Construction method of six-span continuous mixed beam bridge

By synchronously constructing the concrete beam section from the intermediate bridge pier and gradually hoisting large-segment steel beams, the construction risks and low efficiency in the construction of six-span continuous hybrid beam bridges are solved, and an efficient and safe construction process is achieved.

CN118932881APending Publication Date: 2024-11-12CHINA RAILWAY 18TH BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411363797.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-28
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The prior art cannot effectively solve the construction method of six-span continuous hybrid beam bridges, resulting in high construction risks, low efficiency and increased costs.

Method used

The concrete beam section is constructed simultaneously from the intermediate piers, and the large-segment steel beams are gradually hoisted through the bridge deck crane, and installed in sequence from both ends to the middle. The temporary steel support platform and sandbags are used for assembly and pressure weight, and the steel twist is optimized. The wire is pre-tightened and relaxed, combining the hanging basket and the bridge crane into one equipment.

Benefits of technology

The construction efficiency of the six-span hybrid beam bridge has been improved, the construction risks and costs have been reduced, and the smooth integration of the hybrid beam bridge has been achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932881A_ABST
    Figure CN118932881A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of beam bridge construction, and discloses a construction method of a six-span continuous mixed beam bridge, which comprises the following steps of: 1, simultaneously constructing five bridge piers positioned at a middle section, and constructing a concrete beam body on the bridge piers; secondly, a temporary steel supporting platform is erected in water, and the large-section steel beams are assembled on the steel supporting platform; thirdly, the spliced large-section steel beams are sequentially installed on the concrete beam body from the two ends to the middle through a deck crane; and fourthly, after the large-section steel beam is installed, the deck crane is dismantled, and construction of a bridge accessory structure is conducted. The problem that in the prior art, construction of the six-span continuous mixed beam bridge needs to solve the overall construction method and the construction sequence of the concrete beams and the steel beams in the mixed beams is solved, the construction efficiency of the mixed beam bridge is improved, the construction risk is reduced, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of beam bridge construction, and in particular to a construction method of a six-span continuous hybrid beam bridge. Background Art

[0002] At present, there is no construction method for six-span continuous hybrid beam bridges. The closest construction method is the construction method of multi-span concrete beam bridges. For the construction of multi-span concrete beam bridges, the middle piers of the bridge are usually constructed simultaneously and in parallel, and then the cantilever casting method is used to construct symmetrically from each middle pier to both sides of the bridge span. The concrete beams on the side spans are then constructed by the bracket method to complete the closure of the beams on the side spans first, and then the concrete beams from the secondary side spans to the middle spans are gradually closed. However, when closing the secondary side span concrete beams, it is necessary to weight the adjacent middle span concrete beams. After the secondary side span concrete beams are closed, the weight of the middle span concrete is removed, and the middle span beams are closed in turn until the beams of the entire bridge are closed. The construction method of multi-span concrete beam bridges cannot be directly applied to the construction of multi-span hybrid beam bridges. If the construction method of multi-span concrete beam bridges is used, it will generate greater construction risks in the construction of multi-span hybrid beam bridges. The main reason is that the weight of the large-segment steel beam in a multi-span hybrid beam bridge is greater than the weight of the concrete segment in a multi-span concrete beam bridge. The use of counterweights requires heavier counterweight objects, and the installation and removal of counterweight objects requires more time, making construction extremely inconvenient and increasing construction risks.

[0003] Another relatively close construction method is the construction method of a three-span hybrid beam bridge. A three-span hybrid beam bridge usually has a large segmental steel beam in the middle of the middle span, and the rest of the span is a concrete beam. The construction method starts with the middle pier, and then the cantilever casting method is used to symmetrically construct concrete from each pier to both sides. The concrete beams on the side spans are then constructed using the bracket method to first complete the closure of the beams on the side spans, and then the bridge crane is used to hoist the middle large segmental steel beam to complete the closure of the middle span. The construction method of the three-span hybrid beam bridge cannot be directly applied to the construction of multi-span hybrid beam bridges, because the three-span hybrid beam bridge only has one large segmental steel beam in the middle span, and only one lifting is required to complete the closure of the bridge, but the six-span continuous hybrid beam has six large segmental steel beams, and the number of steel beam hoisting times is more than that of the three-span hybrid beam.

[0004] Therefore, there is an urgent need for a construction method for a six-span continuous hybrid beam bridge to solve the above problems. Summary of the invention

[0005] The purpose of the present invention is to provide a construction method for a six-span continuous hybrid beam bridge to solve the problems existing in the above-mentioned prior art.

[0006] To achieve the above object, the present invention provides the following solution: The present invention provides a construction method for a six-span continuous hybrid beam bridge, comprising:

[0007] Step 1: construct five bridge piers located in the middle section at the same time, and construct concrete beams on the bridge piers;

[0008] Step 2: Setting up a temporary steel support platform in the water, and assembling the large-section steel beams on the steel support platform;

[0009] Step 3: Using a bridge crane, the assembled large-segment steel beams are installed on the concrete beam body in sequence from both ends to the middle;

[0010] Step 4: After the large-section steel beam is installed, the bridge crane is removed and the construction of the bridge auxiliary structure is carried out.

[0011] Preferably, when installing the large-section steel beams, the large-section steel beams of the first span and the sixth span located at the side span are installed first, and then the large-section steel beams of the second span and the fifth span located at the secondary side span are installed, and finally the large-section steel beams of the third span and the fourth span located at the middle span are installed to complete the bridge closure.

[0012] Preferably, when the large-section steel beams are installed, the large-section steel beams of the second span and the fifth span need to be weighted when hoisting the large-section steel beams of the first span and the sixth span, and the large-section steel beams of the third span and the fourth span need to be weighted when hoisting the large-section steel beams of the second span and the fifth span.

[0013] Preferably, during the hoisting process of the large-section steel beam of the side span, it is necessary to pre-tighten the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span; during the hoisting process of the large-section steel beam of the secondary side span, it is necessary to pre-tighten the steel strands connecting the bridge crane of the secondary side middle span and the large-section steel beam of the middle span.

[0014] Preferably, after the installation of the large-section steel beam of the side span is completed, the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span need to be loosened; after the installation of the large-section steel beam of the secondary side span is completed, the steel strands connecting the bridge crane of the secondary side middle span and the large-section steel beam of the middle span need to be loosened.

[0015] Preferably, sandbags are provided on the large-section steel beam, and the sandbags are located on the beam body of the large-section steel beam near one end of the hanging point.

[0016] Preferably, hanging baskets are respectively installed on both sides of the pier.

[0017] Preferably, the steel support platform is located at the vertical projection position of the steel beam of the six-span continuous beam bridge.

[0018] Preferably, the hanging basket and the bridge crane are two in one device.

[0019] Preferably, the weight of the sandbag is 50t-55t.

[0020] Compared with the prior art, the present invention has the following advantages and technical effects:

[0021] The present invention provides a construction method for a six-span continuous hybrid beam bridge. For the six-span hybrid beam bridge, concrete beam sections are synchronously constructed starting from the middle pier, and large segment steel beams are gradually hoisted from the side spans to the middle span. This solves the problem of the overall construction method and construction sequence of concrete beams and steel beams in the hybrid beams that need to be solved in the construction of the six-span continuous hybrid beam bridge in the prior art, thereby improving the construction efficiency of the hybrid beam bridge, reducing construction risks, and reducing construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative labor:

[0023] Figure 1 This is a schematic diagram of the pouring concrete beam state of the present invention;

[0024] Figure 2 This is a schematic diagram of the state of splicing steel beams of the present invention;

[0025] Figure 3 This is a schematic diagram of the state of hoisting a side span steel beam segment of the present invention;

[0026] Figure 4 It is a schematic diagram of the state of the steel beam segment of the secondary side span hoisted in the present invention;

[0027] Figure 5 It is a schematic diagram of the state of the steel beam segment of the mid-span hoisting of the present invention;

[0028] Figure 6 This is a schematic diagram of the overall structure of the present invention after the steel beam is hoisted;

[0029] Figure 7 It is a schematic cross-sectional view of the present invention when hoisting a steel beam. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0032] Reference Figure 1-Figure 7 The present invention provides a construction method for a six-span continuous hybrid beam bridge, comprising:

[0033] Step 1: Construct five bridge piers in the middle section at the same time, and construct concrete beams on the bridge piers;

[0034] Step 2: Set up a temporary steel support platform in the water and assemble the large-section steel beams on the steel support platform;

[0035] Step 3: Use a bridge crane to install the assembled large segment steel beams on the concrete beam body in sequence from both ends to the middle;

[0036] Step 4: After the installation of the large-section steel beams is completed, remove the bridge deck crane and proceed with the construction of the bridge's auxiliary structures.

[0037] In one embodiment of the present invention, the same construction method as that of a multi-span concrete beam bridge is used to simultaneously construct the concrete beam bodies of the multi-span hybrid beams to complete the construction of all concrete beam bodies. The concrete beam body construction adopts a construction method of symmetrical cantilever casting with a hanging basket.

[0038] To further optimize the plan, when installing the large-section steel beams, first install the large-section steel beams of the first span and the sixth span located at the side spans, then install the large-section steel beams of the second span and the fifth span located at the secondary side spans, and finally install the large-section steel beams of the third span and the fourth span located at the middle span to complete the bridge closure.

[0039] In one embodiment of the present invention, referring to Figure 3 , Figure 4 , Figure 5 When installing the large-segment steel beams, the two large segment steel beams of the side span are installed first by the bridge crane, and then the two large segment steel beams of the secondary side span are installed, and finally the two large segment steel beams located in the middle span are installed to complete the bridge closure, realizing the construction sequence from both ends to the middle, improving the construction efficiency of the hybrid beam bridge, reducing construction risks, and reducing construction costs.

[0040] To further optimize the plan, when installing large-section steel beams, the large-section steel beams of the second and fifth spans are needed to carry out weight lifting when hoisting the large-section steel beams of the first and sixth spans; and the large-section steel beams of the third and fourth spans are needed to carry out weight lifting when hoisting the large-section steel beams of the second and fifth spans.

[0041] To further optimize the plan, during the hoisting process of the large-section steel beam of the side span, the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span need to be pre-tightened; during the hoisting process of the large-section steel beam of the secondary side span, the steel strands connecting the bridge crane of the secondary middle span and the large-section steel beam of the middle span need to be pre-tightened.

[0042] To further optimize the plan, after the installation of the large-section steel beam of the side span is completed, the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span need to be loosened; after the installation of the large-section steel beam of the secondary side span is completed, the steel strands connecting the bridge crane of the secondary side middle span and the large-section steel beam of the middle span need to be loosened.

[0043] To further optimize the solution, sandbags are provided on the large-section steel beams. The sandbags are located on the beam body of the large-section steel beams near one end of the lifting point.

[0044] In one embodiment of the present invention, taking the hoisting of the first span as an example, when the first span steel beam is hoisted by a bridge crane, in order to balance the force and prevent overturning, the existing steel beam segment, i.e., the second span steel beam, is used as a weight. Therefore, when hoisting the first span steel beam, it is necessary to pre-tighten the steel strands of the secondary side span to ensure that the secondary side span can serve as a weight for hoisting the first span steel beam. In addition, sandbags are placed on the beam body near one end of the lifting point to prevent the beam body from being pulled too hard by the lifting point when serving as a weight, resulting in one side of the steel beam being detached.

[0045] In summary, this construction method uses the existing un-hoisted steel beam segments as weights, and in order to avoid the phenomenon of emptying, sandbags are placed on one side of the un-hoisted steel beam lifting point to ensure the safety of construction. The hanging basket and bridge crane are combined into one to improve construction efficiency.

[0046] To further optimize the plan, hanging baskets were installed on both sides of the pier.

[0047] To further optimize the scheme, the steel support platform is located at the vertical projection position of the steel beam of the six-span continuous beam bridge.

[0048] To further optimize the plan, the hanging basket and the bridge crane are combined into one device.

[0049] Further optimization plan, the weight of sandbags is 50t-55t.

[0050] The present invention provides a construction method for a six-span continuous hybrid beam bridge. For the six-span hybrid beam bridge, concrete beam sections are synchronously constructed starting from the middle pier, large segment steel beams are gradually hoisted from the side span to the middle span, and a device combining a hanging basket and a bridge deck crane is used, thereby improving the construction efficiency of the six-span hybrid beam bridge and reducing the construction risk.

[0051] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0052] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A construction method for a six-span continuous hybrid beam bridge, characterized in that: include: Step 1: construct five bridge piers located in the middle section at the same time, and construct concrete beams on the bridge piers; Step 2: Setting up a temporary steel support platform in the water, and assembling the large-section steel beams on the steel support platform; Step 3: Using a bridge crane, the assembled large-segment steel beams are installed on the concrete beam body in sequence from both ends to the middle; Step 4: After the large-section steel beam is installed, the bridge crane is removed and the construction of the bridge auxiliary structure is carried out.

2. The construction method of a six-span continuous hybrid beam bridge according to claim 1, characterized in that: When installing the large-section steel beams, first install the large-section steel beams at the first span and the sixth span of the side span, then install the large-section steel beams at the second span and the fifth span of the secondary side span, and finally install the large-section steel beams at the third span and the fourth span of the middle span to complete the bridge closure.

3. The construction method of a six-span continuous hybrid beam bridge according to claim 2, characterized in that: When the large-section steel beams are installed, the large-section steel beams of the second span and the fifth span are needed to carry out weight lifting when the large-section steel beams of the first span and the sixth span are hoisted; and the large-section steel beams of the third span and the fourth span are needed to carry out weight lifting when the large-section steel beams of the second span and the fifth span are hoisted.

4. The construction method of a six-span continuous hybrid beam bridge according to claim 2, characterized in that: During the lifting process of the large-section steel beam of the side span, it is necessary to pre-tighten the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span; during the lifting process of the large-section steel beam of the secondary side span, it is necessary to pre-tighten the steel strands connecting the bridge crane of the secondary side middle span and the large-section steel beam of the middle span.

5. The construction method of a six-span continuous hybrid beam bridge according to claim 4, characterized in that: After the installation of the large-section steel beam of the side span is completed, the steel strands connecting the bridge crane of the secondary side span and the large-section steel beam of the secondary side span need to be loosened; after the installation of the large-section steel beam of the secondary side span is completed, the steel strands connecting the bridge crane of the secondary side middle span and the large-section steel beam of the middle span need to be loosened.

6. The construction method of a six-span continuous hybrid beam bridge according to claim 3, characterized in that: Sandbags are arranged on the large-section steel beam, and the sandbags are located on the beam body of the large-section steel beam near one end of the hanging point.

7. The construction method of a six-span continuous hybrid beam bridge according to claim 1, characterized in that: Hanging baskets are respectively installed on both sides of the pier.

8. The construction method of a six-span continuous hybrid beam bridge according to claim 1, characterized in that: The steel support platform is located at the vertical projection position of the steel beam of the six-span continuous beam bridge.

9. The construction method of a six-span continuous hybrid beam bridge according to claim 7, characterized in that: The hanging basket and the bridge crane are two-in-one equipment.

10. The construction method of a six-span continuous hybrid beam bridge according to claim 6, characterized in that: The weight of the sandbag is 50t-55t.