The application discloses a construction method for a large-section rectangular
pipe jacking to pass through a river
shoal and to avoid obstacles, and comprises the following steps: S1, when the rectangular
pipe jacking passes through the river
shoal and encounters a cutter head and a screw
machine, the current of the screw
machine is high, and the torque of the cutter head and the screw
machine increases sharply, the cause should be checked in time by means of positive and negative rotation of the cutter head and positive and negative rotation of the screw machine blade; S2, the river
shoal has a small
water flow, and a local excavation method can be adopted for treatment, and the
river water should be diverted before local excavation; S3, a
shovel is adopted to excavate and clean the soil, rock filling and the like in the soil range of the
river bed in front of the
pipe jacking machine, and the excavation depth is the
soil depth from the top of the pipe jacking machine to the bottom of the
river bed; S4, according to the cutter head and the screw machine stuck situation, the pipe jacking machine is smoothly pushed to the other side of the river by adopting the single screw machine to unload or not to unload; and S5, after the pipe jacking machine smoothly passes through the river, the treatment of the boulders at the cutter head or the screw machine is carried out, at this time, the conditions for opening the warehouse for treatment are much better than those at the bottom of the river, and the construction safety is more effectively guaranteed. The method is safe and efficient, and construction cost is saved.