Intelligent control method for grouting quality of super-long pipe shed of shallow-buried tunnel of high-speed rail

Through the intelligent control system, the grouting parameters are monitored and adjusted in real time, the problems of grouting in the existing technology are solved, and an efficient and safe grouting process is achieved, and material waste and environmental pollution are reduced.

CN118911713AInactive Publication Date: 2024-11-08CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1

Patent Information

Application Number
CN202410959646.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the grouting process is difficult to accurately control the uniform distribution of slurry in the pipe shed, which can easily lead to insufficient local strata reinforcement, increase construction risks, and lack of real-time monitoring and feedback systems, resulting in waste of materials and environmental pollution.

Method used

The intelligent control system is adopted to collect data during the grouting process through sensors in real time, analyze and adjust grouting parameters in real time, and dynamic adjustment strategies are used to ensure the uniform distribution of the slurry and grouting effect, providing abnormal warnings and emergency treatment.

Benefits of technology

The uniform distribution of slurry is achieved, the construction risks are reduced, the grouting efficiency is improved, material waste and environmental pollution are reduced, and construction safety and quality are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911713A_ABST
    Figure CN118911713A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent control method for grouting quality of a super-long pipe shed of a shallow-buried tunnel of a high-speed rail. The intelligent control method comprises the following steps that S1, a grouting material is prepared, the slurry proportion is adjusted, a grouting pump and a stirrer are started, and grouting operation is started; s2, a sensor collects data such as pressure, flow, concentration and temperature in the grouting process in real time, and continuity and accuracy of the data are ensured; s3, transmitting real-time data to an intelligent control center through a data acquisition and transmission system, analyzing and processing various parameters monitored by a sensor network in real time, and transmitting the data to an intelligent control system in real time; according to the intelligent control method for the grouting quality of the super-long pipe shed of the shallow-buried tunnel of the high-speed rail, the grouting uniformity and effect are improved, slurry loss and leakage are reduced through real-time monitoring and control, the grouting efficiency is improved, the construction risk is reduced through an abnormal early warning and emergency treatment system, the construction safety is ensured, the construction efficiency is improved through automatic and intelligent control, and the construction cost is reduced. And the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of engineering technology, and in particular to an intelligent control method for grouting quality of an ultra-long pipe shed in a shallow buried tunnel of a high-speed railway. Background Art

[0002] With the large-scale development of high-speed railway construction, a large number of shallow tunnels have emerged, posing a huge challenge to the stability and construction safety of the tunnels. Pipe-roof support is a common support method for shallow tunnel construction. Before tunnel excavation, steel pipes are pre-set along the perimeter of the tunnel and grouting is performed inside the steel pipes to effectively support the surrounding strata and reduce the risk of surface settlement and collapse.

[0003] The grouting process is the core step of the pipe-roof construction method. Slurry (such as cement slurry, chemical slurry, etc.) is injected into the pipe-roof to fill the gaps in the stratum, improve the strength and stability of the stratum, and then form an overall force system with the pipe-roof. However, there are many uncertainties in the grouting process in the prior art, such as the slurry ratio, grouting pressure, flow rate, etc., which make it difficult to control the grouting quality, and easily lead to problems such as uneven grouting, slurry leakage, and insufficient grouting. Especially when the length of the pipe-roof increases, the grouting quality is more difficult to guarantee. Among them, the grouting technology in the prior art is difficult to accurately control the distribution of slurry in the pipe-roof, and uneven grouting is prone to occur, which may lead to insufficient reinforcement of local strata, thereby affecting the stability of the tunnel. Under complex geological conditions, the slurry is easy to Loss or leakage through cracks, voids and other paths will result in the failure to achieve the expected reinforcement effect. In addition, slurry leakage may also pollute groundwater resources and bring environmental problems. The grouting process is affected by many factors, such as formation conditions, grouting pressure, flow rate, etc., and existing methods are difficult to monitor and adjust in real time. This uncertainty increases the construction risk and may cause surface subsidence, tunnel deformation and other problems. Existing grouting technology relies on manual experience and operation, and it is difficult to accurately control grouting parameters (such as pressure, flow, slurry ratio, etc.), which not only affects the construction quality, but also may lead to material waste and increase construction costs. The existing technology lacks advanced real-time monitoring and feedback systems, and cannot promptly warn and deal with abnormal situations during the grouting process, resulting in the accumulation of problems and construction quality risks. Summary of the invention

[0004] The purpose of the present invention is to provide an intelligent control method for the grouting quality of super-long pipe-roof in shallow buried tunnels of high-speed railways, so as to solve the problem that the existing technology may lead to insufficient reinforcement of local strata, thereby affecting the stability of the tunnel. Under complex geological conditions, slurry is easy to lose or leak through cracks, gaps and other paths, resulting in the expected reinforcement effect cannot be achieved. The existing method is difficult to monitor and adjust in real time. This uncertainty increases the construction risk and may cause problems such as surface settlement and tunnel deformation. The existing grouting technology relies on manual experience and operation, and it is difficult to accurately control grouting parameters (such as pressure, flow, slurry ratio, etc.), which not only affects the construction quality, but also may cause material waste and increase construction costs. The existing technology lacks advanced real-time monitoring and feedback systems, and cannot timely warn and handle abnormal situations during the grouting process, resulting in the accumulation of problems and hidden dangers in construction quality.

[0005] To achieve the above object, the present invention provides the following technical solution: a method for intelligently controlling the grouting quality of an ultra-long pipe shed in a shallow buried tunnel of a high-speed railway, the method comprising the following steps:

[0006] S1: Prepare grouting materials, adjust the slurry ratio, start the grouting pump and mixer, and start the grouting operation;

[0007] S2: The sensor collects data such as pressure, flow, concentration, temperature, etc. during the grouting process in real time to ensure the continuity and accuracy of the data;

[0008] S3: Through the data acquisition and transmission system, the real-time data is transmitted to the intelligent control center for analysis and processing. The sensor network monitors various parameters in real time, and the data is transmitted to the intelligent control system in real time;

[0009] S4: The intelligent control system performs real-time analysis on the transmitted data to determine whether the various parameters in the grouting process meet the design requirements;

[0010] S5: Based on the analysis results, the intelligent control system automatically adjusts the grouting parameters to ensure uniform distribution of the slurry and the grouting effect.

[0011] Preferably, the data collection operation in step S2 is implemented by using a pressure sensor, a flow meter, and a density meter at the end of the grouting pipe to monitor the slurry pressure state in the pipe shed, the amount of slurry injected into the pipe shed, and the slurry concentration state in real time.

[0012] Preferably, the intelligent control system can dynamically adjust the grouting strategy according to changes in formation conditions and construction conditions.

[0013] Preferably, the intelligent control system continuously learns and improves by applying machine learning and optimization algorithms.

[0014] Preferably, the intelligent control system analyzes monitoring data in real time, detects and identifies possible abnormal situations, and when an abnormal situation is detected, the system immediately feeds back to the control center and automatically adjusts the grouting parameters to cope with the abnormal situation.

[0015] Preferably, the intelligent control system uses artificial intelligence and machine learning algorithms to automatically adjust grouting parameters according to real-time monitoring data to ensure uniform distribution of slurry and grouting effect. The adaptive control algorithm can be dynamically adjusted according to changes in formation conditions and construction conditions.

[0016] Preferably, the grouting equipment can accurately control the grouting amount, grouting speed and slurry ratio to ensure uniform injection of the slurry during the construction process.

[0017] It can be seen from the above technical solution that the present invention has the following beneficial effects:

[0018] The intelligent control method for grouting quality of ultra-long pipe-roof in shallow buried tunnel of high-speed railway ensures uniform distribution of slurry through intelligent control system, avoids uneven grouting problem, improves grouting uniformity and effect, reduces slurry loss and leakage through real-time monitoring and control, improves grouting efficiency, reduces construction risk and ensures construction safety, and improves construction efficiency through automation and intelligent control, reduces material waste and construction cost. It solves the problem that the existing technology may lead to insufficient reinforcement of local strata, thus affecting the stability of the tunnel. Under complex geological conditions, slurry is easy to lose or leak through cracks, gaps and other paths, resulting in the inability to achieve the expected reinforcement effect. The existing method is difficult to monitor and adjust in real time. This uncertainty increases the construction risk and may cause problems such as surface settlement and tunnel deformation. The existing grouting technology relies on manual experience and operation, and it is difficult to accurately control grouting parameters (such as pressure, flow, slurry ratio, etc.), which not only affects the construction quality, but also may cause material waste and increase construction cost. The existing technology lacks advanced real-time monitoring and feedback system, and cannot timely warn and handle abnormal conditions in the grouting process, resulting in the accumulation of problems and construction quality hidden dangers. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 is a flow chart of the method of the present invention;

[0020] Figure 2 It is a schematic structural diagram of the grouting device of the present invention.

[0021] In the figure: 1. Extra-long steel pipes of the pipe rack; 2. Grouting holes; 3. Sensor system; 4. Data processing and display system; 5. Grouting pipe; 6. Valve; 7. Grouting pump; 8. Slurry pool. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0023] like Figure 1 and Figure 2 As shown, a method for intelligently controlling the grouting quality of an ultra-long pipe shed in a shallow buried tunnel of a high-speed railway is provided, and the method comprises the following steps:

[0024] S1: Prepare grouting materials, adjust the slurry ratio, start the grouting pump and mixer, and start the grouting operation;

[0025] S2: The sensor collects data such as pressure, flow, concentration, temperature, etc. during the grouting process in real time to ensure the continuity and accuracy of the data;

[0026] S3: Through the data acquisition and transmission system, the real-time data is transmitted to the intelligent control center for analysis and processing. The sensor network monitors various parameters in real time, and the data is transmitted to the intelligent control system in real time;

[0027] S4: The intelligent control system performs real-time analysis on the transmitted data to determine whether the various parameters in the grouting process meet the design requirements;

[0028] S5: Based on the analysis results, the intelligent control system automatically adjusts the grouting parameters to ensure uniform distribution of the slurry and the grouting effect.

[0029] The pressure sensor, flow meter and density meter at the end of the grouting pipe monitor the slurry pressure state, the amount of slurry injected into the pipe shed and the slurry concentration state in real time. Before grouting, the equipment is debugged to ensure the normal operation of the data acquisition and transmission system. According to the design requirements, the grouting materials, such as cement slurry, chemical slurry, etc., are prepared, and the slurry ratio is adjusted to ensure that the engineering requirements are met. Under the guidance of the intelligent control system, the grouting pump and the mixer are started to start the grouting operation. The grouting pump 7 is connected to the slurry pool 8 through a pipeline, and the other end of the grouting pump 7 is also connected to another pipeline. The end of the pipeline is provided with a sensor system 3. Multiple grouting holes 2 are opened on the super-long pipe shed steel pipe 1. The pipeline on the grouting pump 7 goes deep into the super-long pipe shed steel pipe 1. The sensor system 3 is electrically connected to the data processing and display system 4. The sensor system 3 collects data such as pressure, flow, concentration, temperature, etc. in real time during the grouting process to ensure the continuity and accuracy of the data. Through the data acquisition and transmission system, real-time data is transmitted to the intelligent control center for analysis and processing. The sensor network monitors various parameters in real time, and the data is transmitted to the intelligent control system in real time. The intelligent control system analyzes the transmitted data in real time to determine whether the various parameters in the grouting process meet the design requirements. According to the analysis results, the intelligent control system automatically adjusts the grouting parameters (such as grouting pressure, flow, slurry ratio, etc.) to ensure the uniform distribution of slurry and the grouting effect. The intelligent control system can dynamically adjust the grouting strategy according to the changes in the formation conditions and construction conditions to ensure the stability and reliability of the construction process. By applying machine learning and optimization algorithms, the system can continuously learn and improve to improve the accuracy and efficiency of the grouting process. The sensor network continuously monitors all parameters in the grouting process to ensure the real-time and integrity of the data. The intelligent control system analyzes the monitoring data in real time, detects and identifies possible abnormal conditions, such as slurry leakage, pressure abnormality, etc. When an abnormal situation is detected, the system immediately feeds back to the control center and automatically adjusts the grouting parameters to deal with the abnormality. If a serious abnormality occurs, the emergency treatment mechanism is activated and corresponding emergency measures are taken to ensure construction safety.

[0030] Furthermore, it is equipped with an advanced sensor network to monitor in real time the key parameters of the grouting process, such as grouting pressure, flow, slurry concentration, temperature, etc. The real-time monitoring data is fed back to the control center through the data acquisition and transmission system, which is convenient for timely parameter adjustment and decision-making. Artificial intelligence and machine learning algorithms are used to automatically adjust the grouting parameters according to the real-time monitoring data to ensure uniform distribution of the slurry and the grouting effect. The adaptive control algorithm can be dynamically adjusted according to the changes in the formation conditions and construction conditions, improving the stability and reliability of the grouting process. The use of high-precision grouting equipment can accurately control the grouting amount, grouting speed and slurry ratio to ensure uniform slurry injection during construction. The equipment should have automatic operation functions to reduce manual intervention and improve construction efficiency and accuracy. It has strong data storage and analysis capabilities to record and store all data during the construction process for subsequent analysis and optimization. The data analysis system can generate construction reports, evaluate the grouting effect, and provide reference and improvement suggestions for future construction projects. It is equipped with an intelligent early warning system that can timely identify and warn of abnormal situations such as slurry leakage and formation instability based on monitoring data, establish an emergency response mechanism, and take quick measures to reduce risks and losses when abnormalities occur. This setting can effectively solve the problems existing in the existing pipe-roof grouting technology, improve grouting quality and construction efficiency, reduce construction risks and environmental impacts, and reduce slurry loss and leakage through real-time monitoring and control, improve grouting efficiency, abnormal early warning and emergency response systems reduce construction risks and ensure construction safety. Automation and intelligent control improve construction efficiency, reduce material waste, and reduce construction costs.

[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An intelligent control method for grouting quality of ultra-long pipe shed in shallow buried tunnel of high-speed railway, characterized in that: The method comprises the following steps: S1: Prepare grouting materials, adjust the slurry ratio, start the grouting pump and mixer, and start the grouting operation; S2: The sensor collects data such as pressure, flow, concentration, temperature, etc. during the grouting process in real time to ensure the continuity and accuracy of the data; S3: Through the data acquisition and transmission system, the real-time data is transmitted to the intelligent control center for analysis and processing. The sensor network monitors various parameters in real time, and the data is transmitted to the intelligent control system in real time; S4: The intelligent control system performs real-time analysis on the transmitted data to determine whether the various parameters in the grouting process meet the design requirements; S5: Based on the analysis results, the intelligent control system automatically adjusts the grouting parameters to ensure uniform distribution of the slurry and the grouting effect.

2. According to claim 1, a method for intelligently controlling grouting quality of an ultra-long pipe shed in a high-speed railway shallow tunnel is characterized by: The data collection in step S2 is specifically implemented by using a pressure sensor, a flow meter, and a density meter at the end of the grouting pipe to monitor the slurry pressure state in the pipe shed, the amount of slurry injected into the pipe shed, and the slurry concentration state in real time.

3. According to claim 1, a method for intelligently controlling grouting quality of an ultra-long pipe shed in a high-speed railway shallow tunnel is characterized by: The intelligent control system can dynamically adjust the grouting strategy according to changes in formation conditions and construction conditions.

4. According to claim 1, a method for intelligently controlling grouting quality of an ultra-long pipe shed in a high-speed railway shallow tunnel is characterized by: The intelligent control system continuously learns and improves by applying machine learning and optimization algorithms.

5. According to claim 1, a method for intelligently controlling grouting quality of an ultra-long pipe shed in a high-speed railway shallow tunnel is characterized by: The intelligent control system analyzes monitoring data in real time, detects and identifies possible abnormal situations. When an abnormal situation is detected, the system immediately feeds back to the control center and automatically adjusts the grouting parameters to cope with the abnormal situation.

6. The intelligent control method for grouting quality of ultra-long pipe shed in shallow buried tunnel of high-speed railway according to claim 1 is characterized by: The intelligent control system uses artificial intelligence and machine learning algorithms to automatically adjust grouting parameters according to real-time monitoring data to ensure uniform distribution of slurry and grouting effect. The adaptive control algorithm can be dynamically adjusted according to changes in ground conditions and construction situations.

7. The intelligent control method for grouting quality of ultra-long pipe shed in shallow buried tunnel of high-speed railway according to claim 1 is characterized by: The grouting equipment can accurately control the grouting amount, grouting speed and slurry ratio to ensure uniform injection of slurry during the construction process.

Citation Information

Patent Citations

  • Tunnel supporting grouting equipment and grouting method thereof

    CN107489432A

  • Intelligent grouting pressure controller and intelligent grouting method

    CN112506242A

  • Intelligent existing building grouting lifting monitoring system

    CN113700061A

  • Tunnel long pipe shed digital twin body and fine modeling system and method

    CN115062368A

  • Intelligent engineering grouting servo control and early warning system and using method thereof

    CN118244705A

Cited By

  • Tunnel leaking stoppage reinforcement construction management monitoring system based on statistical analysis

    CN119228081A

  • Hole sealing and grouting method and device special for flexible gas hole sealing material

    CN120211673A

  • Special sealing grouting method and device for flexible gas sealing material

    CN120211673B