Glass insulator thermal shock test equipment and test method
By introducing a drive structure and a sealing structure into the glass insulator thermal shock testing equipment, the problems of difficulty in moving the placement frame and insufficient stability of the insulator in traditional tests were solved, and efficient thermal shock test and heating effects were achieved.
Patent Information
- Application Number
- CN202410973193.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2024-11-08
AI Technical Summary
In thermal shock test, traditional glass insulators cannot move quickly due to the insulator, which makes it difficult to operate when the temperature changes sharply, affects the test effect, and lacks fixed limit components, which can easily lead to insulator damage.
A glass insulator thermal shock testing equipment was designed, including a test machine, a drive structure, an extension structure, a pick-up structure, a limit structure and a sealing structure. The drive structure realizes rapid movement and sealing of the placement frame to ensure that the insulator is heated and cooled. Stability and safety in the process.
The efficiency and effect of thermal shock test of insulators is improved, the operation difficulty is reduced, the stability of the placement frame and the transport stability of the insulators are enhanced, the heat loss is reduced, and the heating effect is improved.
Smart Images

Figure CN118913981A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of thermal shock test equipment, in particular to a thermal shock test equipment and a test method for a glass insulator. Background Art
[0002] Insulators are generally made of glass and porcelain; they are mainly used to fix conductors on poles and insulate the conductors from poles. Insulators are one of the key components of high-voltage transmission lines, and their performance directly affects the safe operation of the entire transmission line. Glass insulators need to undergo multiple tests during production to detect their various production indicators. Thermal shock test is one of them. Thermal shock test refers to an important indicator for evaluating the material's ability to resist damage when subjected to rapid temperature changes.
[0003] However, when a traditional glass insulator is subjected to a thermal shock test, the temperature rises sharply, making it inconvenient to take the placement frame and the glass insulator out of the oven, and the placement frame cannot be quickly transferred to the cooling tank, thus affecting the test effect of the glass insulator. The placement frame is located in the exact center of the cooling tank and the drying oven, so it is far from the edge of the testing machine, making it inconvenient to quickly place the glass insulator in the placement frame. There is no fixed limit assembly inside the placement frame, and when the glass insulator is transported, multiple glass insulators are prone to collision due to inertia, causing damage to the glass insulator. Summary of the invention
[0004] In view of the problems in the prior art, the present invention provides a glass insulator thermal shock test device and a test method.
[0005] The technical solution adopted by the present invention to solve the technical problem is: a glass insulator thermal shock test equipment, including a test machine, a test structure arranged on the test machine, a driving structure arranged on the test machine, an extension structure arranged on the driving structure, a pick-and-place structure arranged on the extension structure, a limit structure arranged on the extension structure, a placement frame hung on the pick-and-place structure, a fixing structure arranged inside the placement frame, a sealing structure arranged on the test machine, and an insulator body installed on the fixing structure;
[0006] The test structure includes a drying box and a cooling pool. The drying box and the cooling pool are arranged inside the test machine. A water inlet pipe and a water outlet pipe are fixedly connected to the cooling pool.
[0007] The driving structure includes four fixed plates and a first motor fixedly connected to one of the fixed plates, wherein two first guide rods are fixedly connected between the two fixed plates, an output end of the first motor is fixedly connected to a first screw, the first screw is rotatably connected to the other two fixed plates, and another first guide rod is fixedly connected to the two fixed plates, a slide plate is slidably connected to the lower one of the first guide rods, another slide plate is slidably connected to the upper two first guide rods, the first screw is threadedly connected to the lower slide plate, a second guide rod is fixedly connected between the two slide plates, the lower slide plate is fixedly connected to the second motor, the output end of the second motor is fixedly connected to a second screw, the second screw is rotatably connected to the two slide plates, a sliding bar is threadedly connected to the second screw, the sliding bar is slidably connected to the second guide rod, and an extension structure is provided on the sliding bar.
[0008] Specifically, the extension structure includes a slide rail and a pressure strip slidably connected to the slide rail, the slide bar is slidably connected to the slide rail with a T-shaped cross-section, the cross-section of the pressure strip is an L-shaped structure, a pressure block is fixedly connected to the pressure strip, a first spring is fixedly connected between the pressure strip and the slide rail, a block with a trapezoidal cross-section is fixedly connected to the pressure strip, the block is slidably connected to the slide rail, two slots are provided on the slide bar, the block is engaged with one of the slots, and a connecting frame with a T-shaped cross-section is fixedly connected to the slide rail.
[0009] Specifically, a guide shaft passes through the interior of the first spring, two ends of the guide shaft are fixedly connected to the interior of the slide rail, and the pressure strip is slidably connected to the guide shaft.
[0010] Specifically, the picking and placing structure includes a fixed block and a fixed rod, four fixed blocks are fixedly connected to the connecting frame, a fixed rod is fixedly connected to the fixed block, a fixed shaft is fixedly connected to the fixed block, a hanging bar is slidably connected to the fixed rod, the hanging bar is slidably connected to the fixed shaft, a second spring is fixedly connected between the hanging bar and the fixed block, a placement frame is hung on two of the hanging bars, two fixing ears are fixedly connected to the placement frame, a fixing groove is provided on the fixing ear, the hanging bar is engaged with the fixing groove, a resist block is fixedly connected to the hanging bar, two fixing bars are fixedly connected to the interior of the drying box, and rollers are installed on the fixing bars.
[0011] Specifically, the cross section of the bottom end of the suspension bar is a U-shaped structure, the top surface of the fixing ear is inclined, and the cross section of the stop block is a trapezoidal structure.
[0012] Specifically, the limiting structure includes a mounting frame and a pull rod slidably connected to the mounting frame, two mounting frames with U-shaped cross-sections are fixedly connected to the connecting frame, a stopper with a trapezoidal cross-section is fixedly connected to the pull rod, a third spring is fixedly connected between the stopper and the mounting frame, a pull ring is fixedly connected to the pull rod, a slider is fixedly connected to the suspension bar, and the slider is slidably connected to the connecting frame.
[0013] Specifically, the fixing structure includes a mounting seat and a slot provided on the mounting seat, four mounting seats are fixedly connected to the placement frame, a mounting seat and an insertion rod are fixedly connected to each of the insulator bodies, the insertion rod on one of the insulator bodies is plugged into the slot on the mounting seat on another insulator body, and the insertion rods on the four bottom insulator bodies are plugged into the slots on the four mounting seats on the placement frame.
[0014] Specifically, the cross-section of the insertion rod is a T-shaped structure, the cross-section of the slot is a T-shaped structure, a pressure plate is slidably connected to the mounting seat, a positioning rod with a square cross-section is fixedly connected to the pressure plate, the positioning rod is slidably connected to the mounting seat, a positioning hole with a square cross-section is provided on the insertion rod, the positioning rod is engaged with the positioning hole, a fourth spring is fixedly connected between the pressure plate and the mounting seat, a lifting block is fixedly connected to the pressure plate, and the lifting block is slidably connected to the mounting seat.
[0015] Specifically, the sealing structure includes a fixed frame and a sealing plate slidably connected to the fixed frame, the testing machine is fixedly connected to the fixed frame, the testing machine is fixedly connected to two mounting bars, the mounting bars are provided with mounting grooves, the sealing plate is engaged with the mounting grooves, a sliding frame is slidably connected to the drying box, a fifth spring is fixedly connected between the sliding frame and the drying box, a sliding rod passes through the interior of the fifth spring, one end of the sliding rod is fixedly connected to the sliding frame, the other end of the sliding rod is slidably connected to the drying box, a sealing groove is provided on the sealing plate, the sliding frame is engaged with the sealing groove, the cross-section of one side of the sliding frame is a trapezoidal structure, the cross-section of the end of the sealing plate is a trapezoidal structure, and two handles are fixedly connected to the sealing plate.
[0016] A test method for a glass insulator thermal shock test device comprises the following steps:
[0017] S1: First, the placement frame is unfolded by the stretching structure, and then the insulator body is fixed inside the placement frame by the fixing structure, and then the placement frame is moved to the top of the test structure by the stretching structure;
[0018] S2: When it is necessary to perform a thermal shock test on the insulator body, the driving structure is started, the position of the placement frame is transferred through the driving structure, and the thermal shock test is performed on the insulator body through the test structure to detect the anti-breakage ability of the insulator body;
[0019] S3: When the insulator body is subjected to a thermal shock test, the driving structure drives the placement frame to be lowered into the interior of the heating box, the placement frame is limited by the pick-and-place structure, and the pick-and-place structure is limited by the limiting structure. After the driving structure drives the pick-and-place structure to rise, the sealing structure is moved to seal the heating box, and then the insulator body is heated. After the heating is completed, the sealing structure is opened, and then the placement frame and the insulator body are taken out by the driving structure in cooperation with the pick-and-place structure.
[0020] The beneficial effects of the present invention are:
[0021] (1) In the glass insulator thermal shock test equipment and test method described in the present invention, an extension structure is provided on the test machine, and a placement frame is unfolded by the extension structure, which facilitates the placement of the insulator body inside the placement frame, thereby reducing the difficulty of operation.
[0022] (2) The glass insulator thermal shock test equipment and test method described in the present invention are provided with a driving structure on the test machine, and a test structure is provided on the test machine. The test structure is used to perform a thermal shock test on the insulator body, and the placement frame and the insulator body are driven to move by the driving structure, thereby accelerating the transfer efficiency of the insulator body in the thermal shock test, thereby improving the test effect.
[0023] (3) The glass insulator thermal shock test equipment and test method described in the present invention have a pick-up and place structure on the slide rail and a limit structure on the connecting frame. The placement frame can be quickly placed and taken out by the pick-up and place structure, and the suspension bar can be limited by the limit structure, thereby improving the stability of the suspension placement frame.
[0024] (4) In the glass insulator thermal shock test equipment and test method described in the present invention, a fixed structure is provided on the placement frame, and the insulator body is fixed and limited by the fixed structure, thereby avoiding shaking of the insulator body during transportation and improving the stability of the insulator body during transportation.
[0025] (5) The glass insulator thermal shock test equipment and test method described in the present invention have a sealing structure on the test machine, which seals the drying box through the sealing structure, thereby reducing heat loss and improving the heating effect of the drying box on the insulator body. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0027] Figure 1 A schematic diagram of the overall structure of a preferred embodiment of a glass insulator thermal shock test device provided by the present invention;
[0028] Figure 2 for Figure 1An enlarged schematic diagram of the structure of section A is shown;
[0029] Figure 3 for Figure 1 An enlarged schematic diagram of the structure of part B is shown;
[0030] Figure 4 It is a schematic diagram of the connection structure between the testing machine and the testing structure of the present invention;
[0031] Figure 5 for Figure 4 An enlarged schematic diagram of the C-section structure is shown;
[0032] Figure 6 for Figure 4 An enlarged schematic diagram of the D-section structure is shown;
[0033] Figure 7 for Figure 6 An enlarged schematic diagram of the structure of part E is shown;
[0034] Figure 8 It is a schematic diagram of the connection structure between the placement frame and the fixing ears of the present invention;
[0035] Fig. 9 for Figure 8 The enlarged schematic diagram of the F part structure is shown;
[0036] Fig.10 It is a schematic diagram of the connection structure between the second screw rod and the slide bar of the present invention;
[0037] Fig.11 for Fig.10 The enlarged schematic diagram of the G-section structure shown;
[0038] Fig.12 It is a schematic diagram of the connection structure between the testing machine and the driving structure of the present invention.
[0039] In the figure: 1. testing machine; 2. testing structure; 201. drying box; 202. cooling pool; 203. water inlet pipe; 204. water outlet pipe; 3. driving structure; 301. fixing plate; 302. first motor; 303. first screw rod; 304. first guide rod; 305. sliding plate; 306. second motor; 307. second screw rod; 308. slide bar; 309. second guide rod; 4. stretching structure; 401. slide rail; 402. pressure bar; 403. pressure block; 404. guide shaft; 405. first spring; 406. card block; 407. card slot; 408. connecting frame; 5. pick-and-place structure; 501. fixing block; 502. fixing rod; 503. hanging bar; 504. second spring; 505. fixing shaft; 5 06, fixing ear; 507, stop block; 508, fixing groove; 509, fixing strip; 510, roller; 6, limiting structure; 601, mounting frame; 602, pull rod; 603, stop block; 604, third spring; 605, slider; 606, pull ring; 7, fixing structure; 701, mounting seat; 702, slot; 703, plug rod; 704, pressure plate; 705, positioning rod; 706, positioning hole; 707, fourth spring; 708, lifting block; 8, sealing structure; 801, fixing frame; 802, sealing plate; 803, mounting strip; 804, mounting groove; 805, sliding frame; 806, sliding rod; 807, fifth spring; 808, sealing groove; 809, handle; 9, placement frame; 10, insulator body. DETAILED DESCRIPTION
[0040] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0041] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Fig.10 , Fig.11 and Fig.12 As shown, a glass insulator thermal shock test device according to the present invention comprises a test machine 1, a test structure 2 arranged on the test machine 1, a driving structure 3 arranged on the test machine 1, an extension structure 4 arranged on the driving structure 3, a pick-and-place structure 5 arranged on the extension structure 4, a limit structure 6 arranged on the extension structure 4, a placement frame 9 hung on the pick-and-place structure 5, a fixing structure 7 arranged inside the placement frame 9, a sealing structure 8 arranged on the test machine 1, and an insulator body 10 installed on the fixing structure 7;
[0042] The test structure 2 includes a drying box 201 and a cooling pool 202. The drying box 201 and the cooling pool 202 are provided inside the test machine 1. The cooling pool 202 is fixedly connected with a water inlet pipe 203 and a water outlet pipe 204.
[0043] The driving structure 3 includes four fixed plates 301 and a first motor 302 fixedly connected to one of the fixed plates 301, wherein two first guide rods 304 are fixedly connected between the two fixed plates 301, a first screw 303 is fixedly connected to the output end of the first motor 302, the first screw 303 is rotatably connected to the other two fixed plates 301, and another first guide rod 304 is fixedly connected to the two fixed plates 301, a slide plate 305 is slidably connected to the lower first guide rod 304, and another slide plate 305 is slidably connected to the upper two first guide rods 304, and the first screw 30 3 is threadedly connected to the slide plate 305 below, a second guide rod 309 is fixedly connected between the two slide plates 305, a second motor 306 is fixedly connected to the slide plate 305 below, a second screw 307 is fixedly connected to the output end of the second motor 306, the second screw 307 is rotatably connected to the two slide plates 305, a slide bar 308 is threadedly connected to the second screw 307, the slide bar 308 is slidably connected to the second guide rod 309, and a stretching structure 4 is provided on the slide bar 308; during the thermal shock test, the second motor 306 can be started, the second motor 306 drives the second screw 307 to rotate, and the second screw 307 rotates to drive the slide bar 3 08 moves up and down, the slide bar 308 moves up and down, thereby driving the pick-and-place structure 5 and the placement frame 9 to move up and down, the placement frame 9 and the insulator body 10 move downward to the inside of the drying box 201, the pick-and-place structure 5 removes the placement frame 9, and then drives the second motor 306 to drive the second screw 307 to rotate in the opposite direction, thereby driving the slide bar 308 to rise, after the slide bar 308 rises, the sealing structure 8 is started to seal the drying box 201, and then the temperature of the drying box 201 is set, and after the insulator body 10 is heated for a period of time, the sealing structure 8 is opened, and then the placement frame 9 and the insulator body 10 are taken out through the pick-and-place structure 5, and after taking them out, the first motor 302 is started, and the first motor 30 The first screw rod 303 is driven to rotate, and the rotation of the first screw rod 303 drives the slide plate 305 to move. The slide plate 305 moves horizontally, and then drives the second guide rod 309 and the slide bar 308 on the second screw rod 307 to move horizontally, and then drives the pick-and-place structure 5 and the placement frame 9 to move horizontally. Then, the second motor 306 is started, and then the placement frame 9 is suspended inside the cooling pool 202. At the same time, the valves of the water inlet pipe 203 and the water outlet pipe 204 are opened, and the water flow simulates the low temperature environment, and then the thermal shock test of the insulator body 10 is completed. The setting of the first guide rod 304 improves the sliding stability of the two slide plates 305, and the setting of the second guide rod 309 improves the sliding stability of the slide bar 308.
[0044] Specifically, Figure 3 , Figure 6 and Fig.11As shown, the extension structure 4 includes a slide rail 401 and a pressure strip 402 slidably connected to the slide rail 401, the slide bar 308 is slidably connected to the slide rail 401 with a T-shaped cross-section, the cross-section of the pressure strip 402 is an L-shaped structure, the pressure strip 402 is fixedly connected to a pressure block 403, a first spring 405 is fixedly connected between the pressure strip 402 and the slide rail 401, a block 406 with a trapezoidal cross-section is fixedly connected to the pressure strip 402, the block 406 is slidably connected to the slide rail 401, the slide bar 308 is provided with two slots 407, the block 406 is engaged with one of the slots 407, and a connecting frame 408 with a T-shaped cross-section is fixedly connected to the slide rail 401; a guide shaft 404 is passed through the interior of the first spring 405, and both ends of the guide shaft 404 are fixedly connected to the interior of the slide rail 401, and the pressure strip 402 slides with the guide shaft 404 When the insulator body 10 needs to be placed, the pressing block 403 can be pressed downward, and the pressing block 403 descends, thereby driving the pressure strip 402 to descend, the first spring 405 is compressed, the pressure strip 402 descends, thereby driving the card block 406 to slide, and the card block 406 is no longer engaged with the card slot 407 on the slide bar 308. At this time, the slide rail 401 can be slid, and the slide rail 401 drives the connecting frame 408 to slide outward, thereby driving the pick-up and placement structure 5 and the placement frame 9 on the connecting frame 408 to slide out, and then release the pressing block 403, the first spring 405 resets, thereby driving the pressure strip 402 to reset, and then driving the card block 406 to engage in another card slot 407, thereby fixing the slide rail 401. After the slide rail 401 is unfolded, the operating space for placing the insulator body 10 is increased, the operating difficulty is reduced, and the setting of the guide shaft 404 improves the sliding stability of the pressure strip 402 and avoids the deviation of the first spring 405.
[0045] Specifically, Figure 3 , Figure 5 , Figure 6 , Figure 7 , Figure 8 and Fig.11As shown, the pick-and-place structure 5 includes a fixed block 501 and a fixed rod 502. The connecting frame 408 is fixedly connected with four fixed blocks 501. The fixed block 501 is fixedly connected with a fixed rod 502. The fixed block 501 is fixedly connected with a fixed shaft 505. The fixed rod 502 is slidably connected with a hanging bar 503. The hanging bar 503 is slidably connected with the fixed shaft 505. A second spring 504 is fixedly connected between the hanging bar 503 and the fixed block 501. Two hanging bars 503 are hung with a A placing frame 9, wherein two fixing ears 506 are fixedly connected to the placing frame 9, and a fixing groove 508 is provided on the fixing ear 506. The hanging bar 503 is engaged with the fixing groove 508, and a stopper 507 is fixedly connected to the hanging bar 503. Two fixing bars 509 are fixedly connected to the interior of the drying box 201, and a roller 510 is installed on the fixing bar 509; the cross section of the bottom end of the hanging bar 503 is a U-shaped structure, the top surface of the fixing ear 506 is inclined, and the cross section of the stopper 507 is a trapezoidal structure;
[0046] The limiting structure 6 includes a mounting frame 601 and a pull rod 602 slidably connected to the mounting frame 601, two mounting frames 601 with U-shaped cross sections are fixedly connected to the connecting frame 408, a stopper 603 with a trapezoidal cross section is fixedly connected to the pull rod 602, a third spring 604 is fixedly connected between the stopper 603 and the mounting frame 601, a pull ring 606 is fixedly connected to the pull rod 602, a slider 605 is fixedly connected to the suspension bar 503, and the slider 605 is slidably connected to the connecting frame 408; when the placing frame 9 is placed inside the drying box 201, the suspension continues to descend. The hanging bar 503 is first separated from the fixing groove 508 on the fixing ear 506, and then the hanging bar 503 continues to be lowered. The stopper 507 on the hanging bar 503 contacts the roller 510 on the fixing bar 509, and the hanging bar 503 continues to be lowered. Since the cross section of the stopper 507 is a trapezoid, the hanging bar 503 will slide to both sides, the second spring 504 is compressed, and the hanging bar 503 moves to drive the slider 605 to slide. The slider 605 first contacts the stopper 603, driving the stopper 603 to rise. The third spring 604 is compressed. When the slider 605 passes over the stopper 603, the third spring 604 is reset to drive the stopper 603 descends to block the slider 605, thereby limiting the slider 605 and the hanging bar 503. At this time, the connecting frame 408 and the hanging bar 503 can be driven to rise, and then the placement frame 9 and the insulator body 10 inside the placement frame 9 are placed inside the drying box 201. The setting of the fixing rod 502 improves the sliding stability of the hanging bar 503. When the placement frame 9 inside the drying box 201 needs to be taken out, the pull ring 606 is pulled first, and the pull ring 606 rises to drive the pull rod 602 to rise, and the pull rod 602 rises to drive the stopper 603 to rise, and the stopper 603 no longer limits the slider 605 and the hanging bar 503. The second spring 504 resets and drives the suspension bar 503 to reset, then the suspension bar 503 is lowered, the suspension bar 503 first conflicts with the fixed ear 506, and the suspension bar 503 continues to be lowered, and the suspension bar 503 moves horizontally. When the suspension bar 503 passes over the fixed ear 506, the second spring 504 resets and drives the suspension bar 503 to reset, and the bottom end of the suspension bar 503 slides to the bottom end of the fixed ear 506, and then drives the suspension bar 503 to rise. The suspension bar 503 rises and then engages with the fixed groove 508 on the fixed ear 506. At this time, the suspension bar 503 is lifted, and the placement frame 9 can be lifted out of the drying box 201.
[0047] Specifically, Figure 3 , Figure 6 and Fig. 9As shown, the fixing structure 7 includes a mounting seat 701 and a slot 702 provided on the mounting seat 701, four mounting seats 701 are fixedly connected to the placement frame 9, and each of the insulator bodies 10 is fixedly connected to a mounting seat 701 and a plug 703, and the plug 703 on one of the insulator bodies 10 is plugged into the slot 702 on the mounting seat 701 on another insulator body 10, and the plugs 703 on the four insulator bodies 10 at the bottom are plugged into the four mounting seats on the placement frame 9. The slot 702 on the seat 701 is plugged in; the cross-section of the insertion rod 703 is a T-shaped structure, the cross-section of the slot 702 is a T-shaped structure, the mounting seat 701 is slidably connected with a pressure plate 704, and the pressure plate 704 is fixedly connected with a positioning rod 705 with a square cross-section, the positioning rod 705 is slidably connected to the mounting seat 701, and the insertion rod 703 is provided with a positioning hole 706 with a square cross-section, the positioning rod 705 is engaged with the positioning hole 706, and the pressure plate 704 is fixedly connected to the mounting seat 701 A fourth spring 707 is connected, and a lifting block 708 is fixedly connected to the pressure plate 704, and the lifting block 708 is slidably connected to the mounting seat 701; when fixing the insulator body 10, multiple insulator bodies 10 can be installed together first, and when splicing multiple insulator bodies 10, it is only necessary to slide the insertion rod 703 on one insulator body 10 into the inside of the mounting seat 701 on another insulator body 10. Before sliding, the lifting block 708 can be slid downward, and the lifting block 708 slides downward to drive the pressure plate 704 to slide downward The fourth spring 707 is moved, and the fourth spring 707 is compressed. At the same time, the downward sliding of the pressure plate 704 will drive the positioning rod 705 to slide downward. When the insertion rod 703 slides into the interior of the slot 702, the lifting block 708 can be released, and the fourth spring 707 is reset to drive the pressure plate 704 to slide upward. The pressure plate 704 drives the positioning rod 705 to be inserted into the interior of the positioning hole 706 on the insertion rod 703, thereby splicing a plurality of insulator bodies 10, and then the insulator body 10 at the bottom is fixed to the mounting seat 701 on the placement frame 9 in the same way.
[0048] Specifically, Figure 1 , Figure 2 , Figure 3 , Figure 5 and Fig.10As shown, the sealing structure 8 includes a fixed frame 801 and a sealing plate 802 slidably connected to the fixed frame 801, the testing machine 1 is fixedly connected with the fixed frame 801, the testing machine 1 is fixedly connected with two mounting strips 803, the mounting strips 803 are provided with mounting grooves 804, the sealing plate 802 is engaged with the mounting grooves 804, the drying box 201 is slidably connected with a sliding frame 805, a fifth spring 807 is fixedly connected between the sliding frame 805 and the drying box 201, a sliding rod 806 runs through the interior of the fifth spring 807, one end of the sliding rod 806 is fixedly connected to the sliding frame 805, and the other end of the sliding rod 806 is slidably connected to the drying box 201, the sealing plate 802 is provided with a sealing groove 808, the sliding frame 805 is engaged with the sealing groove 808, and the cross-section of one side of the sliding frame 805 is a trapezoidal structure. The cross-section of the end of the sealing plate 802 is a trapezoidal structure, and two handles 809 are fixedly connected to the sealing plate 802; that is, when the drying box 201 needs to be sealed, the handle 809 on the sealing plate 802 is pulled to slide the sealing plate 802, and the sealing plate 802 first contacts the sliding frame 805. Since the cross-sections of the ends of the sealing plate 802 and the sliding frame 805 are trapezoidal, the sliding frame 805 will be pressed down first, and the fifth spring 807 will be compressed. When the end of the sealing plate 802 is engaged into the mounting groove 804 on the mounting strip 803, the fifth spring 807 is reset and drives the sliding frame 805 to engage into the sealing groove 808 on the sealing plate 802, thereby improving the sealing effect of the drying box 201, reducing heat loss, and improving the heating effect of the insulator body 10. The setting of the sliding rod 806 improves the sliding stability of the sliding frame 805 and avoids the deviation of the fifth spring 807.
[0049] A test method for a glass insulator thermal shock test device comprises the following steps:
[0050] S1: firstly, the placement frame 9 is unfolded by the stretching structure 4, then the insulator body 10 is fixed inside the placement frame 9 by the fixing structure 7, and then the placement frame 9 is moved to the top of the test structure 2 by the stretching structure 4;
[0051] S2: When it is necessary to perform a thermal shock test on the insulator body 10, the driving structure 3 is started, the position of the placement frame 9 is moved by the driving structure 3, and the thermal shock test is performed on the insulator body 10 by the test structure 2 to detect the anti-breakage ability of the insulator body 10;
[0052] S3: When the insulator body 10 is subjected to a thermal shock test, when the driving structure 3 drives the placement frame 9 to be lowered into the interior of the heating box, the placement frame 9 is limited by the pick-and-place structure 5, and the pick-and-place structure 5 is limited by the limiting structure 6. After the driving structure 3 drives the pick-and-place structure 5 to rise, the sealing structure 8 is moved to seal the heating box, and then the insulator body 10 is heated. After the heating is completed, the sealing structure 8 is opened, and then the placement frame 9 and the insulator body 10 are taken out by the driving structure 3 in cooperation with the pick-and-place structure 5.
[0053] When the present invention is in use, when the insulator body 10 needs to be placed, the pressing block 403 can be pressed downward, the pressing block 403 descends and drives the pressure strip 402 to descend, the first spring 405 is compressed, the pressure strip 402 descends and drives the card block 406 to slide, and the card block 406 is no longer engaged with the card slot 407 on the slide bar 308, and the slide rail 401 can be slid at this time, and the slide rail 401 drives the connecting frame 408 to slide outward, thereby driving the pick-up and placement structure 5 and the placement frame 9 on the connecting frame 408 to slide out, and then the pressing block 403 is released, the first spring 405 is reset and drives the pressure strip 402 to reset, and then drives the card block 406 to engage in another card slot 407, thereby fixing the slide rail 401, after the slide rail 401 is unfolded, the operation space for placing the insulator body 10 is increased, and the operation difficulty is reduced, and the setting of the guide shaft 404 improves the sliding stability of the pressure strip 402 and avoids the deviation of the first spring 405;
[0054] During the thermal shock test, the second motor 306 can be started, and the second motor 306 drives the second screw 307 to rotate. The second screw 307 rotates and drives the slide bar 308 to move up and down. The slide bar 308 moves up and down and drives the pick-up and place structure 5 and the placement frame 9 to move up and down. The placement frame 9 and the insulator body 10 move downward to the inside of the drying box 201. The pick-up and place structure 5 removes the placement frame 9, and then drives the second motor 306 to drive the second screw 307 to rotate in the opposite direction, thereby driving the slide bar 308 to rise. After the slide bar 308 rises, the sealing structure 8 is started to seal the drying box 201, and then the temperature of the drying box 201 is set. After the insulator body 10 is heated for a period of time, the sealing structure 8 is opened, and then the placement frame 9 and the insulator body 10 are placed together through the pick-up and place structure 5. The body 10 is taken out. After the body 10 is taken out, the first motor 302 is started. The first motor 302 drives the first screw 303 to rotate. The rotation of the first screw 303 drives the slide plate 305 to move. The slide plate 305 moves horizontally and drives the second guide rod 309 and the slide bar 308 on the second screw 307 to move horizontally, thereby driving the pick-and-place structure 5 and the placement frame 9 to move horizontally. Then the second motor 306 is started again, and the placement frame 9 is suspended inside the cooling pool 202. At the same time, the valves of the water inlet pipe 203 and the water outlet pipe 204 are opened. The water flow simulates a low temperature environment, thereby completing the thermal shock test of the insulator body 10. The setting of the first guide rod 304 improves the sliding stability of the two slide plates 305, and the setting of the second guide rod 309 improves the sliding stability of the slide bar 308.
[0055] When the placement frame 9 is placed inside the drying box 201, the hanging bar 503 is further lowered, and the hanging bar 503 is first separated from the fixing groove 508 on the fixing ear 506, and then the hanging bar 503 is further lowered, and the stop block 507 on the hanging bar 503 contacts the roller 510 on the fixing bar 509, and the hanging bar 503 is further lowered. Since the cross section of the stop block 507 is a trapezoid, the hanging bar 503 will slide to both sides, the second spring 504 is compressed, and the hanging bar 503 moves to drive the slider 605 slides, the slider 605 first contacts the stopper 603, driving the stopper 603 to rise, and the third spring 604 is compressed. When the slider 605 passes over the stopper 603, the third spring 604 is reset to drive the stopper 603 to descend and block the slider 605, thereby limiting the slider 605 and the suspension bar 503. At this time, the connecting frame 408 and the suspension bar 503 can be driven to rise, thereby placing the placement frame 9 and the insulator body 10 inside the placement frame 9 on the drying box 201. The setting of the fixed rod 502 inside improves the sliding stability of the hanging bar 503. When the placement frame 9 inside the drying box 201 needs to be taken out, the pull ring 606 is pulled first, and the pull ring 606 rises to drive the pull rod 602 to rise, and the pull rod 602 rises to drive the stopper 603 to rise, and the stopper 603 no longer blocks the slider 605 and the hanging bar 503, and the second spring 504 resets to drive the hanging bar 503 to reset, and then the hanging bar 503 is lowered, and the hanging bar 503 is firstly connected with the fixed rod 502. The fixed ear 506 conflicts, and the hanging bar 503 continues to be lowered. The hanging bar 503 moves horizontally. When the hanging bar 503 passes over the fixed ear 506, the second spring 504 is reset to drive the hanging bar 503 to reset. The bottom end of the hanging bar 503 slides to the bottom end of the fixed ear 506, and then drives the hanging bar 503 to rise. The hanging bar 503 rises and then engages with the fixing groove 508 on the fixed ear 506. At this time, the hanging bar 503 is lifted, and the placement frame 9 can be taken out from the drying box 201.
[0056] When fixing the insulator body 10, multiple insulator bodies 10 can be installed together first. When splicing multiple insulator bodies 10, it is only necessary to slide the insertion rod 703 on one insulator body 10 into the inside of the mounting seat 701 on another insulator body 10. Before sliding, the lifting block 708 can be slid downward. The lifting block 708 slides downward and then drives the pressure plate 704 to slide downward. The fourth spring 707 is compressed. At the same time, the downward sliding of the pressure plate 704 will drive the positioning rod 705 to slide downward. When the insertion rod 703 slides into the interior of the slot 702, the lifting block 708 can be released. The fourth spring 707 is reset and then drives the pressure plate 704 to slide upward. The pressure plate 704 drives the positioning rod 705 to be inserted into the interior of the positioning hole 706 on the insertion rod 703, thereby splicing multiple insulator bodies 10, and then the insulator body 10 at the bottom is fixed on the mounting seat 701 on the placement frame 9 in the same way.
[0057] When it is necessary to seal the drying box 201, pull the handle 809 on the sealing plate 802 to slide the sealing plate 802. The sealing plate 802 first contacts the sliding frame 805. Since the end cross-sections of the sealing plate 802 and the sliding frame 805 are trapezoidal, the sliding frame 805 will be pressed down first, and the fifth spring 807 will be compressed. When the end of the sealing plate 802 is engaged into the mounting groove 804 on the mounting strip 803, the fifth spring 807 is reset and drives the sliding frame 805 to engage into the sealing groove 808 on the sealing plate 802, thereby improving the sealing effect of the drying box 201, reducing heat loss, and improving the heating effect of the insulator body 10. The setting of the slide rod 806 improves the sliding stability of the sliding frame 805 and avoids the deviation of the fifth spring 807.
[0058] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0059] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A glass insulator thermal shock test equipment, characterized in that: The invention comprises a testing machine (1), a testing structure (2) arranged on the testing machine (1), a driving structure (3) arranged on the testing machine (1), an extension structure (4) arranged on the driving structure (3), a pick-and-place structure (5) arranged on the extension structure (4), a limiting structure (6) arranged on the extension structure (4), a placement frame (9) hung on the pick-and-place structure (5), a fixing structure (7) arranged inside the placement frame (9), a sealing structure (8) provided on the testing machine (1), and an insulator body (10) mounted on the fixing structure (7); The test structure (2) comprises a drying box (201) and a cooling pool (202); the drying box (201) and the cooling pool (202) are arranged inside the test machine (1); a water inlet pipe (203) and a water outlet pipe (204) are fixedly connected to the cooling pool (202); The driving structure (3) comprises four fixed plates (301) and a first motor (302) fixedly connected to one of the fixed plates (301), wherein two first guide rods (304) are fixedly connected between the two fixed plates (301), an output end of the first motor (302) is fixedly connected to a first screw rod (303), the first screw rod (303) is rotatably connected to the other two fixed plates (301), and another first guide rod (304) is fixedly connected to the two fixed plates (301), a slide plate (305) is slidably connected to the lower one of the first guide rods (304), and the upper two first guide rods (304) are fixedly connected to the lower one of the first guide rods (304). Another slide plate (305) is slidably connected to the upper part, the first screw rod (303) is threadedly connected to the lower slide plate (305), a second guide rod (309) is fixedly connected between the two slide plates (305), a second motor (306) is fixedly connected to the lower slide plate (305), a second screw rod (307) is fixedly connected to the output end of the second motor (306), the second screw rod (307) is rotatably connected to the two slide plates (305), a slide bar (308) is threadedly connected to the second screw rod (307), the slide bar (308) is slidably connected to the second guide rod (309), and an extension structure (4) is provided on the slide bar (308).
2. The glass insulator thermal shock test equipment according to claim 1, characterized in that: The extension structure (4) comprises a slide rail (401) and a pressure strip (402) slidably connected to the slide rail (401); the slide rail (401) having a T-shaped cross section is slidably connected to the slide bar (308); the cross section of the pressure strip (402) is an L-shaped structure; a pressure block (403) is fixedly connected to the pressure strip (402); a first spring (405) is fixedly connected between the pressure strip (402) and the slide rail (401); a clamping block (406) having a trapezoidal cross section is fixedly connected to the pressure strip (402); the clamping block (406) is slidably connected to the slide rail (401); two clamping grooves (407) are provided on the slide bar (308); the clamping block (406) is engaged with one of the clamping grooves (407); and a connecting frame (408) having a T-shaped cross section is fixedly connected to the slide rail (401).
3. A glass insulator thermal shock test equipment according to claim 2, characterized in that: A guide shaft (404) passes through the interior of the first spring (405), two ends of the guide shaft (404) are fixedly connected to the interior of the slide rail (401), and the pressure strip (402) is slidably connected to the guide shaft (404).
4. The glass insulator thermal shock test equipment according to claim 2, characterized in that: The pick-and-place structure (5) comprises a fixed block (501) and a fixed rod (502); four fixed blocks (501) are fixedly connected to the connecting frame (408); the fixed blocks (501) are fixedly connected to the fixed rods (502); the fixed blocks (501) are fixedly connected to the fixed shafts (505); the fixed rods (502) are slidably connected to the hanging bars (503); the hanging bars (503) are slidably connected to the fixed shafts (505); the hanging bars (503) are fixedly connected to the fixed blocks (501); A second spring (504) is connected, a placement frame (9) is hung on the two hanging bars (503), two fixing ears (506) are fixedly connected to the placement frame (9), a fixing groove (508) is provided on the fixing ear (506), the hanging bar (503) is engaged with the fixing groove (508), a stop block (507) is fixedly connected to the hanging bar (503), two fixing bars (509) are fixedly connected to the interior of the drying box (201), and a roller (510) is installed on the fixing bar (509).
5. The glass insulator thermal shock test equipment according to claim 4, characterized in that: The cross section of the bottom end of the hanging bar (503) is a U-shaped structure, the top surface of the fixing ear (506) is arranged at an angle, and the cross section of the stop block (507) is a trapezoidal structure.
6. The glass insulator thermal shock test equipment according to claim 4, characterized in that: The limiting structure (6) comprises a mounting frame (601) and a pull rod (602) slidably connected to the mounting frame (601); two mounting frames (601) with U-shaped cross sections are fixedly connected to the connecting frame (408); a stopper (603) with a trapezoidal cross section is fixedly connected to the pull rod (602); a third spring (604) is fixedly connected between the stopper (603) and the mounting frame (601); a pull ring (606) is fixedly connected to the pull rod (602); a slider (605) is fixedly connected to the suspension bar (503); and the slider (605) is slidably connected to the connecting frame (408).
7. The glass insulator thermal shock test equipment according to claim 1, characterized in that: The fixing structure (7) comprises a mounting seat (701) and a slot (702) provided on the mounting seat (701); four mounting seats (701) are fixedly connected to the placement frame (9); each of the insulator bodies (10) is fixedly connected to a mounting seat (701) and an insertion rod (703); the insertion rod (703) on one of the insulator bodies (10) is plugged into the slot (702) on the mounting seat (701) on another insulator body (10); and the insertion rods (703) on the four insulator bodies (10) at the bottom are plugged into the slots (702) on the four mounting seats (701) on the placement frame (9).
8. The glass insulator thermal shock test equipment according to claim 7, characterized in that: The cross section of the insertion rod (703) is a T-shaped structure, the cross section of the slot (702) is a T-shaped structure, a pressure plate (704) is slidably connected to the mounting seat (701), a positioning rod (705) with a square cross section is fixedly connected to the pressure plate (704), the positioning rod (705) is slidably connected to the mounting seat (701), a positioning hole (706) with a square cross section is provided on the insertion rod (703), the positioning rod (705) is engaged with the positioning hole (706), a fourth spring (707) is fixedly connected between the pressure plate (704) and the mounting seat (701), a lifting block (708) is fixedly connected to the pressure plate (704), and the lifting block (708) is slidably connected to the mounting seat (701).
9. The glass insulator thermal shock test equipment according to claim 1, characterized in that: The sealing structure (8) comprises a fixing frame (801) and a sealing plate (802) slidably connected to the fixing frame (801); the fixing frame (801) is fixedly connected to the testing machine (1); two mounting bars (803) are fixedly connected to the testing machine (1); the mounting bars (803) are provided with mounting grooves (804); the sealing plate (802) is engaged with the mounting grooves (804); the drying box (201) is slidably connected to a sliding frame (805); a fifth spring (802) is fixedly connected between the sliding frame (805) and the drying box (201); 07), a slide bar (806) runs through the interior of the fifth spring (807), one end of the slide bar (806) is fixedly connected to the slide frame (805), and the other end of the slide bar (806) is slidably connected to the drying box (201), a sealing groove (808) is provided on the sealing plate (802), and the slide frame (805) is engaged with the sealing groove (808), the cross-section of one side of the slide frame (805) is a trapezoidal structure, the cross-section of the end of the sealing plate (802) is a trapezoidal structure, and two handles (809) are fixedly connected to the sealing plate (802).
10. A test method for glass insulator thermal shock test equipment according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1: firstly, the placement frame (9) is unfolded by the stretching structure (4), then the insulator body (10) is fixed inside the placement frame (9) by the fixing structure (7), and then the placement frame (9) is moved to the top of the test structure (2) by the stretching structure (4); S2: When it is necessary to perform a thermal shock test on the insulator body (10), the driving structure (3) is started, the position of the placement frame (9) is transferred by the driving structure (3), and the thermal shock test is performed on the insulator body (10) by the test structure (2) to detect the anti-breakage ability of the insulator body (10); S3: When the insulator body (10) is subjected to a thermal shock test, the driving structure (3) drives the placement frame (9) to be lowered into the interior of the heating box, and the placement structure (5) is used to release the limit on the placement frame (9), and the placement structure (5) is limited by the limit structure (6). After the driving structure (3) drives the placement structure (5) to rise, the sealing structure (8) is moved to seal the heating box, and then the insulator body (10) is heated. After the heating is completed, the sealing structure (8) is opened, and then the placement frame (9) and the insulator body (10) are taken out by the driving structure (3) in cooperation with the placement structure (5).
Citation Information
Cited By
Intelligent boiling test device for polymerized crystalline silicon insulator
CN119224475A
A thermal shock testing machine for glass insulators
CN224788484U