Movable bridge temporary support dismantling channel device and using method
By designing a convenient connection structure for load-bearing beams and hanging point beams, the problem of inconvenience in disassembly and assembly in the existing technology is solved, construction efficiency and safety are improved, and costs are reduced.
Patent Information
- Application Number
- CN202411126055.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-08-16
AI Technical Summary
There is a problem of inconvenience in disassembly between the load-bearing beam and the hoisting point beam of the temporary bearing removal channel device of the existing mobile bridge, resulting in high construction costs, high safety risks and affecting the construction progress.
A temporary bearing removal channel device for mobile bridges including load-bearing beams spanning the central partition belt, a removable first link, a hanging point connecting beam, an I-steel joist and a vertical ladder were designed, through auxiliary The device and positioning mechanism enable convenient installation and disassembly between the load-bearing beam and the lifting point beam.
It realizes convenient installation and disassembly between load-bearing beams and lifting point beams, reduces construction costs, improves safety, and speeds up construction progress.
Smart Images

Figure CN118911022A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge engineering, and in particular to a mobile bridge temporary support removal channel device and a use method thereof. Background Art
[0002] During the erection of prefabricated box girders and T-beams in bridge construction, a process is often used depending on the design concept: first, a temporary support is set on the top of the pier, and then the prefabricated box girders and T-beams are erected on the temporary support. After completing the processes of wet joints, wet hinges, negative moment tensioning and grouting, the temporary supports are removed to complete the system conversion. During the system conversion process, the temporary supports need to be removed in advance. Since the bridge supports are high from the ground and some bridges cross rivers and seas, the use of simple ladders alone cannot meet the construction requirements. Setting up scaffolds or using large machinery and ships for lifting operations not only has high costs and high safety risks, but also affects the construction progress.
[0003] The load-bearing beam and the suspension point tie beam of the existing mobile bridge temporary support removal channel device are fixed by welding, which has the technical problem of inconvenient disassembly and assembly. Summary of the invention
[0004] In order to solve the technical problems raised in the above-mentioned background technology, the present invention provides a movable bridge temporary support removal channel device and a use method.
[0005] The present invention is implemented by the following technical scheme: a mobile bridge temporary support dismantling channel device, comprising two load-bearing beams spanning a central dividing strip, the two load-bearing beams are parallel to each other and are both located above the guardrails, an auxiliary device capable of supporting the load-bearing beams to move on the bridge deck along the extension direction of the central dividing strip is arranged at the bottom of the load-bearing beams, two first connecting rods parallel to the extension direction of the central dividing strip are detachably arranged between the two load-bearing beams, a suspension point connecting beam located directly above the central dividing strip is commonly sleeved and fixed on the two first connecting rods, a dismantling channel is installed at the bottom of the suspension point connecting beam through a bracket, an I-beam support beam is arranged at the bottom of the dismantling channel, a horizontal channel is fixedly arranged on the I-beam support beam, and a vertical ladder is arranged on the horizontal channel.
[0006] As a further improvement of the above solution, inclined rods are provided at both ends of the horizontal channel, and the tops of the two inclined rods are respectively arranged on both sides of the outer wall of the bracket.
[0007] As a further improvement of the above solution, a second insertion hole is provided on the suspension point connecting beam, through which the first connecting rod can be inserted and fixed.
[0008] As a further improvement of the above solution, the length of the load-bearing beam is greater than the distance between the two guardrails.
[0009] As a further improvement of the above solution, the load-bearing beam is provided with a first insertion hole through which the first connecting rod can be inserted and fixed.
[0010] As a further improvement of the above scheme, the auxiliary device includes two support rods, which are respectively located on both sides of the extension direction of the central dividing strip and at the bottom of the load-bearing beam. The bottoms of both ends of the support rods are equipped with caster sets through brackets. Seat grooves are provided on both sides of the top of the support rods. Positioning seats for the corresponding load-bearing beam to be clamped are inserted in the seat grooves. The positioning seats are provided with a positioning mechanism. When the load-bearing beam is clamped on the positioning seats, the positioning mechanism can complete the locking and fixation of the positioning seats in the seat grooves.
[0011] As a further improvement of the above solution, a slot is provided on the top of the positioning seat for the bottom of the load-bearing beam to be inserted into, an insert block is arranged in the slot, and a slot matching the insert block is provided at the bottom of the load-bearing beam.
[0012] As a further improvement of the above scheme, the positioning mechanism includes a first cylinder arranged inside the wall of the positioning seat, a second connecting rod is inserted into the top of the first cylinder, the top of the second connecting rod extends into the slot and is fixed to the bottom of the insertion block, a first spring is sleeved on the outside of the second connecting rod, the two ends of the first spring are respectively connected to the bottom of the insertion block and the bottom wall of the slot, a spiral groove is axially opened inside the top wall of the first cylinder, a protrusion is provided on the outer wall of the second connecting rod close to the bottom and slidingly engaged with the groove, a screw is concentrically slidably clamped on the bottom of the first cylinder, a screw hole matching the screw is opened on the bottom wall of the seat slot, and a second spring is arranged between the top of the screw and the inner bottom wall of the first cylinder.
[0013] As a further improvement of the above scheme, a second clamping rod is provided inside the load-bearing beam along its axial sliding direction, and an inclined hole that is press-fitted with the first connecting rod is provided on the outer wall of the second clamping rod near one end of the first plug hole, and a second clamping hole that cooperates with the other end of the second clamping rod is provided on the plug block.
[0014] The present invention also provides a method for using the above-mentioned mobile bridge temporary support removal passage device, comprising the following steps: S1. Place two load-bearing beams across the central dividing strip and install them on the auxiliary device; S2. Place the suspension point connecting beam between the two load-bearing beams and suspend it just above the central dividing strip, penetrate and fix the two first connecting rods on the two load-bearing beams respectively, and sleeve the two ends of the suspension point connecting beam on the two first connecting rods respectively; S3. Install the bracket, I-beam support beam and horizontal channel in sequence at the bottom of the hanging point connecting beam, and install the vertical ladder on the horizontal channel.
[0015] Compared with the prior art, the present invention has the following beneficial effects: The mobile bridge temporary support removal channel device of the present invention first detachably installs the first connecting rod on the load-bearing beam, and then the suspension point connecting beam is sleeved and fixed on the first connecting rod to complete the installation between the load-bearing beam and the suspension point connecting beam, and the subsequent removal is also convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a partial top view structural schematic diagram of the whole device of the present invention; Figure 2 for Figure 1 A schematic diagram of the partial main structure of the device in the middle; Figure 3 for Figure 1 A schematic diagram of a partial cross-sectional structure of the middle load-bearing beam in a locked and fixed state on the support rod; Figure 4 for Figure 3 A schematic diagram of a partial cross-sectional structure of a central positioning seat inserted on a support rod; Figure 5 for Figure 1 A partial top view of the structure of the middle load-bearing beam; Figure 6 The figure is a flow chart of the method for using the present invention.
[0017] Description of main symbols: 1. Central dividing strip; 2. Guardrail; 3. Load-bearing beam; 4. First plug hole; 5. First connecting rod; 6. Hanging point connecting beam; 7. Second plug hole; 8. Bracket; 9. Horizontal channel; 10. Vertical ladder; 11. Diagonal tie rod; 12. Support rod; 13. Caster set; 14. Seat groove; 15. Positioning seat; 16. Slot; 17. Slot; 18. Insert block; 19. First cylinder; 20. Second connecting rod; 21. Bump; 22. Groove; 23. Screw; 24. Screw hole; 25. Ear block; 26. Positioning rod; 27. Positioning hole; 28. First bevel gear; 29. First fixing plate; 30. Second cylinder; 31. First clamping rod; 32. Second fixing plate; 33. Telescopic rod; 34. First clamping hole; 35. Second bevel gear; 36. Second clamping rod; 37. Oblique hole; 38. Second clamping hole. DETAILED DESCRIPTION
[0018] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.
[0019] Example 1
[0020] Please combine Figures 1 to 5The movable bridge temporary support removal channel device includes two load-bearing beams 3 spanning the central dividing strip 1, the two load-bearing beams 3 are parallel to each other and are both located above the guardrail 2, and an auxiliary device capable of supporting the load-bearing beams 3 to move along the extension direction of the central dividing strip 1 on the bridge deck is arranged at the bottom thereof, and two first connecting rods 5 parallel to the extension direction of the central dividing strip 1 are detachably arranged between the two load-bearing beams 3.
[0021] A lifting point connecting beam 6 located just above the central dividing strip 1 is commonly sleeved and fixed on the two first connecting rods 5 , and the channel device can be lifted and transported through the lifting point connecting beam 6 and the vertical supporting force of the load-bearing beam 3 can be strengthened.
[0022] A dismantling channel is installed at the bottom of the hanging point connecting beam 6 through a bracket 8, an I-beam joist is arranged at the bottom of the dismantling channel, a horizontal channel 9 is fixedly arranged on the I-beam joist, and a vertical ladder 10 is arranged on the horizontal channel 9.
[0023] Both ends of the horizontal channel 9 are provided with inclined rods 11, and the tops of the two inclined rods 11 are respectively arranged on both sides of the outer wall of the bracket 8. The inclined rods 11 can strengthen the overall structural stability of the device and achieve a certain wind resistance effect.
[0024] The suspension point connecting beam 6 is provided with a second insertion hole 7 through which the first connecting rod 5 can be inserted and fixed. The second insertion hole 7 can facilitate the penetration and fastening between the first connecting rod 5 and the suspension point connecting beam 6.
[0025] The length of the load-bearing beam 3 is greater than the distance between the two guardrails 2. In order to prevent the passage device from being affected by the embedded steel bars of the guardrail 2, the length of the load-bearing beam 3 is greater than the inner distance of the guardrail 2 at the central dividing strip 1.
[0026] The load-bearing beam 3 is provided with a first insertion hole 4 through which the first connecting rod 5 can be inserted and fixed. The first insertion hole 4 can facilitate the penetration and fastening between the load-bearing beam 3 and the first connecting rod 5.
[0027] The auxiliary device includes two support rods 12, which are respectively located on both sides of the extension direction of the central dividing strip 1 and at the bottom of the load-bearing beam 3. The bottoms of both ends of the support rods 12 are equipped with caster sets 13 through brackets (not shown in the figure). Both sides of the top of the support rods 12 are provided with seat grooves 14, and positioning seats 15 for the corresponding load-bearing beam 3 to be clamped are inserted in the seat grooves 14. The positioning seats 15 are provided with positioning mechanisms. When the load-bearing beam 3 is clamped on the positioning seats 15, the positioning mechanisms can complete the locking and fixing of the positioning seats 15 in the seat grooves 14.
[0028] A slot 16 is formed on the top of the positioning seat 15 for the bottom of the load-bearing beam 3 to be inserted into. An insert block 18 is arranged in the slot 16 . A slot 17 matching with the insert block 18 is formed on the bottom of the load-bearing beam 3 .
[0029] The positioning mechanism includes a first cylinder 19 arranged inside the seat wall of the positioning seat 15, a second connecting rod 20 is inserted into the top of the first cylinder 19, the top of the second connecting rod 20 extends into the slot 16 and is fixed to the bottom of the insert block 18, a first spring (not marked) is sleeved on the outside of the second connecting rod 20, and the two ends of the first spring are respectively connected to the bottom of the insert block 18 and the bottom wall of the slot 16. When the load-bearing beam 3 is inserted into the slot 16 and the insert block 18 is inserted into the slot 17, the first spring is in a compressed deformation state.
[0030] A spiral groove 22 is axially opened inside the top wall of the first cylinder 19, and a protrusion 21 slidingly engaged with the groove 22 is provided on the outer wall of the second connecting rod 20 near the bottom. A screw 23 is concentrically slidably engaged with the bottom of the first cylinder 19, and a screw hole 24 matching with the screw 23 is opened on the bottom wall of the seat groove 14.
[0031] A second spring (not shown) is provided between the top of the screw rod 23 and the inner bottom wall of the first cylinder 19 , and the bottom of the screw rod 23 can always be kept in a tight state at the screw hole 24 through the second spring.
[0032] A second clamping rod 36 is slidably mounted inside the load-bearing beam 3 along its axial direction. An inclined hole 37 for contact and pressure fit with the first connecting rod 5 is formed on the outer wall of the second clamping rod 36 near one end of the first insertion hole 4. A second clamping hole 38 for fit with the other end of the second clamping rod 36 is formed on the insertion block 18.
[0033] When the first connecting rod 5 is inserted through the first insertion hole 4, the first connecting rod 5 will press the wall of the inclined hole 37, forcing the second clamping rod 36 to move toward the direction close to the insertion block 18, so that the second clamping rod 36 is clamped into the second clamping hole 38, thereby realizing the mutual fixation between the load-bearing beam 3 and the insertion block 18.
[0034] A cushion block (not shown) is arranged inside the load-bearing beam 3, and a third spring (not shown) is arranged on one side of the cushion block and on the end of the second clamping rod 36 away from the inserting block 18. When the second clamping rod 36 is clamped into the second clamping hole 38, the third spring is in a stretched deformation state.
[0035] In summary, the auxiliary device of this embodiment is assembled as follows: First, place the positioning seat 15 in the seat groove 14 corresponding to the top of the support rod 12, so that the positioning rod 26 can be inserted into the positioning hole 27, and then place the load-bearing beam 3 in the slot 16 at the top of the positioning seat 15. During this period, the plug block 18 will be inserted into the slot 17. When the plug block 18 is fully inserted into the slot 17 (the position of the second slot 38 corresponds to the second clamping rod 36 in the load-bearing beam 3), the top of the plug block 18 will be subjected to the downward pressure from the top wall of the slot 17, so that the plug block 18 drives the second connecting rod 20 to move vertically downward so that the protrusion 21 thereon rubs and squeezes the groove wall of the spiral groove 22, forcing the first cylinder 19 and the screw rod 23 to rotate unidirectionally, so that the bottom of the screw rod 23 is rotated and screwed into the screw hole 24, completing the effective fixation of the positioning seat 15 in the seat groove 14, that is, the positioning and fixation of the load-bearing beam 3 on the support rod 12.
[0036] Subsequently, the suspension point connecting beam 6 is suspended between the two load-bearing beams 3 and located directly above the central dividing strip 1. The first connecting rod 5 is used to penetrate the first insertion hole 4 and the second insertion hole 7 of the load-bearing beam 3 to complete the positioning and fixation of the load-bearing beam 3 on the load-bearing beam 3. During this period, the first connecting rod 5 will touch the inclined hole 37 when passing through the first insertion hole 4, forcing the second clamping rod 36 to be clamped into the second clamping hole 38 of the plug block 18, thereby realizing the mutual fixation between the load-bearing beam 3 and the plug block 18, that is, realizing the common fixation between the load-bearing beam 3, the support rod 12, the first connecting rod 5 and the suspension point connecting beam 6, so that the load-bearing beam 3, the support rod 12, the first connecting rod 5 and the suspension point connecting beam 6 form a stable whole.
[0037] Furthermore, a first bevel gear 28 is sleeved and fixed on the outer side of the first cylinder 19, a first fixing plate 29 is provided inside the positioning seat 15, a second cylinder 30 is rotatably inserted on the first fixing plate 29, a second bevel gear 35 matching the first bevel gear 28 is provided at one end of the second cylinder 30, and a first clamping rod 31 is threadedly inserted at the other end of the second cylinder 30. A second fixing plate 32 is sleeved and fixed on the outer side of the first clamping rod 31, and a telescopic rod 33 is provided between the second fixing plate 32 and the first fixing plate 29.
[0038] Ear blocks 25 are arranged opposite to each other on both sides of the positioning seat 15, and positioning rods 26 are arranged at the bottom of the two ear blocks 25. A positioning hole 27 for inserting the positioning rod 26 is opened on the top of the support rod 12, and a first clamping hole 34 is opened on the positioning rod 26 to be clamped with the first clamping rod 31.
[0039] When the first cylinder 19 rotates unidirectionally, the first cylinder 19 can drive the first bevel gear 28, the second bevel gear 35, and the second cylinder 30 to rotate, so that the second cylinder 30 and the first clamping rod 31 interact with each other in a threaded manner, and under the limiting action of the telescopic rod 33, the first clamping rod 31 extends axially from the first cylinder 19 to be clamped into the first clamping hole 34 of the positioning rod 26, so that the installation of the positioning seat 15 in the seat groove 14 is more stable, thereby improving the overall stability of the device installation, and the disassembly and assembly are efficient and convenient.
[0040] Example 2
[0041] Please combine Figure 6 This embodiment provides a method for using the mobile bridge temporary support removal channel device applied to the above-mentioned embodiment 1, comprising the following steps: S1. Place two load-bearing beams 3 across the central dividing strip 1 and install them on the auxiliary device.
[0042] S2. Place the hanging point connecting beam 6 between the two load-bearing beams 3 and suspend it directly above the central dividing strip 1. Pass the two first connecting rods 5 through and fix them on the two load-bearing beams 3 respectively, and make the two ends of the hanging point connecting beam 6 be respectively sleeved on the two first connecting rods 5.
[0043] S3. Install the bracket 8, I-beam support beam, and horizontal channel 9 in sequence at the bottom of the hanging point connecting beam 6, and install the vertical ladder 10 on the horizontal channel 9.
[0044] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A mobile bridge temporary support removal channel device, characterized in that: It comprises two load-bearing beams spanning the central dividing strip, the two load-bearing beams are parallel to each other and are both located above the guardrails, an auxiliary device capable of supporting the load-bearing beams to move on the bridge deck along the extension direction of the central dividing strip is arranged at the bottom of the load-bearing beams, two first connecting rods parallel to the extension direction of the central dividing strip are detachably arranged between the two load-bearing beams, a suspension point connecting beam located directly above the central dividing strip is commonly sleeved and fixed on the two first connecting rods, a dismantling channel is installed at the bottom of the suspension point connecting beam through a bracket, an I-beam support beam is arranged at the bottom of the dismantling channel, a horizontal channel is fixedly arranged on the I-beam support beam, and a vertical ladder is arranged on the horizontal channel.
2. The mobile bridge temporary support removal channel device according to claim 1, characterized in that: Both ends of the horizontal channel are provided with inclined tie rods, and the tops of the two inclined tie rods are respectively arranged on both sides of the outer wall of the bracket.
3. The mobile bridge temporary support removal channel device according to claim 1, characterized in that: The suspension point connecting beam is provided with a second insertion hole through which the first connecting rod can be inserted and fixed.
4. The mobile bridge temporary support removal passage device according to claim 1, characterized in that: The length of the load-bearing beam is greater than the distance between the two guardrails.
5. The mobile bridge temporary support removal channel device according to claim 1, characterized in that: The load-bearing beam is provided with a first insertion hole through which the first connecting rod can be inserted and fixed.
6. The mobile bridge temporary support removal passage device according to claim 5, characterized in that: The auxiliary device includes two support rods, which are respectively located on both sides of the extension direction of the central dividing strip and at the bottom of the load-bearing beam. The bottoms of both ends of the support rods are equipped with caster sets through brackets. Both sides of the top of the support rods are provided with seat grooves, and positioning seats for the corresponding load-bearing beam to be clamped are inserted in the seat grooves. The positioning seats are provided with a positioning mechanism, and when the load-bearing beam is clamped on the positioning seats, the positioning mechanism can complete the locking and fixation of the positioning seats in the seat grooves.
7. The mobile bridge temporary support removal passage device according to claim 6, characterized in that: The top of the positioning seat is provided with a slot for the bottom of the load-bearing beam to be inserted into, an insert block is arranged in the slot, and the bottom of the load-bearing beam is provided with a slot matched with the insert block.
8. The mobile bridge temporary support removal passage device according to claim 7, characterized in that: The positioning mechanism includes a first cylinder arranged inside the wall of the positioning seat, a second connecting rod is inserted into the top of the first cylinder, the top of the second connecting rod extends into the slot and is fixed to the bottom of the insertion block, a first spring is sleeved on the outside of the second connecting rod, two ends of the first spring are respectively connected to the bottom of the insertion block and the bottom wall of the slot, a spiral groove is axially opened inside the top wall of the first cylinder, a protrusion is provided on the outer wall of the second connecting rod close to the bottom and slidingly engaged with the groove, a screw is concentrically slidably clamped at the bottom of the first cylinder, a screw hole matching the screw is opened on the bottom wall of the seat slot, and a second spring is arranged between the top of the screw and the bottom wall of the first cylinder.
9. The mobile bridge temporary support removal passage device according to claim 8, characterized in that: A second clamping rod is provided inside the load-bearing beam for axial sliding. An oblique hole for contact and press-fit with the first connecting rod is provided on the outer wall of the second clamping rod near one end of the first plug hole. A second clamping hole for contact and press-fit with the other end of the second clamping rod is provided on the plug block.
10. A method for using the mobile bridge temporary support removal channel device according to claim 1, characterized in that: The steps include: S1. Place two load-bearing beams across the central dividing strip and install them on the auxiliary device; S2. Place the suspension point connecting beam between the two load-bearing beams and suspend it just above the central dividing strip, penetrate and fix the two first connecting rods on the two load-bearing beams respectively, and sleeve the two ends of the suspension point connecting beam on the two first connecting rods respectively; S3. Install the bracket, I-beam support beam and horizontal channel in sequence at the bottom of the hanging point connecting beam, and install the vertical ladder on the horizontal channel.
Citation Information
Patent Citations
Installation method for installing roof net rack system by utilizing truss vehicle in sliding mode
CN114658232A
Anchoring anti-sliding device and method for open slope mine mining
CN117661607A
Soft rock bedding high slope landslide treatment system
CN118065400A
Testing device for bending resistance of anchor rod
CN118168946A
Construction method for non-blasting demolition of pier to enable bridge to land
CN118481052A