Construction method for increasing permanent fixed ballast of ship

By mixing steel wire pelleted iron sand with silicate cement in proportion to form a flow object and verified according to the ship tilt test results, the problems of cumbersome design and low construction efficiency in the existing technology are solved, and accurate accounting of ship fixation is achieved The ballast weight and the effect of shortening the construction cycle ensure the stability and delivery of the ship on schedule.

CN118907339APending Publication Date: 2024-11-08CHINA SHIPBUILDING (TIANJIN) SHIPBUILDING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411163692.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

When the prior art increases the permanent fixed ballast of the ship, the design is cumbersome, the construction efficiency is low, and it is difficult to accurately calculate the weight center of gravity of the ship, resulting in a long construction cycle, high cost, and does not meet the stability requirements of the initial design.

Method used

By mixing steel wire-cut iron sand with silicate cement in a certain proportion to form a flow substance, filling it into a specific compartment, and conducting a complete stability verification based on the data of the inclination test results, ensuring that the weight and density of the ballast material after solidification meet the fixed fixation Ballasting requirements shorten the construction cycle and improve construction efficiency.

Benefits of technology

The accurate calculation of the weight center of gravity of the fixed ballast of the ship is achieved, shortening the construction cycle, improving construction efficiency, saving costs, and ensuring the stability and delivery of the ship on time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118907339A_ABST
    Figure CN118907339A_ABST
Patent Text Reader

Abstract

The invention relates to a construction method for increasing permanent fixed ballast of a ship, which comprises the following steps of: according to inclination test result data of the ship, checking the complete stability of the ship and calculating the finished load, and determining a specific cabin needing to be filled with the permanent fixed ballast and the weight of the fixed ballast; checking the local strength, the total longitudinal strength of the ship, the stability of the ship and the minimum freeboard according to the specific cabin position and the fixed ballast weight, and checking whether the standard requirements are met or not; if not, a specific cabin needs to be replaced or the fixed ballast weight needs to be reduced; if the requirements are met, preparing the ship permanent fixed ballast material: uniformly mixing the steel wire shot cutting iron sand and Portland cement with water in proportion to obtain a ballast material fluid; through calculation, the ballast material flow is filled into the specific cabin, and the weight of the solidified ballast material meets the fixed ballast weight; the construction period of the fixed ballast of the ship can be greatly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of ship construction, and in particular relates to a construction method for increasing permanent fixed ballast of a ship. Background Art

[0002] The common characteristics of fishery administration vessels, navigation ships, fishery resource survey vessels, scientific research vessels, engineering ships, etc. are that the main dimensions of the hull are small, the hull lines are large, the displacement is basically below 5,000 tons, and there are many types of special equipment or scientific research equipment on the whole ship. Such ships are generally newly designed and developed ships, and there is no mother ship to refer to. In addition to the above reasons, under normal circumstances, the calculation of the weight and center of gravity data of the whole ship is inaccurate during the detailed design stage, which makes the actual weight and center of gravity of the new ship after the tilting test not meet the initial design requirements, so it is necessary to increase the permanent fixed ballast to meet the stability requirements of the initial design of the ship.

[0003] At present, the conventional method of increasing the permanent fixed ballast of a ship is to add steel plates to a specific cabin. The additional steel plates need to be stacked and laid out in small pieces according to the cabin size and the outer plate profile. Then the cut small steel plates are transported to the cabin in a certain order and placed and welded according to the requirements of the drawings. This method is cumbersome in design, low in construction efficiency and long in construction period. After construction, repainting is required, and it is not convenient to calculate the final weight center of gravity of the ship. Summary of the invention

[0004] The object of the present invention is to provide a design and construction method which can be constructed efficiently and quickly and can accurately calculate the weight of the fixed ballast.

[0005] The present invention solves the technical problem by adopting the following technical solutions:

[0006] The construction method for increasing the permanent fixed ballast of a ship comprises the following steps:

[0007] Based on the ship's inclination test results, the ship's complete stability check and completed loading calculation are carried out to determine the specific compartments that need to be filled with permanent fixed ballast and the fixed ballast weight;

[0008] According to the specific compartment position and fixed ballast weight, local strength, ship longitudinal strength, ship stability and minimum freeboard are checked to see whether they meet the requirements of the regulations. If not, it is necessary to replace the specific compartment or reduce the fixed ballast weight. If it is satisfied, then:

[0009] Preparation of permanent fixed ballast material for ships: evenly mix cut wire shot iron sand and silicate cement with water in proportion to obtain a ballast material fluid;

[0010] By calculation, the ballast material flow is filled into a specific compartment, and the weight of the ballast material after solidification satisfies the fixed ballast weight.

[0011] Furthermore, when preparing the permanent fixed ballast material for ships, the cut wire shot iron sand, silicate cement and water are uniformly mixed in a volume ratio of 2:1:1 to obtain a ballast material flow; wherein the pile weight of the cut wire shot iron sand is 4400kg / m 3 , the density of silicate cement is 2900kg / m 3 .

[0012] Furthermore, before filling a specific cabin with ballast material, the space of the specific cabin needs to be checked. If the fixed ballast weight is met, filling is performed. If the fixed ballast weight is not met, the specific cabin needs to be replaced or the fixed ballast weight needs to be reduced.

[0013] Furthermore, when calibrating the space of a specific cabin, it is necessary to determine in advance the density of the ballast material flow after solidification, and use the fixed ballast weight to be filled and the density of the ballast material flow after solidification to obtain the fixed ballast volume to be filled, which can be compared and verified with the space of the specific cabin.

[0014] Furthermore, before the ballast material flow is filled into a specific compartment, the weight of the corresponding cut wire shot iron sand, silicate cement and water required for each compartment needs to be calculated according to the determined fixed ballast weight.

[0015] Furthermore, when a specific compartment that needs to be filled with permanent fixed ballast is determined, the safety of the equipment and pipelines in the specific compartment must be ensured, and it must be ensured that no cross-compartment occurs when the compartment is filled with the ballast material flow.

[0016] Furthermore, on the top platform or deck of a specific cabin that needs to be filled with permanent fixed ballast, process holes are added between each rib position to allow the ballast material to flow into the cabin, and process hole sealing plate steel liner rings are added around the process holes.

[0017] Furthermore, when the fixed ballast in a specific compartment that needs to be filled with permanent fixed ballast is filled and solidified, the process hole is originally cut and sealed with single-sided welding. After all welding construction is completed, touch-up paint is applied according to painting requirements.

[0018] The advantages and positive effects of the present invention are:

[0019] The present invention can accurately calculate the weight center of gravity of the fixed ballast of the ship, so as to facilitate the complete stability calculation of the ship; at the same time, it can greatly shorten the construction period of the fixed ballast of the ship, improve the construction efficiency, save the construction cost, and ensure the on-time delivery of the ship. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments, but it should be understood that these drawings are designed only for explanation purposes and are not intended to limit the scope of the present invention. In addition, unless otherwise specified, these drawings are intended only to conceptually illustrate the structural configurations described herein and are not necessarily drawn to scale.

[0021] Figure 1 It is a schematic diagram of density calculation using mixed fillings in a wooden frame sample box provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0022] First, it should be noted that the specific structure, features and advantages of the present invention will be specifically described below by way of example, but all descriptions are only for illustration and should not be understood as limiting the present invention in any way. In addition, any single technical feature described or implied in the embodiments mentioned herein can still be combined or deleted between these technical features (or their equivalents) to obtain more other embodiments of the present invention that may not be directly mentioned herein.

[0023] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application may be combined with each other.

[0024] The construction method for increasing the permanent fixed ballast of a ship of the present invention comprises the following steps: mixing cut wire shot iron sand with ordinary silicate cement and water in a certain proportion to form a fluid, and then filling the fluid into a specific cabin according to a certain construction process, and using the fluid as the permanent fixed ballast of the ship after the filling in the cabin solidifies; the weight center of gravity of the fixed ballast of the ship can be accurately calculated to facilitate the calculation of the complete stability of the ship; and at the same time, the construction period of the fixed ballast of the ship can be greatly shortened, the construction efficiency can be improved, and the construction cost can be saved.

[0025] The specific method flow is as follows:

[0026] Step 1: Based on the inclination test result data of the ship, the complete stability check and completion loading calculation of the ship are carried out to determine the compartments that need to be filled with fixed ballast and the fixed ballast weight;

[0027] Step 2: According to the location of the specific cabin and the fixed ballast weight, it is necessary to check the local strength of the specific cabin, check the longitudinal strength of the ship, the stability of the ship and the minimum freeboard to ensure that the above meet the requirements of the specification; if not, it is necessary to replace the specific cabin or reduce the fixed ballast weight; if satisfied, proceed with the following steps:

[0028] Step 3: After the compartment to be filled with fixed ballast is determined, it is necessary to remove the useless mechanical and electrical equipment in the specific compartment, and make corresponding adjustments and modifications to the oil and water ventilation pipelines, etc., to ensure the tightness of the compartment, so as to ensure that there is no cross-communicating when the compartment is filled with fluid fixed ballast;

[0029] Step 4: On the platform or deck at the top of a specific cabin, add as many circular process holes as possible between each rib position to facilitate the uniform pouring of the flow-like filler into the cabin; add a 50mm wide ring around the process hole as a steel liner for the process hole sealing plate;

[0030] Step 5: Make a wooden frame sample box with a length*width*height of 30cm*30cm*4cm;

[0031] Step 6: The pile weight is 4400kg / m 3 Cut wire shot iron sand, density 2900kg / m 3 Ordinary Portland cement P0 42.5 and density 1000kg / m 3 Water is uniformly mixed in a volume ratio of 2:1:1 to make a small amount of fluid mortar and filled into the wooden frame sample box prepared in step 5, and placed in a ventilated place for 24 hours to dry and solidify;

[0032] Step 7: After the mixed filling in the wooden frame sample box in step 6 is completely dry, weigh it and calculate its density. The formula for density calculation is: Finally, the weight of the dried test sample is 17.64 kg and the volume is 0.3*0.3*0.04=0.0036 m 3 , density is 4.9t / m 3 ;

[0033] It should be noted that the weight of evaporated water has been ignored when calculating the density here. When the volume of the cabin required for fixed ballast is determined by density later, there may be a certain deviation, but since the volume change is small, it can be ignored.

[0034] Step 8: According to the solidified density of the sample block in step 7 and the fixed ballast weight determined in step 1, prepare the corresponding weight of cut wire shot iron sand and silicate cement;

[0035] Step 9: Mix the corresponding weight of cut wire shot iron sand, ordinary Portland cement and water according to the proportioning method in step 6 and fill them into the specific compartment in a flowing state. Be careful not to fill the specific compartment with the mixed mortar at one time. It should be filled and dried in several batches to ensure that the mixed mortar inside the compartment can be fully flowed, filled, dried and solidified;

[0036] Step 10. After the mortar in the cabin has been poured and solidified, the holes opened in step 4 are sealed with original single-sided welding. After all welding work is completed, touch-up paint is applied according to painting requirements. The fixed ballast construction is now completed.

[0037] As an example, in this embodiment, the empty ship displacement and center of gravity coordinates obtained after a certain type of fishery resource survey ship is tilted and tested are shown in the following table:

[0038] Table 1 Calculation table of empty displacement and center of gravity position of a certain type of ship

[0039]

[0040]

[0041] After obtaining the above tilt test result data, compare it with the ship's theoretical statistical weight center of gravity:

[0042] Table 2

[0043]

[0044] Through complete stability calculation, according to detailed design data, the stern trim value of this ship when fully loaded out of the port is 0.25m; by comparing with Table 2, it can be seen that the longitudinal coordinate of the center of gravity of the ship's tilt test results is 1.982m backward compared with the detailed design statistical results, and 0.412m backward compared with the shipyard production design lofting results. The stern trim value of this ship when fully loaded out of the port is about 0.89m, and the ship has a certain degree of stern trim. The center of gravity height is 0.256m higher than the detailed design data, and 0.216 higher than the shipyard lofting results. After preliminary calculation by the design institute, the ship's stability can meet the requirements of the specifications, but the stern trim of the ship is more serious when leaving the port, and the increase in the vertical coordinate of the center of gravity is not conducive to the navigation safety of the ship in severe sea conditions. In summary, in order to improve the ship's stern trim and reduce the center of gravity height, it was finally decided to add 40 tons of permanent fixed ballast to the No. 1 ballast tank at the bow of the ship. The volume of the No. 1 ballast tank is 10.5m 3 According to the density calculated in step 7, the volume required to fill 40 tons of fixed ballast is about 8.2m 3 , meeting the filling requirements; of course, if it is found during the calculation process that the filling requirements are not met, it is necessary to replace the specific cabin or increase or decrease the fixed ballast weight.

[0045] According to step 8, the material ratio of permanent fixed ballast in a specific compartment of the ship is calculated as follows:

[0046] Material Name Corresponding weight (kg) Weight Ratio <![CDATA[Material density kg / m 3 > Volume ratio Cut Wire Shot Iron Sand 30000 9 4400 2 Ordinary Portland Cement 10000 3 2900 1 water 3000 1 1000 1

[0047] When water and cement are mixed, a chemical reaction occurs which evaporates a portion of the weight. According to the table above, the final permanent fixed ballast weight remaining in a specific compartment is approximately 40 tons.

[0048] The above embodiments describe the present invention in detail, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A construction method for increasing the permanent fixed ballast of a ship, characterized in that: The steps include: Based on the ship's inclination test results, the ship's complete stability check and completed loading calculation are carried out to determine the specific compartments that need to be filled with permanent fixed ballast and the fixed ballast weight; According to the specific compartment position and fixed ballast weight, local strength, ship longitudinal strength, ship stability and minimum freeboard are checked to see whether they meet the requirements of the regulations. If not, it is necessary to replace the specific compartment or reduce the fixed ballast weight. If it is satisfied, then: Preparation of permanent fixed ballast material for ships: evenly mix cut wire shot iron sand and silicate cement with water in proportion to obtain a ballast material fluid; By calculation, the ballast material flow is filled into a specific compartment, and the weight of the ballast material after solidification satisfies the fixed ballast weight.

2. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: When preparing permanent fixed ballast materials for ships, steel cut wire shot iron sand, silicate cement and water are uniformly mixed in a volume ratio of 2:1:1 to obtain a ballast material flow; wherein the pile weight of steel cut wire shot iron sand is 4400kg / m 3 , the density of silicate cement is 2900kg / m 3 .

3. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: Before filling a specific compartment with ballast material, the space of the specific compartment needs to be checked. If the fixed ballast weight is met, filling is carried out. If the fixed ballast weight is not met, the specific compartment needs to be replaced or the fixed ballast weight needs to be reduced.

4. The construction method for increasing the permanent fixed ballast of a ship according to claim 3, characterized in that: When calibrating the space of a specific cabin, it is necessary to determine in advance the density of the ballast material flow after solidification, and use the fixed ballast weight to be filled and the density of the ballast material flow after solidification to obtain the fixed ballast volume to be filled, which can be compared and verified with the space of the specific cabin.

5. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: Before filling the ballast material stream into a specific compartment, the weight of the corresponding cut wire shot iron sand, silicate cement and water required for each compartment needs to be calculated based on the determined fixed ballast weight.

6. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: When a specific tank that needs to be filled with permanent fixed ballast is determined, the safety of the equipment and pipelines in the specific tank must be ensured, and there must be no cross-tank phenomenon when the tank is filled with ballast material flow.

7. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: On the top platform or deck of a specific cabin that needs to be filled with permanent fixed ballast, process holes are added between each rib position to allow the ballast material to flow into the cabin, and process hole sealing plate steel liner rings are added around the process holes.

8. The construction method for increasing the permanent fixed ballast of a ship according to claim 1, characterized in that: When the fixed ballast in the specific cabin that needs to be filled with permanent fixed ballast is filled and solidified, the process hole is originally cut and sealed with single-sided welding. After all welding construction is completed, touch-up paint is carried out according to painting requirements.