Rapid underground diaphragm wall obstacle removing method

Through the combination of rectangular steel pipes and high-speed rock crushers, combined with mud assisted cleaning and retaining protective layers, the problems of steel casing positioning difficulties and soil erosion in track projects are solved, and rapid and safe underground continuous wall cleaning is achieved, which improves the Construction efficiency and structural stability.

CN118911144AActive Publication Date: 2024-11-08CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1

Patent Information

Application Number
CN202411145858.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-08
Estimated Expiration
2044-08-20

AI Technical Summary

Technical Problem

In the construction of track engineering, the steel casing is difficult to rotate and position, which may lead to soil erosion inside and outside the wall, affecting the safety of the station structure, the process of cleaning up the barriers is cumbersome and time-consuming, and the cleared obstacles may jamm the machinery, forming a new obstacles.

Method used

Rectangular steel pipes are combined with high-speed rock crushers, and the underground continuous wall protection layer is retained through mud assisted cleaning. High-speed rotors and high-strength alloy cutters are used to crush rocks to avoid drilling and drilling and ensure cleanup accuracy and safety.

Benefits of technology

Fast and safe underground continuous wall clearance is achieved, soil erosion is avoided, construction efficiency is improved, the risk of mechanical obstacles is reduced, and the stability of the station structure is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911144A_ABST
    Figure CN118911144A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid underground diaphragm wall obstacle removing method which specifically comprises the following steps: cleaning the ground surface, leveling the ground and hardening the construction ground with concrete. The immersed tube inserting plane position of the rectangular steel tube is marked on the ground; a rectangular steel pipe is inserted, soil in the steel pipe is taken out by combining a crane with soil taking equipment during insertion, and slurry is injected; hoisting the rock into a horizontal high-speed rock crusher by using a crane, and crushing the rock; adjusting the height of the rectangular steel pipe and repeatedly crushing rocks; pulling out the rectangular steel pipe, moving the horizontal position of the steel pipe, and repeating rock crushing construction; the steps are repeated, after all obstacles are removed, the machine is hoisted out, and the rectangular steel pipe is pulled out; according to the method, the high-speed drilling machine is adopted to drive the cutter head to grind the underground diaphragm wall, drilling coring treatment is replaced, and the method has the advantages that slag is easy to remove, and machines are not clamped; the scheme that a protective layer of the underground diaphragm wall is reserved instead of drilling to penetrate through the underground diaphragm wall is adopted, and the method has the advantages of well controlling cracking and deformation of the existing station structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a rapid underground continuous wall obstacle clearing method. Background Art

[0002] During the construction of rail engineering, obstacle clearance operations are required. Patent number: CN115653495A discloses an obstacle clearance method of vertical sinking of ultra-large diameter steel casing combined with horizontal core drilling. This patent inserts a large diameter steel casing next to the structure that needs to be cleared. The steel casing has holes, and the size of the holes is reserved according to the size of the obstacle clearance drilling rig. By adjusting the different positions of the casing, the horizontal drilling rig is used to gradually clear the obstacles. The horizontal drilling rig obstacle clearance plan is: a large diameter drilling rig is hoisted in from the inside of the casing, and the drilling rig extends out of the reserved hole to coring. After the coring is completed, the cutter head carrying the core sample is retracted into the casing, and then the horizontal drilling rig and the core sample are hoisted out of the casing as a whole. Then move the casing up and down and left and right to gradually coring and clear obstacles.

[0003] The above existing patents have the following disadvantages: (1) After the steel casing is rotated underground, it is not easy to locate the hole position, and the plane of the hole needs to be parallel to the plane of the obstacle clearance structure (the hole faces the obstacle clearance structure); (2) Mechanical directional drilling is used in the obstacle clearance process. After completion, the wall is connected inside and outside, which may cause soil erosion behind the wall and form a cavity under the existing station. This situation poses a serious threat to the safety of the existing station structure and may cause cracking, leakage and large deformation, thereby affecting the normal passage of vehicles; (3) The cleared obstacles will enter the tunneling pipe and need to be mechanically withdrawn and then hoisted to the ground for cleaning. This process is cumbersome and time-consuming; (4) Concrete blocks may get stuck in mechanical equipment, thus forming new obstacles. In view of the above problems, further in-depth research is needed to optimize the design of construction methods to ensure construction safety and efficiency. Summary of the invention

[0004] The main purpose of the present invention is to provide a rapid underground continuous wall obstacle clearing method, aiming to solve the existing technical problems.

[0005] To achieve the above object, the present invention provides a rapid underground continuous wall obstacle removal method, which specifically includes the following steps:

[0006] Clean the surface, level the ground, and harden the concrete construction ground;

[0007] Mark the plane position of the rectangular steel pipe on the ground;

[0008] Insert the rectangular steel pipe, and use the crane combined with the soil taking equipment to take out the soil in the rectangular steel pipe and inject mud;

[0009] Use a crane to hoist in a horizontal high-speed rock crusher and crush the rock;

[0010] Adjust the height of the rectangular steel pipe and repeat the rock crushing;

[0011] Pull out the rectangular steel pipe, move the steel pipe to a horizontal position, and repeat the rock crushing construction;

[0012] Lift out the machine, pull out the steel pipe, and backfill; move the ground horizontally forward 1 meter along the wall that needs to be cleared, repeat the above steps, and after all obstacles are cleared, lift out the machine and pull out the rectangular steel pipe.

[0013] Furthermore, during the process of hoisting the rock crusher, four vertical angle steel limit slide grooves are arranged on the rectangular steel pipe, and four horizontal angle steel support brackets are arranged at the bottom to limit the height and support the rock crusher.

[0014] Furthermore, during the rock crushing process, the rock crushing depth retains the inner protective layer of the underground continuous wall, and mud is pumped to the cutter head of the rock crusher to cool the cutter head and replace the cut residues through the mud. When the second layer of steel bars of the underground continuous wall is broken and the inner protective layer of concrete remains, the rock crushing is stopped, the concrete protective layer is retained, and the rock crusher cutter head is retracted into the rectangular steel pipe.

[0015] Furthermore, the limiting height of the angle steel is the center position of the opening position or half of the height of the rectangular box.

[0016] Furthermore, the insertion depth of the rectangular steel pipe is the center position of the steel pipe opening - 50 cm, that is, this position is the deepest position that needs to be cleaned, and the verticality of the rectangular steel pipe is controlled within a deviation range of 2 cm.

[0017] Furthermore, the rock crushing depth is determined according to the extension length of the cutter disc, that is, the extension length = (outer diameter of the steel pipe - steel pipe wall thickness - thickness of the chute angle steel + interval between the steel pipe and the wall + thickness of the underground continuous wall - thickness of the underground continuous wall protective layer) - length of the rock crusher.

[0018] Furthermore, one side of the opening of the rectangular steel pipe is parallel to the underground continuous wall that needs to be cleared, and the rectangular steel pipe is spaced 15 cm from the wall.

[0019] Furthermore, the rock crusher includes a high-speed rotor, which is equipped with a power supply device, the power supply device is connected to a transmission rod, the transmission rod passes through an external steel casing and is connected to a high-strength alloy cutter disc, and a grouting pipe is provided inside the transmission rod, the grouting pipe is connected to the high-strength alloy cutter disc and the ground at the front and back, and a sliding steel plate is provided at the bottom of the high-speed rotor, and the movement of the sliding steel plate is controlled by a retractable excavation recovery cylinder.

[0020] Furthermore, a reinforcing triangular steel plate connected to the high-strength alloy cutter disc is provided at the end of the transmission rod.

[0021] The beneficial effects of the present invention are embodied in:

[0022] In the present invention, a high-speed drill is used to drive a cutter disc to grind the underground continuous wall instead of drilling and coring. Due to the characteristics of high-pressure mud for replacing crushed slag, it has the advantages of easy slag cleaning without mechanical jamming. The solution of retaining the protective layer of the underground continuous wall is adopted instead of drilling through the underground continuous wall. Since retaining the protective layer of the underground continuous wall can prevent soil and water loss on the inner side of the underground continuous wall, it has the advantage of good control of cracking and deformation of the existing station structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the obstacle removal method of the present invention;

[0024] Figure 2 It is a schematic diagram of the vertical angle steel limiting slideway structure of the present invention;

[0025] Figure 3 This is a schematic diagram of the rock crusher structure construction of the present invention;

[0026] Figure 4 For the present invention Figure 3 Another perspective structural diagram;

[0027] Figure 5 This is a schematic diagram of the grid drilling operation of the present invention;

[0028] Figure 6 It is a schematic diagram of the structure of the rock crusher of the present invention.

[0029] Description of reference numerals:

[0030] 1. High-speed transfer machine; 2. Power supply device; 3. Transmission rod; 4. High-strength alloy cutter head; 5. Sliding steel plate; 6. Retractable excavation recovery cylinder; 7. Grouting pipe; 8. Rectangular steel pipe; 9. Vertical angle steel limit slide; 10. Horizontal angle steel support bracket; 11. Reinforced triangular steel plate. DETAILED DESCRIPTION

[0031] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. In the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0032] See also Figure 1-5 The present invention provides a rapid underground continuous wall obstacle removal method, which specifically includes the following steps:

[0033] Clean the surface, level the ground, and harden the concrete construction ground;

[0034] Measure and lay out, mark the plane position of the rectangular steel pipe 8 on the ground; according to the size of the rectangular steel pipe 8 (rectangular steel pipe with an outer diameter of 4m), draw the position of the rectangular steel pipe 8 on the ground, and the opening side of the rectangular steel pipe 8 is parallel to the underground continuous wall that needs to be cleared. Considering the construction accuracy and process of the underground continuous wall, the distance between the rectangular steel pipe 8 and the wall is 15cm.

[0035] Use the extra-large rectangular steel pipe 8 sinking equipment for insertion. At the same time, use the crane combined with the soil-taking equipment to remove the soil inside the rectangular steel pipe 8 and inject mud. One is to assist the sinking, and the other is to reduce the pressure difference between the inside and outside of the steel pipe. Taking into account the production, processing, lifting and transportation of rectangular steel pipes, each section of the steel pipe is 4 meters long, and the sections are set up as internal and external socket structures and fixed with bolts. The wall thickness of the steel pipe is 4cm. A circular hole with a diameter of 1.3m is set in the middle of the first opening section as the working space for the obstacle clearance machinery. The depth of steel pipe insertion: the center position of the steel pipe opening - 50cm = the deepest position that needs to be cleaned at this position. The verticality of the steel pipe is controlled within a deviation of 2cm.

[0036] The horizontal high-speed rock crusher is hoisted in by a crane; the cutter head of the rock crusher has a diameter of 1.2 meters. Four vertical angle steel limit slides 9 are set in the steel pipe according to the size of the rectangular shell of the rock crusher, so that the machine can slide down smoothly; four horizontal angle steel support brackets 10 are set at the bottom to limit the height of the machine and support the rock crusher. The limit height of the angle steel is: the center position of the opening position - half of the height of the rectangular box.

[0037] Use a horizontal high-speed rock crusher to crush the rock; the crushing depth retains the inner protective layer of the underground continuous wall. The crushing depth is calculated based on the extension length of the cutter head, which is (steel pipe outer diameter 4m-steel pipe wall thickness-chute angle steel thickness+15cm interval between steel pipe and wall+underground continuous wall thickness-underground continuous wall protective layer thickness)-total length of the machine

[0038] Start the motor, the cutter disc rotates at a speed of 100r / min. At the same time, the jacking cylinder pushes forward (the maximum extension of the jacking cylinder must be greater than the calculated extension length required above). The axial force of the jacking cylinder is 10KN. The jacking speed is controlled to be no more than 1mm / min. At the same time, high-quality mud is pumped to the cutter disc to cool the cutter disc and replace the residue cut off.

[0039] The cutter disc is equipped with high-strength alloy cutter heads, and the cutter disc opening rate is 40%.

[0040] After the second layer of steel bars of the underground continuous wall is broken, the rock crushing is stopped when the inner protective layer of concrete remains, so as to retain the concrete protective layer and prevent internal soil and water loss. At this time, the jacking cylinder retracts and the rock crushing machine cutter disc retracts into the steel pipe.

[0041] 1) Adjust the height of the steel pipe and repeat the rock crushing; the pulling height is 1 meter.

[0042] 2) Pull out the steel pipe and move it to a horizontal position, repeat the rock crushing construction; lift out the machine, pull out the steel pipe, and backfill; move the ground horizontally forward 1 meter along the wall that needs to be cleared, and repeat steps 2-6.

[0043] After all obstacles are cleared, the machinery is hoisted out, the steel pipes are pulled out, cleaned, stacked neatly, and transported out of the site.

[0044] In one embodiment, see Figure 6 The rock crusher includes a high-speed rotary machine 1, which is provided with a power supply device 2. The power supply device 2 is connected to a transmission rod 3. The transmission rod 3 passes through an external steel casing and is connected to a high-strength alloy cutter disc 4. A grouting pipe 7 is provided inside the transmission rod 4. The grouting pipe 7 is connected to the high-strength alloy cutter disc 4 and the ground at the front and rear. A slidable steel plate 5 is provided at the bottom of the high-speed rotary machine 1. The slidable steel plate 5 is controlled to move by a retractable excavation recovery cylinder 6. Specifically, the power supply device 2 provides operating power for the high-strength alloy cutter disc 4, and at the same time, the retractable excavation recovery cylinder 6 is opened to provide excavation power for the high-speed rotary machine 1. Water is passed from the ground to the grouting pipe 7 to the high-strength alloy cutter disc 4, and the debris generated by the operation is replaced and discharged while the cutter disc is cooled and lubricated;

[0045] Longitudinal repeated operation: After completing one operation, the high-strength alloy cutter head 4 is recovered by the retractable excavation recovery cylinder 6, the whole device is moved up (the casing is pulled up), re-fixed and positioned, and the above operation steps are repeated;

[0046] Repeat the horizontal operation: After completing the above-mentioned longitudinal operation once, readjust the position of the external steel sleeve horizontally. After the external steel sleeve is installed, repeat the above-mentioned longitudinal operation steps until all operations are completed and ready to recover the obstacle removal machinery and steel sleeve.

[0047] In one embodiment, a reinforcing triangular steel plate 11 connected to the high-strength alloy cutter disc 4 is provided at the end of the transmission rod 4. This arrangement of the embodiment can improve the connection strength of the high-strength alloy cutter disc 4 and the stability during operation.

[0048] It should be noted that if the embodiments of the present invention involve directional indications such as up, down, left, right, front, back, etc., then the directional indications are only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture as shown in the accompanying drawings. If the specific posture changes, the directional indication will also change accordingly.

[0049] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or schemes that A and B meet at the same time. In addition, "multiple" refers to more than two. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist.

[0050] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A rapid underground continuous wall obstacle removal method, characterized in that: The specific steps include: Clean the surface, level the ground, and harden the concrete construction ground; Mark the plane position of the rectangular steel pipe (8) on the ground; Insert the rectangular steel pipe, and at the same time use a crane in combination with soil taking equipment to take out the soil inside the rectangular steel pipe (8), and inject mud; Use a crane to hoist in a horizontal high-speed rock crusher and crush the rock; Adjust the height of the rectangular steel pipe (8) and repeat the rock crushing; Pull out the rectangular steel pipe (8), move the steel pipe to a horizontal position, and repeat the rock crushing operation; Lift out the machine, pull out the steel pipe, and backfill; move forward 1 meter horizontally along the wall that needs to be cleared, repeat the above steps, and after all obstacles are cleared, lift out the machine and pull out the rectangular steel pipe (8).

2. A rapid underground continuous wall obstacle removal method as claimed in claim 1, characterized in that: During the process of hoisting the rock crusher, four vertical angle steel limit slide grooves (9) are arranged on the rectangular steel pipe (8), and four horizontal angle steel support brackets (10) are arranged at the bottom to limit the height and support the rock crusher.

3. A rapid underground continuous wall obstacle removal method as claimed in claim 1, characterized in that: During the rock crushing process, the rock crushing depth retains the inner protective layer of the underground continuous wall, and mud is pumped to the cutter head of the rock crusher to cool the cutter head and replace the cut residues through the mud. When the second layer of steel bars of the underground continuous wall is broken and the inner protective layer of concrete remains, the rock crushing is stopped, the concrete protective layer is retained, and the rock crusher cutter head is retracted into the rectangular steel pipe (8).

4. A rapid underground continuous wall obstacle removal method as claimed in claim 2, characterized in that: The limiting height of the angle steel is the center position of the opening position or half of the height of the rectangular box.

5. A rapid underground continuous wall obstacle removal method as claimed in claim 1, characterized in that: The insertion depth of the rectangular steel pipe (8) is the center position of the steel pipe opening - 50 cm, that is, the deepest position that needs to be cleaned, and the verticality of the rectangular steel pipe (8) is controlled within a deviation range of 2 cm.

6. A rapid underground continuous wall obstacle removal method as claimed in claim 3, characterized in that: The rock crushing depth is determined according to the extension length of the cutter disc, that is, the extension length = (outer diameter of the steel pipe - steel pipe wall thickness - thickness of the chute angle steel + interval between the steel pipe and the wall + thickness of the underground continuous wall - thickness of the underground continuous wall protective layer) - length of the rock crusher.

7. A rapid underground continuous wall obstacle removal method as claimed in claim 1, characterized in that: One side of the opening of the rectangular steel pipe (8) is parallel to the underground continuous wall that needs to be cleared, and the rectangular steel pipe (8) is spaced 15 cm from the wall.

8. A rapid underground continuous wall obstacle removal method as claimed in claim 1, characterized in that: The rock crusher comprises a high-speed rotary machine (1) in which a power supply device (2) is arranged. The power supply device (2) is connected to a transmission rod (3). The transmission rod (3) passes through an external steel casing and is connected to a high-strength alloy cutter disc (4). A grouting pipe (7) is arranged inside the transmission rod (4). The grouting pipe (7) is connected to the high-strength alloy cutter disc (4) and the ground at the front and rear. A slidable steel plate (5) is arranged at the bottom of the high-speed rotary machine (1). The slidable steel plate (5) is controlled to move by a retractable excavation recovery cylinder (6).

9. A rapid underground continuous wall obstacle removal method as claimed in claim 8, characterized in that: The end of the transmission rod (4) is provided with a reinforcing triangular steel plate (11) connected to the high-strength alloy cutter disc (4).

Citation Information

Patent Citations

  • Deeply buried sewage pipe barrier clearance structure and method suitable for underground continuous wall construction

    CN110004916A

  • Reverse jacking-pipe obstacle-clearing construction method

    CN111706347A

  • Construction method for removing underground shield segments through full-slewing drilling machine

    CN112324441A

  • Horizontal long-distance obstacle removing device and omnibearing high-pressure jet grouting method

    CN115306300A

  • Construction method for removing obstacles by combining vertical pipe sinking and horizontal drilling of super-large-diameter steel sleeve

    CN115653495A

Cited By

  • Section steel removing device of underground diaphragm wall and implementation method

    CN120776925A