Method, device and equipment for determining grouting position of deep foundation pit in karst area and medium

By monitoring the water level around the deep foundation pit in the karst area and drawing three-dimensional models to determine the grouting reinforcement position, the waste problem of determining the grouting position of the deep foundation pit in the karst area is solved, and precise grouting and cost savings are achieved.

CN118911146APending Publication Date: 2024-11-08CHINA RAILWAY 20TH BUREAU GRP SOUTHERN ENG CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411072385.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the construction of deep foundation pits in karst areas, the conventional grouting bottom sealing measures have caused a large amount of waste of air pipes due to the deep karst location, and the cost reaches one-third of the grouting measures, causing unnecessary economic losses.

Method used

By arranging water level monitoring locations around deep foundation pits, obtaining water head parameters, drawing a three-dimensional water head distribution model, combining real-time water head monitoring data to amp regulating, eliminating geological errors, and establishing a BIM three-dimensional excavation safety surface distribution model to determine the specific grouting and reinforcement operations. Location.

Benefits of technology

The precise location determination of the grouting construction of deep foundation pits in karst areas is achieved, which avoids slurry waste, saves costs, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911146A_ABST
    Figure CN118911146A_ABST
Patent Text Reader

Abstract

The invention discloses a karst area deep foundation pit grouting position determining method and device, equipment and a medium, and relates to the technical field of foundation pit construction, a plurality of water level monitoring positions are arranged on the periphery of a karst area corresponding to a deep foundation pit, water head parameters of the water level monitoring positions are obtained, and then according to the water head parameters and preset data, the grouting position of the deep foundation pit is determined. And drawing a three-dimensional distribution model of all water heads in the karst area, modulating the amplitude of the corresponding water head in the three-dimensional distribution model in combination with the obtained real-time water head monitoring data of each water head so as to eliminate geological errors, and determining the excavation safety surface depth of the deep foundation pit according to the obtained excavation safety surface depth of the deep foundation pit. The current excavation face of the deep foundation pit is excavated to the target position, a BIM three-dimensional excavation safety face distribution model of the deep foundation pit is established, and the position where grouting reinforcement operation needs to be conducted is determined according to the size relation between the current distance between the current position and the corresponding water surface of the dissolving cavity and the preset distance between the dissolving cavity and a bottom plate of the deep foundation pit. And the grouting device has the advantage of accurate grouting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of foundation pit construction, and in particular to a method, device, equipment and medium for determining a grouting position for a deep foundation pit in a karst area. Background Art

[0002] Grouting technology is an important means of treating adverse geological conditions in karst areas. Especially before excavation of deep foundation pits in karst areas, grouting technology is often used to treat the karst revealed by geological drilling or other geophysical exploration methods, which is crucial to ensuring the safety of foundation pit excavation.

[0003] For foundation pit excavation and grouting in karst areas, the conventional operation is to take measures of grouting to seal the bottom of the foundation pit. Karst is often located in a deeper position of the foundation pit, and the bottom sealing treatment is usually started from the ground. There will be a large number of empty pipes, and the cost can even reach one-third of the grouting measures, causing unnecessary waste. Summary of the invention

[0004] The main purpose of the present application is to provide a method, device, equipment, system and medium for determining the grouting position of a deep foundation pit in a karst area, aiming to solve the technical problem of taking grouting bottom sealing measures for the foundation pit in the related technology. Karst is often located in a deeper position of the foundation pit, and the bottom sealing treatment is generally started from the ground. There will be a large number of empty pipes, and the cost can even reach one-third of the grouting measures, causing unnecessary waste.

[0005] To achieve the above objectives, in a first aspect, the present application proposes a method for determining a grouting position for a deep foundation pit in a karst area, comprising the following steps:

[0006] Arrange a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and obtain the hydraulic head parameters of each of the water level monitoring positions;

[0007] Drawing a three-dimensional distribution model of all the water heads in the karst area according to the water head parameters and preset geological data;

[0008] Combining the acquired real-time water head monitoring data of each water head, performing amplitude modulation on the corresponding water head in the three-dimensional distribution model to eliminate geological errors;

[0009] According to the obtained excavation safety surface depth of the deep foundation pit, the current excavation surface of the deep foundation pit is excavated to the target position, and a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit is established; wherein the current distance between the target position and the water surface of the karst cavity in the karst area is calculated using Formula 1, which is:

[0010]

[0011] Z his the current distance between the target location and the water surface of the karst cavity in the karst area,

[0012] T h is the water head after amplitude modulation,

[0013] t is the safety factor,

[0014] γ w is the weight of water,

[0015] γ is the density of the soil layer;

[0016] The position where grouting reinforcement work needs to be performed is determined based on the size relationship between the current distance from the current position to the corresponding water surface of the dissolution cavity and the preset distance between the dissolution cavity and the bottom plate of the deep foundation pit.

[0017] In one embodiment, the step of arranging a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit and obtaining the hydraulic head parameters of each of the water level monitoring positions includes:

[0018] A plurality of holes distributed at intervals are arranged around the karst area corresponding to the deep foundation pit;

[0019] Installing water pressure monitoring gauges in all the holes in sequence to form a plurality of water level monitoring positions;

[0020] The initial water head data corresponding to each of the water level monitoring positions are recorded in sequence by all the water pressure monitoring gauges; wherein the initial water head data include the initial water head of the ST1 water level observation hole, the initial water head of the ST2 water level observation hole, and the initial water head of the ST3 water level observation hole;

[0021] The permeability coefficient of each water level monitoring position is obtained according to the initial water head data to obtain the water head parameter of each water level monitoring position; wherein the permeability coefficient is expressed by Formula 2, which is:

[0022] and

[0023] k1 is the permeability coefficient of the first layer of soil,

[0024] k2 is the permeability coefficient of the second layer of soil,

[0025] k3 is the permeability coefficient of the third layer of soil,

[0026] H1 is the depth of the first water level observation hole,

[0027] H2 is the depth of the second water level observation hole,

[0028] H3 is the depth of the third water level observation hole.

[0029] H0 is the depth of groundwater level.

[0030] In one embodiment, the step of obtaining the permeability coefficient of each water level monitoring position according to the initial water head data to obtain the water head parameter of each water level monitoring position includes:

[0031] Acquire the permeability coefficient of each water level monitoring position according to the initial water head data;

[0032] According to the locations of the caves in the karst area and the corresponding stratum thickness data revealed by the boreholes, the head size of each water head is obtained to obtain the head parameters of each water level monitoring position; wherein the head size is expressed by Formula 3, which is:

[0033]

[0034] h is the adjusted water head,

[0035] H is the initial water head,

[0036] H0 is the depth of groundwater level,

[0037] The head reduced by infiltration is

[0038] l i is the thickness of a certain soil layer,

[0039] k i is the permeability coefficient of a certain type of soil layer.

[0040] In one embodiment, before the step of sequentially recording the initial water head data corresponding to each of the water level monitoring positions by all of the water pressure monitoring gauges, the method further includes:

[0041] The corresponding holes are vented through the vent holes provided on the water pressure monitoring gauge.

[0042] In one embodiment, the step of combining the acquired real-time water head monitoring data of each water head and performing amplitude modulation on the corresponding water head in the three-dimensional distribution model to eliminate geological errors includes:

[0043] Combined with the real-time head monitoring data of each of the water heads, the corresponding water heads are modulated by head difference calculation in the three-dimensional distribution model to eliminate geological errors, wherein the head difference is expressed by Formula 4, which is:

[0044] f(x i )=m×l i +n×z i ,

[0045] f(x i ) is the water head difference between the water head calculated according to the theoretical formula and the water head of the water level observation hole, m is the distance l between the calculated borehole and the water level observation hole i The parameter calculated by the variable, n is the thickness of the permeable layer in the borehole z i The parameter calculated from the variable, l i is the distance from the water level observation hole, z i is the thickness of the borehole permeable layer, and the calculation formula of m and n is expressed by Formula 5, which is:

[0046] In one embodiment, the step of determining the position where grouting reinforcement operation is required based on the BIM three-dimensional excavation safety surface distribution model and the size relationship between the current distance between the current position and the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit comprises:

[0047] In combination with the BIM three-dimensional excavation safety surface distribution model and according to the size relationship between the current distance from the current position to the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit, it is determined whether grouting reinforcement work is required;

[0048] When each current distance is smaller than the corresponding preset distance, the corresponding current position is determined to be a position where grouting reinforcement operation is required.

[0049] In addition, to achieve the above-mentioned purpose, in a second aspect, the present application also proposes a device for determining a grouting position of a deep foundation pit in a karst area, the device comprising:

[0050] An acquisition module is used to arrange a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and to acquire the hydraulic head parameters of each of the water level monitoring positions;

[0051] A first modeling module is used to draw a three-dimensional distribution model of all the water heads in the karst area according to each of the water head parameters and preset geological data;

[0052] An error processing module, used to combine the acquired real-time water head monitoring data of each water head and modulate the corresponding water head in the three-dimensional distribution model to eliminate geological errors;

[0053] The second modeling module is used to excavate the current excavation surface of the deep foundation pit to a target position according to the acquired excavation safety surface depth of the deep foundation pit, and establish a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit;

[0054] The output module is used to determine the position where grouting reinforcement operation is required in combination with the BIM three-dimensional excavation safety surface distribution model and based on the size relationship between the current distance between the current position and the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit.

[0055] In addition, to achieve the above-mentioned purpose, in the third aspect, the present application also proposes a device for determining the grouting position of a deep foundation pit in a karst area, the device comprising: a memory, a processor, and a computer program stored on the memory and executable on the processor, the computer program being configured to implement the steps of the method for determining the grouting position of a deep foundation pit in a karst area described in the first aspect.

[0056] In addition, to achieve the above objectives, in a fourth aspect, the present application also proposes a grouting system, comprising:

[0057] The grouting position determination device for deep foundation pit in karst area according to the third aspect; and

[0058] The grouting equipment is communicatively connected with the grouting position determining device for the deep foundation pit in the karst area.

[0059] In addition, to achieve the above-mentioned purpose, in the fifth aspect, the present application also proposes a storage medium, wherein the storage medium is a computer-readable storage medium, and a computer program is stored on the storage medium. When the computer program is executed by the processor, the steps of the method for determining the grouting position of a deep foundation pit in a karst area described in the first aspect are implemented.

[0060] One or more technical solutions proposed in this application have at least the following technical effects:

[0061] The present application discloses a method for determining the grouting position of a deep foundation pit in a karst area. A plurality of water level monitoring positions are arranged around the karst area corresponding to the deep foundation pit, and the water head parameters of each water level monitoring position are obtained. Then, a three-dimensional distribution model of all water heads in the karst area is drawn according to each water head parameter and preset data. Next, the corresponding water heads are modulated in the three-dimensional distribution model in combination with the real-time water head monitoring data of each water head obtained to eliminate geological errors. Then, according to the obtained excavation safety surface depth of the deep foundation pit, the current excavation surface of the deep foundation pit is excavated to the target position. The BIM three-dimensional excavation safety surface distribution model of the deep foundation pit is established, and finally the position where grouting reinforcement operation needs to be carried out is determined according to the relationship between the current distance between the current position and the corresponding solution cavity water surface and the preset distance between the solution cavity and the bottom plate of the deep foundation pit. When used, the present application can accurately determine the specific position where grouting operation needs to be carried out when grouting construction is carried out on the deep foundation pit in the karst area, avoiding the defect of slurry waste caused by grouting at any position during grouting operation in the prior art, and has the advantages of precise grouting, saving grouting slurry and reducing construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0062] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.

[0063] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0064] Figure 1 A flow chart provided for the first embodiment of the method for determining the grouting position of a deep foundation pit in a karst area of ​​the present application;

[0065] Figure 2 for Figure 1 A flow chart of step S100 in the example;

[0066] Figure 3 for Figure 2 Schematic diagram of the process of step S140 in the example;

[0067] Figure 4 A flow chart provided for the second embodiment of the method for determining the grouting position of a deep foundation pit in a karst area of ​​the present application;

[0068] Figure 5 This is a schematic diagram of the module structure of a device for determining a grouting position for a deep foundation pit in a karst area according to an embodiment of the present application;

[0069] Figure 6 It is a schematic diagram of the equipment structure of the hardware operating environment involved in the method for determining the grouting position of a deep foundation pit in a karst area in an embodiment of the present application.

[0070] The purpose, features and advantages of this application will be further described in conjunction with the embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0071] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0072] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture. If the specific posture changes, the directional indication will also change accordingly.

[0073] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features limited to "first" and "second" may explicitly or implicitly include at least one of the features. In addition, if "and / or" or "and / or" appears in the full text, its meaning includes three parallel solutions. Taking "A and / or B" as an example, it includes solution A, solution B, or solutions that satisfy both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0074] The invention provides a method for determining the grouting position of a deep foundation pit in a karst area.

[0075] It should be noted that the execution subject of this embodiment can be a computing service device with data processing, network communication and program running functions, such as a tablet computer, a personal computer, a mobile phone, etc., or an electronic device, a control device, etc. that can realize the above functions. The following takes the control device as an example to illustrate this embodiment and the following embodiments.

[0076] See also Figures 1 to 6 In one embodiment of the present invention, a method for determining a grouting position of a deep foundation pit in a karst area comprises the following steps:

[0077] S100, arranging a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and obtaining a hydraulic head parameter at each of the water level monitoring positions;

[0078] It should be noted that the water head in this embodiment refers to the mechanical energy of a unit weight of liquid, including position head, pressure head, and flow rate head. The sum of the three is the total head, and the sum of the position head and the pressure head is the pressure gauge head. The water head in this patent refers to the position head.

[0079] In this embodiment, during specific implementation, step S100 should include:

[0080] S110, setting a plurality of holes distributed at intervals around the karst area corresponding to the deep foundation pit;

[0081] S120, sequentially installing water pressure monitoring gauges in all the holes to form a plurality of water level monitoring positions;

[0082] S130, recording the initial water head data corresponding to each of the water level monitoring positions in sequence through all the water pressure monitoring gauges; wherein the initial water head data includes ST1, ST2, and ST3;

[0083] It should be noted that the water pressure monitoring meter in this embodiment can be, but is not limited to, directly using the existing technology. This embodiment does not improve the design, so it will not be described here one by one. The location of the hole is selected at the boundary of the stratum, that is, the interface of different types of soil layers. The holes should be evenly arranged along the periphery of the foundation pit, and the spacing should be set at 30 to 50 meters according to the complexity of the stratum.

[0084] S140, obtaining the permeability coefficient of each of the water level monitoring positions according to the initial water head data to obtain the water head parameters of each of the water level monitoring positions; wherein the permeability coefficient is expressed using Formula 2, which is:

[0085] and

[0086] k1 is the permeability coefficient of the first layer of soil,

[0087] k2 is the permeability coefficient of the second layer of soil,

[0088] k3 is the permeability coefficient of the third layer of soil,

[0089] H1 is the depth of the first water level observation hole,

[0090] H2 is the depth of the second water level observation hole,

[0091] H3 is the depth of the third water level observation hole.

[0092] H0 is the depth of groundwater level.

[0093] In one embodiment, step S140 includes:

[0094] S141, obtaining the permeability coefficient of each water level monitoring position according to the initial water head data;

[0095] S142, and according to the location of each cave in the karst area and the corresponding stratum thickness data revealed by each borehole, obtain the head size of each water head to obtain the head parameter of each water level monitoring position; wherein the head size is expressed by Formula 3, and Formula 3 is:

[0096]

[0097] h is the adjusted water head,

[0098] H is the initial water head,

[0099] H0 is the depth of groundwater level,

[0100] The head reduced by infiltration is

[0101] l i is the thickness of a certain type of soil layer,

[0102] k i is the permeability coefficient of a certain type of soil layer.

[0103] S200, drawing a three-dimensional distribution model of all the water heads in the karst area according to the water head parameters and preset geological data;

[0104] In this embodiment, when drawing the three-dimensional distribution model, the three-dimensional distribution model is established directly using the BIM modeling software of the Autodesk series, or the three-dimensional distribution model is established using the three-dimensional modeling software of the Bentley series, or the three-dimensional distribution model is established using MADIS. In this embodiment, the modeling process is not described in detail, but it can be clearly stated that the three-dimensional distribution model established in this embodiment should include data such as the stratum thickness, stratum trend, stratum distribution, stratum data, hydraulic head position, hydraulic head distribution, etc. of the karst area.

[0105] S300, combining the acquired real-time water head monitoring data of each water head, and performing amplitude modulation on the corresponding water head in the three-dimensional distribution model to eliminate geological errors;

[0106] In this embodiment, step S300 includes:

[0107] S310, combining the real-time hydraulic head monitoring data of each hydraulic head, performing hydraulic head difference calculation and amplitude modulation on the corresponding hydraulic head in the three-dimensional distribution model to eliminate geological errors, wherein the hydraulic head difference is expressed by Formula 4, which is:

[0108] f(x i )=m×l i +n×z i ,

[0109] f(x i ) is the water head difference between the water head calculated according to the theoretical formula and the water head of the water level observation hole, m is the distance l between the calculated borehole and the water level observation hole i The parameter calculated by the variable, n is the thickness of the permeable layer in the borehole z i The parameter calculated from the variable, li is the distance from the water level observation hole, z i is the thickness of the borehole permeable layer, and the calculation formula of m and n is expressed by Formula 5, which is: i is the number of exploration holes.

[0110] S400, excavating the current excavation surface of the deep foundation pit to a target position according to the obtained excavation safety surface depth of the deep foundation pit, and establishing a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit; wherein the current distance between the target position and the water surface of the karst cavity in the karst area is calculated using Formula 1, and Formula 1 is:

[0111]

[0112] Z h is the current distance between the target location and the water surface of the karst cavity in the karst area,

[0113] T h is the water head after amplitude modulation,

[0114] t is the safety factor,

[0115] γ w is the weight of water,

[0116] γ is the density of the soil layer;

[0117] S500. Determine the position where grouting reinforcement operation is required based on the BIM three-dimensional excavation safety surface distribution model and the relationship between the current distance from the current position to the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit.

[0118] In this embodiment, step S500 includes:

[0119] S510, judging whether grouting reinforcement operation is required based on the BIM three-dimensional excavation safety surface distribution model and the size relationship between the current distance from the current position to the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit;

[0120] S520: When each current distance is smaller than the corresponding preset distance, the corresponding current position is determined to be a position where grouting reinforcement operation is required.

[0121] Of course, when each current distance is greater than or equal to the corresponding preset distance, the corresponding current position does not need to perform grouting reinforcement work.

[0122] In this embodiment, by arranging several water level monitoring positions around the karst area corresponding to the deep foundation pit, and obtaining the head parameters of each water level monitoring position, then drawing a three-dimensional distribution model of all water heads in the karst area according to each water head parameter and preset data, and then combining the real-time head monitoring data of each water head obtained, the corresponding water head is modulated in the three-dimensional distribution model to eliminate geological errors, and then according to the obtained excavation safety surface depth of the deep foundation pit, the current excavation surface of the deep foundation pit is excavated to the target position, and a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit is established, and finally, according to the current distance between the current position and the corresponding karst cavity water surface and the preset distance between the karst cavity and the bottom plate of the deep foundation pit, the position where grouting reinforcement operation needs to be performed is determined, so that the present application can accurately determine the specific position where grouting operation needs to be performed when grouting construction is performed on the deep foundation pit in the karst area, avoiding the defect of slurry waste caused by grouting at any position during grouting operation in the prior art, and having the advantages of precise grouting, saving grouting slurry, and reducing construction costs.

[0123] In one embodiment, before step S130, the method further includes:

[0124] S150, exhausting the corresponding holes through the exhaust holes provided on the water pressure monitoring gauge.

[0125] In this embodiment, by utilizing the exhaust holes provided on the water pressure monitoring gauge to vent the corresponding holes, the present invention can utilize the exhaust holes provided in the water pressure monitoring gauge when in use to avoid changes in water level monitoring results caused by changes in air pressure during the grouting process.

[0126] Of course, in some exemplary embodiments, after step S500, the following should be included: S600, according to the deep foundation pit BIM three-dimensional excavation safety surface distribution map, reasonably divide the construction sequence, according to the real-time water level of the water level observation device, and redraw the deep foundation pit BIM three-dimensional excavation safety surface distribution map in accordance with the requirements of steps S100-S400 to obtain a dynamic distribution map. The dynamic excavation of the foundation pit and the dynamic adjustment of grouting are realized, and the grouting position is simulated in real time to solve the problem that the grouting position of the deep foundation pit in the karst area cannot be accurately determined in the prior art.

[0127] In addition, to achieve the above-mentioned purpose, in a second aspect, the present application also proposes a device for determining a grouting position of a deep foundation pit in a karst area, the device comprising:

[0128] An acquisition module 10 is used to arrange a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and to acquire a hydraulic head parameter at each of the water level monitoring positions;

[0129] A first modeling module 20 is used to draw a three-dimensional distribution model of all the water heads in the karst area according to each of the water head parameters and preset geological data;

[0130] An error processing module 30 is used to combine the acquired real-time water head monitoring data of each water head and modulate the corresponding water head in the three-dimensional distribution model to eliminate geological errors;

[0131] The second modeling module 40 is used to excavate the current excavation surface of the deep foundation pit to a target position according to the obtained excavation safety surface depth of the deep foundation pit, and establish a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit;

[0132] The output module 50 is used to determine the position where grouting reinforcement operation needs to be performed in combination with the BIM three-dimensional excavation safety surface distribution model and based on the relationship between the current distance between the current position and the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit.

[0133] The device for determining the grouting position of a deep foundation pit in a karst area provided by the present application adopts the method for determining the grouting position of a deep foundation pit in a karst area in the above-mentioned embodiment, which can solve the technical problem of taking grouting bottom sealing measures for the foundation pit in the related technology. Karst is often located at a deeper position of the foundation pit, and the bottom sealing treatment of the base is generally started from the ground, which will result in a large number of empty pipes, and the cost can even reach one-third of the grouting measures, causing unnecessary waste. Compared with the prior art, the beneficial effects of the device for determining the grouting position of a deep foundation pit in a karst area provided by the present application are the same as the beneficial effects of the method for determining the grouting position of a deep foundation pit in a karst area provided by the above-mentioned embodiment, and the other technical features of the device for determining the grouting position of a deep foundation pit in a karst area are the same as the features disclosed in the above-mentioned embodiment method, which will not be repeated here.

[0134] In addition, to achieve the above-mentioned purpose, in the third aspect, the present application also proposes a device for determining the grouting position of a deep foundation pit in a karst area, the device comprising: a memory, a processor, and a computer program stored on the memory and executable on the processor, the computer program being configured to implement the steps of the method for determining the grouting position of a deep foundation pit in a karst area described in the first aspect.

[0135] Reference below Figure 6, which shows a schematic diagram of the structure of a device for determining the grouting position of a deep foundation pit in a karst area suitable for implementing the embodiment of the present application. The device for determining the grouting position of a deep foundation pit in a karst area in the embodiment of the present application may include but is not limited to mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (Personal Digital Assistants), PADs (Portable Application Descriptions), PMPs (Portable Media Players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), etc., and fixed terminals such as digital TVs, desktop computers, etc. Figure 6 The device for determining the grouting position of a deep foundation pit in a karst area shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0136] like Figure 6 As shown, the karst area deep foundation pit grouting position determination device may include a processing device 1001 (such as a central processing unit, a graphics processor, etc.), which can perform various appropriate actions and processes according to the program stored in a read-only memory (ROM: Read Only Memory) 1002 or the program loaded from a storage device 1003 to a random access memory (RAM: Random Access Memory) 1004. In RAM1004, various programs and data required for the operation of the karst area deep foundation pit grouting position determination device are also stored. The processing device 1001, ROM1002 and RAM1004 are connected to each other through a bus 1005. An input / output (I / O) interface 1006 is also connected to the bus. Typically, the following systems can be connected to the I / O interface 1006: input devices 1007 including, for example, a touch screen, a touchpad, a keyboard, a mouse, an image sensor, a microphone, an accelerometer, a gyroscope, etc.; output devices 1008 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; storage devices 1003 including, for example, a magnetic tape, a hard disk, etc.; and communication devices 1009. The communication device 1009 can allow the karst area deep foundation pit grouting position determination device to communicate wirelessly or wired with other devices to exchange data. Although the figure shows a karst area deep foundation pit grouting position determination device with various systems, it should be understood that it is not required to implement or have all the systems shown. More or fewer systems can be implemented or have alternatively.

[0137] In particular, according to the embodiments disclosed in the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, the embodiments disclosed in the present application include a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication device, or installed from a storage device 1003, or installed from a ROM 1002. When the computer program is executed by the processing device 1001, the above-mentioned functions defined in the method of the embodiment disclosed in the present application are executed.

[0138] The grouting position determination device for deep foundation pits in karst areas provided by the present application adopts the grouting position determination method for deep foundation pits in karst areas in the above-mentioned embodiments, which can solve the problem of taking grouting bottom sealing measures for foundation pits in related technologies. Karst is often located at a deeper position in the foundation pit, and the bottom sealing treatment of the base is generally started from the ground. There will be a large number of empty pipes, and the cost can even reach one-third of the grouting measures, causing unnecessary waste of technical problems. Compared with the prior art, the beneficial effects of the grouting position determination device for deep foundation pits in karst areas provided by the present application are the same as the beneficial effects of the grouting position determination method for deep foundation pits in karst areas provided by the above-mentioned embodiments, and the other technical features of the grouting position determination device for deep foundation pits in karst areas are the same as the features disclosed in the method of the previous embodiment, which will not be repeated here.

[0139] It should be understood that the various parts disclosed in this application can be implemented by hardware, software, firmware or a combination thereof. In the description of the above embodiments, specific features, structures, materials or characteristics can be combined in any one or more embodiments or examples in a suitable manner.

[0140] In addition, to achieve the above objectives, in a fourth aspect, the present application also proposes a grouting system, comprising:

[0141] The grouting position determination device for deep foundation pit in karst area according to the third aspect; and

[0142] The grouting equipment is communicatively connected with the grouting position determining device for the deep foundation pit in the karst area.

[0143] The grouting system provided by the present application adopts the method for determining the grouting position of a deep foundation pit in a karst area in the above-mentioned embodiment, which can solve the problem of taking grouting bottom sealing measures for the foundation pit in the related technology. Karst is often located at a deeper position in the foundation pit, and the bottom sealing treatment of the base is generally started from the ground, which will result in a large number of empty pipes, and the cost can even reach one-third of the grouting measures, causing unnecessary waste of technical problems. Compared with the prior art, the beneficial effects of the grouting system provided by the present application are the same as the beneficial effects of the method for determining the grouting position of a deep foundation pit in a karst area provided by the above-mentioned embodiment, and the other technical features of the grouting system are the same as the features disclosed in the above-mentioned embodiment method, which will not be repeated here.

[0144] In addition, to achieve the above-mentioned purpose, in the fifth aspect, the present application also proposes a storage medium, wherein the storage medium is a computer-readable storage medium, and a computer program is stored on the storage medium. When the computer program is executed by the processor, the steps of the method for determining the grouting position of a deep foundation pit in a karst area described in the first aspect are implemented.

[0145] The computer-readable storage medium provided in the present application may be, for example, a USB flash drive, but is not limited to electrical, magnetic, optical, electromagnetic, infrared, or semiconductor systems, systems or devices, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In this embodiment, the computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, system or device. The program code contained on the computer-readable storage medium may be transmitted using any appropriate medium, including but not limited to: wires, optical cables, RF (Radio Frequency), etc., or any suitable combination of the above.

[0146] The computer-readable storage medium may be included in the device for determining the grouting position of a deep foundation pit in a karst area; or may exist independently without being assembled into the device for determining the grouting position of a deep foundation pit in a karst area.

[0147] The above-mentioned computer-readable storage medium carries one or more programs. When the above-mentioned one or more programs are executed by the device for determining the grouting position of a deep foundation pit in a karst area, the device for determining the grouting position of a deep foundation pit in a karst area can implement the method for determining the grouting position of a deep foundation pit in a karst area exemplified in the previous embodiment.

[0148] Computer program code for performing the operations of the present application may be written in one or more programming languages ​​or a combination thereof, including object-oriented programming languages ​​such as Java, Smalltalk, C++, and conventional procedural programming languages ​​such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., via the Internet using an Internet service provider).

[0149] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present application. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0150] The modules involved in the embodiments described in this application may be implemented by software or hardware, wherein the name of the module does not constitute a limitation on the unit itself in some cases.

[0151] The readable storage medium provided by the present application is a computer-readable storage medium, which stores computer-readable program instructions (i.e., computer programs) for executing the above-mentioned method for determining the grouting position of a deep foundation pit in a karst area, and can solve the problem of taking grouting bottom sealing measures for the foundation pit in the related art. Karst is often located in a deeper position of the foundation pit, and the bottom sealing treatment of the base is generally started from the ground, and there will be a large number of empty pipes. The cost can even reach one-third of the grouting measures, causing unnecessary waste. Technical problems. Compared with the prior art, the beneficial effects of the computer-readable storage medium provided by the present application are the same as the beneficial effects of the method for determining the grouting position of a deep foundation pit in a karst area provided by the above-mentioned embodiment, and will not be repeated here.

[0152] The above descriptions are only some embodiments of the present application, and are not intended to limit the patent scope of the present application. All equivalent structural changes made using the contents of the present application specification and drawings under the technical concept of the present application, or direct / indirect applications in other related technical fields are included in the patent protection scope of the present application.

Claims

1. A method for determining the grouting position of a deep foundation pit in a karst area, characterized in that: The steps include: Arrange a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and obtain the hydraulic head parameters of each of the water level monitoring positions; Drawing a three-dimensional distribution model of all the water heads in the karst area according to the water head parameters and preset geological data; Combining the acquired real-time water head monitoring data of each water head, performing amplitude modulation on the corresponding water head in the three-dimensional distribution model to eliminate geological errors; According to the obtained excavation safety surface depth of the deep foundation pit, the current excavation surface of the deep foundation pit is excavated to the target position, and a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit is established; wherein the current distance between the target position and the water surface of the karst cavity in the karst area is calculated using Formula 1, which is: Z h is the current distance between the target location and the water surface of the karst cavity in the karst area, T h is the water head after amplitude modulation, t is the safety factor, γ w is the weight of water, γ is the density of the soil layer; In combination with the BIM three-dimensional excavation safety surface distribution model and based on the relationship between the current distance between the current position and the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit, the position where grouting reinforcement work needs to be carried out is determined.

2. The method for determining the grouting position of a deep foundation pit in a karst area according to claim 1, characterized in that: The step of arranging a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit and obtaining the water head parameters of each of the water level monitoring positions comprises: A plurality of holes distributed at intervals are arranged around the karst area corresponding to the deep foundation pit; Installing water pressure monitoring gauges in all the holes in sequence to form a plurality of water level monitoring positions; The initial water head data corresponding to each of the water level monitoring positions are recorded in sequence by all the water pressure monitoring gauges; wherein the initial water head data include the initial water head of the ST1 water level observation hole, the initial water head of the ST2 water level observation hole, and the initial water head of the ST3 water level observation hole; The permeability coefficient of each water level monitoring position is obtained according to the initial water head data to obtain the water head parameter of each water level monitoring position; wherein the permeability coefficient is expressed by Formula 2, which is: and K1 is the permeability coefficient of the first layer of soil, k2 is the permeability coefficient of the second layer of soil, k3 is the permeability coefficient of the third layer of soil, H1 is the depth of the first water level observation hole, H2 is the depth of the second water level observation hole, H3 is the depth of the third water level observation hole. H0 is the depth of groundwater level.

3. The method for determining the grouting position of a deep foundation pit in a karst area according to claim 2, characterized in that: The step of obtaining the permeability coefficient of each water level monitoring position according to the initial water head data to obtain the water head parameter of each water level monitoring position comprises: Acquire the permeability coefficient of each water level monitoring position according to the initial water head data; According to the locations of the caves in the karst area and the corresponding stratum thickness data revealed by the boreholes, the head size of each water head is obtained to obtain the head parameters of each water level monitoring position; wherein the head size is expressed by Formula 3, which is: h is the adjusted water head, H is the initial water head, H0 is the depth of groundwater level, The head reduced by infiltration is l i is the thickness of a certain soil layer, k i is the permeability coefficient of a certain type of soil layer.

4. The method for determining the grouting position of a deep foundation pit in a karst area according to claim 2, characterized in that: Before the step of recording the initial water head data corresponding to each of the water level monitoring positions in sequence by all the water pressure monitoring gauges, the method further includes: The corresponding holes are vented through the vent holes provided on the water pressure monitoring gauge.

5. The method for determining the grouting position of a deep foundation pit in a karst area according to any one of claims 1 to 4, characterized in that: The step of combining the real-time water head monitoring data of each water head obtained and performing amplitude modulation on the corresponding water head in the three-dimensional distribution model to eliminate geological errors includes: Combined with the real-time head monitoring data of each of the water heads, the corresponding water heads are modulated by head difference calculation in the three-dimensional distribution model to eliminate geological errors, wherein the head difference is expressed by Formula 4, which is: f(x i )=m×l i +n×z i , f(x i ) is the water head difference between the water head calculated according to the theoretical formula and the water head of the water level observation hole, m is the distance l between the calculated borehole and the water level observation hole i The parameter calculated by the variable, n is the thickness of the permeable layer in the borehole z i The parameter calculated from the variable, l i is the distance from the water level observation hole, z i is the thickness of the borehole permeable layer, and the calculation formula of m and n is expressed by Formula 5, which is:

6. The method for determining the grouting position of a deep foundation pit in a karst area according to any one of claims 1 to 4, characterized in that: The step of determining the position where grouting reinforcement operation is required in combination with the BIM three-dimensional excavation safety surface distribution model and according to the size relationship between the current distance from the current position to the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit, comprises: In combination with the BIM three-dimensional excavation safety surface distribution model and according to the size relationship between the current distance from the current position to the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit, it is determined whether grouting reinforcement work is required; When each current distance is smaller than the corresponding preset distance, the corresponding current position is determined to be a position where grouting reinforcement operation is required.

7. A device for determining the grouting position of a deep foundation pit in a karst area, characterized in that: The device comprises: An acquisition module is used to arrange a plurality of water level monitoring positions around the karst area corresponding to the deep foundation pit, and to acquire the water head parameters of each of the water level monitoring positions; A first modeling module is used to draw a three-dimensional distribution model of all the water heads in the karst area according to each of the water head parameters and preset geological data; An error processing module, used to combine the acquired real-time water head monitoring data of each water head and modulate the corresponding water head in the three-dimensional distribution model to eliminate geological errors; The second modeling module is used to excavate the current excavation surface of the deep foundation pit to a target position according to the acquired excavation safety surface depth of the deep foundation pit, and establish a BIM three-dimensional excavation safety surface distribution model of the deep foundation pit; The output module is used to determine the position where grouting reinforcement operation is required in combination with the BIM three-dimensional excavation safety surface distribution model and based on the size relationship between the current distance between the current position and the corresponding water surface of the solution cavity and the preset distance between the solution cavity and the bottom plate of the deep foundation pit.

8. A device for determining the grouting position of a deep foundation pit in a karst area, characterized in that: The device comprises: a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the computer program is configured to implement the steps of the method for determining the grouting position of a deep foundation pit in a karst area as described in any one of claims 1 to 6.

9. A grouting system, characterized in that: include: The grouting position determination device for deep foundation pit in karst area as claimed in claim 8; and The grouting equipment is communicatively connected with the grouting position determining device for the deep foundation pit in the karst area.

10. A storage medium, characterized in that: The storage medium is a computer-readable storage medium, and a computer program is stored on the storage medium. When the computer program is executed by a processor, the steps of the method for determining the grouting position of a deep foundation pit in a karst area as described in any one of claims 1 to 6 are implemented.