Vertical pile casing conveying belt installation method

Through the step-by-step operation of homemade fixtures and winches combined with pulley sets, the problem of inconvenience in installation of large-angle vertical casing conveyor belts in small spaces is solved, and a fast and convenient installation process is achieved, manpower and mechanical equipment are saved, and construction period and cost are shortened. .

CN118929073AActive Publication Date: 2024-11-12CHINA MCC22 GROUP CORP LTD +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411286275.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-12
Estimated Expiration
2044-09-13

AI Technical Summary

Technical Problem

The insufficient lifting space for large lifting equipment leads to inconvenient installation of large-angle vertical casing conveyor belts in narrow spaces, long construction period, large construction occupies a large site and high cost.

Method used

The self-made belt clamp, winch and pulley set are used to fix and lift the corrugated edge-retaining conveyor belt into the cartridge through step-by-step operations. The winch and fixture are used to achieve rapid installation, saving manpower and mechanical equipment.

Benefits of technology

It realizes the rapid and convenient installation of vertical casing conveyor belts, shortens construction periods, saves labor and mechanical equipment costs, and has a fast installation speed in a narrow space. It is suitable for steelmaking and loading sites with compact space resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118929073A_ABST
    Figure CN118929073A_ABST
Patent Text Reader

Abstract

The invention discloses an installation method of a vertical pile casing conveying belt. The installation method comprises the following steps that a wavy flange conveying belt is placed according to requirements; one end of the wavy flange conveying belt is fixed through a first clamp. A winch and a pulley block are used for hoisting the wavy flange conveying belt; after the conveying belt is lifted to the position of a machine head, a second clamp is used for fixing the wavy flange conveying belt; after the position of the pulley block is replaced, the wavy flange conveying belt is continuously pulled to a set position, a machine head fixing wheel is placed at one end of the wavy flange conveying belt, a machine tail fixing wheel is placed at the other end, and installation is completed. Compared with the prior art, installation of the vertical pile casing conveying belt is achieved through the self-made clamp, the winch and the pulley block, and the method is simple and convenient to install; labor cost and hoisting machinery cost are saved; under the condition of narrow space resources, the method is high in installation speed and short in construction period; in addition, the method can also be used when the conveying belt is replaced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of installation of a vertical casing conveyor belt with a large inclination angle, and in particular to an installation method of a vertical casing conveyor belt. Background Art

[0002] The high-angle corrugated conveyor belt consists of three parts: base belt, sidewalls and transverse partitions. The sidewalls prevent materials from slipping and scattering. To facilitate bypassing the drum, the sidewalls are designed to be corrugated; the transverse partitions support materials. In order to achieve high-angle conveying, T-type and TC-type are adopted. The sidewalls and transverse partitions are connected to the base belt by secondary vulcanization, which has a high connection strength. It is used to convey powdery, granular, small block, paste and liquid materials that are easy to scatter. It is widely used in coal, grain, building materials, chemical, hydropower and metallurgical industries.

[0003] 90% of the feeding systems in steel mills are equipped with transfer stations. The feeding systems with transfer stations are generally around 200m, occupying a large construction site, requiring a large selection of lifting equipment, and requiring a long installation period. The high-angle vertical casing conveyor belt is suitable for steel mills with compact space resources, but the steel mill feeding site is small, and there is insufficient space for large lifting equipment to be hoisted, making the vertical casing conveyor belt inconvenient to install. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a method for installing a vertical casing conveyor belt and a self-made belt clamp, which is simple and convenient to install and saves manpower and mechanical equipment.

[0005] To achieve this technical purpose, the present invention adopts the following scheme: A method for installing a vertical casing conveyor belt comprises the following steps: The first step is to fix the winch near the head of the vertical casing conveyor belt, fix the pulley block on the top of the head, and pass the wire rope of the winch through the pulley block; The second step is to arrange the corrugated sidewall conveyor belt according to the feeding direction and place it; In the third step, the corrugated sidewall conveyor belt is fixed by a first clamp, and the wire rope passes through the casing and is connected to the first clamp; The fourth step is to start the winch, use the winch to pull the corrugated sidewall conveyor belt into the casing, and slowly raise it; Step 5: When the corrugated sidewall conveyor belt is hoisted to the vertical casing conveyor belt head position, the corrugated sidewall conveyor belt is fixed with a second clamp; Step 6. Change the position of the pulley block, loosen the second clamp and continue to pull the corrugated sidewall conveyor belt to the set position, install the head fixed wheel, and after completion, install the tail fixed wheel at the other end of the corrugated sidewall conveyor belt. The installation of the corrugated sidewall conveyor belt is completed.

[0006] Compared with the prior art, the present invention has the following beneficial effects: The present invention utilizes a self-made clamp, a winch and a pulley block to realize the installation of a vertical casing conveyor belt. The method is simple and convenient to install; it saves labor costs and lifting machinery costs; in the case of limited space resources, the method has a fast installation speed and a short construction period; in addition, the method can also be used when replacing a conveyor belt.

[0007] As a preferred solution, the first clamp in the third step includes a sliding roller and a connecting rod, a first connecting plate is provided at both ends of the sliding roller, a second connecting plate is provided at both ends of the connecting rod, the first connecting plate and the second connecting plate are connected by bolts, and an ear plate is provided on the upper part of the connecting rod.

[0008] Furthermore, in the third step, the sliding roller is passed through the corrugated sidewall conveyor belt, the first connecting plate and the second connecting plate are connected and fixed by bolts, and the wire rope is connected to the ear plate on the connecting rod.

[0009] Furthermore, in the fifth step, the second clamp includes a fixed rod and a movable rod arranged in parallel, a support rod is arranged between the fixed rod and the movable rod, one end of the support rod is fixedly connected to the fixed rod, a gasket is arranged at the other end of the support rod, and the fixed rod and the movable rod are connected by bolts.

[0010] Furthermore, in the fifth step, the fixed rod is placed on one side of the corrugated sidewall conveyor belt, the support rod is against the base belt on both sides of the corrugated sidewall conveyor belt, the movable rod is placed on the other side of the corrugated sidewall conveyor belt, and the movable rod is connected to the fixed rod by bolts to fix the corrugated sidewall conveyor belt.

[0011] Furthermore, in the sixth step, the pulley block after the position change is fixedly set in front of the running direction of the conveyor belt. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the installation of an embodiment of the present invention; Figure 2 Another installation diagram of an embodiment of the present invention; Figure 3 This is a schematic diagram showing the completion of the installation of an embodiment of the present invention; Figure 4 This is a schematic diagram of the first clamp structure according to an embodiment of the present invention; Figure 5 This is a schematic diagram of the second clamp structure according to an embodiment of the present invention; Figure 6 for Figure 5 The left side view of the second fixture; The markings in the figure are: 1. corrugated sidewall conveyor belt; 2. pulley block; 3. steel wire rope; 4. winch; 10. first clamp; 101. sliding roller; 102. connecting rod; 103. first connecting plate; 104. second connecting plate; 105. ear plate; 20. second clamp; 201. fixed rod; 202. movable rod; 203. support rod; 204. gasket. DETAILED DESCRIPTION

[0013] In order to fully understand the purpose, features and effects of the present invention, the present invention is described in detail through the following specific implementation methods, but the present invention is not limited thereto.

[0014] See also Figures 1 to 3 The present invention provides a technical solution: a method for installing a vertical casing conveyor belt, comprising the following steps: A method for installing a vertical casing conveyor belt comprises the following steps: The first step is to fix the winch 4 near the head of the vertical casing conveyor belt, fix the pulley block 2 on the top of the head, and pass the wire rope 3 of the winch 4 through the pulley block 2; The second step is to arrange the corrugated sidewall conveyor belt 1 according to the feeding direction and place it. The corrugated sidewall conveyor belt 1 is placed using a mid-span single beam crane; In the third step, the corrugated sidewall conveyor belt 1 is fixed by using the first clamp 10 .

[0015] See also Figure 4 In this embodiment, the first clamp 10 includes a sliding roller 101 and a connecting rod 102. First connecting plates 103 are provided at both ends of the sliding roller 101, and second connecting plates 104 are provided at both ends of the connecting rod 102. The sliding roller 101 passes through the corrugated sidewall conveyor belt 1, and the first connecting plate 103 and the second connecting plate 104 are connected and fixed by bolts. An ear plate 105 is provided on the upper part of the connecting rod 102, and the wire rope 3 is connected to the ear plate 105 on the connecting rod 102.

[0016] The fourth step is to start the winch 4, use the winch 4 to pull the corrugated sidewall conveyor belt 1 into the casing, and slowly lift it up; in the process of pulling the corrugated sidewall conveyor belt 1, the mid-span single beam hoist lifts the middle part of the corrugated sidewall conveyor belt 1 and feeds it into the casing mouth, and the winch 4 is lifted and cooperated with the mid-span single beam hoist to ensure the smooth installation process; Step 5: When the corrugated sidewall conveyor belt 1 is hoisted to the vertical casing conveyor belt head position, the corrugated sidewall conveyor belt 1 is fixed by using the second clamp 20; See also Figure 5 and Figure 6In this embodiment, the second clamp 20 includes a fixed rod 201 and a movable rod 202 arranged in parallel, a support rod 203 is arranged between the fixed rod 201 and the movable rod 202, one end of the support rod 203 is fixedly connected to the fixed rod 201, and a gasket 204 is arranged at the other end of the support rod 203, and the fixed rod 201 and the movable rod 202 are connected by bolts.

[0017] The fixing method of the second clamp 20 in this embodiment is to place the fixed rod 201 on one side of the corrugated sidewall conveyor belt 1, the support rod 203 is against the base belt on both sides of the corrugated sidewall conveyor belt 1, and the movable rod 202 is placed on the other side of the corrugated sidewall conveyor belt 1, and the movable rod 202 is connected to the fixed rod 201 by bolts to fix the corrugated sidewall conveyor belt 1.

[0018] The sixth step is to change the position of the pulley block 2. After the position is changed, the pulley block 2 is fixed on the beam / column in front of the conveyor belt running direction. Release the second clamp 20 and continue to pull the corrugated sidewall conveyor belt 1 to the set position. Install the head fixed wheel. After completion, install the tail fixed wheel at the other end of the corrugated sidewall conveyor belt 1. The installation of the corrugated sidewall conveyor belt 1 is completed.

[0019] The present invention utilizes a self-made clamp, a winch 4 and a pulley block 2 to realize the installation of a vertical casing conveyor belt. The method is simple and convenient to install; it saves labor costs and lifting machinery costs; in the case of limited space resources, the method has a fast installation speed and a short construction period; and the method can also be used when replacing a conveyor belt.

[0020] Finally, it should be noted that the above are only preferred embodiments of the present invention. Of course, those skilled in the art can make changes and modifications to the present invention. If these modifications and variations fall within the scope of the claims of the present invention and their equivalent technologies, they should be considered to be within the scope of protection of the present invention.

Claims

1. A method for installing a vertical casing conveyor belt, characterized in that: The following steps are involved: The first step is to fix the winch (4) near the head of the vertical casing conveyor belt, fix the pulley block (2) on the top of the head, and pass the steel wire rope (3) of the winch (4) through the pulley block (2); The second step is to arrange the corrugated sidewall conveyor belt (1) according to the feeding direction and place it; In the third step, the corrugated sidewall conveyor belt (1) is fixed by using a first clamp (10), and the steel wire rope (3) is passed through the casing and connected to the first clamp (10); Step 4: start the winch (4), use the winch (4) to pull the corrugated sidewall conveyor belt (1) into the casing, and slowly raise it; Step 5: When the corrugated sidewall conveyor belt (1) is hoisted to the vertical casing conveyor belt head position, the corrugated sidewall conveyor belt (1) is fixed using a second clamp (20); Step 6: Replace the position of the pulley block (2), loosen the second clamp (20), continue to pull the corrugated sidewall conveyor belt (1) to the set position, install the head fixed wheel, and after completion, install the tail fixed wheel at the other end of the corrugated sidewall conveyor belt (1). The installation of the corrugated sidewall conveyor belt (1) is completed.

2. The vertical casing conveyor belt installation method according to claim 1 is characterized in that: In the third step, the first clamp (10) comprises a sliding roller (101) and a connecting rod (102), first connecting plates (103) are arranged at both ends of the sliding roller (101), and second connecting plates (104) are arranged at both ends of the connecting rod (102), the first connecting plate (103) and the second connecting plate (104) are connected by bolts, and an ear plate (105) is arranged on the upper part of the connecting rod (102).

3. The vertical casing conveyor belt installation method according to claim 2 is characterized in that: In the third step, the sliding roller (101) is passed through the corrugated sidewall conveyor belt (1), the first connecting plate (103) and the second connecting plate (104) are connected and fixed by bolts, and the steel wire rope (3) is connected to the ear plate (105) on the connecting rod (102).

4. The vertical casing conveyor belt installation method according to claim 1 is characterized in that: In the fifth step, the second clamp (20) comprises a fixed rod (201) and a movable rod (202) arranged in parallel, a support rod (203) is arranged between the fixed rod (201) and the movable rod (202), one end of the support rod (203) is fixedly connected to the fixed rod (201), and a gasket (204) is arranged at the other end of the support rod (203), and the fixed rod (201) and the movable rod (202) are connected by bolts.

5. The vertical casing conveyor belt installation method according to claim 4 is characterized in that: In the fifth step, the fixed rod (201) is placed on one side of the corrugated sidewall of the corrugated sidewall conveyor belt (1), the support rod (203) is pressed against the base belt on both sides of the corrugated sidewall conveyor belt (1), the movable rod (202) is placed on the other side of the corrugated sidewall conveyor belt (1), and the movable rod (202) is connected to the fixed rod (201) by bolts to fix the corrugated sidewall conveyor belt (1).

6. The vertical casing conveyor belt installation method according to claim 1 is characterized in that: In the sixth step, the pulley block (2) after the position change is fixedly arranged in front of the running direction of the conveyor belt.

Citation Information

Patent Citations

  • Method for replacing closed type large-inclination-angle wavelike and annular conveying belt

    CN103170818A

  • Vertical shaft continuous tunneling elevation system and elevation method thereof

    CN109896232A

  • Tunneling machine and muck discharging device thereof

    CN111285024A

  • Hoisting system for installing high-altitude device and hoisting method

    CN112938786A

  • Lifting clamp device for vertical wave-shaped flange conveying belt

    CN219585657U