Building decoration design engineering marking method
By using wall, floor and ceiling marking methods during building decoration, combined with 3D laser scanners and different color marking tools, the problem of incomplete marking in the existing technology is solved, and accuracy and consistency during construction is achieved. , improves construction efficiency and safety and reduces costs.
Patent Information
- Application Number
- CN202410572463.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2024-11-08
AI Technical Summary
The lack of a complete and clear marking method in the existing building decoration technology has led to low accuracy, high error rate, and frequent rework during the construction process, which increases additional costs and reduces construction efficiency.
The wall, floor and ceiling marking method is adopted to determine the flatness through detection tools, mark the direction of electrical equipment, water pipes, doors and windows, and use different colors of marking tools and numbering systems to ensure the accurate installation and spatial layout planning of each decoration component, and Set up safety warning signs during construction, and use 3D laser scanners and specific marking tools to improve the accuracy and efficiency of detection and marking.
It achieves accuracy and consistency during the construction process, reduces errors and rework, improves construction efficiency and safety, ensures decoration quality and reasonable use of materials, reduces costs, and enhances the management and communication efficiency of the construction site.
Smart Images

Figure CN118911422A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building decoration, and in particular relates to a marking method for a building decoration design project. Background Art
[0002] Architectural decoration refers to the beautification and improvement of the external appearance or internal environment of houses, bridges, stadiums, temples, etc., which are built with stone, wood and other building materials for people to live in and use, using various materials to make them more romantic and have both residential and commercial value. Architectural decoration design engineering refers to the entire process of interior and exterior design and construction of buildings, including multiple sub-projects, such as flooring, plastering, doors and windows, ceilings, lightweight partitions, decorative panels, curtain walls, painting, mounting and soft packaging, details, etc.
[0003] In order to ensure the accurate installation of decoration components and reduce the possibility of errors during the construction process when decorating walls, floors and ceilings, most of the time, marking tools are used to mark the walls, floors and ceilings. However, there is no complete and clear marking method in the prior art. Manual marking is mainly based on the experience of construction workers. Not only is the accuracy low, but the marking is also incomplete, which is not conducive to planning space layout, and increases the probability of errors and omissions in the construction process, thereby leading to rework and additional costs, and reducing construction efficiency. Summary of the invention
[0004] The purpose of the present invention is to provide a marking method for building decoration design engineering to solve the problem that the marking method in the prior art is not comprehensive.
[0005] In order to achieve the above object, the present invention provides the following technical solution: a marking method for a building decoration design project, comprising the following steps:
[0006] Sp1: Wall marking. First, use the wall detection tool to determine the flatness of the wall, and mark the uneven parts of the wall. Then fill and polish the marked parts, and then determine the HVAC equipment and switch layout on the wall. Mark the direction of electrical sockets, switches, water pipes and wires on the wall, reserve wall positions, and ensure the accurate installation of decoration components such as switches, sockets, doors, windows, cabinets, etc. to ensure the safety and functionality of electrical installation. Finally, mark the reserved positions of doors and windows by drawing lines to avoid errors in subsequent construction.
[0007] Sp2: Floor marking, use floor detection tools to determine the flatness of the wall, mark the floor where there are depressions or cracks, repair them to make them flat, clean the floor, ensure that the floor is flat, dry and dust-free, measure the size of the room, determine the starting point and direction of floor laying, use marking tools to mark reference lines on the floor to guide the laying position of the floor, and before laying, the boards should be tried out, the patterns and colors should be matched, and the numbers should be marked, and finally the positions of floor drains and drainage outlets should be determined and marked, so as to avoid color difference and pattern mismatch problems and ensure the overall effect of the laid floor is coordinated and consistent;
[0008] Sp3: Ceiling marking, determine the installation location of lighting equipment, vents, suspended ceilings and smoke alarms, including the frame outline of suspended ceilings, and the location of any embedded lamps or decorations. Use ceiling marking tools to mark them one by one to ensure the correct installation of safety facilities. When the ceiling is painted or decorated with wallpaper, different color areas should be marked separately. For those who plan to install audio equipment on the ceiling, the location of the audio should be marked on the ceiling to facilitate the pre-embedding of lines and installation of equipment;
[0009] Sp4: Construction marking. When workers are carrying out construction, they need to set up safety warning signs in dangerous areas or areas under construction to ensure the safety of construction workers. After completing each day's work, they need to mark the construction steps on the construction fence to help supervisors and owners monitor the progress and quality of construction, identify problems in a timely manner and deal with them. Through construction marking, the accuracy and consistency of each construction link can be ensured, construction deviations can be reduced, and the final decoration quality can be guaranteed.
[0010] Sp5: Special marking. When carrying out building decoration, checkpoints are marked for quality inspection during acceptance, and special marking is performed on wet areas and reinforced areas. This helps to remind construction personnel to take appropriate waterproof and moisture-proof measures, such as setting up concrete guide walls, ensuring smooth drainage, etc., thereby reducing quality problems caused by moisture, such as mildew and corrosion. As a guide to the construction process, it ensures that the construction steps meet quality requirements. For example, the drainage slope of the ground leveling layer must not be less than 1%. The control of these details is crucial to the final waterproof effect. For areas that need to be reinforced, special markings help to clarify the scope and methods of reinforcement, such as the application of grouting reinforcement technology, which can improve the bearing capacity and stability of the foundation or structure, which is crucial to the overall safety of the building.
[0011] Preferably, the wall detection tool and the ground detection tool both use 3D laser scanners. Traditional flatness detection methods usually require manual operation, which is time-consuming and inefficient. However, 3D laser scanners can quickly complete data acquisition, greatly improving the efficiency of detection, and can provide high-precision three-dimensional point cloud data. These data can accurately reflect the concave and convex features of the wall and the ground, thereby making the detection results more accurate and reliable, and can save a lot of manpower and material costs in long-term applications. In addition, the use of 3D laser scanning technology for detection will not cause any damage to the wall and the ground. It is a non-contact detection method that is conducive to protecting the integrity of the wall and the ground.
[0012] Preferably, the wall markings are marked with a dark pen, and the directions of the electrical sockets, switches, water pipes and wires are marked with chalk. The dark pen markings are convenient for the staff to identify clearly. The chalk markings can clearly indicate the directions of the wires and water pipes, help the construction staff understand the design intent, reduce errors and rework in construction, and are easy to erase without leaving traces, so that the space layout can be better planned, and space waste or aesthetic problems caused by unreasonable pipeline directions can be avoided. When installing switches and sockets, accurate markings help to ensure the horizontal and vertical installation, make the panel installation smoother, improve the overall appearance, reduce material waste caused by measurement errors, and improve the efficiency of material use.
[0013] Preferably, the ground is marked with a marker, and the marking tools include a level and a vertical line marker. The plate numbering is systematic, and the systematic numbering is performed according to the installation order or a specific pattern of the plates. The marker marking is durable and can quickly make clear and visible marks on the ground, improving work efficiency. It has bright colors and can be easily seen even in darker environments. It is water-resistant and will not fade even when used on wet ground. The markings on the ground can resist wear to a certain extent, especially in a short period of time, reducing errors and rework during construction and improving construction quality. The level can provide an accurate horizontal reference line, which is critical for objects that need to be installed horizontally. The vertical line marker can quickly mark accurate vertical lines on the wall, which is critical to ensuring the vertical alignment of the structure and helping to avoid vertical errors caused by human visual inspection. Deviations can be reduced, the precision of construction can be improved, and time can be greatly saved. Systematic numbering can simplify the material labeling process and help to quickly find and verify material information, especially when it comes to a variety of different types and specifications of floor panels, such as solid wood boards, particle boards, density boards, etc. An effective numbering system can reduce confusion and errors, help optimize the use of materials, and reduce waste. With a unified numbering system, communication between construction teams, designers, and suppliers will be smoother. Numbering, as a common language, can reduce misunderstandings and communication costs. When a floor needs to be replaced or repaired, systematic numbering can quickly locate the specific panel, which is convenient for later maintenance and management.
[0014] Preferably, after the plates are numbered, the marks are covered with tape or plastic film to prevent wear or dirt during subsequent transportation and installation.
[0015] Preferably, the ceiling is marked with a pencil, and the different colored areas of the ceiling are marked with stickers of different colors, and the colors of the stickers correspond one-to-one with the colors of the paint areas. Pencils are convenient for marking on wood or softer materials, and are easy to erase and modify. And by having labels of the same color correspond one-to-one with the paint areas, staff can be better reminded and the construction efficiency of staff can be improved.
[0016] Preferably, the construction mark is a tape mark, which is convenient for moving the construction mark after each construction is completed and can be quickly placed before the next construction, which is very convenient.
[0017] Preferably, the checkpoints are marked with dot markers, and the wet areas and reinforced areas are marked with spray paint. The small dot marks are clear and eye-catching, which are convenient for construction personnel to identify and locate. The dot marks take up little space and will not affect other marks or features around the checkpoints. They are small in size and easy to carry. Compared with easily erasable marking tools such as chalk, the wet areas and reinforced areas are marked with spray paint. Spray paint marks are more durable, especially in humid environments. They are not easily blurred or disappeared due to environmental changes. Spray paint marks are usually brightly colored, which are convenient for construction personnel to quickly identify and improve work efficiency. Whether it is a smooth metal surface or a rough concrete surface, it can ensure that the marks are clearly visible.
[0018] The beneficial effects of the present invention are as follows:
[0019] The present invention provides a complete and clear marking method. By marking on walls, floors and ceilings, the accurate installation of decoration components such as switches, sockets, doors, windows, cabinets, etc. can be ensured, and the direction of wires and water pipes can be clearly indicated, so as to help construction personnel understand the design intention and better plan the space layout, avoid space waste or aesthetic problems caused by unreasonable pipeline direction, help reduce errors in the construction process, such as wrong drilling position or improper pipeline installation, thereby avoiding rework and additional costs, speeding up construction, allowing workers to quickly find the required location, and reducing the time for measurement and positioning. Construction markings can alert workers to potential dangerous areas, such as power lines, pipelines or structural supports, thereby improving the safety of the construction site, and help project managers and designers track the construction progress to ensure that the project proceeds as planned. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 Schematic diagram of the labeling method of the present invention. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] Example:
[0023] like Figure 1 As shown, an embodiment of the present invention provides a method for marking a building decoration design project, comprising the following steps:
[0024] For wall marking, first determine the flatness of the wall using a wall detection tool, and mark the uneven areas of the wall. Then fill and polish the marked areas, and then determine the HVAC equipment and switch layout on the wall. Mark the direction of electrical sockets, switches, water pipes, and wires on the wall, reserve wall positions, and ensure the accurate installation of decorative components such as switches, sockets, doors, windows, and cabinets to ensure the safety and functionality of electrical installations. Finally, mark the reserved positions for doors and windows by drawing lines to avoid errors in subsequent construction. Use a dark pen to mark the walls, and use chalk to mark the direction of electrical sockets, switches, water pipes, and wires. Dark pen markings are easy for workers to identify. Chalk markings can clearly indicate the direction of wires and water pipes, helping construction workers understand the design intent and reduce errors and rework in construction. They are easy to erase and leave no traces, which can better plan space layout and avoid space waste or aesthetic problems caused by unreasonable pipeline directions. When installing switches and sockets, accurate markings help ensure the horizontal and vertical installation, making the panel installation smoother, improving the overall appearance, reducing material waste due to measurement errors, and improving material utilization efficiency.
[0025] Marking the floor, using floor detection tools to determine the flatness of the wall, marking the floor where there are depressions or cracks, repairing and leveling, cleaning the floor to ensure that the floor is flat, dry and dust-free, measuring the size of the room, determining the starting point and direction of the floor, using marking tools to mark reference lines on the floor to guide the flooring position, before laying, the boards should be tried out, the patterns and colors should be matched, and the numbers should be marked, and finally the positions of the floor drains and drainage outlets should be determined and marked, so as to avoid color differences and pattern mismatches, and ensure that the overall effect of the laid floor is coordinated and consistent; the floor markings are marked with markers, and the marking tools include a level and a vertical line marker. The board numbers are systematically numbered, and the systematic numbering is based on the installation order or specific pattern of the boards. After the boards are numbered, the marks are covered with tape or plastic film to prevent wear or dirt during subsequent handling and installation. Marker pen markings are durable and can quickly make clear and visible marks on the ground, improving work efficiency. They have bright colors and can be easily seen even in darker environments. They are water-resistant and will not fade even when used on wet ground. The markings on the ground can resist wear to a certain extent, especially in a short period of time, reducing errors and rework during construction and improving construction quality. The level can provide an accurate horizontal reference line, which is very important for objects that need to be installed horizontally. The vertical line marker can quickly mark accurate vertical lines on the wall, which is essential to ensure the vertical alignment of the structure and help avoid vertical errors caused by human visual inspection. Deviations can be reduced, the precision of construction can be improved, and time can be greatly saved. Systematic numbering can simplify the material labeling process and help to quickly find and verify material information, especially when it comes to a variety of different types and specifications of floor panels, such as solid wood boards, particle boards, density boards, etc. An effective numbering system can reduce confusion and errors, help optimize the use of materials, and reduce waste. With a unified numbering system, communication between construction teams, designers, and suppliers will be smoother. Numbering, as a common language, can reduce misunderstandings and communication costs. When a floor needs to be replaced or repaired, systematic numbering can quickly locate the specific panel, which is convenient for later maintenance and management.
[0026] Ceiling marking, determine the installation location of lighting equipment, vents, suspended ceilings and smoke alarms, including the frame outline of suspended ceilings, and the location of any recessed lamps or decorations. Use ceiling marking tools to mark them one by one to ensure the correct installation of safety facilities. When the ceiling is painted or decorated with wallpaper, different colored areas are marked separately. For those who plan to install audio equipment on the ceiling, the location of the audio should be marked on the ceiling to facilitate the pre-embedding of lines and the installation of equipment. The ceiling is marked with pencils, and different colored areas of the ceiling are marked with stickers of different colors, and the color of the stickers corresponds to the color of the paint area. Pencils are convenient for marking on wood or softer materials, easy to erase and modify, and the same color labels correspond to the paint area one by one, which can better remind staff and prevent improving staff's construction efficiency.
[0027] Construction markings are marked with tape, which is convenient for moving after each construction is completed, and can be quickly placed before the next construction, which is very convenient. When the staff is carrying out the construction, they need to set up safety warning signs in dangerous areas or areas where construction is in progress to ensure the safety of the construction workers, and mark the construction steps on the construction fence after the completion of each day, which helps the supervisor and the owner to supervise the construction progress and quality, find problems in time and deal with them. Through construction marking, the accuracy and consistency of each construction link can be ensured, the construction deviation can be reduced, and the final decoration quality can be guaranteed;
[0028] Special marking: during building decoration, checkpoints are marked for quality inspection during acceptance, and special marking is performed on wet areas and reinforced areas. Checkpoints are marked with dot markers, and wet areas and reinforced areas are marked with spray paint. The small dot markings are clear and eye-catching, which is convenient for construction personnel to identify and locate. The dot markings take up little space and will not affect other marks or features around the checkpoints. They are small in size and easy to carry. Compared with easily erasable marking tools such as chalk, wet areas and reinforced areas are marked with spray paint. Spray paint markings are more durable, especially in humid environments. They are not easily blurred or disappeared due to environmental changes. Spray paint markings are usually bright in color, which is convenient for construction personnel to quickly identify and improve work efficiency. Whether it is a smooth metal surface or a rough concrete surface, it can ensure that the markings are clearly visible. It helps to remind construction workers to take corresponding waterproof and moisture-proof measures, such as setting up concrete guide walls and ensuring smooth drainage, so as to reduce quality problems caused by moisture, such as mildew and corrosion. It serves as a guide for the construction process to ensure that the construction steps meet the quality requirements. For example, the drainage slope of the ground leveling layer must not be less than 1%. The control of these details is crucial to the final waterproof effect. For areas that need to be reinforced, special markings help to clarify the scope and methods of reinforcement, such as the application of grouting reinforcement technology, which can improve the bearing capacity and stability of the foundation or structure, which is crucial to the overall safety of the building.
[0029] Both the wall detection tool and the ground detection tool use 3D laser scanners. Traditional flatness detection methods usually require manual operation, which is time-consuming and inefficient. 3D laser scanners can quickly complete data acquisition, greatly improving the efficiency of detection, and can provide high-precision three-dimensional point cloud data. These data can accurately reflect the concave and convex features of the wall and the ground, making the detection results more accurate and reliable. In long-term applications, a lot of manpower and material costs can be saved. In addition, the use of 3D laser scanning technology for detection will not cause any damage to the wall and the ground. It is a non-contact detection method that is conducive to protecting the integrity of the wall and the ground.
[0030] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A marking method for a building decoration design project, characterized in that: The following steps are involved: Sp1: Wall marking: first determine the flatness of the wall using a wall detection tool, and mark the uneven parts of the wall. Then fill and polish the marked parts, determine the HVAC equipment and switch layout on the wall, mark the direction of electrical sockets, switches, water pipes and wires on the wall, reserve wall positions, and finally mark the reserved positions of doors and windows by drawing lines. Sp2: Floor marking: Use floor detection tools to determine the flatness of the wall, mark the floor where there are depressions or cracks, and after repairing them to make them flat, measure the size of the room, determine the starting point and direction of floor laying, and use marking tools to mark reference lines on the floor to guide the laying position of the floor. Before laying, the boards should be tried out, the patterns and colors should be matched, and they should be marked and numbered. Finally, the positions of floor drains and drainage outlets should be determined and marked. Sp3: Ceiling marking, determine the installation locations of lighting equipment, vents, ceilings and smoke alarms, and use ceiling marking tools to mark them one by one. When the ceiling is painted or decorated with wallpaper, mark the different colored areas separately; Sp4: Construction marking. When workers are carrying out construction, they need to set up safety warning signs in dangerous areas or areas under construction to ensure the safety of construction workers. After completing work every day, they need to mark the construction steps on the construction fence to help supervisors and owners monitor the progress and quality of construction, and identify and handle problems in a timely manner. Sp5: Special marking, when carrying out building decoration, mark the inspection points for quality inspection during acceptance, and make special markings for wet areas and reinforced areas.
2. A marking method for building decoration design engineering according to claim 1, characterized in that: The wall detection tool and the ground detection tool both use 3D laser scanners.
3. A marking method for building decoration design engineering according to claim 1, characterized in that: The wall markings are marked with a dark pen, and the electrical sockets, switches, and the directions of water pipes and wires are marked with chalk.
4. A marking method for building decoration design engineering according to claim 1, characterized in that: The ground marking is performed with a marker pen, the marking tools include a level and a vertical line marker, and the plate numbering is performed with a systematic numbering, which is performed according to the installation sequence or a specific pattern of the plates.
5. A marking method for building decoration design engineering according to claim 4, characterized in that: After the plates are numbered, the markings are covered with tape or plastic film.
6. A marking method for building decoration design engineering according to claim 1, characterized in that: The ceiling is marked with a pencil, and the areas of different colors on the ceiling are marked with stickers of different colors, and the colors of the stickers correspond to the colors of the paint areas one by one.
7. A marking method for building decoration design engineering according to claim 1, characterized in that: The construction marks are made by using adhesive tape.
8. A marking method for building decoration design engineering according to claim 1, characterized in that: The inspection points are marked with dot markers and the wet areas and reinforced areas are marked with spray paint.
Citation Information
Patent Citations
Full projection paying-off method
CN106320707A
Indoor lofting construction method
CN109930863A
Domestic identifier laying-off method
CN110748172A
BIM-based construction and decoration method
WO2018145510A1