Efficient micro-motion exploration equipment and micro-motion exploration geological construction method
By using shock components and clamping components in micro-movement exploration equipment, the problem of low efficiency of traditional micro-movement exploration methods is solved, efficient stratigraphic structure exploration is achieved, and detection efficiency and applicability are improved.
Patent Information
- Application Number
- CN202411175712.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-08
AI Technical Summary
Traditional micro-movement exploration methods require digging detection holes on the ground and using manual strikes on the source, resulting in low detection efficiency, high cost and great environmental impact.
An efficient micro-movement exploration equipment was designed, using the combination of shock components and clamping components to generate vibrations through the impact of shock hammer and shock plate, and through the rebound characteristics of the clamping spring and return spring, the pickup is achieved. The efficient insertion and decimation of the shock absorber improves detection efficiency and practicality.
It improves the detection efficiency and practicality of micro-moving exploration equipment, reduces the lag caused by adhesion between the cross cone head and the soil layer, and enhances the applicability and detection accuracy of the device.
Smart Images

Figure CN118915130A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of geological exploration technology, and in particular to a high-efficiency micro-motion exploration equipment and a micro-motion exploration geological construction method. Background Art
[0002] With the continuous development of engineering construction, the importance of geological exploration in various engineering projects has become increasingly prominent. Although traditional geological exploration methods, such as drilling and seismic exploration, have met engineering needs to a certain extent, they still have many shortcomings in terms of exploration efficiency, cost and environmental friendliness. Therefore, the development of a new type of geological exploration equipment and construction method that is efficient, low-cost and environmentally friendly has become an urgent need in the industry.
[0003] Micro-vibration exploration is a geological exploration technology based on seismic wave theory. It collects and analyzes tiny vibration signals that are widely present in nature (such as ground micro-vibrations caused by wind, water flow, human activities, etc.), extracts surface wave dispersion curves that reflect stratum structure information, and then realizes the exploration of stratum structure. Compared with traditional methods, micro-vibration exploration has the advantages of no need for artificial seismic sources, convenient data collection, low exploration cost, and little impact on the environment.
[0004] Although micro-seismic exploration technology has many advantages, it still faces some technical bottlenecks in its actual application. The traditional micro-seismic exploration method requires digging a detection hole on the ground, inserting the detector into the hole, and then manually striking the source to generate micro-seismic signals. This detection method is time-consuming and labor-intensive, reducing the detection efficiency of the device. Summary of the invention
[0005] The purpose of the present application is to solve the problem that the traditional micro-motion exploration method requires digging a detection hole on the ground, inserting the detector into the hole, and then manually striking the source to generate a micro-motion signal. This detection method is time-consuming and labor-intensive, and reduces the detection efficiency of the device. The present application provides an efficient micro-motion exploration equipment and a micro-motion exploration geological construction method.
[0006] In order to achieve the above-mentioned purpose, this application specifically adopts the following technical solutions: The top of the lifting gear is connected with the lifting gear of the lifting gear, and the bottom of the lifting gear is connected with the lifting gear of the lifting gear.
[0007] By adopting the above technical scheme, by setting the coordinated use of the shock component and the clamping component, it is convenient to drive the shock hammer to move away from the shock plate along the length direction of the lifting slide when pushing the lifting slide along the length direction of the lifting slide to drive the cross cone head to insert into the ground, and when the lifting slide drives the shock plate to fit the ground, the shock component is twisted to drive the shock hammer to hit the shock plate along the length direction of the lifting slide to generate vibration, so that it is convenient to complete the accumulation of power for the shock hammer while guiding the shock pickup to be inserted into the ground, and then use the shock component to drive the shock hammer to cooperate with the shock plate to hit the ground, which effectively improves the detection efficiency of the device and improves the practicability of the device.
[0008] Furthermore, the shock assembly includes a positioning rod fixedly connected to one end of the bracket, the top end of the shock hammer passes through the inverted L-shaped mounting platform and is fixedly connected to a hook rod adapted to the positioning rod, one end of the shock hammer is provided with a shock spring, and the shock spring is installed between the inverted L-shaped mounting platform and the shock hammer.
[0009] By adopting the above technical scheme, by setting the positioning rod, the hook rod and the shock spring for coordinated use, it is convenient to make the hook rod hook one end of the positioning rod in the process of driving the hook rod to drive the shock plate to fit with the ground, and cooperate with the inverted L-shaped mounting platform to squeeze the shock spring, and then the hook rod is rotated to release the hook with the positioning rod, so that the shock spring rebounds and pushes the shock hammer to collide with the shock plate, thereby facilitating the driving of the shock hammer to collide with the shock plate, effectively improving the practicability of the device.
[0010] Furthermore, the clamping assembly includes a storage groove opened at one end of the bracket, an arc-shaped clamping block 1 is slidably connected inside the storage groove, one end of the arc-shaped clamping block 1 is fixedly connected to a clamping spring, and the clamping spring is installed inside the storage groove, and one end of the lifting slide is symmetrically fixedly connected to an arc-shaped clamping block 2 adapted to the arc-shaped clamping block 1.
[0011] By adopting the above technical solution, by setting the arc-shaped clamping block one and the use of the clamping spring and the arc-shaped clamping block two, it is convenient to utilize the rebound characteristics of the clamping spring and the return spring, so that when the arc-shaped clamping block two moves to the bottom of the arc-shaped clamping block one, the arc-shaped clamping block two is pushed to form a conflict with the arc-shaped clamping block one, so that the lifting slide is clamped and fixed inside the lifting slide groove, which effectively improves the practicality of the device.
[0012] Furthermore, one end of the arc-shaped block is fixedly connected to an unlocking slide rod, one end of the unlocking slide rod passes through the bracket and is fixedly connected to an unlocking handle, and one end of the unlocking handle is installed with a lifting mechanism for driving the lifting slide to move upward along the length of the lifting slide groove.
[0013] By adopting the above technical scheme and setting the cooperation between the lifting mechanism and the unlocking handle, it is convenient to pull the unlocking handle to drive the unlocking slide rod to pull the arc-shaped clamping block to squeeze the clamping spring into the interior of the storage groove, and then push the lifting slide to drive the cross cone head to move upward along the length direction of the lifting slide groove and leave the ground, thereby effectively reducing the situation where the cross cone head is stuck in the ground due to adhesion with the soil layer, making it impossible for the reset spring to rebound and push out the lifting slide, thereby effectively improving the practicality of the device.
[0014] Furthermore, the jacking mechanism includes a jacking slide groove symmetrically opened at one end of the bracket, a jacking slider is slidably connected inside the jacking slide groove, an L-shaped jacking block is fixedly connected to the top of the two jacking sliders, one end of the two unlocking handles is fixedly connected to a transmission rod, one end of the lifting slide is fixedly connected to a jacking triangle block adapted to the L-shaped jacking block, and one end of the transmission rod is installed with a follower component for guiding the L-shaped jacking block to move along the length direction of the jacking slide groove.
[0015] By adopting the above technical scheme, by setting the follow-up component for use with the L-shaped jacking block and the jacking triangle block, it is convenient to make the L-shaped jacking block and the jacking triangle block form a conflict when the unlocking handle is pulled to drive the L-shaped jacking block to move along the length direction of the jacking slide, and push the jacking triangle block to drive the lifting slide to move upward along the length direction of the lifting slide, thereby facilitating the lifting slide to drive the cross cone head out of the ground, effectively improving the practicability of the device.
[0016] Furthermore, the follower assembly includes a traction plate fixedly connected to one end of the L-shaped lifting block, and one end of the transmission rod is fixedly connected to an L-shaped redundant hook plate adapted to the traction plate.
[0017] By adopting the above technical solution, by setting the traction plate and the L-shaped redundant hook plate for coordinated use, it is convenient to utilize the redundant partial space between the L-shaped redundant hook plate and the traction plate, so that the arc-shaped card block will not cause the L-shaped redundant hook plate to form a conflict with the traction plate until it is completely retracted into the storage groove, thereby improving the applicability of the device.
[0018] Furthermore, the top of the L-shaped lifting block is rotatably connected to a lifting roller.
[0019] By adopting the above technical solution, by setting the coordination between the lifting roller and the lifting triangle block, the L-shaped lifting block forms a rolling conflict with the lifting triangle block through the lifting roller, thereby effectively reducing the wear between the lifting roller and the lifting triangle block and improving the smoothness of the device.
[0020] Furthermore, one end of the lifting slide is fixedly connected to a rubber isolation block, and the rubber isolation block is installed between the lifting slide and the inverted L-shaped mounting platform.
[0021] By adopting the above technical solution, by setting up the rubber isolation block and the inverted L-shaped mounting platform for use, the situation where the shock plate directly transmits the vibration force to the vibration pickup through the lifting slide is effectively reduced, thereby improving the detection accuracy of the device.
[0022] A micro-seismic geological exploration construction method, the method steps are as follows: S1: First, mark multiple areas to be inspected on the ground, then push the bracket to drive the universal wheel to form rolling contact with the ground, and pass through the ground areas to be inspected one by one; S2: When the equipment passes over the ground area to be tested, use the foot to push the cross cone head to drive the vibration pickup to move downward along the length direction of the lifting slide and insert into contact with the soil layer of the ground area to be tested; S3: The hook rod and the positioning rod are used to pull the shock hammer to squeeze the shock spring to generate a contraction deformation, and the hook rod is rotated to release the hook from the positioning rod, so that the shock hammer is pushed out by the rebound deformation of the shock spring to hit the shock plate and the ground to be tested to generate vibration; S4: At the same time, the vibration pickup is used to sense the dispersion curve of the surface wave generated underground, and the sensing signal is transmitted to the controller for collection and analysis; S6: Repeat the above operation to collect surface wave dispersion curve signals of multiple areas to be detected, and perform joint inversion analysis to improve the accuracy of stratigraphic stratification; S7: When it is necessary to release the connection between arc block 1 and arc block 2, manually pull the unlocking handle to drive arc block 1 to retract into the storage slot, and at the same time drive the jacking mechanism to push the lifting slide to drive the cross cone head out of the ground, so as to complete the exploration and recover the equipment.
[0023] In summary, the present application includes at least one of the following beneficial effects: 1. By setting up the coordinated use of the shock component and the clamping component, when the lifting slide is pushed along the length direction of the lifting slide to drive the cross cone head to be inserted into the ground, the shock component drives the shock hammer to move away from the shock plate along the length direction of the lifting slide, and when the lifting slide drives the shock plate to fit the ground, the shock component is twisted to drive the shock hammer to hit the shock plate along the length direction of the lifting slide to generate vibration, so that it is convenient to complete the accumulation of power for the shock hammer while guiding the shock pickup to be inserted into the ground, and then the shock component is used to drive the shock hammer to cooperate with the shock plate to hit the ground, which effectively improves the detection efficiency of the device and improves the practicability of the device.
[0024] 2. By setting the positioning rod, the hook rod and the shock spring for use together, it is convenient to make the hook rod hook one end of the positioning rod in the process of driving the hook rod to drive the shock plate to fit with the ground, and cooperate with the inverted L-shaped mounting table to squeeze the shock spring, and then the hook rod is rotated to release the hook with the positioning rod, so that the shock spring rebounds and pushes the shock hammer to collide with the shock plate, thereby facilitating the driving of the shock hammer to collide with the shock plate, effectively improving the practicability of the device.
[0025] 3. By setting up the coordinated use of the jacking mechanism and the unlocking handle, it is convenient to pull the unlocking handle to drive the unlocking slide rod to pull the arc-shaped clamping block and squeeze the clamping spring into the interior of the storage groove, and then push the lifting slide to drive the cross cone head to move upward along the length direction of the lifting slide groove and leave the ground, thereby effectively reducing the situation where the cross cone head is stuck in the ground due to adhesion with the soil layer, making it impossible for the reset spring to rebound and eject the lifting slide, thereby effectively improving the practicability of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the three-dimensional structure of the device body in this application.
[0027] Figure 2 It is a side cross-sectional view of the device body in this application.
[0028] Figure 3 It is a three-dimensional structural exploded diagram of the device body in this application.
[0029] Figure 4 It is an exploded view of the internal structure of the storage tank in this application.
[0030] Description of reference numerals: 1. Bracket; 2. Lifting slide; 3. Lifting slide bar; 4. Lifting slide; 5. Reset spring; 6. Cross cone head; 7. Vibration pickup; 8. Controller; 9. Universal wheel; 10. Inverted L-shaped mounting platform; 11. Shock plate; 12. Shock hammer; 13. Positioning rod; 14. Hook rod; 15. Shock spring; 16. Storage slot; 17. Arc block 1; 18. Clamping spring; 19. Arc block 2; 20. Unlocking slide bar; 21. Unlocking handle; 22. Lifting slide; 23. Lifting slider; 24. L-shaped lifting block; 25. Transmission rod; 26. Traction plate; 27. L-shaped redundant hook plate; 28. Lifting roller; 29. Lifting triangle block; 30. Rubber isolation block. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-4 This application is described in further detail.
[0032] The embodiments of the present application disclose a highly efficient micro-motion exploration device and a micro-motion exploration geological construction method.
[0033] Reference Figure 1-Figure 4 , a high-efficiency micro-motion exploration equipment, including a bracket 1, a lifting slide slot 2 is opened at one end of the bracket 1, a lifting slide rod 3 is fixedly connected inside the lifting slide slot 2, one end of the lifting slide rod 3 is slidably connected to a lifting slide 4, one end of the lifting slide rod 3 is sleeved with a return spring 5, the top of the return spring 5 is fixedly connected to the lifting slide 4, one end of the lifting slide 4 is fixedly connected to a cross cone head 6, one end of the cross cone head 6 is fixedly connected to a vibration pickup 7, the top of the bracket 1 is fixedly connected to a controller 8 electrically connected to the vibration pickup 7, the bottom four corners of the bracket 1 are fixedly connected to universal wheels 9, an inverted L-shaped mounting platform 10 is installed on one side of the bracket 1, the bottom of the inverted L-shaped mounting platform 10 is fixedly connected to a shock plate 11, one end of the inverted L-shaped mounting platform 10 is slidably connected to a shock hammer 12, one end of the lifting slide 4 is installed with a shock component for driving the shock hammer 12 to collide with the shock plate 11, and one end of the bracket 1 is symmetrically installed with a clamping component for fixing the lifting slide 4; The shock assembly includes a positioning rod 13 fixedly connected to one end of the bracket 1, the top end of the shock hammer 12 passes through the inverted L-shaped mounting platform 10, and is fixedly connected to a hook rod 14 adapted to the positioning rod 13, and one end of the shock hammer 12 is sleeved with a shock spring 15, which is installed between the inverted L-shaped mounting platform 10 and the shock hammer 12; In addition, the clamping assembly includes a receiving groove 16 opened at one end of the bracket 1, and an arc-shaped clamping block 17 is slidably connected inside the receiving groove 16, and one end of the arc-shaped clamping block 17 is fixedly connected to a clamping spring 18, which is installed inside the receiving groove 16, and one end of the lifting slide 4 is symmetrically fixedly connected to an arc-shaped clamping block 19 adapted to the arc-shaped clamping block 17.
[0034] When in use, first mark a plurality of areas to be detected on the ground, then push the bracket 1 to drive the universal wheel 9 to form rolling contact with the ground, and drive the cross cone head 6 to pass through the ground areas to be detected in sequence, and when the cross cone head 6 passes above the ground areas to be detected, use the foot-operated lifting slide 4 to push the cross cone head 6 to move downward along the length direction of the lifting slide 2, and make the lifting slide 4 squeeze the reset spring 5 to produce contraction deformation, and at the same time make the lifting slide 4 drive the cross cone head 6 and the vibration pickup 7 to insert into the soil layer of the ground area to be detected; At the same time, the lifting slide 4 drives the arc block 2 19 to form a conflict with the arc block 1 17, and pushes the clamping spring 18 to produce a contraction deformation, and at the same time, the arc block 17 is retracted into the storage groove 16, and then when the arc block 2 19 moves to the bottom of the arc block 17, the clamping spring 18 rebounds and pushes out the arc block 17, and at the same time, the rebound characteristics of the reset spring 5 are used to push the arc block 2 19 and the arc block 1 17 to form a clamping fixation, so as to achieve the fixation of the lifting slide 4; Then, the lifting slide 4 drives the inverted L-shaped mounting platform 10 to move downward along the length direction of the lifting slide slot 2, and the inverted L-shaped mounting platform 10 drives the shock plate 11 to fit with the ground. At this time, the hook rod 14 drives the shock hammer 12 to hook one end of the positioning rod 13, and cooperates with the inverted L-shaped mounting platform 10 to squeeze the shock spring 15 to produce a contraction deformation. Then, the hook rod 14 is manually pushed to drive the shock spring 15 to produce axial deflection, and the hook of the hook rod 14 and the positioning rod 13 is released. At this time, the shock spring 15 rebounds and pushes the shock hammer 12 to collide with the shock plate 11 along the length direction of the lifting slide slot 2. At the same time, the shock plate 11 amplifies the impact force generated by the shock hammer 12 and transmits it to the ground in the ground area to be detected; Next, when the jar 12 is driven to impact the ground in the area to be detected, the vibration pickup 7 is used to sense the surface wave dispersion curve generated underground, and the sensing signal is transmitted to the controller 8 for collection and analysis, and then the above operation is repeated to collect the surface wave dispersion curve signals of multiple areas to be detected, and the controller 8 performs a joint inversion analysis to improve the accuracy of the stratum stratification, so as to facilitate the completion of the accumulation of power for the jar 12 while guiding the vibration pickup 7 to be inserted into the ground, and then the jar 12 is driven by the vibration assembly to cooperate with the vibration plate 11 to impact the ground, which effectively improves the detection efficiency of the device and improves the practicability of the device.
[0035] Reference Figure 2-Figure 4 One end of the arc-shaped block 17 is fixedly connected to an unlocking slide rod 20, one end of the unlocking slide rod 20 passes through the bracket 1 and is fixedly connected to an unlocking handle 21, and one end of the unlocking handle 21 is installed with a lifting mechanism for driving the lifting slide 4 to move upward along the length of the lifting slide 2; The lifting mechanism includes a lifting slot 22 symmetrically opened at one end of the bracket 1, a lifting slider 23 is slidably connected inside the lifting slot 22, an L-shaped lifting block 24 is fixedly connected to the top of the two lifting sliders 23, one end of the two unlocking handles 21 is fixedly connected to a transmission rod 25, one end of the lifting slide 4 is fixedly connected to a lifting triangle block 29 adapted to the L-shaped lifting block 24, and one end of the transmission rod 25 is installed with a follower component for guiding the L-shaped lifting block 24 to move along the length direction of the lifting slot 22; Moreover, the follower assembly includes a traction plate 26 fixedly connected to one end of the L-shaped lifting block 24, and one end of the transmission rod 25 is fixedly connected to an L-shaped redundant hook plate 27 adapted to the traction plate 26; Furthermore, a lifting roller 28 is rotatably connected to the top of the L-shaped lifting block 24 .
[0036] When in use, when it is necessary to release the clamping connection between the arc-shaped clamping block 17 and the arc-shaped clamping block 2 19, the unlocking handle 21 is manually held to pull the unlocking slide bar 20 to drive the arc-shaped clamping block 17 to retract into the interior of the storage groove 16 along the length direction of the storage groove 16, and squeeze the clamping spring 18 to produce contraction deformation, and at the same time, the unlocking handle 21 drives the transmission rod 25 to pull the L-shaped redundant hook plate 27 to form a conflict with the traction plate 26, and pulls the traction plate 26 to drive the L-shaped jacking block 24 to move along the length direction of the jacking slide 22, and at the same time, the L-shaped jacking block 24 drives the jacking roller 28 to form a rolling conflict with the jacking triangle block 29, and pushes the jacking triangle block 29 to drive the lifting slide 4 to move upward along the length direction of the lifting slide 2, so that the lifting slide 4 drives the cross cone head 6 to leave the ground, thereby effectively reducing the situation that the cross cone head 6 is stuck in the ground due to the adhesion of the cross cone head 6 to the soil layer, making it impossible for the reset spring 5 to rebound and eject the lifting slide 4, and effectively improving the practicability of the device.
[0037] Reference Figure 1 and Figure 3 One end of the lifting slide 4 is fixedly connected with a rubber isolation block 30 , and the rubber isolation block 30 is installed between the lifting slide 4 and the inverted L-shaped mounting platform 10 .
[0038] During use, when the driving hammer 12 hits the shock plate 11, so that the shock plate 11 directly transmits the shock force to the shock pickup 7 through the lifting slide 4, the rubber isolation block 30 absorbs part of the shock force transmitted from the shock plate 11 to the lifting slide 4, thereby effectively improving the detection accuracy of the shock pickup 7.
[0039] A micro-seismic geological exploration construction method, the method steps are as follows: S1: First, mark multiple areas to be detected on the ground, then push the bracket 1 to drive the universal wheel 9 to form a rolling conflict with the ground, and pass through the ground areas to be detected in turn; S2: When the equipment passes above the ground area to be inspected, the cross cone head 6 is pushed by the foot on the lifting slide 4 to drive the vibration pickup 7 to move downward along the length direction of the lifting slide 2 and to be inserted into the soil layer of the ground area to be inspected; S3: The hook rod 14 and the positioning rod 13 are used to pull the shock hammer 12 to squeeze the shock spring 15 to generate a contraction deformation, and the hook rod 14 is rotated to release the hook from the positioning rod 13, so that the shock hammer 12 is pushed out by the rebound deformation of the shock spring 15 to hit the shock plate 11 and the ground to be detected to generate vibration; S4: At the same time, the vibration pickup 7 is used to sense the dispersion curve of the surface wave generated underground, and the sensing signal is transmitted to the controller 8 for collection and analysis; S6: Repeat the above operation to collect surface wave dispersion curve signals of multiple areas to be detected, and perform joint inversion analysis to improve the accuracy of stratigraphic stratification; S7: When it is necessary to release the connection between the arc block 17 and the arc block 2 19, the arc block 17 is retracted into the storage groove 16 by manually pulling the unlocking handle 21, and at the same time, the jacking mechanism is driven to push the lifting slide 4 to drive the cross cone head 6 out of the underground, completing the exploration and recovering the equipment.
[0040] The implementation principle of the high-efficiency micro-motion exploration equipment and micro-motion exploration geological construction method of the present embodiment is as follows: first, a plurality of areas to be detected are marked on the ground, and then the universal wheel 9 is driven to form rolling contact with the ground by pushing the bracket 1, and the cross cone head 6 is driven to pass through the ground areas to be detected in sequence, and when the cross cone head 6 passes above the ground area to be detected, the cross cone head 6 is pushed to move downward along the length direction of the lifting slide 2 by using the foot-operated lifting slide 4, and the lifting slide 4 squeezes the reset spring 5 to produce contraction deformation, and at the same time, the lifting slide 4 drives the cross cone head 6 and the vibration pickup 7 to insert into the soil layer of the ground area to be detected; At the same time, the lifting slide 4 drives the arc block 2 19 to form a conflict with the arc block 1 17, and pushes the clamping spring 18 to produce a contraction deformation, and at the same time, the arc block 17 is retracted into the storage groove 16, and then when the arc block 2 19 moves to the bottom of the arc block 17, the clamping spring 18 rebounds and pushes out the arc block 17, and at the same time, the rebound characteristics of the reset spring 5 are used to push the arc block 2 19 and the arc block 1 17 to form a clamping fixation, so as to achieve the fixation of the lifting slide 4; Then, the lifting slide 4 drives the inverted L-shaped mounting platform 10 to move downward along the length direction of the lifting slide slot 2, and the inverted L-shaped mounting platform 10 drives the shock plate 11 to fit with the ground. At this time, the hook rod 14 drives the shock hammer 12 to hook one end of the positioning rod 13, and cooperates with the inverted L-shaped mounting platform 10 to squeeze the shock spring 15 to produce a contraction deformation. Then, the hook rod 14 is manually pushed to drive the shock spring 15 to produce axial deflection, and the hook of the hook rod 14 and the positioning rod 13 is released. At this time, the shock spring 15 rebounds and pushes the shock hammer 12 to collide with the shock plate 11 along the length direction of the lifting slide slot 2. At the same time, the shock plate 11 amplifies the impact force generated by the shock hammer 12 and transmits it to the ground in the ground area to be detected; Next, when the jar hammer 12 is driven to strike the jar plate 11 to produce an impact on the ground of the ground area to be detected, the vibration pickup 7 is used to sense the surface wave dispersion curve generated underground, and the sensing signal is transmitted to the controller 8 for collection and analysis, and then the above operation is repeated to collect the surface wave dispersion curve signals of multiple areas to be detected and perform joint inversion analysis through the controller 8, so as to improve the accuracy of stratum stratification; Then, when it is necessary to release the clamping fixation between the arc-shaped clamping block 17 and the arc-shaped clamping block 2 19, the unlocking handle 21 is manually held to pull the unlocking slide bar 20 to drive the arc-shaped clamping block 17 to retract into the interior of the storage groove 16 along the length direction of the storage groove 16, and squeeze the clamping spring 18 to produce a contraction deformation, and at the same time, the unlocking handle 21 drives the transmission rod 25 to pull the L-shaped redundant hook plate 27 to form a conflict with the traction plate 26, and pulls the traction plate 26 to drive the L-shaped jacking block 24 to move along the length direction of the jacking slide 22, and at the same time, the L-shaped jacking block 24 drives the jacking roller 28 to form a rolling conflict with the jacking triangle block 29, and pushes the jacking triangle block 29 to drive the lifting slide 4 to move upward along the length direction of the lifting slide 2, so that the lifting slide 4 drives the cross cone head 6 out of the ground.
Claims
1. An efficient micro-motion exploration device, comprising a bracket (1), characterized in that: One end of the bracket (1) is provided with a lifting slot (2), the interior of the lifting slot (2) is fixedly connected with a lifting slide rod (3), one end of the lifting slide rod (3) is slidably connected with a lifting slide table (4), one end of the lifting slide rod (3) is sleeved with a return spring (5), the top of the return spring (5) is fixedly connected to the lifting slide table (4), one end of the lifting slide table (4) is fixedly connected with a cross cone head (6), one end of the cross cone head (6) is fixedly connected with a vibration pickup (7), and the top of the bracket (1) is fixedly connected with a vibration pickup (7). An electrically connected controller (8), the four corners of the bottom of the bracket (1) are fixedly connected to universal wheels (9), one side of the bracket (1) is installed with an inverted L-shaped mounting platform (10), the bottom of the inverted L-shaped mounting platform (10) is fixedly connected to a shock plate (11), one end of the inverted L-shaped mounting platform (10) is slidably connected to a shock hammer (12), one end of the lifting slide (4) is installed with a shock component for driving the shock hammer (12) to collide with the shock plate (11), and one end of the bracket (1) is symmetrically installed with a clamping component for fixing the lifting slide (4).
2. The high-efficiency micro-motion exploration equipment according to claim 1 is characterized in that: The shock assembly comprises a positioning rod (13) fixedly connected to one end of the bracket (1); the top end of the shock hammer (12) passes through the inverted L-shaped mounting platform (10) and is fixedly connected to a hook rod (14) adapted to the positioning rod (13); one end of the shock hammer (12) is sleeved with a shock spring (15), and the shock spring (15) is installed between the inverted L-shaped mounting platform (10) and the shock hammer (12).
3. The high-efficiency micro-motion exploration equipment according to claim 1 is characterized in that: The clamping assembly comprises a receiving groove (16) provided at one end of the bracket (1), an arc-shaped clamping block 1 (17) being slidably connected inside the receiving groove (16), a clamping spring (18) being fixedly connected at one end of the arc-shaped clamping block 1 (17), and the clamping spring (18) being installed inside the receiving groove (16), and an arc-shaped clamping block 2 (19) adapted to the arc-shaped clamping block 1 (17) being symmetrically fixedly connected at one end of the lifting slide (4).
4. The high-efficiency micro-motion exploration equipment according to claim 3 is characterized in that: One end of the arc-shaped clamping block (17) is fixedly connected to an unlocking slide rod (20), one end of the unlocking slide rod (20) passes through the bracket (1) and is fixedly connected to an unlocking handle (21), and one end of the unlocking handle (21) is installed with a lifting mechanism for driving the lifting slide (4) to move upward along the length of the lifting slide groove (2).
5. The high-efficiency micro-motion exploration equipment according to claim 4 is characterized in that: The lifting mechanism comprises a lifting slot (22) symmetrically arranged at one end of the bracket (1); a lifting slider (23) is slidably connected inside the lifting slot (22); the tops of the two lifting sliders (23) are fixedly connected with L-shaped lifting blocks (24); one end of the two unlocking handles (21) is fixedly connected with a transmission rod (25); one end of the lifting slide (4) is fixedly connected with a lifting triangle block (29) adapted to the L-shaped lifting block (24); and one end of the transmission rod (25) is installed with a follower component for guiding the L-shaped lifting block (24) to move along the length direction of the lifting slot (22).
6. The high-efficiency micro-motion exploration equipment according to claim 5, characterized in that: The follower assembly comprises a traction plate (26) fixedly connected to one end of an L-shaped lifting block (24), and one end of the transmission rod (25) is fixedly connected to an L-shaped redundant hook plate (27) adapted to the traction plate (26).
7. The high-efficiency micro-motion exploration equipment according to claim 5, characterized in that: The top of the L-shaped lifting block (24) is rotatably connected to a lifting roller (28).
8. The high-efficiency micro-motion exploration equipment according to claim 1, characterized in that: One end of the lifting slide (4) is fixedly connected to a rubber isolation block (30), and the rubber isolation block (30) is installed between the lifting slide (4) and the inverted L-shaped installation platform (10).
9. A micro-seismic geological exploration construction method, characterized in that: The method is applicable to a high-efficiency micro-motion exploration device as described in any one of claims 1 to 8, and the steps of the method are as follows: S1: First, a plurality of areas to be inspected are marked on the ground, and then the bracket (1) is pushed to drive the universal wheel (9) to form rolling contact with the ground, and the universal wheel (9) passes through the areas to be inspected in sequence; S2: When the device passes above the ground area to be inspected, the cross cone head (6) is pushed by the foot-operated lifting slide (4) to drive the vibration pickup (7) to move downward along the length direction of the lifting slide (2) and to be inserted into and contacted with the soil layer of the ground area to be inspected; S3: using the hook rod (14) and the positioning rod (13) to pull the shock hammer (12) to squeeze the shock spring (15) to generate a contraction deformation, and by rotating the hook rod (14) to release the hook from the positioning rod (13), the shock spring (15) is used to push out the shock hammer (12) to hit the shock plate (11) and the ground to be detected to generate vibration; S4: using the vibration pickup (7) to sense the dispersion curve of the surface wave generated underground, and transmitting the sensing signal to the controller (8) for collection and analysis; S6: Repeat the above operation to collect surface wave dispersion curve signals of multiple areas to be detected, and perform joint inversion analysis to improve the accuracy of stratigraphic stratification; S7: When it is necessary to release the connection between the arc-shaped clamping block 1 (17) and the arc-shaped clamping block 2 (19), the arc-shaped clamping block 1 (17) is retracted into the storage groove (16) by manually pulling the unlocking handle (21), and at the same time, the lifting mechanism is driven to push the lifting slide (4) to drive the cross cone head (6) out of the ground, thereby completing the exploration and recovering the equipment.