Steel concrete continuous wall of underground structure and construction method of steel concrete continuous wall

Through the construction method of combining guide grooves and steel pipe piles, the uniform sinking of the continuous steel concrete wall is achieved by using mud buoyancy and wall panel control devices, solving the problems of low construction efficiency and high cost in the existing technology, and improving construction safety and degree of mechanization.

CN118911115APending Publication Date: 2024-11-08JIANGSU DONGHENAN GEOTECHNICAL TECH CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411075028.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing continuous wall construction methods for underground structures have problems such as deviating the placement of steel cages, easy touching the inner wall of the groove when sinking, resulting in landslide, low construction efficiency and high cost, which limits the scope of use and construction efficiency of continuous walls.

Method used

The construction method of combining guide grooves and steel pipe piles is adopted. The wall panel sinking speed is adjusted through the mud buoyancy in the guide grooves and the wall panel control device to ensure uniform sinking of the wall panels, and a combination structure of prefabricated wall panels and steel pipe piles is used. Reduce the difficulty and construction cost of foundation pit excavation.

Benefits of technology

It improves the construction efficiency and safety of steel concrete continuous walls, reduces costs, enhances the stability and connection strength of wall panel sinking, avoids the risk of landslides, and improves the degree of construction mechanization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911115A_ABST
    Figure CN118911115A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a steel concrete continuous wall of an underground structure, which comprises the following steps: constructing a guide wall and a guide groove of a construction section, forming slurry in the guide groove, and forming a cement soil continuous wall on the lower side of the guide groove; the steel pipe piles are inserted into the cement soil continuous wall through the guide grooves; connecting beams are constructed on the steel pipe piles, and wallboard control devices are erected; a first section of wall plate is poured between the connecting beam and the ground; the steel pipe pile is used as a guide rod, and the first section of wallboard sinks into the guide groove; all the wallboards sink and are connected with one another to form a construction section; the construction sections are mutually connected to form a steel concrete continuous wall, a foundation pit is excavated, and an underground structure is constructed; and after the underground structure is constructed to positive and negative zero, the steel pipe piles are pulled out. The invention further discloses the steel concrete continuous wall formed through the construction method. According to the construction method, the wallboards are sunken through the slurry in the guide grooves and the wallboard control device, and the problem that the continuous wall cannot be constructed due to collapse is solved due to the adoption of the construction mode of slurry and prefabricated wallboards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a steel concrete continuous wall of an underground structure and a construction method of the steel concrete continuous wall. Background Art

[0002] When constructing underground structures, in order to avoid collapse of the side walls of the foundation pit, a support system is usually used to support the side walls of the foundation pit to ensure the safety of the construction. When constructing some small underground structures, underground continuous walls are usually used as support systems. In order to reduce construction costs, some underground structures will use the underground continuous walls as the outer walls of the underground structures at the same time, forming a two-wall-in-one construction method.

[0003] There are two existing continuous wall construction methods: cast-in-place and prefabrication. When cast-in-place is used, the placement of the steel cage is prone to deviation, which affects the quality of the continuous wall. Therefore, it is often used for continuous walls with a smaller construction depth. When the prefabrication method is used, the prefabricated wall section is sunk into the continuous groove, and the joints of the prefabricated wall section are connected. When the prefabricated wall section sinks, it will inevitably touch the inner wall of the continuous groove, causing landslides in some areas of the continuous groove. Therefore, it is generally only used in areas with better soil conditions. Due to the above reasons, the use of continuous walls is limited, and overlapping mixing piles, rotary jet piles or cast-in-place piles are often used to replace continuous walls, which not only reduces construction efficiency, but also increases construction costs. Therefore, how to improve the construction process of continuous walls and expand the scope of use of continuous walls to reduce construction costs and improve construction efficiency has also become a need. Summary of the invention

[0004] In order to solve at least some of the above problems, the present application first proposes a construction method of a steel concrete continuous wall of an underground structure, wherein the steel concrete continuous wall includes at least two construction sections, and the steel concrete continuous wall in each construction section includes N layers of walls connected together along the height direction, where N is an integer ≥1; each layer of the wall includes M sections of wall panels connected together along the length direction, where M is an integer ≥1; the wall panels located at the lowest layer are called the first section of wall panels, and the construction method includes the following steps:

[0005] (1) Construct the guide wall corresponding to a construction section;

[0006] (2) constructing a guide groove and forming a cement soil continuous wall on the lower side of the guide groove, wherein the top surface of the cement soil continuous wall is lower than the set elevation of the bottom surface of the foundation pit; the soil in the guide groove becomes mud;

[0007] (3) inserting a steel pipe pile into the guide groove, and inserting the lower end of the steel pipe pile into the cement soil continuous wall;

[0008] (4) constructing a connecting beam on the steel pipe pile, forming a wall panel construction space between the connecting beam and the ground, and setting up a wall panel control device on the connecting beam;

[0009] (5) Casting the first section of wall panels in the wall panel construction space, with the panel body of the first section of wall panels wrapped around the steel pipe piles;

[0010] (6) After the concrete of the first wall panel reaches the designed strength, the first wall panel is sunk into the guide groove using the steel pipe pile as a guide rod, and the sinking speed of the first wall panel is adjusted using the wall panel control device; during the sinking process of the first wall panel, the mud in the guide groove is pumped out;

[0011] (7) When N=1 and M=1, the first section of the wall panel is formed as the construction section;

[0012] When N≥2 or M≥2, repeat steps (5) and (6) until all wall panels are sunk and connected to form the construction section.

[0013] (8) After the construction of all construction sections is completed, the construction sections are connected to form a steel concrete continuous wall and the foundation pit is excavated;

[0014] (9) Construction of underground structures in foundation pits;

[0015] (10) After the underground structure is constructed to zero, the steel pipe piles are removed and the holes left by the removal of the steel pipe piles are filled.

[0016] For the convenience of description in this application, each layer of wall is referred to as the first layer of wall, the second layer of wall, ..., the Nth layer of wall from bottom to top, among which the wall panels of the first layer of wall are referred to as the first section of wall panels, the wall panels of the second layer of wall are referred to as the second section of wall panels, and the wall panels of the Nth layer of wall are referred to as the Nth section of wall panels.

[0017] When constructing the guide groove, equipment such as a double-wheel milling machine or a chain-type troughing machine (TRD) is used. The guide groove and the cement soil continuous wall can be completed continuously using the same equipment or different equipment. The cement soil continuous wall can also be constructed using equipment other than a double-wheel milling machine or a chain-type troughing machine, such as a double-axis or three-axis mixing pile driver and a rotary jet pile driver. The top surface of the cement soil continuous wall is preferably set 0.5-2 meters below the bottom surface of the foundation pit.

[0018] The steel pipe piles are preferably inserted into the cement soil continuous wall to a depth of 5-10 meters so that the steel pipe piles can generate sufficient friction in the cement soil continuous wall to ensure that they will not sink under the friction of the wall panels when the wall panels sink, thereby ensuring the stability of the steel pipe piles.

[0019] In order to facilitate the removal of the bottom formwork of the wall panel, it is preferred that the bottom formwork adopts a block assembly structure, and a bottom formwork hole for the steel pipe pile to pass through is provided on the bottom formwork. The connecting beam can be a steel concrete structure or a steel structure, and both structural forms can be constructed by on-site production or prefabrication.

[0020] In order to improve the stability of the wall panel when it sinks, a number of steel pipe piles are arranged along the length direction of the guide groove, and in the thickness direction of the wall panel, the steel pipe piles are located in the middle part of the wall panel.

[0021] When the upper and lower wall panels are arranged opposite to each other in the vertical direction, the following methods can be used when sinking each wall panel: Method A, when a section of wall panel completely enters the guide groove, the next section of wall panel is poured, and when the next section of wall panel sinks, the wall panel in the guide groove is pushed to continue sinking until all the wall panels have completed the sinking and reached the set position; Method B, when each section of wall panel sinks, it sinks to its set position at one time. The two methods can be used separately or simultaneously. When the above two methods are used at the same time, the wall panel at the bottom can be sunk to its set position at one time, and the upper wall panel can be sunk using method A. This wall panel sinking method is only suitable for the construction of steel concrete continuous wall sections with a foundation pit depth of no more than 3 meters.

[0022] When the wall panels in the upper and lower adjacent walls are arranged in a staggered manner, each wall panel can be connected to the two wall panels in the upper layer or the two wall panels in the lower layer. When this staggered construction method is used, the wall panels in the two adjacent construction sections need to be partially sunk in the form of a pyramid first, and a gap of an inverted pyramid is formed between the two construction sections, and then the gap is filled with wall panels. This wall panel sinking method is suitable for the construction of all steel concrete continuous walls.

[0023] In the steel concrete continuous wall construction method of the present application, the buoyancy of the mud in the guide groove and the control of the wall panel sinking speed by the wall panel control device are utilized to make the wall panel sink safely and evenly. Since the construction method of mud + prefabricated wall panels is adopted, the problem that some underground soil is prone to collapse and the continuous wall cannot be constructed is avoided. Since the foundation pit is excavated after the wall panels are sunk on the ground, large-scale construction machinery can be fully used for earth excavation, which minimizes the difficulty of earth excavation, not only improves the safety of the operation, but also improves the construction efficiency and saves construction costs. Specifically, the construction method has the following advantages:

[0024] 1. The steel-concrete continuous wall and steel pipe piles form a composite structure. During the excavation process, the composite structure has high rigidity and strength, and small deformation during the excavation process. After the construction reaches zero, the steel pipe piles can be pulled out and reused, which is economical and environmentally friendly.

[0025] 2. The cement-soil continuous wall on the lower side serves as a water-stop curtain to avoid the problem of the bottom bulging upward and the sudden surge of groundwater. When precipitation measures are adopted in the foundation pit, the impact on the surrounding environment is relatively small.

[0026] 3. The connection of the connecting beam increases the overall stability of the steel pipe piles; the steel pipe piles also serve as guide rods, which can control the sinking of the wall panels with high precision. The sinking speed of the wall panels is controlled by the wall panel control device to avoid sudden sinking of the wall panels.

[0027] 4. The construction method of traditional steel concrete continuous wall has been changed. The original soil is fully mixed by double-wheel milling, TRD or multi-axis mixing pile driver, which greatly reduces the sinking resistance of the wall panel, completely separates the side wall of the guide groove from the surrounding soil, and the geological conditions are relatively uniform.

[0028] Since the soil in the guide trough is stirred into mud, it can protect the guide trough wall to avoid the collapse of the trough wall, and can also provide buoyancy for the wall panel to ensure uniform sinking of the wall panel.

[0029] 5. The wall panels are cast on the ground, with reliable construction quality, good integrity, impermeability and durability.

[0030] Furthermore, in order to smoothly mix the earthwork in the guide groove into mud, when constructing the guide groove, slurry is sprayed into the underground soil at the same time to mix the underground soil into mud. The slurry is mixed with the following components in mass percentage: 70-90% clean water, 5-29% bentonite, and 1-5% adhesive. The adhesive can be carboxymethyl cellulose (CMC) or polyacrylamide (PAM) or other similar adhesives. In a specific embodiment, it is necessary to conduct experiments according to the different soil types in the construction area to determine the appropriate ratio. The density of the mud is preferably 1.05-1.2g / ml.

[0031] Furthermore, in order to improve the connection strength between the upper and lower walls, after the steel pipe piles are pulled out, a reinforced steel cage is placed in the hole left by the steel pipe piles, and concrete is poured.

[0032] Furthermore, in order to increase the pile end resistance of the steel pipe pile in the cement soil continuous wall and improve the compressive capacity of the steel pipe pile, the bottom of the steel pipe pile is closed.

[0033] Furthermore, in order to smoothly lower the wall panels, a pipe insertion hole is reserved in the axial direction on each wall panel, and the pipe insertion holes on the upper and lower adjacent wall panels are connected in the vertical direction. When the wall panel is difficult to sink, the water jet tube is inserted into the pipe insertion hole, and water is sprayed to the bottom of the first section of the wall panel through the water jet tube to punch and cut the mud under the first section of the wall panel. When using the water jet tube to spray water downward, it is necessary to spray evenly along the length direction of the wall panel to avoid excessive or insufficient local spraying, which will cause the wall panel to tilt. When the wall panel tilts, it is necessary to adjust the spray volume of each water jet tube in time to correct the wall panel.

[0034] Furthermore, in order to reduce the friction between the wallboard and the steel pipe pile, an isolation membrane is provided on the outer wall of the steel pipe pile. The isolation membrane can be made of geotextile, plastic film or other materials, or isolation paint is applied on the outer wall of the steel pipe pile, and the paint film formed by the isolation paint forms the isolation membrane.

[0035] Specifically, the wall panel control device includes a lifting mechanism and a pressing mechanism, wherein the lifting mechanism is used to bear the weight of the wall panel, and the pressing mechanism is used to push the wall panel downward. Furthermore, the lifting mechanism is fixedly installed on the ground or fixedly installed on the connecting beam, and the pressing mechanism adopts a jack, which is arranged between the connecting beam and the wall panel to be sunk. The lifting mechanism can specifically adopt a winch or a lifting machine. When the lifting mechanism is installed on the ground, a pulley needs to be installed on the connecting beam to facilitate the arrangement of the lifting rope of the lifting mechanism. The jack can specifically adopt a mechanical jack or a hydraulic jack.

[0036] Alternatively, the wall panel control device includes a piston cylinder, the cylinder barrel of the piston cylinder is fixed on the connecting beam, and the piston rod of the piston cylinder extends downward and is detachably connected to the wall panel. The piston cylinder has the dual ability of lifting and pressing down, which can improve the construction efficiency. The piston cylinder diameter can be an electric piston cylinder or a hydraulic piston cylinder for unified control.

[0037] Secondly, the present application also provides a steel concrete continuous wall, which is constructed using any of the above-mentioned construction methods. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a construction flow chart of the present invention.

[0039] Figure 2 It is a structural diagram of an underground pipe gallery made by the construction method in this application.

[0040] Figure 3 yes Figure 1 Enlarged view of part A.

[0041] Figure 4 It is a schematic diagram of the structure in which the wall panel control device is a piston cylinder.

[0042] Figure 5 It is a structural diagram of the wall panel.

[0043] Figure 6 It is a structural diagram of the bottom mold.

[0044] Figure 7 It is the connection structure diagram of two adjacent wall panels in the horizontal direction.

[0045] Figure 8 It is a simplified diagram of the construction process of two adjacent construction sections. DETAILED DESCRIPTION

[0046] The following is a detailed description of the construction method of the steel concrete continuous wall in this application. Please refer to Figure 1 and Figure 2 , Figure 1 The mark 100 in the figure represents the ground. The steel concrete continuous wall in this embodiment is Figure 2 As shown in the figure, the outer walls on both sides of the underground tunnel, the steel concrete continuous wall in this embodiment is divided into several construction sections along the extension direction of the underground tunnel, i.e., the length direction, each construction section includes three layers of walls connected together along the height direction, and each layer of walls includes three sections of wall panels connected together along the vertical direction. For the convenience of description, the three layers of walls are referred to as the first layer of walls, the second layer of walls and the third layer of walls from bottom to top, wherein the wall panels of the first layer of walls are referred to as the first section of wall panels 21, the wall panels of the second layer of walls are referred to as the second section of wall panels 22, and the wall panels of the third layer of walls are referred to as the third section of wall panels 23.

[0047] The construction method specifically comprises the following steps:

[0048] (1) Please refer to Figure 1 (a) A guide wall 11 is constructed in an area corresponding to the first construction section. The guide wall includes a first guide wall 111 and a second guide wall 112 which are spaced apart.

[0049] (2) Please refer to Figure 1 (b), construct the guide groove 13 downward along the area between the first guide wall and the second guide wall, and form a cement soil continuous wall 31 on the lower side of the guide groove, the top surface of the cement soil continuous wall 31 is 1 meter lower than the set elevation of the bottom surface of the foundation pit. It can be understood that in other embodiments, the top surface of the cement soil continuous wall 31 can also be 0.2 meters, 0.5 meters, 1.5 meters, 2 meters or other distances between 0.2-2 meters lower than the set elevation of the bottom surface of the well hole of the sinking wall plate wall.

[0050] When constructing the guide groove, slurry is sprayed into the guide groove at the same time to stir the earth in the guide groove into mud. In this embodiment, a double-wheel groove milling machine is specifically used to construct the guide groove. It can be understood that in other embodiments, a chain groove machine (TRD) and other equipment can also be used to construct the guide groove. The cement soil continuous wall 31 is used as a water-stop curtain to avoid the problem of the bottom of the foundation pit bulging upward and the sudden surge of groundwater due to the external pressure of the foundation pit. When precipitation measures are adopted in the foundation pit, the groundwater outside the foundation pit has less impact on the surrounding environment due to the barrier effect of the cement soil continuous wall.

[0051] The slurry is formed by stirring the following raw materials in mass percentage, 85% clean water, 12% bentonite and 3% adhesive. The density of the mud is controlled between 1.06-1.08g / ml. It is understood that in other embodiments, the composition of the slurry can also be 70% clean water, 25% bentonite and 5% adhesive, or 90% clean water, 6% bentonite and 4% adhesive, or 83% clean water, 16% bentonite and 1% adhesive, or 90% clean water, 5% bentonite and 5% adhesive. The density of the mud can also be 1.05-1.06g / ml, 1.08-1.11g / ml or 1.12-1.15g / ml. It is specifically carried out according to factors such as the convenience of construction. In the present embodiment, the adhesive specifically adopts carboxymethyl cellulose (CMC), and it is understood that in other embodiments, polyacrylamide (PAM) or similar adhesives can also be used.

[0052] (3) Insert the steel pipe pile 14 into the guide groove 13, and insert the lower end of the steel pipe pile 14 into the cement soil continuous wall. The depth of the steel pipe pile inserted into the cement soil continuous wall is 5 meters. In this embodiment, in order to increase the pile end resistance of the steel pipe pile, the bottom of the steel pipe pile is closed. It can be understood that in other embodiments, the depth of the steel pipe pile inserted into the cement soil continuous wall can also be 6 meters, 7 meters, 8 meters, 10 meters or other data between 5-10 meters.

[0053] (4) Please refer to Figure 1 (c), a connecting beam 15 is constructed on the top of the steel pipe pile 14, and the connecting beam 15 connects the steel pipe piles into a whole. The space between the connecting beam 15 and the ground forms a wall panel construction space, and then a wall panel control device 16 is installed on the connecting beam. In this embodiment, in order to improve the working efficiency, the connecting beam adopts a prefabricated steel structure beam. It can be understood that in another embodiment, a connecting beam constructed on site by a steel section can also be adopted. The connecting beam can also adopt a steel concrete structure. When a steel concrete structure is adopted, a prefabricated beam or a cast-in-place beam can be selected as needed.

[0054] Please also see Figure 3 In this embodiment, the wall panel control device 16 includes a lifting mechanism and a pressing mechanism, wherein the lifting mechanism is used to bear the weight of the wall panel, and the pressing mechanism is used to push the wall panel downward. The lifting mechanism in this embodiment specifically includes a bracket 168 mounted on the upper side of the connecting beam and an electric hoist 161 fixed on the bracket 168. A rope threading hole 151 is opened on the connecting beam, and a lifting rope 162 of the electric hoist freely passes through the rope threading hole 151, and a hook 163 is installed at the lower end of the lifting rope.

[0055] The pressing mechanism specifically adopts a jack, and both a mechanical jack and a hydraulic jack are acceptable. There is no special requirement for the structural form of the jack, and other forms of jacks may also be adopted. In the present embodiment, a hydraulic jack is specifically adopted.

[0056] In this embodiment, the electric hoist serving as the lifting mechanism is installed on a bracket above the connecting beam. It can be understood that in another implementation, the electric hoist can also be installed on the ground, and then the lifting rope can pass through the pulley installed on the bracket and then hooked on the wall panel. Of course, in another embodiment, the lifting mechanism can also use a winch, and the winding machine can be specifically installed on the connecting beam or the ground. Of course, other lifting equipment can also be used.

[0057] (5) Please refer to Figure 1 (d) Cast the first wall panel 21 in the wall panel construction space, and wrap the first wall panel around the steel pipe pile. Figure 5 and Figure 6 When pouring the first section of the wall panel 21, first lay the bottom mold 51 on the ground. To facilitate the removal of the bottom mold 51, the bottom mold adopts a block assembly structure. Specifically, in this embodiment, the bottom mold 51 is divided into an inner bottom mold 53 and an outer bottom mold 54 as a whole, and the inner bottom mold is divided into a plurality of inner sub-bottom molds 531, and the outer bottom mold 54 is divided into a plurality of outer sub-bottom molds 541. A bottom mold hole 52 for the steel pipe pile to pass through is opened on the bottom mold, and the outer semicircle of the bottom mold hole is located on the outer bottom mold, and the inner semicircle is located on the inner bottom mold. Figure 6 This is only to illustrate the structure of the bottom mold, not a specific embodiment. During the specific construction, the inner and outer sub-bottom molds need to be specifically designed and cut according to the needs of removing the bottom mold. The inner bottom mold refers to the part of the bottom mold facing the inside of the pipe gallery, and the outer bottom mold refers to the part of the bottom mold facing the outside of the pipe gallery. The inner bottom mold and the outer bottom mold are mainly for the convenience of description and have no other meanings.

[0058] After the bottom form 51 is laid, the steel cage 26 is tied on the bottom form, and the inner and outer formworks are supported. The support of the inner and outer formworks and the tying of the steel cage can be constructed according to the existing technology without special requirements. Finally, the concrete 27 is poured. After the concrete reaches the designed strength, the first section of the wall panel 21 is formed. In order to facilitate hooking, a lifting lug 28 is embedded at the top of the first section of the wall panel. In order to avoid the lifting lug affecting the sinking of the upper wall panel, it is preferred to set the lifting lug to a sinking type so that the top of the lifting lug does not exceed the top surface of the first section of the wall panel. If it is necessary to make the top surface of the lifting lug exceed the top surface of the first section of the wall panel, before sinking the second section of the wall panel, the lifting lug on the first section of the wall panel needs to be cut off, or a receiving cavity for accommodating the lifting lug is set at the bottom of the second section of the wall panel. This method is used in the subsequent pouring construction of other wall panels and will not be repeated.

[0059] A hook is installed on the lifting rope 162 of the electric hoist in this embodiment, so a lifting ear is set on the top of the wall panel. It can be understood that in other embodiments, other forms of hanging components can be set as needed. For example, an internal threaded tube can be embedded in the top of the wall panel, and the hook can be replaced with a bolt. When the wall panel is sunk, the bolt is screwed onto the internal threaded tube.

[0060] In order to reduce the friction between the wallboard and the steel pipe pile, in this embodiment, a plastic film is wrapped on the outer wall of the steel pipe pile, and the plastic film is used as an isolation film. It can be understood that in another embodiment, geotextile can also be used to replace the plastic film, or isolation paint can be applied on the outer wall of the steel pipe pile, and the paint film formed by the isolation paint forms an isolation film. When pouring each section of the wallboard, it is necessary to re-set the isolation film on the outer wall of the steel pipe pile to avoid damage to the isolation film due to friction.

[0061] (6) Please refer to Figure 1 (e) After the concrete of the first section of the wall panel 21 reaches the designed strength, the hook of the wall panel control device is hooked on the lifting lug of the first section of the wall panel, and the first section of the wall panel is sunk into the guide groove using the steel pipe pile as a guide rod. The sinking speed of the first section of the wall panel is adjusted using the wall panel control device.

[0062] During the sinking process of the first wall panel, the sinking is mainly completed by the deadweight of the first wall panel. If it cannot sink or the sinking speed is too slow when sinking only by its deadweight, the jack as a pressing mechanism is arranged between the first wall panel and the connecting beam to provide auxiliary sinking force. During the sinking process of the wall panel, the mud in the guide groove is pumped out by a mud pump.

[0063] (7) Please also refer to Figure 1 (f) and see Figure 1 (g) Repeat steps (5) and (6) until all wall panels are sunk and adjacent wall panels are connected up and down to form a sunken wall panel wall 20. Figure 1 In (f), the second wall panel 22 has sunk into the ground, and the third wall panel 23 has been cast.

[0064] In this embodiment, the first section of wall panels, the second section of wall panels and the third section of wall panels are connected together in the vertical direction. This construction method is only applicable to foundation pit construction with a relatively low depth.

[0065] To ensure that the adjacent wall segments in the horizontal direction are stably connected together, in this embodiment, the adjacent wall segments in the horizontal direction are connected together through the slots 202 and the protrusions 201. For details, please refer to Figure 7 Of course, in order to make the connection between the upper and lower adjacent wall sections more stable, the upper and lower connected wall sections can also be connected together through similar slots and protrusions.

[0066] See also Figure 8 It can be understood that in another embodiment, the wall panels in the walls of two adjacent layers can be arranged in a staggered manner so that each wall panel can be connected to the two wall panels of the upper layer or the two wall panels of the lower layer. When the staggered construction is carried out in this manner, the wall panels in the two adjacent construction sections need to be partially sunk in the form of a pyramid first, and an inverted pyramid gap 207 is formed between the two construction sections, and then the gap 207 is filled with wall panels. Figure 8 In (a), part of the wall panels in the first construction section 205 have completed the pyramid-shaped sinking; Figure 8 In (b), part of the wall panels in the second construction section 206 have completed the pyramid-shaped sinking. Figure 8 In (b), the gap 207 is represented by an elliptical double-dotted line; in 8(c), the wall panel in the gap 207 area has been sunk, connecting the first construction section and the second construction section into a whole. The staggered arrangement can improve the integrity of the steel concrete continuous wall.

[0067] (8) Please also refer to Figure 1 (h) and Figure 1 (i) After the construction of all construction sections is completed, a foundation pit 40 is excavated. During the excavation of the foundation pit, a surrounding purlin 41 is simultaneously erected on the inner surface of the steel concrete continuous wall.

[0068] (9) Please refer to Figure 1 (j) Lay a cushion layer in the foundation pit and construct the bottom plate 61 and top plate of the underground structure 60.

[0069] (10) Please continue to participate Figure 1 (j) After the underground structure 60 is constructed to zero, the steel pipe piles 14 are removed and recycled. In this embodiment, in order to improve the connection strength between the two layers of wall panels, a reinforced steel cage is placed in the hole left by removing the steel pipe piles, and concrete is poured.

[0070] In this embodiment, when a section of wall panel completely enters the guide groove, the next section of wall panel is cast, and when the next section of wall panel sinks, it will push the wall panel in the guide groove to continue to sink until all the wall panels have finished sinking and reach the set position. It can be understood that in another embodiment, each section of wall panel can also sink to its set position at one time when it sinks. However, when the wall panels are arranged in a staggered manner, each wall panel needs to be sunk to its set position at one time.

[0071] In this embodiment, a pipe insertion hole 29 is reserved on each wall panel along the axial direction of the wall panel, and the pipe insertion holes on adjacent wall panels are connected along the axial direction of the wall panel. When the wall panel is difficult to sink, the water jet pipe is inserted into the pipe insertion hole, and water is sprayed to the bottom of the first section of the wall panel through the water jet pipe to punch and cut the mud under the first section of the wall panel. The downward pressure mechanism and the water jet pipe can be used simultaneously or separately, and can be selected according to the specific conditions of the construction. The water jet pipe is specifically made of steel pipe.

[0072] Since in this embodiment, the outer wall of the pipe gallery is constructed, it can be understood that the construction method in this application can also be used to construct underground ditches and foundation pit supports, and can also be used to construct caissons.

[0073] In this embodiment, the wall panel control device has a lifting mechanism and a pressing mechanism, wherein the lifting mechanism is used to bear the weight of the wall panel, and the pressing mechanism is used to push the wall panel downward. Figure 4 In another embodiment, the lifting mechanism and the pressing mechanism can be combined into one mechanism, and the piston cylinder 17 is directly used. When the piston cylinder 17 is used as the wall panel control device, the cylinder barrel 171 of the piston cylinder is fixed to the top of the connecting beam 15, and a corresponding piston hole 152 is provided on the connecting beam, so that the piston rod 172 of the piston cylinder can extend downward through the piston hole and be detachably connected to the wall panel after freely passing through the piston hole. The piston cylinder is preferably an electric piston cylinder or a hydraulic piston cylinder for unified control.

Claims

1. A method for constructing a steel-concrete continuous wall of an underground structure, characterized in that: The steel concrete continuous wall comprises at least two construction sections, and the steel concrete continuous wall in each construction section comprises N layers of wall bodies connected together along the height direction, where N is an integer ≥1; each layer of the wall comprises M sections of wall panels connected together along the length direction, where M is an integer ≥1; the wall panels located at the lowest layer are called the first section of wall panels, and the construction method comprises the following steps: (1) Construct the guide wall corresponding to a construction section; (2) constructing a guide groove and forming a cement soil continuous wall on the lower side of the guide groove, wherein the top surface of the cement soil continuous wall is lower than the set elevation of the bottom surface of the foundation pit; the soil in the guide groove becomes mud; (3) inserting a steel pipe pile into the guide groove, and inserting the lower end of the steel pipe pile into the cement soil continuous wall; (4) constructing a connecting beam on the steel pipe pile, forming a wall panel construction space between the connecting beam and the ground, and setting up a wall panel control device on the connecting beam; (5) Casting the first section of wall panels in the wall panel construction space, with the panel body of the first section of wall panels wrapped around the steel pipe piles; (6) After the concrete of the first wall panel reaches the designed strength, the first wall panel is sunk into the guide groove using the steel pipe pile as a guide rod, and the sinking speed of the first wall panel is adjusted using the wall panel control device; during the sinking process of the first wall panel, the mud in the guide groove is pumped out; (7) When N=1 and M=1, the first section of the wall panel is formed as the construction section; When N≥2 or M≥2, repeat steps (5) and (6) until all wall panels are sunk and connected to form the construction section. (8) After the construction of all construction sections is completed, the construction sections are connected to form a steel concrete continuous wall and the foundation pit is excavated; (9) Construction of underground structures in foundation pits; (10) After the underground structure is constructed to zero, the steel pipe piles are removed and the holes left by the removal of the steel pipe piles are filled.

2. The construction method according to claim 1, characterized in that: When constructing the guide trough, slurry is sprayed into the underground soil at the same time to stir the underground soil into mud.

3. The construction method according to claim 1, characterized in that: After the steel pipe piles are removed, a reinforcing steel cage is placed in the hole left by the steel pipe piles and concrete is poured.

4. The construction method according to claim 1, characterized in that: The bottom of the steel pipe pile is closed.

5. The construction method according to claim 1, characterized in that: A pipe insertion hole is reserved in the axial direction on each wall panel, and the pipe insertion holes on the upper and lower adjacent wall panels are connected in the vertical direction. When the wall panel has difficulty in sinking, the water jet tube is inserted into the pipe insertion hole, and water is sprayed to the bottom of the first section of the wall panel through the water jet tube to punch and cut the mud under the first section of the wall panel.

6. The construction method according to claim 1, characterized in that: An isolation membrane is arranged on the outer wall of the steel pipe pile.

7. The construction method according to claim 1, characterized in that: The wall panel control device comprises a lifting mechanism and a pressing mechanism, wherein the lifting mechanism is used to bear the weight of the wall panel, and the pressing mechanism is used to push the wall panel downward.

8. The construction method according to claim 7, characterized in that: The lifting mechanism is fixedly installed on the ground or on the connecting beam, and the pressing mechanism adopts a jack, which is arranged between the connecting beam and the wall panel to be sunk.

9. The construction method according to claim 1, characterized in that: The wall panel control device comprises a piston cylinder, a cylinder barrel of the piston cylinder is fixed on a connecting beam, and a piston rod of the piston cylinder extends downward and is detachably connected to the wall panel.

10. A steel-concrete continuous wall, characterized in that: The structure is constructed by the construction method described in any one of claims 1 to 9.