Intelligent construction method for squat silo of grain depot
By using an intelligent monitoring system to monitor the verticality of the sliding mode in real time in the construction of shallow round warehouses, the verticality deviation problem caused by sliding mode displacement deformation is solved, and the construction quality and safety are improved.
Patent Information
- Application Number
- CN202410907023.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-11-08
AI Technical Summary
During the construction process, the shallow round warehouse is affected by the sliding mold due to the self-weight, construction live load and friction resistance, and the sliding mold displacement deformation is prone to occur, resulting in serious verticality and torsion deviation of the warehouse wall, which affects the construction quality.
Design an intelligent construction method for shallow round warehouses in the grain warehouse. The monitoring system is used to monitor the verticality of the sliding mode in real time, extending along the axis of the shallow round warehouse through the connecting rod and the monitoring end. The monitoring end conflicts on the inside of the cast ware wall, and adjusts in real time The sliding mold position ensures the verticality of the warehouse wall, and monitors the verticality of the sliding mold in real time during the pouring process to ensure construction quality.
It effectively avoids sliding form displacement deformation, ensures the verticality and construction quality of shallow round silo walls, and improves construction accuracy and safety.
Smart Images

Figure CN118911408A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and specifically relates to an intelligent construction method for a shallow circular silo in a grain depot. Background Art
[0002] A shallow silo is a cylindrical ground silo with a ratio of silo wall height to inner diameter less than 1.5. It is widely used in the grain industry due to its small footprint, large diameter, high grain pile, large silo capacity, reasonable structural force, strong earthquake resistance, good sealing performance, easy mechanized operation, and convenience for the implementation of grain "scattered" operations.
[0003] Slipform construction is the main construction method for shallow silos, which has the advantages of high mechanization, fast construction speed, small site occupation, guaranteed safe operation and significant comprehensive benefits. Due to the large diameter of the silo, the platform is greatly affected by its own weight, construction live load, concrete friction and various additional loads. Therefore, it is easy for the slipform to shift and deform, which will affect the verticality of the inner wall of the shallow silo, causing the verticality of the structure to exceed the verticality, serious torsional deviation, and even the inability to continue sliding.
[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention
[0005] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art, and the present invention provides a system for monitoring the verticality of a shallow circular silo wall in a grain depot.
[0006] In order to achieve the above object, the present invention provides the following technical solutions:
[0007] An intelligent construction method for a grain depot shallow silo comprises the following steps:
[0008] Step S1, designing a construction plan, and performing site hardening and material preparation at the construction site;
[0009] Step S2, draw the center of the sliding mold on the sliding start surface, draw the radius position of the inner leg of the lifting frame, and use the theodolite to lay out the position of the lifting frame according to the divided angles;
[0010] Step S3, installing the slipform, lifting frame and center plate, and tying steel bars inside the slipform;
[0011] Step S4, dividing the slipform casting sections, and continuously casting multiple casting sections by pumping, inserting a vibrating rod to vibrate the concrete after it enters the mold, and after the cast silo wall is cured to a preset strength, sliding the slipform upward to the next casting position;
[0012] Step S5, installing a monitoring system on the inner template of the slipform, the monitoring system comprising a connecting rod and a monitoring end, the connecting rod extending downward in a direction parallel to the axis of the shallow circular silo, the monitoring end connected to the lower end of the connecting rod, the monitoring end abutting against the inner side of the cast silo wall, monitoring the verticality of the slipform through the monitoring end, tying the steel bars corresponding to the next casting position inside the slipform, and sliding the slipform again after casting until casting to the preset elevation of the silo wall, and monitoring the verticality of the slipform in real time during the casting process;
[0013] Step S6, installing the embedded sleeve, using the slipform hanger to install the tripod and scaffolding board on the outside of the warehouse wall, and then removing the slipform, splicing the umbrella rib steel truss inside the shallow round warehouse, using the electric hoist to lift the umbrella rib steel truss to the top of the embedded sleeve, installing the steel bracket through the embedded sleeve, and lowering the umbrella rib steel truss to the steel bracket;
[0014] Step S7, installing the silo roof cone shell formwork and tying the corresponding silo roof steel bars before pouring the silo roof. After pouring, remove the steel brackets and lower the umbrella-shaped steel truss to the ground.
[0015] Preferably, the lifting frame is an N-shaped frame straddling both sides of the slipform, with the inner and outer slipform forms fixed to them by bolts at both ends, a support rod extending longitudinally into the warehouse wall is provided in the middle of the lifting frame, and a jack corresponding to the support rod is provided at the top of the lifting frame, and the support rod is extended according to the pouring progress of the warehouse wall.
[0016] Preferably, the center disk is circumferentially provided with a plurality of tie rods distributed in a central radial form, the ends of the tie rods are connected to the lifting frames through basket bolts, and the number of the tie rods matches the number of the lifting frames.
[0017] Preferably, two enclosures are respectively provided on the inner and outer sides of the sliding form, and the upper and lower edges of the inner and outer templates of the sliding form are respectively connected to the enclosures;
[0018] When the slipform rises to a height of 1.8m, scaffolding is installed on both sides of the slipform.
[0019] Preferably, in step S6, after the sliding formwork is removed, a support frame is positioned on the top of the warehouse wall using a theodolite before installation, so that the support frame is on the same vertical line just above the corbel, and an electric hoist for hoisting the umbrella-shaped steel truss is installed on the support frame;
[0020] After the silo wall concrete reaches 80% of the preset strength, the truss is hoisted with multiple electric hoists. The stability of the truss is observed after it is 20 cm off the ground.
[0021] After the umbrella-frame steel truss is in place, the deformation of the umbrella-frame steel truss is monitored by using multiple plumb lines.
[0022] Preferably, the silo roof concrete construction is carried out 28 days after the silo wall pouring is completed or the strength reaches 100%, and the pouring is divided into multiple circles along the circumference by a car pump. After the pouring is completed, the surface is pressed and polished in time. After the concrete pouring is completed, it is covered and watered for maintenance within 12 hours.
[0023] Preferably, after the silo roof concrete reaches 100%, the silo roof grain inlet hole is lowered to the umbrella-shaped steel truss to remove the silo roof cone shell template;
[0024] During the pouring of concrete on the silo roof, hanging holes corresponding to the hanging points of the umbrella-shaped steel trusses are reserved, and an electric hoist is installed on the silo roof to lower the umbrella-shaped steel trusses.
[0025] Preferably, the monitoring terminal includes:
[0026] A main body, the main body is correspondingly connected to the lower end of the connecting rod, and a central hole extending along the radial direction of the shallow silo is provided inside the main body;
[0027] A slide rod extending along the central hole, wherein a buffer spring is provided at one end of the central hole away from the cast warehouse wall to squeeze the other end of the slide rod against the inner side of the cast warehouse wall;
[0028] A monitoring element is provided on the inner wall of the central hole, and a plurality of the monitoring elements are evenly distributed along the radial direction of the shallow silo.
[0029] Preferably, the monitoring element is electrically connected to the controller, the inner template of the sliding formwork includes a plurality of groups of unit molds spliced to each other, each unit mold is correspondingly provided with a monitoring mechanism, and a pulley is provided at one end of the sliding rod close to the cast warehouse wall so that it can slide along the cast warehouse wall through the pulley.
[0030] Preferably, the monitoring system further comprises a displacement sensor, which is arranged on the monitoring end head and is electrically connected to the controller for monitoring each displacement sensor and monitoring the radial position of each unit mold.
[0031] Beneficial effect: During the silo wall construction process, the monitoring end moves up with the slipform according to the pouring progress, and uses the already poured silo wall as a reference to reflect the verticality of the silo wall of the next pouring section, thereby ensuring the construction quality of the shallow circular silo. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:
[0033] Figure 1 It is a schematic diagram of the assembly of the monitoring system in the specific embodiment provided by the present invention;
[0034] Figure 2 for Figure 1 The enlarged schematic diagram at A in the middle;
[0035] Figure 3 This is a simplified structural diagram of the monitoring terminal in a specific embodiment provided by the present invention.
[0036] In the figure: 1. Sliding formwork inner template; 2. Connecting rod; 3. Pulley; 4. 3D scanner; 5. Main body; 6. Sliding rod; 7. Buffer spring; 8. Monitoring element; 9. Plug; 10. Support rod; 11. Suspension scaffold; 12. Enclosure; 13. Jack; 14. Lifting frame; 15. Adjustment rod; 16. Short column DETAILED DESCRIPTION
[0037] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.
[0038] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0039] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.
[0040] like Figure 1-3 As shown, a method for intelligent construction of shallow circular silos in a grain depot comprises the following steps: Step S1, designing a construction plan according to the design drawings, hardening the site and preparing materials at the construction site, and reasonably arranging construction access roads.
[0041] Step S2, draw the center of the sliding mold on the sliding starting surface, draw the radius position of the inner leg of the lifting frame 14, and use the theodolite to lay out the position of the lifting frame 14 according to the divided angles.
[0042] Step S3, installing the slipform, the lifting frame 14 and the center plate, tying the steel bars inside the slipform, and the ring bars can be tied to a height of 1.3 meters before assembling the slipform.
[0043] Shallow silo wall reinforcement is mainly divided into horizontal reinforcement, vertical reinforcement and embedded reinforcement with silo top ring beam, etc. Shallow silo reinforcement is all connected by binding. According to the drawing requirements, the vertical reinforcement lap length is 40d, the joints are staggered, and the reinforcement joints of any horizontal section (lap length range is the same section) do not exceed 25% of the total number of sections. The lap length of the hoop horizontal reinforcement is 60d, the joints are staggered, the horizontal spacing of the joints is not less than one lap length and not less than 1m, there is a lap joint for every three reinforcements in the same vertical section, and the internal and external horizontal reinforcements are also evenly staggered.
[0044] Step S4, divide the slipform casting section, and continuously cast multiple casting sections by pumping. When the top surface of the concrete is 3 to 5 cm lower than the template after each pouring, stop pumping, move to the next point nearby and continue to place the material in the above manner. After the concrete enters the mold, insert a vibrating rod to vibrate it. After the poured warehouse wall is cured to a preset strength, slide the slipform upward to the next casting position. After a full circle, the second circle of material needs to be moved about 3 meters, that is, two gantries need to be placed again to avoid placing too much concrete strength at the same place.
[0045] Step S5, install a monitoring system on the inner template 1 of the slipform, the monitoring system includes a connecting rod 2 and a monitoring end, the connecting rod 2 extends downward in a direction parallel to the axis of the shallow silo, the monitoring end is connected to the lower end of the connecting rod 2, and the monitoring end is against the inner side of the cast silo wall, and the verticality of the slipform is monitored by the monitoring end, so that the verticality of the silo wall of the next casting section can be reflected based on the already cast silo wall as a reference, thereby ensuring the construction quality of the shallow silo. After the concrete reaches the preset strength, the slipform is lifted, and the concrete has plasticity after being removed from the mold, and it must be inspected and repaired in time, and a dedicated person will perform surface repair and calendering operations.
[0046] Tie the steel bars corresponding to the next pouring position inside the slipform, and after pouring, slide the slipform up again until pouring reaches the preset elevation of the silo wall. Monitor the verticality of the slipform in real time during the pouring process.
[0047] Step S6, when the warehouse wall is slipformed, when it slides to a predetermined height, an embedded sleeve is installed as the internal bolt support of the truss bracket, and the tripod and scaffolding board are installed on the outer side of the warehouse wall by using the slipform hanger, and then the slipform is removed. Before the slipform is removed, the pre-made external tripod is fixed to the embedded sleeve of the warehouse wall by using the slipform hanger with 8.8-grade 22mm bolts, and then scaffolding pipes + bamboo springboards are laid on each external tripod to form a circular cantilever frame as a cantilever eaves support platform and pedestrian passage.
[0048] Splice the rib-shaped steel truss inside the shallow silo, use the electric hoist to lift the rib-shaped steel truss to the top of the embedded sleeve, install the steel bracket through the embedded sleeve, and lower the rib-shaped steel truss to the steel bracket;
[0049] Step S7, install the silo top cone shell formwork and tie the corresponding silo top steel bars before pouring the silo top. The silo top cone shell structure steel bars are from bottom to top: lower ring beam steel bars, upper ring beam steel bars, cone shell structure radial and annular steel bars, and double-layer bidirectional steel bars of the silo top circumferential plate. The silo top cone shell beam and plate steel bars are connected by tying.
[0050] After pouring is completed, the steel corbels are removed and the umbrella-shaped steel trusses are lowered to the ground.
[0051] In an optional embodiment, the lifting frame 14 is an n-shaped frame spanning both sides of the slipform, and its two ends are respectively fixed to the inner formwork 1 of the slipform and the outer formwork of the slipform by bolts. A support rod 10 extending into the warehouse wall along the longitudinal direction is provided in the middle of the lifting frame 14, and a jack 13 corresponding to the support rod 10 is provided on the top of the lifting frame 14. The support rod 10 is extended according to the pouring progress of the warehouse wall. The length of the first batch of support rods 10 inserted and fixed in the jack 13 is generally divided into 3m, 4m, 5m and 6m, so that the height difference between the joints of each two adjacent support rods 10 is ≥1m, and the number of joints at the same height accounts for ≤1 / 4 of the total number of support rods 10. The support rods 10 are connected by socket first and then welding. The pipe head with a length of about 70 mm at the end of the support rod 10 is compressed to an outer diameter of 38 mm by a steel pipe reducer so that it can be smoothly inserted into another support rod 10 with a diameter of 48.3 mm. The joint is then spot welded and polished to be smooth so that the joint can pass through the jack 13 smoothly. After the joint passes through the jack 13, it is promptly reinforced by full welding.
[0052] During the sliding process, the support rod 10 passes through the holes of doors and windows, so the length of the support rod 10 is too long, which may cause the support rod 10 to become unstable and bend. Therefore, the following reinforcement measures must be taken: add a steel pipe on each side of the support rod 10, arranged in a triangle, and weld and fix the steel pipe in the horizontal direction with a spacing of 500mm.
[0053] Before the first concrete pouring, short steel bars with a diameter greater than 20 mm are used to weld the support rod 10 to the silo wall steel bars. Before welding, the verticality of the support rod 10 must be adjusted. The axis of the support rod 10 is consistent with the axis of the jack 13, and the allowable deviation of its deflection is one thousandth.
[0054] In an optional embodiment, the center disk adopts a Φ600*8mm thick steel plate, and a plurality of tie rods distributed in a central radial form are arranged around the center disk. The ends of the tie rods are connected to the lifting frame 14 through basket bolts. The number of tie rods is matched with that of the lifting frame 14. When adjusting and tightening the tie rods, all the tie rods are tightened first, and then a spirit level is placed on the lower beam of the lifting frame 14, and the tie rods are tightened until the beam of the lifting frame 14 is horizontal.
[0055] In an optional embodiment, two enclosures 12 are provided on the inner and outer sides of the slipform, respectively, and the upper and lower sections of the inner and outer templates 1 of the slipform and the outer and inner templates of the slipform are connected to the enclosures 12 respectively; the outer slope control value of the enclosure 12 is 0-2mm, and the inner slope control value is 2-4mm. The enclosure 12 between the two lifting frames 14 shall not have more than two splicing joints. When installing the template, the verticality of the template must be controlled within 8‰ and the overall verticality deviation of the shallow silo shall not exceed 10mm. At the template position with the opening, the wooden board of the opening should be sealed at the same time, and the wooden box should be placed in the opening less than 1 meter in time. Note that the thickness of all wooden sealing boards and wooden boxes should be less than the thickness of the wall, 2-3mm smaller on each side. When the size of the opening is large, the template should be prepared in advance, the template should be reinforced, and reinforcing steel bars should be set at the opening according to the design requirements.
[0056] When the sliding formwork slides up to a height of 1.8 m, hanging scaffolds 11 are installed on both sides of the sliding formwork, the outer hanging scaffold 11 is installed on the outer lower cantilever beam, and the inner hanging scaffold 11 is installed on the inner lower cantilever beam.
[0057] In an optional embodiment, in step S6, after the sliding form is removed, the support frame is positioned on the top of the warehouse wall using a theodolite before installation, so that the support frame is on the same vertical line just above the corbel, and the electric hoist for hoisting the umbrella-shaped steel truss is installed on the support frame; a total of 18 support frames are arranged along the circumference of the warehouse wall, and a 10T electric hoist is fixed on the support frame. 18 10-ton electric hoists are connected to the control box to synchronously lift the truss. When the truss is 20 cm off the ground, stability observation is performed for 2 hours to observe whether the truss components, warehouse wall cards, and warehouse walls are deformed. After checking that there are no problems, a high-altitude construction safety net is installed at the bottom of the component, and then the computer control box is switched to the automatic control state, and the steel truss is synchronously lifted by computer automatic control plus manual supervision and synchronous control, and the electric hoist travel speed is controlled at 18 cm per minute. Every time it is lifted 1.8 meters, it is necessary to observe for 20 minutes, and so on until it is lifted to a height of 150mm above the corbel, and then the corbel is installed. After all the corbels are installed, use an electric hoist to drop the steel truss to the corbel position, adjust the position and weld it firmly.
[0058] After the umbrella-frame steel truss is in place, follow multiple plumb lines, and then set up a 1.5m long steel pipe next to the plumb line, drive it 0.3m into the ground, stick a 200mm long scale paper on the top of the steel pipe, and use the plumb line to monitor the deformation of the umbrella-frame steel truss.
[0059] In an optional embodiment, the silo roof concrete construction is carried out 28 days after the silo wall pouring is completed or the strength reaches 100%. The pouring is divided into multiple circles along the ring direction by a car pump. The horizontal projection length of the conical shell plate is 11.00m. In order to make the steel truss evenly and slowly stressed, it is planned to be poured in 14 rings, with each pouring of 0.8m. The next ring is poured before the joint begins to set, and the process is carried out in sequence until the circular flat surface of the silo roof is reached.
[0060] After pouring, the surface should be smoothed and finished in time. After the concrete is poured, it should be covered and watered for maintenance within 12 hours.
[0061] In an optional embodiment, after the concrete on the silo roof reaches 100%, the grain inlet hole on the silo roof is lowered to the umbrella-shaped steel truss to remove the silo roof cone shell formwork, and the steel truss is lowered by an electric hoist. During the pouring of the silo roof concrete, lifting holes corresponding to the lifting points of the umbrella-shaped steel truss are reserved, and the electric hoist is installed on the silo roof to lower the umbrella-shaped steel truss.
[0062] When the steel truss lands safely, restore the demolished opening; prepare a 150mm*10mm round steel plate, weld φ8 steel bars to the round steel plate, extend it into the bottom of the reserved hole, and fully weld it; seal it with micro-expansion concrete that is one grade higher than the silo top concrete.
[0063] In an optional embodiment, the platform deviation correction adopts the platform tilting method to achieve the purpose of deviation correction. When it is found that the verticality deviation exceeds 10mm, the jack on the offset side is appropriately increased to make the platform tilt (not more than 1%) and then slide up. After the deviation is corrected, it slides normally. After the bottom section of the silo wall is cast and the sliding form is moved up, the connecting rod 2 is fixed. The connecting rod 2 extends downward in a direction parallel to the axis (longitudinal) of the shallow circular silo. The monitoring end is connected to the lower end of the connecting rod 2. The monitoring end contacts the inner side of the cast silo wall. The monitoring end is used to monitor the silo wall during the sliding process of the sliding form, so as to accurately grasp the verticality of the silo wall of the casting section and ensure the verticality of the silo wall construction.
[0064] The monitoring end includes a main body 5, a slide rod 6, and a monitoring element 8. The main body 5 is connected to the lower end of the connecting rod 2. The main body 5 is used to connect the slide rod 6. A center hole extending radially along the shallow circular silo is provided inside the main body 5. The main body 5 can be a square or round tube. The slide rod 6 extends axially along the center hole and is slidably assembled along its axial direction. A buffer spring 7 corresponding to the slide rod 6 is provided at the end of the center hole away from the cast silo wall. The buffer spring 7 squeezes the other end of the slide rod 6 to contact the inner side of the cast silo wall, thereby keeping the slide rod 6 able to continuously stick to the silo wall. A monitoring element 8 is provided on the inner wall of the center hole. Multiple monitoring elements 8 are evenly distributed along the radial direction of the shallow circular silo to determine the position of the slide rod 6 through the monitoring element 8. Specifically, the slide rod 6 can be a metal rod, and the detection element can be a Hall element, a touch switch, an infrared rangefinder or other detection device, as long as the relative sliding position of the slide rod 6 can be detected.
[0065] For example, a plurality of touch switches are provided on the inner wall of the center hole, and the displacement of the slide bar 6 is determined according to the relative positions of the different touch switches, so as to judge whether the specific slide form is tilted. In actual use, by moving the slide form upward, the slide bar 6 can provide driving force through the buffer spring 7 during the movement, and by monitoring the relative position of the slide bar 6, if the slide form tilts inward, the distance between the lower end of the slide bar 6 and the warehouse wall changes, so as to judge whether the slide form is tilted, and then the technicians can adjust the slide form according to the needs to ensure the casting quality.
[0066] In an optional embodiment, the monitoring element 8 is electrically connected to the controller, the slipform inner template 1 includes a plurality of groups of unit molds spliced to each other, each unit mold is provided with a corresponding monitoring mechanism, and a pulley 3 is provided at one end of the sliding rod 6 close to the cast warehouse wall so as to slide along the cast warehouse wall through the pulley 3.
[0067] An articulated seat is provided at one end of the slide bar 6 close to the cast warehouse wall, so that the slide bar 6 can be rotatably connected to the pulley 3 through the articulated seat, so as to slide along the cast warehouse wall through the pulley 3, thereby reducing the friction during the sliding process and ensuring the accuracy of use.
[0068] A plug 9 is provided at one end of the center hole away from the cast warehouse wall, and the outer wall of the plug 9 is provided with threads, so that it is connected to the center hole through a threaded connection. The buffer spring 7 is correspondingly arranged between the slide rod 6 and the plug 9 so that the slide rod 6 has a tendency to move toward the cast warehouse wall.
[0069] In an optional embodiment, the monitoring system further includes a displacement sensor, which is disposed on the monitoring end and electrically connected to the controller for monitoring each displacement sensor and the radial position of each unit mold.
[0070] The slipform includes a plurality of unit molds spliced together, and each unit mold is provided with a corresponding monitoring mechanism, which can monitor each unit mold, so as to accurately determine the unit mold to be adjusted. In order to ensure smooth and accurate sliding of the pulley 3, the outer edge of the pulley 3 is provided with an arc surface corresponding to the inner wall of the cast warehouse wall to prevent the pulley 3 from damaging the inner surface of the warehouse wall.
[0071] The controller may be a single chip microcomputer or a plc, the monitoring element 8 is electrically connected to the controller, and the controller is correspondingly connected to the controller, so that an intuitive display can be achieved.
[0072] A three-dimensional scanner 4 is arranged in the middle of the shallow silo to scan and measure the inner wall of the poured part. The characteristics of the three-dimensional laser scanning technology, such as fast data collection speed, high data accuracy and wide data collection range, are utilized to measure the poured part in real time, so as to adjust and correct the monitoring data.
[0073] In an optional embodiment, the circle 12 is formed by splicing multiple arc-shaped structures, which are fixed to each other by bolts. The sliding formwork inner template 1 and the sliding formwork outer template correspond one to one. A group of sliding formwork inner template 1 and sliding formwork outer template are lifted by a lifting frame 14, so that the two ends of the lifting frame 14 correspond one to one with the sliding formwork inner template 1 and the sliding formwork outer template respectively. The two circles 12 on the inner side of the sliding form are respectively located at the lower part and the middle and upper part of the sliding formwork inner template 1. The middle and upper parts of the lifting frame 14 are provided with short columns 16 corresponding to the support circles 12. The short columns 16 located at the middle and upper part of the lifting frame 14 are hinged to the corresponding sliding formwork inner template 1 or the sliding formwork outer template. Two adjustment rods 15 corresponding to the upper and lower edges of the sliding formwork inner template 1 are provided on the inner side of each lifting frame 14. The adjustment rod 15 can be a hydraulic cylinder, and the piston end of the hydraulic cylinder is hinged on the sliding formwork inner template 1. The sliding formwork inner template 1 can be adjusted by extending and retracting the adjusting rod 15, so that the angle of the sliding formwork inner template 1 can be conditioned according to the monitoring results.
[0074] Preferably, two adjustment rods 15 corresponding to the upper and lower edges of the outer template of the slipform are provided on the outside of each lifting frame 14, and data is compared with the built three-dimensional digital model to determine whether the verticality of the shallow round warehouse of the poured part meets the design requirements.
[0075] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.
Claims
1. An intelligent construction method for a grain depot shallow silo, characterized in that: The following steps are involved: Step S1, designing a construction plan, and performing site hardening and material preparation at the construction site; Step S2, draw the center of the sliding mold on the sliding start surface, draw the radius position of the inner leg of the lifting frame, and use the theodolite to lay out the position of the lifting frame according to the divided angles; Step S3, installing the slipform, lifting frame and center plate, and tying steel bars inside the slipform; Step S4, dividing the slipform casting sections, and continuously casting multiple casting sections by pumping, inserting a vibrating rod to vibrate the concrete after it enters the mold, and after the cast silo wall is cured to a preset strength, sliding the slipform upward to the next casting position; Step S5, installing a monitoring system on the inner template of the slipform, the monitoring system comprising a connecting rod and a monitoring end, the connecting rod extending downward in a direction parallel to the axis of the shallow circular silo, the monitoring end connected to the lower end of the connecting rod, the monitoring end abutting against the inner side of the cast silo wall, monitoring the verticality of the slipform through the monitoring end, tying the steel bars corresponding to the next casting position inside the slipform, and sliding the slipform again after casting until casting to the preset elevation of the silo wall, and monitoring the verticality of the slipform in real time during the casting process; Step S6, installing the embedded sleeve, using the slipform hanger to install the tripod and scaffolding board on the outside of the warehouse wall, and then removing the slipform, splicing the umbrella rib steel truss inside the shallow round warehouse, using the electric hoist to lift the umbrella rib steel truss to the top of the embedded sleeve, installing the steel bracket through the embedded sleeve, and lowering the umbrella rib steel truss to the steel bracket; Step S7, installing the silo roof cone shell formwork and tying the corresponding silo roof steel bars before pouring the silo roof. After pouring, remove the steel brackets and lower the umbrella-shaped steel truss to the ground.
2. The intelligent construction method of grain depot shallow silo according to claim 1 is characterized in that: The lifting frame is an N-shaped frame spanning both sides of the slipform, with the inner and outer slipform forms fixed to them by bolts at both ends. A support rod extending longitudinally into the silo wall is provided in the middle of the lifting frame, and a jack corresponding to the support rod is provided on the top of the lifting frame. The support rod is extended according to the pouring progress of the silo wall.
3. The intelligent construction method of grain depot shallow silo according to claim 1 is characterized in that: The central disk is circumferentially provided with a plurality of tie rods distributed in a central radial form, the ends of the tie rods are connected to the lifting frames through basket bolts, and the number of the tie rods matches the number of the lifting frames.
4. The intelligent construction method for shallow silos in grain depots according to claim 1 is characterized in that: Two enclosures are respectively arranged on the inner and outer sides of the sliding form, and the upper and lower edges of the inner and outer templates of the sliding form are respectively connected to the enclosures; When the slipform rises to a height of 1.8m, scaffolding is installed on both sides of the slipform.
5. The intelligent construction method of grain depot shallow silo according to claim 1 is characterized in that: In step S6, after the sliding formwork is removed, the support frame is positioned on the top of the warehouse wall using a theodolite before installation, so that the support frame is on the same vertical line just above the corbel, and an electric hoist for hoisting the umbrella-shaped steel truss is installed on the support frame; After the silo wall concrete reaches 80% of the preset strength, the truss is hoisted with multiple electric hoists. The stability of the truss is observed after it is 20 cm off the ground. After the umbrella-frame steel truss is in place, the deformation of the umbrella-frame steel truss is monitored by using multiple plumb lines.
6. The intelligent construction method for grain storage shallow silo according to claim 1 is characterized in that: The silo roof concrete construction will be carried out 28 days after the silo wall pouring is completed or the strength reaches 100%. The concrete will be poured in multiple circles along the circumference using a truck pump. After the pouring is completed, the surface will be pressed and finished in time. After the concrete pouring is completed, it will be covered and watered for maintenance within 12 hours.
7. The intelligent construction method for shallow silos in grain depots according to claim 1 is characterized in that: After the silo roof concrete reaches 100%, the silo roof grain inlet hole is lowered to the umbrella-shaped steel truss to remove the silo roof cone shell formwork; During the pouring of concrete on the silo roof, hanging holes corresponding to the hanging points of the umbrella-shaped steel trusses are reserved, and an electric hoist is installed on the silo roof to lower the umbrella-shaped steel trusses.
8. The intelligent construction method for grain storage shallow silo according to claim 1 is characterized in that: The monitoring terminal includes: A main body, the main body is correspondingly connected to the lower end of the connecting rod, and a central hole extending along the radial direction of the shallow silo is provided inside the main body; A slide rod extending along the central hole, wherein a buffer spring is provided at one end of the central hole away from the cast warehouse wall to squeeze the other end of the slide rod against the inner side of the cast warehouse wall; A monitoring element is provided on the inner wall of the central hole, and a plurality of the monitoring elements are evenly distributed along the radial direction of the shallow silo.
9. The intelligent construction method for grain storage shallow silo according to claim 8 is characterized in that: The monitoring element is electrically connected to the controller, the inner template of the sliding formwork includes a plurality of mutually connected unit molds, each of the unit molds is provided with a corresponding monitoring mechanism, and a pulley is provided at one end of the sliding rod close to the cast warehouse wall so as to slide along the cast warehouse wall through the pulley.
10. The intelligent construction method for grain storage shallow silo according to claim 9 is characterized in that: The monitoring system also includes a displacement sensor, which is arranged on the monitoring end head and is electrically connected to the controller for monitoring each displacement sensor and the radial position of each unit mold.
Citation Information
Patent Citations
Sliding mode operating platform system with center vertical cylinder structure
CN103953187A
Connection bin synchronous sliding formwork construction method
CN107587770A
Shallow round bin slip form construction method
CN113006468A
Pulley type perpendicularity real-time monitoring device of slip form construction silo and monitoring method of pulley type perpendicularity real-time monitoring device
CN115371593A
Shallow silo tip conical shell formwork structure and construction process thereof
CN117145200A
Cited By
Vibrating machine for building concrete main body structure construction
CN120556733A
Rapid binding device for circumferential steel bars in slip-form construction of squat silo and using method of rapid binding device
CN121497102A