The application discloses a method for
wind power pipe pile sliding on a ship, which comprises the following steps: arranging a sliding tool at a
wharf front, arranging a sliding tool on a transport ship, placing a
pipe pile to be transported on a roller frame, calculating the center position of the
pipe pile, confirming the pile length and the pile weight, and transporting the pipe pile to the
wharf by two front and rear axis module vehicles; separating a single pile from the front axis module vehicle, driving the rear axis module vehicle to drive out from the side, lowering a lifting sliding device, driving the lifting sliding device to lift and move to a specified position together in the direction of a cab, untying a cable (raising an anchor) of the transport ship, and finally fixing the single pile according to requirements. The application can be applied to a tool for low tide, is not limited by a
wharf and
water depth of the wharf, can be used to smoothly and stably slide the
wind power pipe pile on the ship at low tide, all kinds of tools used can be repeatedly used, and the use condition is not affected by tides and a height of a dry
deck of a ship, so that the cost of loading on the ship is greatly reduced, and the loading time of the
wind power pipe pile on the ship is shortened.