Cured soil lattice ridge combined type ecological bank protection structure and construction method
By solidifying the combined ecological bank protection structure of soil grid and using solidified soil and aquatic plants, the environmental damage and river bank collapse caused by existing ecological bank protection construction methods are solved, and the stability and aesthetics of the river bank are improved.
Patent Information
- Application Number
- CN202411064891.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-12
AI Technical Summary
The existing ecological bank protection structure construction methods are prone to environmental damage and pollution, and are prone to collapse of river bank slopes under groundwater seepage and rainfall, affecting river bank stability.
The combined ecological bank protection structure of solidified soil lattice stem is adopted, and pine piles, plastic steel sheet piles, solidified soil lattice stems, solidified soil slope protection and aquatic plants are used to form a high strength and anti-solution capacity of the solidified soil, combined with pollution-free construction methods. A strong integrity and ecological protection shore protection structure.
It effectively avoids environmental pollution, enhances the self-purification capacity of river channels, improves the stability and aesthetics of the river bank, and meets the requirements of environmental protection and landscaping.
Smart Images

Figure CN118932929A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of river bank protection construction in water conservancy projects, and in particular to a solidified earth grid combined ecological bank protection structure and a construction method. Background Art
[0002] Ecological bank protection refers to the use of plants or a combination of plants and civil engineering. In addition to preventing river bank collapse, it also allows river water and soil to penetrate each other, enhances the self-purification ability of the river, produces a certain natural landscape effect, and protects the river slope.
[0003] As we all know, if the soil on both sides of the river is loose, the groundwater level is high, and the topsoil is easily eroded by rainfall, it is the main factor causing river bank collapse and soil erosion. Therefore, under the action of groundwater infiltration, the original soil slope protection is very easy to infiltrate and deform and collapse. When excavating the river channel, the river slope at the junction of yellow mud and sandy mud often deforms in the form of contact erosion. The foot of the slope begins to be hollowed out, and the upper river slope loses support and collapses, causing serious collapse on both sides and affecting the stability of the river bank. In the process of flood discharge in the surrounding backbone river channels, it is easy to be affected and cause losses along the coast.
[0004] However, the existing construction methods of ecological revetment structures have the following shortcomings:
[0005] The existing revetment construction such as interlocking block revetment, stone revetment and concrete retaining wall is easy to cause damage and pollution to the environment, and is not suitable for areas with high requirements for environmental protection and landscaping.
[0006] Therefore, we proposed a solidified Tuge stem combined ecological bank protection structure and construction method to solve the above problems. Summary of the invention
[0007] The purpose of the present invention is to provide a solidified soil grid combined ecological bank protection structure and construction method. By improving the traditional bank protection structure, full use is made of the pollution-free properties of solidified soil and the growth of aquatic plants on the solidified soil (sponge soil) slope protection, and the high strength and anti-scouring ability of solidified soil grid and solidified soil slope protection are utilized. It has the advantages of strong integrity, no pollution and ecological environmental protection, and has solved the problems raised by the above-mentioned background technology.
[0008] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a solidified soil grid stem combined ecological bank protection structure and construction method, including pine piles, plastic steel sheet piles, solidified soil grid stems, solidified soil slope protection, planting soil, wetland plants, low water level, normal water level and high water level;
[0009] The pine piles are the main supporting structure of the system, providing support for the entire bank protection structure system;
[0010] The plastic-steel sheet piles are connected to the pine wood piles by inserting and driving, so that the two are interlocked with each other and have water-stopping and soil-retaining functions;
[0011] The solidified soil grid stem can fully wrap the pine wood pile and the plastic steel sheet pile to form a whole;
[0012] The solidified soil slope protection, cultivated soil, wetland plants, low water level, normal water level and high water level are described. Solidified soil slope protection is made above the solidified soil grid, and planting soil is spread on the solidified soil slope protection. Then, wetland plants are planted on the planting soil. The bottom elevation of the solidified soil is generally at the low water level, and the top elevation of the solidified soil is generally at the normal water level. The top of the slope protection must be 0.5 meters higher than the designed high water level;
[0013] The revetment structures are constructed according to the following steps:
[0014] 1) Use a small diesel hammer to drive the pine piles to the designed elevation according to the spacing;
[0015] 2) Use the plastic steel sheet pile driver to wrap the pine wood piles in the groove of the plastic steel sheet piles and drive them to the designed elevation. The plastic steel sheet piles need to be embedded in the solidified soil grid 55cm;
[0016] 3) Use colored steel formwork to construct and solidify the soil grid according to the designed dimensions;
[0017] 4) Construct the solidified soil slope protection on the solidified soil grid according to the designed slope ratio and thickness:
[0018] 5) Spread cultivated soil on the solidified soil slope protection and plant aquatic plants.
[0019] Preferably, the length of the pine wood piles is determined according to the depth of river excavation (generally 2-4 meters), and the spacing between the pine wood piles is determined according to the selected plastic steel sheet pile model.
[0020] Preferably, the plastic-steel sheet piles and pine wood piles must interlock with each other to play the role of water stopping and soil retaining.
[0021] Preferably, the dimensions of the solidified soil grid, trench excavation depth and width, etc. are determined according to actual conditions, and the solidified soil raw materials use a solidifying agent produced by a mature manufacturer, and the mix ratio of the solidifying agent to the soil must be determined in a laboratory.
[0022] Preferably, the solidified soil slope protection is laid according to the mix ratio required by the design, and the thickness of the slope protection is generally greater than 20CM.
[0023] Preferably, the planting soil is laid using river bottom mud and surface cultivated soil in accordance with specification requirements.
[0024] Preferably, the wetland plants generally include Iris calamus, Scutellaria baicalensis, Allium wilfordii and Centipedegrass.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] The present invention avoids the damage and pollution to the environment caused by the past bank protection construction such as interlocking block bank protection, stone masonry bank protection and concrete retaining wall, fully utilizes the characteristics of solidified soil being pollution-free and aquatic plants being able to grow on the solidified soil (spongy soil) slope protection, and utilizes the characteristics of solidified soil grid stems, high strength of solidified soil slope protection and strong anti-scour ability, and has the advantages of strong integrity, no pollution and ecological environmental protection. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic plan view of an ecological bank protection structure in a solidified soil stem combined ecological bank protection structure and a construction method of the present invention;
[0028] Figure 2 It is a cross-sectional schematic diagram of an ecological bank protection structure in a solidified Tuge stem combined ecological bank protection structure and a construction method of the present invention;
[0029] Figure 3 The present invention discloses a solidified earth-grid combined ecological bank protection structure and a construction method thereof.
[0030] In the picture: 1. Pine wood pile; 2. Plastic steel sheet pile; 3. Solidified soil grid; 4. Solidified soil slope protection; 5. Planting soil; 6. Wetland plants; 7. Low water level; 8. Normal water level; 9. High water level. DETAILED DESCRIPTION
[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] Example 1, please refer to the attached Figure 1 -Attached Figure 3As shown, the present invention provides a technical solution: a solidified soil grid stem combined ecological revetment structure and construction method, including pine piles 1, plastic steel sheet piles 2, solidified soil grid stems 3, solidified soil slope protection 4, planting soil 5, wetland plants 6, low water level 7, normal water level 8 and high water level 9, pine piles 1, which are the main supporting structure of the system, provide support for the entire revetment structure system, plastic steel sheet piles 2, pine piles 1 are connected to plastic steel sheet piles 2 by inserting and driving, so that the two are interlocked, and have water stopping and soil retaining functions. Yes, solidified soil grid 3, using solidified soil grid 3, can fully wrap the pine pile 1 and the plastic steel sheet pile 2, and form a whole, solidified soil slope protection 4, cultivated soil 5, wetland plants 6, low water level 7, normal water level 8 and high water level 9, make solidified soil slope protection 4 above the solidified soil grid 3, spread planting soil 5 on the solidified soil slope protection, and then plant wetland plants 6 on the planting soil. The bottom elevation of solidified soil is generally at the low water level 7, and the top elevation of solidified soil is generally at the normal water level 8. The top of the slope protection must be higher than the design high water level of 90.5 meters.
[0033] Embodiment 2, a solidified Tugegen combined ecological bank protection structure and construction method, according to Figure 1 , Figure 2 and Figure 3 As shown, the specific construction steps of pine pile 1 are:
[0034] The length of a pine pile is determined according to the depth of river excavation (usually 2-4 meters). It is constructed using a diesel-powered vibrating pile-driving machine and is accurately laid out by professional surveyors to ensure that the plane position and pile top elevation of the pine pile meet the design requirements.
[0035] Process flow: measurement and layout → digging the working surface → stakeout → driving pine wood piles → acceptance.
[0036] Embodiment 3, a solidified Tugegen combined ecological bank protection structure and construction method, according to Figure 1 , Figure 2 and Figure 3 As shown, the specific construction steps of the plastic steel sheet pile 2 are:
[0037] ①Plastic steel sheet piles are a new type of high-strength material developed from polymer reinforced composite materials. The shape of the sheet piles is designed based on the principles of mechanics. They are currently widely used in rivers, waterway revetments, landscape hydrophilic revetments, river slope stabilization, etc.
[0038] ②Plastic steel sheet piles are constructed using a professional plastic steel sheet machine with a centralizer.
[0039] Construction process: layout → trench excavation → piling equipment debugging and positioning → clamping and positioning piles → inserting piles → sinking piles to the designed elevation → moving the pile driver to the next pile.
[0040] Embodiment 4, a solidified Tugegen combined ecological bank protection structure and construction method, according to Figure 3As shown in the figure, the specific steps for digging the ridge trench are:
[0041] The depth and width of the trench excavation are determined according to the actual situation. The trench is excavated after the two sides of the trench are cut out according to the designed size by a slotting machine or manually, and the trench is dug to the designed elevation and the loose soil in the trench is cleaned up manually.
[0042] Example 5, a solidified Tugegen combined ecological bank protection structure and construction method, according to Figure 1 , Figure 2 and Figure 3 As shown, the specific construction steps of the solidified soil grid 3 and the solidified soil slope protection 4 are:
[0043] ①Preparation of curing agent
[0044] The dosage, porosity, 28d unconfined compressive strength and dry density of the solidified soil must meet the design requirements. The raw materials of the solidifying agent (cement, lime, polymer, plant fiber, mineral powder, etc.) must also be tested and can only be used if they meet the requirements.
[0045] ②Confirm the strength of the solidified soil
[0046] According to the requirements of the design drawings for the strength of the solidified soil, a qualified laboratory will carry out the mix design, issue a mix report, and produce according to the mix ratio.
[0047] ③Curing equipment selection
[0048] Select appropriate curing machinery and matching stirring heads, digital curing agent delivery control system, and use forced stirring to meet design requirements, achieve good surface quality, and high work efficiency, thereby achieving the goal of reducing costs while improving project quality.
[0049] ④Concrete construction process of solidification
[0050] Solidified soil production (strong mixing) → Forming and filling solidified soil → Compacting → Curing.
[0051] Example 6, a solidified Tugegen combined ecological bank protection structure and construction method, according to Figure 1 , Figure 2 and Figure 3 As shown, the specific planting steps of wetland plants 6 are:
[0052] Taking advantage of the fact that solidified soil can grow aquatic plants, different aquatic plants are selected to grow at different elevations of the revetment according to the actual situation of water levels flooding the revetment in different seasons, so that the hydrophilic plants are integrated with the revetment.
[0053] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A solidified Tugegen combined ecological bank protection structure and construction method, characterized in that: It includes pine wood piles (1), plastic steel sheet piles (2), solidified soil grid stems (3), solidified soil slope protection (4), planting soil (5), wetland plants (6), low water level (7), normal water level (8) and high water level (9); The pine piles (1) are the main supporting structure of the system, providing support for the entire bank protection structure system; The plastic-steel sheet pile (2) is connected to the pine wood pile (1) by inserting and driving, so that the two are engaged with each other and have water-stopping and soil-retaining functions; The solidified soil grid stem (3) can fully wrap the pine wood pile (1) and the plastic steel sheet pile (2) to form a whole; The solidified soil slope protection (4), cultivated soil (5), wetland plants (6), low water level (7), normal water level (8) and high water level (9) are provided. The solidified soil slope protection (4) is provided above the solidified soil grid (3), and the cultivated soil (5) is spread on the solidified soil slope protection. Then, the wetland plants (6) are planted on the cultivated soil. The bottom elevation of the solidified soil is generally located at the low water level (7), and the top elevation of the solidified soil is generally located at the normal water level (8). The top of the slope protection must be 0.5 meters higher than the designed high water level (9); The revetment structures are constructed according to the following steps: 1) Using a small diesel hammer, the pine piles (1) are driven to the designed elevation according to the spacing; 2) Using a plastic steel sheet pile (2) pile driver, the groove of the plastic steel sheet pile (2) is wrapped with the pine wood pile (1) and driven to the designed elevation. The plastic steel sheet pile (2) needs to be embedded in the solidified soil grid (3) by 55 cm; 3) Use colored steel formwork to construct and solidify the soil grid stem (3) according to the designed dimensions; 4) Construct the solidified soil slope protection (4) on the solidified soil grid (3) according to the designed slope ratio and thickness: 5) Spreading cultivated soil on the solidified soil slope protection (4) and planting aquatic plants (5).
2. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The length of the pinewood piles (1) is determined according to the excavation depth of the river channel (generally 2-4 meters), and the spacing between the pinewood piles (1) is determined according to the model of the selected plastic steel sheet piles (2).
3. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The plastic steel sheet pile (2) and the pine wood pile (1) must interlock with each other to play the role of water stopping and soil retaining.
4. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The dimensions of the solidified soil grid (3), trench excavation depth and width, etc. are determined according to actual conditions. The solidified soil raw material adopts a solidifying agent produced by a mature manufacturer, and the mixing ratio of the solidifying agent to the soil must be determined in a laboratory.
5. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The solidified soil slope protection (4) is laid according to the mix ratio required by the design, and the thickness of the slope protection is generally greater than 20CM.
6. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The planting soil (5) is paved with river bottom mud and surface cultivated soil in accordance with specification requirements.
7. The solidified Tugegen combined ecological bank protection structure and construction method according to claim 1 are characterized by: The wetland plants (6) generally include yellow calamus, yellow jasmine, water plantain and centipede grass.
Citation Information
Cited By
Intelligent anti-seepage plate capable of being monitored for long time and intelligent anti-seepage wall
CN119877517A
Intelligent anti-seepage plate and intelligent anti-seepage wall capable of long-term monitoring
CN119877517B