Large vertical ship lift interstitial water filling and discharging device and working method thereof

By designing the filling and discharge devices of the main water storage pipe, side water storage pipe and gas replenishment components in the vertical hoist, the problems of untimely air emissions and gas explosions in the initial stage of water discharge are solved, and the rapid and safe filling and discharge operations are achieved, improving the improvement of the Replenish exhaust efficiency and reduce the risk of water leakage caused by mechanical failures.

CN118911102APending Publication Date: 2024-11-08CHANGJIANG RIVER SCI RES INST CHANGJIANG WATER RESOURCES COMMISSION
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411314352.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the existing vertical lift clearance water filling and discharge system, the air discharge in the early stage of water discharge is not timely, which leads to slowing down the water discharge speed and air explosion phenomenon. The exhaust valve is prone to mechanical failure, which may lead to water leakage accidents.

Method used

A filling and leakage device including a main water storage pipe, a side water storage pipe and a replenishment and exhaust assembly is designed. By providing a first and second valves at both ends of the main water storage pipe, the replenishment and exhaust assembly is used to extract and exhaust gas according to the pressure change. Ensure the air is discharged quickly and the water discharge level adjustment can be achieved through the water pump motor unit to avoid air explosion and water leakage.

Benefits of technology

It effectively eliminates the phenomenon of gas explosion, improves the efficiency of replenishing exhaust, reduces maintenance needs, prevents water leakage accidents caused by mechanical failures, and ensures the stability and safety of the charging and leakage process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911102A_ABST
    Figure CN118911102A_ABST
Patent Text Reader

Abstract

The filling and discharging device comprises the vertical ship lift, and is characterized by further comprising a main water storage pipe, a main water outlet pipe, a main water outlet pipe, a main water outlet pipe and an auxiliary water outlet pipe, the control valves comprise a first valve and a second valve, and the first valve and the second valve are arranged at the two ends of the main water storage pipe respectively; the flow dividing assembly comprises two sets of side water storage pipes, and the two sets of side water storage pipes are symmetrically arranged on the two sides of the main water storage pipe; wherein the water storage pipes on the two sides are fixedly communicated with a plurality of air supplementing and exhausting assemblies respectively, and water pump motor sets are arranged between the main water storage pipe and the gap water tanks at the two ends of the vertical ship lift. The gas explosion phenomenon caused by the fact that pressure-bearing air in a main pipeline enters a gap due to unsmooth exhaust is eliminated; the air supplementing and exhausting assembly replaces an air supplementing and exhausting valve, the air supplementing and exhausting efficiency is improved, maintenance is avoided, and air supplementing and exhausting failure caused by mechanical faults or water leakage accidents caused after interstitial water is communicated with a reservoir can be effectively prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ship dam-passing facilities, and in particular to a filling and discharging device for gap water of a large vertical ship lift and a working method thereof. Background Art

[0002] A vertical ship lift is a navigation structure built for ships to pass through dams with concentrated water level differences. A vertical ship lift is generally composed of an upper lock head, a ship receiving compartment, and a lower lock head. When a ship is traveling upstream, the ship receiving compartment first docks at the lower lock head, and the ship enters the ship receiving compartment from the downstream channel. Then the lock head and the ship receiving compartment gates are closed, and the gap water between the compartment head door and the lock head working door is drained. Under the action of the driving device, the ship receiving compartment immediately rises and docks at the upper lock head. After the ship receiving compartment and the upper lock head are tightened, sealed, and filled with gap water, the ship compartment and the lock head gates are opened, and the ship immediately enters the upstream channel. When the ship is traveling downstream, the above procedure is reversed, and the ship can enter the downstream channel from the upstream channel.

[0003] At present, the filling and discharging system of the interstitial water of the vertical ship lift is composed of a pipe arranged through the bottom of the cabin, and electric valves, water pumps and air supply and exhaust valves are symmetrically arranged at both ends of the pipe. After the upper (lower) gate and the ship compartment gate are closed, the electric valve is opened, and the interstitial water flows into the water storage pipe by gravity. After the interstitial water is discharged, the ship compartment starts to rise and fall. During the lifting and falling of the cabin, the interstitial water in the water storage pipe is pumped back to the cabin through the water pump. The problem with this method is that the air in the main water storage pipe is not discharged in time at the beginning of the discharge, which slows down the discharge speed; the closed air mass in the main water storage pipe moves to the gap end, causing pressurized air to enter the gap to form adverse phenomena such as gas explosion.

[0004] Based on the above reasons, the present invention provides a device for filling and draining gap water of a large vertical ship lift and a working method thereof. Summary of the invention

[0005] The purpose of the present invention is to provide a large vertical ship lift gap water filling and draining device and a working method thereof, so as to solve the problems existing in the prior art.

[0006] To achieve the above object, the present invention provides the following solution: The present invention provides a large vertical ship lift gap water filling and draining device, comprising a vertical ship lift, characterized in that it also includes:

[0007] A main water filling and draining assembly, the main water filling and draining assembly comprising a main water storage pipe, the main water storage pipe is arranged below the ship holding box of the vertical ship lift, and the two ends of the main water storage pipe are respectively fixedly connected to the bottom of the gap water tank at the two ends of the vertical ship lift;

[0008] A control valve, the control valve comprising a first valve and a second valve, the first valve and the second valve being respectively arranged at two ends of the main water storage pipe;

[0009] A flow diversion component, the flow diversion component includes side water storage pipes, the side water storage pipes are provided with two groups, the two groups of side water storage pipes are symmetrically arranged on both sides of the main water storage pipe, and the two side water storage pipes are fixedly connected to the main water storage pipe through a plurality of connecting pipes;

[0010] Among them, a plurality of air supply and exhaust components are fixedly connected to the two side water storage pipes respectively, and a water pump motor group is arranged between the main water storage pipe and the gap water tanks at both ends of the vertical ship lift.

[0011] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the air supply and exhaust assembly includes an air supply and exhaust pipe, the air supply and exhaust pipe is fixedly connected to the side water storage pipe, and the top elevation of the top of the air supply and exhaust pipe is not less than the elevation of the ship support compartment top of the vertical ship lift.

[0012] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the axes of the two side water storage pipes are arranged in parallel, the axis of the side water storage pipe and the axis of the main water storage pipe are arranged in parallel in space, the axis of the side water storage pipe is located below the axis of the main water storage pipe, and the vertical height difference between the axis of the side water storage pipe and the axis of the main water storage pipe is 100 mm.

[0013] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the length of the side water storage pipe is 55m-60m, and the diameter of the side water storage pipe is DN1000.

[0014] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the number of the connecting pipes on both sides of the main water storage pipe is the same.

[0015] According to the large vertical ship lift gap water filling and draining device provided by the present invention, pressure sensors are respectively installed on the main water storage pipe and the side water storage pipe.

[0016] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the diameter of the air supply and exhaust pipe is 0.5m-0.6m.

[0017] According to the large vertical ship lift gap water filling and draining device provided by the present invention, the diameter of the connecting pipe is DN800.

[0018] A method for filling and draining gap water in a large vertical ship lift includes a water filling method and a water draining method. The water filling method includes the following steps:

[0019] Step 1: Open the first valve on the main water storage pipe, and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift will be rapidly pushed forward in the form of open flow and enter the main water storage pipe, and at the same time enter the side water storage pipe through the connecting pipe. After the interstitial water in the main water storage pipe hits the second valve, a forced pipe sealing water jump is formed and a full section is gradually formed. When the full section extends in the reverse direction to the main flow of the connecting pipe, it is basically diverted to the side water storage pipes on both sides. The gas replenishment and exhaust components extract gas according to the pressure changes in the main water storage pipe and the side water storage pipe;

[0020] Step 2: After the interstitial water level in the interstitial water tanks at both ends of the vertical ship lift is lowered to a predetermined height, the first valve is closed;

[0021] The drainage method includes the following steps:

[0022] Step 1: close one or all of the first valve and the second valve on the main water storage pipe;

[0023] Step 2: The water pump motor unit replenishes the gap water in the main water storage pipe and the side water storage pipe into the gap water tanks at both ends of the vertical ship lift;

[0024] Step 3: After the water level in the gap water tank at both ends of the vertical ship lift reaches the preset height, the water pump motor unit stops working and the water is discharged.

[0025] The present invention discloses the following technical effects:

[0026] When the present invention is filled with water, the first valve on the main water storage pipe is opened, and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift is rapidly pushed forward in the form of open flow and enters the main water storage pipe, and at the same time enters the side water storage pipe through the connecting pipe. After the interstitial water in the main water storage pipe hits the second valve, a forced pipe sealing water jump is formed and a filling section is gradually formed. When the filling section is reversely extended to the connecting pipe, the mainstream is basically all diverted to the side water storage pipes on both sides, and the air replenishment and exhaust components pump out gas according to the pressure changes in the main water storage pipe and the side water storage pipe. After the interstitial water level in the interstitial water tanks at both ends of the vertical ship lift is lowered to a predetermined height, the first valve is closed; when the present invention is draining water, one or all of the first valve and the second valve on the main water storage pipe are closed, and the water pump motor unit replenishes the interstitial water in the main water storage pipe and the side water storage pipe into the interstitial water tanks at both ends of the vertical ship lift; after the water level in the interstitial water tanks at both ends of the vertical ship lift reaches the preset height, the water pump motor unit stops working to complete the draining.

[0027] The present invention eliminates the gas explosion phenomenon caused by the pressurized air in the main pipeline entering the gap due to poor exhaust. The exhaust valve is replaced by an exhaust assembly to improve the exhaust efficiency and avoid maintenance, which can effectively prevent the exhaust failure caused by mechanical failure or water leakage after the gap water is connected to the reservoir. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0029] Figure 1 A top view of the gap water filling and draining device of the large vertical ship lift of the present invention;

[0030] Figure 2 It is a side view of the gap water filling and draining device of the large vertical ship lift of the present invention;

[0031] Figure 3 It is a schematic diagram of the positional relationship between the main water storage pipe and the side water storage pipe of the present invention;

[0032] Figure 4 It is a pressure curve diagram of a specific embodiment of the present invention.

[0033] Among them, 1. Vertical ship lift; 2. Main water storage pipe; 3. First valve; 4. Second valve; 5. Side water storage pipe; 6. Connecting pipe; 7. Supplementary air pipe. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0036] Reference Figure 1-4 The present invention provides a device for filling and draining gap water of a large vertical ship lift, comprising a vertical ship lift 1, characterized in that it also includes:

[0037] The main water filling and draining assembly includes a main water storage pipe 2, which is arranged below the ship-carrying box of the vertical ship lift 1, and the two ends of the main water storage pipe 2 are respectively fixedly connected to the bottom of the gap water tank at the two ends of the vertical ship lift 1;

[0038] A control valve, the control valve comprises a first valve 3 and a second valve 4, the first valve 3 and the second valve 4 are respectively arranged at two ends of the main water storage pipe 2;

[0039] A flow splitter assembly, the flow splitter assembly includes a side water storage pipe 5, and the side water storage pipe 5 is provided with two groups, and the two groups of side water storage pipes 5 are symmetrically arranged on both sides of the main water storage pipe 2, and the water storage pipes 5 on both sides are fixedly connected to the main water storage pipe 2 through a plurality of connecting pipes 6;

[0040] Among them, a number of air supply and exhaust components are fixedly connected to the water storage pipes 5 on both sides, and a water pump motor group is arranged between the main water storage pipe 2 and the gap water tanks at both ends of the vertical ship lift 1.

[0041] When the present invention is filled with water, the first valve 3 on the main water storage pipe 2 is opened, and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift 1 is rapidly pushed forward in the form of open flow and enters the main water storage pipe 2, and at the same time enters the side water storage pipe 5 through the connecting pipe 6. After the interstitial water in the main water storage pipe 2 hits the second valve 4, a forced pipe sealing water jump is formed and a filling section is gradually formed. When the filling section is reversely extended to the connecting pipe 6, the mainstream is basically all diverted to the side water storage pipes 5 on both sides, and the replenishment and exhaust components pump out gas according to the pressure changes in the main water storage pipe 2 and the side water storage pipes 5. After the interstitial water level in the interstitial water tanks at both ends of the vertical ship lift 1 is reduced to a predetermined height, the first valve 3 is closed; when the present invention is drained, one or all of the first valve 3 and the second valve 4 on the main water storage pipe 2 are opened, and the water pump motor unit replenishes the interstitial water in the main water storage pipe 2 and the side water storage pipe 5 into the interstitial water tanks at both ends of the vertical ship lift 1; after the water level in the interstitial water tanks at both ends of the vertical ship lift 1 reaches the preset height, the water pump motor unit stops working, and the draining is completed.

[0042] The present invention eliminates the gas explosion phenomenon caused by the pressurized air in the main pipeline entering the gap due to poor exhaust. The exhaust valve is replaced by an exhaust assembly to improve the exhaust efficiency and avoid maintenance, which can effectively prevent the exhaust failure caused by mechanical failure or water leakage after the gap water is connected to the reservoir.

[0043] A further optimized solution is that the air-supply assembly includes an air-supply pipe 7, which is fixedly connected to the side water storage pipe 5, and the top elevation of the air-supply pipe 7 is not less than the top elevation of the ship-supporting compartment of the vertical ship lift 1.

[0044] A further optimization scheme is that the axes of the water storage pipes 5 on both sides are arranged in parallel, the axes of the side water storage pipe 5 and the main water storage pipe 2 are arranged in parallel in space, the axis of the side water storage pipe 5 is located below the axis of the main water storage pipe 2, and the vertical height difference between the axis of the side water storage pipe 5 and the axis of the main water storage pipe 2 is 100 mm.

[0045] According to a further optimization scheme, the length of the side water storage pipe 5 is 55m-60m, and the diameter of the side water storage pipe 5 is DN1000. The length of the side water storage pipe 5 is preferably 57m.

[0046] According to a further optimization scheme, the number of the connecting pipes 6 on both sides of the main water storage pipe 2 is the same.

[0047] To further optimize the solution, pressure sensors are installed on the main water storage pipe 2 and the side water storage pipe 5 respectively.

[0048] According to a further optimized solution, the diameter of the exhaust pipe 7 is 0.5m-0.6m, preferably 0.5m.

[0049] According to the further optimized solution, the diameter of the connecting pipe 6 is DN800.

[0050] A method for filling and draining gap water in a large vertical ship lift 1 includes a water filling method and a water draining method. The water filling method includes the following steps:

[0051] Step 1: Open the first valve 3 on the main water storage pipe 2, and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift 1 is rapidly pushed forward in the form of open flow and enters the main water storage pipe 2, and at the same time enters the side water storage pipe 5 through the connecting pipe 6. After the interstitial water in the main water storage pipe 2 hits the second valve 4, a forced pipe sealing water jump is formed and a full section is gradually formed. When the full section extends in the reverse direction to the connecting pipe 6, the mainstream is basically all diverted to the side water storage pipes 5 on both sides, and the air replenishment and exhaust components extract gas according to the pressure changes in the main water storage pipe 2 and the side water storage pipe 5;

[0052] Step 2: After the interstitial water level in the interstitial water tanks at both ends of the vertical ship lift 1 is lowered to a predetermined height, the first valve 3 is closed;

[0053] The drainage method includes the following steps:

[0054] Step 1: close one or all of the first valve 3 and the second valve 4 on the main water storage pipe 2;

[0055] Step 2: The water pump motor unit replenishes the interstitial water in the main water storage pipe 2 and the side water storage pipe 5 into the interstitial water tanks at both ends of the vertical ship lift 1;

[0056] Step 3: After the water level in the gap water tank at both ends of the vertical ship lift 1 reaches a preset height, the water pump motor unit stops working and the water is discharged. Specific embodiment:

[0058] refer to Figure 4 , side water storage pipes 5 with a length of 57m and a diameter of DN1000 are set on both sides of the main water storage pipe 2. The center of the side water storage pipe 5 is 100mm lower than the original water storage pipe. Three sections of DN800 transverse pipes are set between the main water storage pipe 2 and the side water storage pipe 5. Two supplementary and exhaust pipes 7 with a diameter of 0.5m are set on the top of each side water storage pipe 5, and are arranged at nearly equal intervals along the length; the volume of the main water storage pipe 2 is 100m 3 According to the diameter and length of the side water storage pipe 5, the volume of the water storage pipe 5 on both sides is 89m 3 , then the total volume of the water storage pipe is 189m 3 , 120m3 After storing the interstitial water, the surplus volume of the water storage pipe is 69m 3 , open the first valve 3 on the main water storage pipe 2, and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift 1 will be rapidly pushed forward in the form of open flow and enter the main water storage pipe 2, and at the same time enter the side water storage pipe 5 through the connecting pipe 6. The interstitial water in the main water storage pipe 2 will form a forced pipe sealing water jump after hitting the second valve 4 and gradually form a full section. When the full section extends in the reverse direction to the connecting pipe 6, the mainstream is basically diverted to the side water storage pipes 5 on both sides. Except for the short-term full pipe flow in the main water storage pipe 2 upstream of the proximal connecting pipe 6 at the initial stage of discharge, and the "stacking" phenomenon of the distal main water storage pipe 2 at the end of discharge to form a local short-term full pipe flow, no other adverse flow states are observed. The interstitial water level process (Z), the discharge valve opening process (e) and the pressure process of each measuring point are shown as follows: Figure 4 As shown in the figure. Affected by the "piston" effect caused by the capping water jump, the pressure measuring points at the top (1#) and bottom (2#) of the near-end supply and exhaust valve fluctuate to a certain extent between 10s and 50s; affected by the "stack" phenomenon and the full pipe flow, the pressure measuring point (6#) near the far-end supply and exhaust valve fluctuates to a certain extent between 40s and 60s, and the other pressure measuring points in the pipe and the water level process lines in the gap are relatively smooth. The gap water discharge is completed in about 60s.

[0059] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0060] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A device for filling and draining gap water of a large vertical ship lift, comprising a vertical ship lift (1), characterized in that: Also includes: A main water filling and draining assembly, the main water filling and draining assembly comprising a main water storage pipe (2), the main water storage pipe (2) being arranged below the ship receiving box of the vertical ship lift (1), and the two ends of the main water storage pipe (2) being fixedly connected to the bottom of the gap water tanks at the two ends of the vertical ship lift (1); A control valve, the control valve comprising a first valve (3) and a second valve (4), the first valve (3) and the second valve (4) being respectively arranged at two ends of the main water storage pipe (2); A flow diversion component, the flow diversion component comprising side water storage pipes (5), the side water storage pipes (5) being provided in two groups, the two groups of side water storage pipes (5) being symmetrically arranged on both sides of the main water storage pipe (2), the two side water storage pipes (5) being fixedly connected to the main water storage pipe (2) via a plurality of connecting pipes (6); Wherein, a plurality of air supply and exhaust components are fixedly connected to the two side water storage pipes (5), and a water pump motor unit is arranged between the main water storage pipe (2) and the gap water tanks at both ends of the vertical ship lift (1).

2. A device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: The air supply and exhaust assembly comprises an air supply and exhaust pipe (7), the air supply and exhaust pipe (7) is fixedly connected to the side water storage pipe (5), and the top elevation of the top of the air supply and exhaust pipe (7) is not less than the top elevation of the ship support compartment of the vertical ship lift (1).

3. The device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: The axes of the two side water storage pipes (5) are arranged in parallel, the axes of the side water storage pipes (5) and the main water storage pipe (2) are arranged in parallel, the axes of the side water storage pipes (5) are located below the axes of the main water storage pipe (2), and the vertical height difference between the axes of the side water storage pipes (5) and the axes of the main water storage pipe (2) is 100 mm.

4. The device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: The length of the side water storage pipe (5) is 55m-60m, and the diameter of the side water storage pipe (5) is DN1000.

5. The device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: The number of the connecting pipes (6) on both sides of the main water storage pipe (2) is the same.

6. The device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: Pressure sensors are installed on the main water storage pipe (2) and the side water storage pipe (5), respectively.

7. The device for filling and draining gap water of a large vertical ship lift according to claim 2, characterized in that: The diameter of the exhaust gas pipe (7) is 0.5m-0.6m.

8. The device for filling and draining gap water of a large vertical ship lift according to claim 1, characterized in that: The diameter of the connecting pipe (6) is DN800.

9. A method for filling and draining gap water of a large vertical ship lift (1), based on the device for filling and draining gap water of a large vertical ship lift according to any one of claims 1 to 8, characterized in that: It includes a water filling method and a water draining method. The water filling method includes the following steps: Step 1: Open the first valve (3) on the main water storage pipe (2), and the interstitial water in the interstitial water tanks at both ends of the vertical ship lift (1) is rapidly pushed forward in the form of open flow and enters the main water storage pipe (2), and at the same time enters the side water storage pipe (5) through the connecting pipe (6). After the interstitial water in the main water storage pipe (2) hits the second valve (4), a forced pipe sealing water jump is formed and a filling section is gradually formed. When the filling section extends in the reverse direction to the connecting pipe (6), the mainstream is basically completely diverted to the side water storage pipes (5) on both sides, and the air supply and exhaust components extract and discharge gas according to the pressure changes in the main water storage pipe (2) and the side water storage pipe (5); Step 2: After the interstitial water level in the interstitial water tanks at both ends of the vertical ship lift (1) is lowered to a predetermined height, the first valve (3) is closed; The drainage method includes the following steps: Step 1: close one or all of the first valve (3) and the second valve (4) on the main water storage pipe (2); Step 2: The water pump motor unit replenishes the interstitial water in the main water storage pipe (2) and the side water storage pipe (5) into the interstitial water tanks at both ends of the vertical ship lift (1); Step 3: After the water level in the gap water tanks at both ends of the vertical ship lift (1) reaches a preset height, the water pump motor unit stops working and the water is discharged.