among them, waste concrete blocks are the most common construction site waste. Waste concrete blocks are composed of waste concrete and other materials such as steel bars. Waste concrete blocks have the significance of secondary utilization as construction waste. Random discarding will result in unnecessary waste of resources. Waste concrete blocks can be used as fillers, aggregates, etc. after being crushed and recycled.

[0003] Based on the above, at present, waste concrete blocks are often directly discarded, which affects the environment and causes unnecessary waste of resources. Waste concrete blocks need to be crushed when used as fillers. Most recycling and processing devices have filler particles of different sizes after crushing. Fillers of different sizes are directly mixed and recycled. At the same time, the light debris mixed inside the waste concrete blocks is difficult to remove simultaneously, affecting the stability of subsequent filler use. Manual cleaning of the device and the screen is required, affecting the efficiency of the regeneration of waste concrete blocks. Summary of the invention

[0004] In view of this, the present invention provides a set of equipment for removing impurities and cleaning concrete mortar recycled from construction solid waste, which is provided with a bearing support frame, a pushing support frame, a closed support frame, a separation support frame, a closed connecting frame, an impurity removal support frame and a bearing bottom frame, so as to solve the problem that waste concrete blocks are often directly discarded. Direct discarding affects the environment and causes unnecessary waste of resources. The waste concrete blocks need to be crushed when used as fillers. Most recycling and processing devices have filler particles of different sizes after crushing. Fillers of different sizes are directly mixed and recycled. At the same time, light debris mixed inside the waste concrete blocks is difficult to remove synchronously, which affects the stability of subsequent use of fillers. Manual cleaning of the device and the screen is required, affecting the efficiency of the regeneration of the waste concrete blocks.

[0005] The present invention provides a complete set of equipment for removing impurities from recycled concrete mortar from construction solid waste, which specifically includes: a bearing support frame, a pushing support frame, a closed support frame, a separation support frame, a closed connection frame, an impurity removal support frame and a bearing bottom frame;

[0006] Two groups of climbing ladders are fixedly installed on the side of the bearing support frame, a pushing motor is fixedly installed on the top of the bearing support frame, a push-pull screw is rotatably installed on the inner side of the bearing support frame, a docking slot is opened on the top of the bearing support frame, and an installation slot is opened on the side of the bearing support frame; the pushing support frame is fixedly installed on the inner side of the bearing support frame through the installation slot, and guide slots are opened on both sides of the pushing support frame, and a discharge side slot is opened at one end of the pushing support frame, and a closed slot is opened inside the discharge side slot; the closed support frame is rotatably installed on the inner side of one end of the pushing support frame through a rotating shaft, an adjusting worm gear is fixedly installed on the side of the closed support frame through a rotating shaft, and a docking support frame is fixedly installed on one end of the closed support frame; the separation support frame is fixedly installed on the top of the bearing support frame, and the installation support frame is fixedly installed on the side of the separation support frame. A separation cylinder is fixedly installed on the inner side of the separation support frame, and a separation motor is fixedly installed on one end of the separation cylinder, and the inner side of the separation cylinder rotates A separation screw is provided, a separation hole is provided on the outside of the separation screw, and a recovery side cylinder is fixedly installed on one end of the separation support frame; the closed connection frame is fixedly installed on the top of the separation support frame, a bearing support groove is provided on the inside of the closed connection frame, a closed support is fixedly installed on the inside of the closed connection frame, and an adjusting motor is fixedly installed on the side of the closed connection frame; the impurity removal support frame is fixedly installed on the top of the closed connection frame, an installation side groove is provided on the side of the impurity removal support frame, a locking support block is fixedly provided on the side of the impurity removal support frame, a rotating support shaft is rotatably provided on the inside of the impurity removal support frame, limited support blocks are provided on the outsides of both ends of the rotating support shaft, and adjusting grip frames are fixedly installed on both ends of the rotating support shaft; the bearing bottom frame is fixedly installed on the side of the installation side groove, a crushing support frame is fixedly installed on the top of the bearing bottom frame, a loading top frame is fixedly installed on the top of the crushing support frame, a guide support is fixedly installed on the inside of the crushing support frame, and an assembly rotating shaft is rotatably provided on the inside of the crushing support frame.

[0007] Preferably, the side of the bearing support frame is further provided with: a recovery support frame and a recovery material frame;

[0008] The recovery support frame is fixedly installed on the side of the bearing support frame; the recovery material frame is fixedly installed on the side of the bearing support frame; the particles generated by concrete crushing can be carried and recovered by the recovery support frame, and the recovery material frame can carry and recover the filling blocks generated by concrete crushing.

[0009] Preferably, one end of the push support frame is further provided with: a rotating support block, an adjusting worm and a rotating gripping rod;

[0010] The rotating support block is fixedly installed on the side of one end of the pushing support frame; the adjusting worm is rotatably arranged on the inner side of the rotating support block; the rotating grip rod is fixedly installed on one end of the adjusting worm; the adjusting worm can be rotated by the rotating support block, and holding the rotating grip rod can drive the adjusting worm to rotate, so that the adjusting worm can drive the adjusting worm wheel to rotate.

[0011] Preferably, the side of the docking support frame is further provided with: a closed card frame and a closed support ring;

[0012] The closed card frame is fixedly installed at one end of the docking support frame; the closed support ring is arranged on the side of the docking support frame; the push support frame can be closed by cooperating with the closed card frame and the closed support ring.

[0013] Preferably, the side surface of the separation carrier tube is further provided with: a separation branch groove and a bearing hole frame;

[0014] The separation branch groove is arranged on the side of the separation carrier tube; the bearing hole frame is fixedly installed on the inner side of the separation branch groove; the bearing hole frame can be fixedly installed through the separation branch groove, so that the bearing hole frame can recycle the cleaned sewage and broken particles.

[0015] Preferably, the inner side of the bearing support groove is also provided with: a closed support and a discharge slot;

[0016] The closed pillar is rotatably arranged on the inner side of the bearing support groove; the discharge groove is opened on the side of the closed pillar; the closed frame can be load-bearing and closed by cooperating with the closed support, and the closed pillar can adjust the position of the discharge groove by rotation so that the closed frame can be load-bearing and discharged.

[0017] Preferably, the outer side of the rotating support shaft is further provided with: a locking support and a debris removal hole plate;

[0018] The locking pillar is slidably sleeved on the outside of the rotating support shaft; the debris removal orifice plate is fixedly installed on the side of the rotating support shaft; the rotating support shaft can be rotationally locked by the locking pillar, so that the locking pillar can fix the debris removal orifice plate and enable the debris removal orifice plate to recover light debris mixed inside the concrete.

[0019] Preferably, the side of the crushing support frame is also provided with: a side frame and a crushing motor;

[0020] The mounting side frame is fixedly mounted on the side of the crushing support frame; the crushing motor is fixedly mounted on the side of the mounting side frame; the mounting side frame can carry the crushing motor and drive the assembly shaft to rotate.

[0021] Preferably, the outer side of the assembly shaft is also provided with: a primary crushing shaft, a secondary crushing shaft and a transmission gear;

[0022] The primary crushing shaft and the secondary crushing shaft are sleeved on the outside of the assembly shaft; the transmission gear is sleeved on the outside of one end of the assembly shaft; the assembly shaft can be driven by the transmission gear to rotate in opposite directions, so that the primary crushing shaft cooperates with the secondary crushing shaft to crush the recycled concrete.

[0023] The invention provides a complete set of equipment for removing impurities and cleaning concrete mortar recycled from construction solid waste, which has the following beneficial effects:

[0024] The present invention is provided with a bearing support frame, a pushing support frame, a closed support frame, a separation support frame, a closed connection frame, a debris removal support frame and a bearing bottom frame. The crushing support frame can carry the recycled concrete blocks, the crushing motor can drive the primary crushing shaft and the secondary crushing shaft to rotate, the concrete blocks are crushed by the clamping force, and the crushed concrete blocks are collected on the inner side of the debris removal support frame and the closed connection frame. The carried cleaning water body soaks the crushed concrete blocks, so that the light debris mixed inside the concrete blocks is floated and separated, and the subsequent debris removal orifice plate supports and recovers the floating light debris. The concrete block crushed materials of different sizes and wastewater recovery are arranged on the inner side of the separation support frame, so that the separation screw cooperates with the bearing hole frame to separate and recover the crushed materials of different sizes, and the crushed concrete particles are further recovered by the recovery support frame, and the concrete fragments crushed by the recovery frame are recovered. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the drawings of the embodiment are briefly introduced below.

[0026] The drawings described below are only related to some embodiments of the present invention, but are not intended to limit the present invention.

[0027] In the attached picture:

[0028] Figure 1 It shows a schematic structural diagram of the overall assembly of a complete set of equipment for removing impurities and cleaning concrete mortar recycled from construction solid waste according to an embodiment of the present invention;

[0029] Figure 2 It shows a structural schematic diagram of the assembly and disassembly arrangement of the whole components of the bearing support frame according to an embodiment of the present invention;

[0030] Figure 3 It shows a schematic structural diagram of the assembly and disassembly arrangement of the entire components of the push support frame according to an embodiment of the present invention;

[0031] Figure 4 It shows a schematic structural diagram of the assembly and disassembly arrangement of the integral components of the closed support frame according to an embodiment of the present invention;

[0032] Figure 5 It shows a schematic structural diagram of the assembly and disassembly arrangement of the separate support frame integral components according to an embodiment of the present invention;

[0033] Figure 6 It shows a schematic structural diagram of the assembly and disassembly of the integral components of the closed frame according to an embodiment of the present invention;

[0034] Figure 7 It shows a schematic structural diagram of the assembly and disassembly of the overall components of the impurity removal support frame according to an embodiment of the present invention;

[0035] Figure 8 A structural schematic diagram of the assembly and disassembly of the integral components of the load-bearing bottom frame according to an embodiment of the present invention is shown.

[0036] Reference numerals list

[0037] 1. Bearing frame;

[0038] 101. Climbing ladder; 102. Pushing motor; 103. Push-pull screw; 104. Butt-jointing slot; 105. Installing support slot; 106. Recycling support frame; 107. Recycling material frame;

[0039] 2. Push the support frame;

[0040] 201, dredge the slot; 202, discharge the side slot; 203, close the slot; 204, rotate the support block; 205, adjust the worm; 206, rotate the handle;

[0041] 3. Close the support frame;

[0042] 301, adjusting worm gear; 302, docking support frame; 303, closing card frame; 304, closing support ring;

[0043] 4. Separate the support frame;

[0044] 401, install the support frame; 402, separate the carrier tube; 403, separate the motor; 404, separate the screw; 405, separate the support slot; 406, the bearing hole frame; 407, recover the side tube; 408, separate the hole;

[0045] 5. Close the frame;

[0046] 501, bearing support slot; 502, closed support; 503, adjustment motor; 504, closed support; 505, discharge slot;

[0047] 6. Remove the miscellaneous support frames;

[0048] 601, install the side groove; 602, lock the support block; 603, rotate the support shaft; 604, limit the support block; 605, adjust the grip frame; 606, lock the pillar; 607, remove the debris hole plate;

[0049] 7. Carrying bottom frame;

[0050] 701, crushing support frame; 702, loading top frame; 703, guide support; 704, assembly shaft; 705, primary crushing shaft; 706, secondary crushing shaft; 707, transmission gear; 708, installation side frame; 709, crushing motor. DETAILED DESCRIPTION

[0051] Example: Please refer to Figures 1 to 8 :

[0052] The present invention proposes a complete set of equipment for removing impurities from recycled concrete mortar from construction solid waste, comprising: a bearing support frame 1, a pushing support frame 2, a closing support frame 3, a separation support frame 4, a closing connection frame 5, an impurity removal support frame 6 and a bearing bottom frame 7;

[0053] Two sets of climbing ladders 101 are fixedly installed on the side of the supporting frame 1, a pushing motor 102 is fixedly installed on the top of the supporting frame 1, a push-pull screw 103 is rotatably installed on the inner side of the supporting frame 1, a docking slot 104 is opened on the top of the supporting frame 1, and a mounting slot 105 is opened on the side of the supporting frame 1; the pushing frame 2 is fixedly installed on the inner side of the supporting frame 1 through the mounting slot 105, and the two sides of the pushing frame 2 are provided with drainage slots 201, and one end of the pushing frame 2 is provided with a discharge side slot 202, and the inner side of the discharge side slot 202 is provided with a sealing slot. The card slot 203 is closed; the closed support frame 3 is rotatably mounted on the inner side of one end of the push support frame 2 through a rotating shaft, an adjusting worm gear 301 is fixedly mounted on the side of the closed support frame 3 through a rotating shaft, and a docking support frame 302 is fixedly mounted on one end of the closed support frame 3; the separation support frame 4 is fixedly mounted on the top of the bearing support frame 1, a mounting support frame 401 is fixedly mounted on the side of the separation support frame 4, a separation carrier 402 is fixedly mounted on the inner side of the separation support frame 4, a separation motor 403 is fixedly mounted on one end of the separation carrier 402, and a separation screw is rotatably arranged on the inner side of the separation carrier 402 404, a separation hole 408 is provided on the outer side of the separation screw 404, and a recovery side cylinder 407 is fixedly installed at one end of the separation support frame 4; the closed frame 5 is fixedly installed on the top of the separation support frame 4, a bearing support groove 501 is provided on the inner side of the closed frame 5, a closed support 502 is fixedly installed on the inner side of the closed frame 5, and an adjustment motor 503 is fixedly installed on the side of the closed frame 5; the impurity removal support frame 6 is fixedly installed on the top of the closed frame 5, an installation side groove 601 is provided on the side of the impurity removal support frame 6, and a locking support block 603 is fixedly provided on the side of the impurity removal support frame 6 02, a rotating support shaft 603 is rotatably arranged on the inner side of the impurity removing support frame 6, and limit support blocks 604 are arranged on the outer sides of both ends of the rotating support shaft 603, and adjustment grip frames 605 are fixedly installed on both ends of the rotating support shaft 603; the supporting bottom frame 7 is fixedly installed on the side of the mounting side groove 601, and a crushing support frame 701 is fixedly installed on the top of the supporting bottom frame 7, and a loading top frame 702 is fixedly installed on the top of the crushing support frame 701, a guide support 703 is fixedly installed on the inner side of the crushing support frame 701, and an assembly rotating shaft 704 is rotatably arranged on the inner side of the crushing support frame 701.

[0054] Embodiment 1: Figures 3 to 8As shown, the side of the separation cylinder 402 is also provided with: a separation branch groove 405 and a bearing hole frame 406; the separation branch groove 405 is opened on the side of the separation cylinder 402; the bearing hole frame 406 is fixedly installed on the inner side of the separation branch groove 405; the inner side of the bearing branch groove 501 is also provided with: a closed support 504 and a discharge slot 505; the closed support 504 is rotatably arranged on the inner side of the bearing support groove 501; the discharge slot 505 is opened on the side of the closed support 504; the outer side of the rotating support shaft 603 is also provided with: a locking support 606 and a debris removal orifice 607; the locking support 606 is slidably sleeved on the outer side of the rotating support shaft 603; the debris removal orifice 607 is fixedly installed on the side of the rotating support shaft 603; the side of the crushing support frame 701 is also provided with: an installation side frame 708 and a crushing motor 709; the installation side frame 708 is fixedly installed on the side of the crushing support frame 701; the crushing motor 7 09 is fixedly installed on the side of the mounting side frame 708; the outer side of the assembly shaft 704 is also provided with: a primary crushing shaft 705, a secondary crushing shaft 706 and a transmission gear 707; the primary crushing shaft 705 and the secondary crushing shaft 706 are sleeved on the outer side of the assembly shaft 704; the transmission gear 707 is sleeved on the outer side of one end of the assembly shaft 704; the cleaning water body can be carried by the debris removal support frame 6 and the closed frame 5, the crushing support frame 701 carries the recovered concrete blocks, and the concrete blocks are crushed by the clamping force of the primary crushing shaft 705 and the secondary crushing shaft 706, so that the crushed concrete blocks are collected on the inner side of the debris removal support frame 6 and the closed frame 5, and at the same time, the cleaning water body can soak the crushed concrete blocks, so that the light debris mixed in the inner side of the concrete blocks can be floated and separated, so that the subsequent debris removal orifice plate 607 can support and recover the floating light debris.

[0055] Embodiment 2: Based on Embodiment 1, Figures 2 to 7 As shown, the side of the bearing support frame 1 is also provided with: a recycling support frame 106 and a recycling material frame 107; the recycling support frame 106 is fixedly installed on the side of the bearing support frame 1; the recycling material frame 107 is fixedly installed on the side of the bearing support frame 1; one end of the push support frame 2 is also provided with: a rotating support block 204, an adjusting worm 205 and a rotating grip 206; the rotating support block 204 is fixedly installed on the side of one end of the push support frame 2; the adjusting worm 205 is rotatably arranged on the inner side of the rotating support block 204; the rotating grip 206 is fixedly installed on one end of the adjusting worm 205; The side of the docking support frame 302 is also provided with: a closed clamping frame 303 and a closed support ring 304; the closed clamping frame 303 is fixedly installed at one end of the docking support frame 302; the closed support ring 304 is arranged on the side of the docking support frame 302; the soaked wastewater and the carried concrete particles can be recovered and supported by the pushing support frame 2, and the worm 205 can be adjusted to push the carried concrete particles, the recovery support frame 106 independently recovers the broken concrete particles, and the recovery frame 107 independently recovers the broken concrete fragments.

[0056] A method for removing impurities and cleaning concrete mortar recycled from construction solid waste: water is injected into the inner side of an impurity removal support frame 6 and a closed joint frame 5 by a water pump, while a crushing support frame 701 carries the recycled concrete blocks, a crushing motor 709 drives a primary crushing shaft 705 and a secondary crushing shaft 706 to rotate, and the concrete blocks are crushed by a clamping force, so that the crushed concrete blocks are collected on the inner side of the impurity removal support frame 6 and the closed joint frame 5, the carried cleaning water body soaks the crushed concrete blocks, so that light impurities mixed inside the concrete blocks are floated and separated, and a subsequent impurity removal orifice plate 607 supports and recovers the floating light impurities, and materials of different sizes of concrete blocks are crushed and wastewater is recovered on the inner side of a separation support frame 4, so that a separation screw 404 cooperates with a bearing orifice frame 406 to separate and recover materials of different sizes of crushed concrete, and further the crushed concrete particles are recovered by a recovery support frame 106, and the crushed concrete fragments of a recovery frame 107 are recovered.

Claims

1. A complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste, characterized in that: include: Bearing frame, pushing frame, closed frame, separated frame, closed joint frame, debris-removing frame and bearing bottom frame; Two sets of climbing ladders are fixedly installed on the side of the bearing support frame, a pushing motor is fixedly installed on the top of the bearing support frame, a push-pull screw is rotatably installed on the inner side of the bearing support frame, a docking slot is provided on the top of the bearing support frame, and an installation slot is provided on the side of the bearing support frame; the pushing support frame is fixedly installed on the inner side of the bearing support frame through the installation slot, and guide slots are provided on both sides of the pushing support frame. A discharge side slot is provided at one end of the pushing support frame, and a closed card slot is provided on the inner side of the discharge side slot; the closed support frame is rotatably installed on the inner side of one end of the pushing support frame through a rotating shaft, an adjusting worm gear is fixedly installed on the side of the closed support frame through a rotating shaft, and a docking support frame is fixedly installed on one end of the closed support frame.

2. According to claim 1, a complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling, characterized in that: The separation support frame is fixedly installed on the top of the bearing support frame, a mounting support frame is fixedly installed on the side of the separation support frame, a separation carrier tube is fixedly installed on the inner side of the separation support frame, a separation motor is fixedly installed on one end of the separation carrier tube, a separation screw is rotatably arranged on the inner side of the separation carrier tube, a separation hole is opened on the outer side of the separation screw, and a recovery side tube is fixedly installed on one end of the separation support frame; the closed connection frame is fixedly installed on the top of the separation support frame, a bearing support groove is opened on the inner side of the closed connection frame, a closed support is fixedly installed on the inner side of the closed connection frame, and an adjusting motor is fixedly installed on the side of the closed connection frame.

3. A complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 2, characterized in that: The debris removing support frame is fixedly installed on the top of the closed frame, an installation side groove is opened on the side of the debris removing support frame, a locking support block is fixedly installed on the side of the debris removing support frame, a rotating support shaft is rotatably arranged on the inner side of the debris removing support frame, limited support blocks are arranged on the outer sides of both ends of the rotating support shaft, and adjustment grip frames are fixedly installed on both ends of the rotating support shaft; the bearing bottom frame is fixedly installed on the side of the installation side groove, a crushing support frame is fixedly installed on the top of the bearing bottom frame, a loading top frame is fixedly installed on the top of the crushing support frame, a guide support is fixedly installed on the inner side of the crushing support frame, and an assembly rotating shaft is rotatably arranged on the inner side of the crushing support frame.

4. A complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3, characterized in that: The side of the bearing support frame is also provided with: a recovery support frame and a recovery material frame; The recovery support frame is fixedly installed on the side of the bearing support frame; the recovery material frame is fixedly installed on the side of the bearing support frame.

5. According to claim 3, a complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling, characterized in that: One end of the push support frame is also provided with: a rotating support block, an adjusting worm and a rotating gripping rod; The rotating support block is fixedly installed on the side of one end of the pushing support frame; the adjusting worm is rotatably arranged on the inner side of the rotating support block; and the rotating gripping rod is fixedly installed on one end of the adjusting worm.

6. A complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3, characterized in that: The side of the docking support frame is also provided with: a closed card frame and a closed support ring; The closed card frame is fixedly installed on one end of the docking support frame; the closed support ring is arranged on the side of the docking support frame.

7. The complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3 is characterized by: The side surface of the separation carrier tube is also provided with: a separation branch groove and a bearing hole frame; The separation branch groove is arranged on the side of the separation carrier tube; and the bearing hole frame is fixedly installed on the inner side of the separation branch groove.

8. The complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3 is characterized by: The inner side of the bearing support groove is also provided with: a closed support column and a discharge slot; The closed support column is rotatably arranged on the inner side of the bearing support groove; and the discharge groove is arranged on the side of the closed support column.

9. The complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3 is characterized by: The outer side of the rotating support shaft is also provided with: a locking support and a debris removal hole plate; The locking support is slidably sleeved on the outer side of the rotating support shaft; and the debris removal hole plate is fixedly installed on the side of the rotating support shaft.

10. The complete set of equipment for removing impurities and cleaning concrete mortar from construction solid waste recycling according to claim 3 is characterized by: The side of the crushing support frame is also provided with: a side frame and a crushing motor are installed; The mounting side frame is fixedly installed on the side of the crushing support frame; the crushing motor is fixedly installed on the side of the mounting side frame; The outer side of the assembly shaft is also provided with: a primary crushing shaft, a secondary crushing shaft and a transmission gear; The primary crushing shaft and the secondary crushing shaft are sleeved on the outside of the assembly rotating shaft; and the transmission gear is sleeved on the outside of one end of the assembly rotating shaft.