Foundation pit supporting structure of building

By using fixing mechanisms and traction devices to guide and support the steel cages in the foundation pit support structure of the building, the problems of shaking and deformation of the steel cages are solved, and the quality of concrete piles and the service life of the sleeves are improved.

CN118933023AInactive Publication Date: 2024-11-12SHANDONG DAYUAN ZHANSHUO CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411336063.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-24
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the construction of drilling piles, the steel cage is prone to shake due to external vibration and the influence of the crane during movement, resulting in collision with the inner wall of the casing, causing casing damage and the load-bearing capacity of the concrete piles to decrease, and the steel cage may be due to itself Weight causes deformation, affecting the uniform distribution of concrete.

Method used

A building foundation pit support structure is designed, using a fixing mechanism and traction device to guide and support the steel cage through a wire rope and an electric rotary shaft system to increase friction, avoid shaking and deformation, and clean the inner wall of the casing through a cleaning mechanism. Residue to ensure the flatness of the concrete.

Benefits of technology

It effectively avoids the shaking and deformation of the steel cage during movement, ensures the uniform distribution and load-bearing capacity of concrete piles, extends the service life of the sleeve, and improves the overall quality and appearance flatness of the concrete piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933023A_ABST
    Figure CN118933023A_ABST
Patent Text Reader

Abstract

The invention discloses a building foundation pit supporting structure, and relates to the technical field of foundation pit supporting. Comprising a sleeve, a reinforcement cage is installed in the sleeve, a fixing mechanism is arranged on the upper portion of the sleeve, the sleeve is provided with a fixing plate through the fixing mechanism, first fixing rings which are evenly distributed in the axial direction are arranged in the sleeve, and a traction device is arranged on the fixing plate. A steel wire rope on a traction device penetrates through the fixing plate and is fixedly connected with the first fixing ring, a first electric rotating shaft is rotationally connected into the first fixing ring, and the first electric rotating shaft is in threaded connection with symmetrically-distributed trigger rings. The reinforcement cage is guided in the moving process, so that the situation that the reinforcement cage collides with the inner wall of the sleeve due to shaking in the moving process, the lower end of the reinforcement cage is deformed due to collision, the reinforcement cage cannot be uniformly distributed in the concrete column, and meanwhile, the inner wall of the sleeve is damaged is avoided; therefore, the sleeve cannot be repeatedly used.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit support, and in particular to a building foundation pit support structure. Background Art

[0002] Bored cast-in-place piles are usually suitable for deep foundation pit support. They are formed by mechanical drilling to form pile holes, placing steel cages in the pile holes, and pouring concrete. During the construction of bored cast-in-place piles, it is necessary to select appropriate casings according to the geological conditions of the construction location (casings are divided into recyclable casings and disposable casings). After the casing is selected, it is necessary to place the casing in the designated position in advance to ensure the accurate lowering of the steel cage and the drill bit, and to prevent the surrounding soil from collapsing during the drilling process. After the casing is placed, it is necessary to drill a hole in the casing first, clean the soil in the casing, and then place the steel cage in the casing. After the steel cage is placed, concrete is poured into it.

[0003] In the process of placing the steel cage, it is necessary to use a crane to lift one end of the steel cage, and then the staff will guide the lower end of the steel cage into the casing, and then the crane will slowly place the remaining part of the steel cage into the casing. In this process, the steel cage is easily affected by the external environment and the vibration of the crane and sways, causing the steel cage to constantly collide with the inner wall of the casing, causing damage to the inner wall of the casing, and even causing the steel cage to deform during the collision with the inner wall of the casing, resulting in a decrease in the bearing capacity of the produced concrete pile. Summary of the invention

[0004] In order to overcome the disadvantage that the steel cage is easily shaken by external influences during the process of placing the steel cage in the pile hole, the present invention provides a building foundation pit supporting structure.

[0005] The technical solution of the present invention is: a building foundation pit support structure, including a casing, a steel cage is installed inside the casing, a fixing mechanism is arranged on the upper part of the casing, and a fixing plate is arranged on the casing through the fixing mechanism, a first fixing ring uniformly distributed axially is arranged inside the casing, a traction device is arranged on the fixing plate, a steel wire rope on the traction device passes through the fixing plate and is fixedly connected to the first fixing ring, a first electric rotating shaft is rotatably connected inside the first fixing ring, the first electric rotating shaft is threadedly connected with a symmetrically distributed trigger ring, two groups of symmetrically distributed extrusion blocks are slidably connected inside the first fixing ring, each group of the extrusion blocks includes a plurality of circumferentially distributed extrusion blocks, the extrusion blocks are extruded and matched with adjacent trigger rings, and the extrusion blocks are extruded and matched with the steel cage.

[0006] Furthermore, a rubber layer is provided on one side of the extrusion block close to the center of the adjacent trigger ring, so as to increase the friction between the extrusion block and the steel cage.

[0007] Furthermore, the opposite sides of the trigger rings symmetrically distributed on the same first electric rotating shaft are rotatably connected to a plurality of circumferentially distributed fixed columns, a torsion spring is fixedly connected between the rotating axis of the fixed column and the adjacent trigger ring, and two symmetrically distributed groups of limit blocks are fixedly connected to the middle part of the first fixed ring, each group of limit blocks is configured as a plurality of circumferentially evenly distributed, and the limit blocks are squeezed and fitted with the adjacent fixed columns.

[0008] Further, the fixing mechanism includes a positioning ring, which is fixed to the fixing plate, and the positioning ring is located at the outside of the sleeve. The outer side of the positioning ring is threadedly connected to a driving ring, and the lower side of the driving ring is rotatably connected to a moving tube. The positioning ring is provided with symmetrical and circumferentially evenly distributed sliding grooves, and a connecting column is rotatably connected in the sliding groove of the positioning ring. The upper and lower adjacent connecting columns are hinged to a fixing block on one side away from the positioning ring, and the fixing block is extruded and matched with the sleeve. The connecting column is slidably connected to an articulated seat, and the articulated seat on the connecting column is hinged to a connecting rod, and the connecting rod is fixed to the moving tube.

[0009] Furthermore, it also includes an axially distributed second electric rotating shaft, the axially distributed second electric rotating shaft is respectively rotatably connected to the adjacent first fixed ring, the first electric rotating shaft and the adjacent second electric rotating shaft are symmetrically distributed on the adjacent first fixed ring, the second electric rotating shaft is threadedly connected with a symmetrically distributed movable plate, the movable plate is slidably connected to the adjacent first fixed ring, the outer side of the first fixed ring is rotatably connected with a symmetrical and circumferentially uniformly distributed connecting shaft through a connecting piece, the connecting shaft is fixedly connected with a roller that rotates with the inner wall of the sleeve, the connecting pieces on the first fixed ring are all fixedly connected with a first liquid storage ring, the connecting shaft passes through the adjacent first liquid storage ring and is rotatably connected thereto, the connecting shaft is fixedly connected with a moving block, the moving block slides in the adjacent first liquid storage ring, and the opposite sides of the moving plates symmetrically distributed on the same second electric rotating shaft are fixedly connected with a plurality of circumferentially uniformly distributed blocking blocks, the blocking blocks are slidably connected to the adjacent first liquid storage ring.

[0010] Furthermore, it also includes a cleaning mechanism, which is used to clean the concrete remaining on the inner wall of the casing, and the cleaning mechanism is arranged at the lower side of the first fixing ring at the lowermost side. The cleaning mechanism includes a mounting ring, and the mounting ring is arranged at the lower side of the first fixing ring at the lowermost side. A lifting device is provided on the fixing plate, and a connecting rope on the lifting device passes through the fixing plate, all the first fixing rings and all the movable plates, and is fixedly connected to the mounting ring. A third electric rotating shaft is threadedly connected to one side of the mounting ring, and a second fixing ring is rotatably connected to the lower side of the third electric rotating shaft. A cleaning ring is fixedly connected to the lower side of the second fixing ring, and the cleaning ring is extruded and matched with the casing. An extrusion ring is fixedly connected to the mounting ring, and the extrusion ring is extruded and matched with the cleaning ring. A trigger mechanism is provided on the upper side of the second fixing ring, and the trigger mechanism is used to change the position of the extrusion ring.

[0011] Furthermore, the cross section of the cleaning ring is triangular, and the distance between the cleaning ring and the inner wall of the sleeve gradually decreases from top to bottom.

[0012] Further, the trigger mechanism includes a second liquid storage ring, the second liquid storage ring is fixedly connected to the upper side of the second fixed ring, the second liquid storage ring is slidably connected with a movable ring, a tension spring is arranged between the movable ring and the mounting ring, the upper side of the second fixed ring is rotatably connected with a plurality of circumferentially evenly distributed mounting shafts through a connecting piece, a torsion spring is arranged between the mounting shaft and the second fixed ring, the mounting shaft is fixedly connected with a positioning column, the positioning column is in contact and cooperate with the steel cage, the connecting pieces on the second fixed ring are all fixedly connected with a third liquid storage ring, the mounting shaft passes through the adjacent third liquid storage ring and is rotatably connected thereto, a through hole is arranged on the lower side of the third liquid storage ring, and the third liquid storage ring is connected to the second liquid storage ring through a connecting pipe.

[0013] Furthermore, a positioning block is fixedly connected inside the third liquid storage ring, and a dividing block sliding inside an adjacent third liquid storage ring is fixedly connected to the mounting shaft.

[0014] Furthermore, the elastic coefficient of the tension spring between the movable ring and the mounting ring is greater than the elastic coefficient of the torsion spring between the third liquid storage ring and the adjacent mounting shaft.

[0015] Compared with the prior art, the present invention has at least the following beneficial effects: the present invention guides the steel cage during its movement to prevent the steel cage from colliding with the inner wall of the casing due to shaking during movement, causing the lower end of the steel cage to be deformed due to the collision, making it impossible for the steel cage to be evenly distributed in the concrete column, and also causing damage to the inner wall of the casing, making the casing unable to be reused.

[0016] On this basis, the present invention also supports the steel cage through the mutual cooperation of the first fixing ring and other parts connected thereto, so as to prevent the steel cage from being deformed in the middle due to the pressure generated by its own weight, causing the center of the steel cage to deviate from the center of the casing, affecting its uniform distribution with the concrete, and even causing voids or weak points to appear after pouring the concrete, thereby reducing the overall quality of the concrete pile.

[0017] On this basis, the present invention also performs secondary fixation on the steel cage by increasing the friction between the first fixing ring and the inner wall of the sleeve, thereby preventing the steel cage from moving upward due to the supporting force generated by the flow of concrete during the concrete pouring process.

[0018] On this basis, the present invention also uses a cleaning ring to clean the residual concrete on the inner wall of the casing to avoid the concrete blocks fixed on the inner wall of the casing affecting the flatness of the outer side of the concrete pile when the casing is used for the second time after the residual concrete on the inner wall of the casing is solidified. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention; Figure 2 It is a three-dimensional structural schematic diagram of the internal parts of the sleeve of the present invention; Figure 3 It is a three-dimensional structural schematic diagram of the internal parts of the positioning ring of the present invention; Figure 4 It is a schematic diagram of the three-dimensional structure of the first fixed ring and the movable plate of the present invention; Figure 5 It is a three-dimensional structural schematic diagram of the extrusion block and the fixing column of the present invention; Figure 6 It is a schematic diagram of the three-dimensional structure of the trigger ring and the extrusion block of the present invention; Figure 7 It is a schematic diagram of the three-dimensional structure of the connecting shaft and the moving block of the present invention; Figure 8 It is a three-dimensional structural schematic diagram of the fixing mechanism of the present invention; Fig. 9 It is a schematic diagram of the three-dimensional structure of the connecting column and the connecting rod of the present invention; Fig.10 It is a three-dimensional structural schematic diagram of the cleaning mechanism of the present invention; Fig.11 It is a schematic diagram of the three-dimensional structure of the mounting ring and the third electric rotating shaft of the present invention; Fig.12 It is a three-dimensional structure explosion diagram of the cleaning mechanism of the present invention; Fig.13 It is a schematic diagram of the three-dimensional structure of the installation shaft and the third liquid storage ring of the present invention.

[0020] The names and serial numbers of the parts in the figure are: 1. casing, 2. steel cage, 3. fixed plate, 4. first fixed ring, 5. first electric shaft, 6. trigger ring, 7. extrusion block, 8. fixed column, 9. limit block, 10. positioning ring, 11. driving ring, 12. moving tube, 13. connecting column, 14. fixed block, 15. connecting rod, 16. second electric shaft, 17. moving plate, 18. connecting shaft, 19. first liquid storage ring, 20. moving block, 21. blocking block, 22. mounting ring, 23. third electric shaft, 24. second fixed ring, 25. cleaning ring, 26. extrusion ring, 27. second liquid storage ring, 28. moving ring, 29. mounting shaft, 30. positioning column, 31. third liquid storage ring. DETAILED DESCRIPTION

[0021] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.

[0022] Embodiment 1: A building foundation pit support structure, such as Figure 1-Figure 6As shown, it includes a casing 1, a steel cage 2 is installed inside the casing 1, a fixing mechanism is arranged on the upper part of the casing 1, a fixing plate 3 is arranged on the casing 1 through the fixing mechanism, and first fixing rings 4 uniformly distributed in the axial direction are arranged inside the casing 1. The specific number of the first fixing rings 4 can be selected according to the specific length of the steel cage 2. The figure and the text are described by taking three as an example, a traction device (an existing device, which is not shown in the figure) connected to the remote control terminal network is arranged on the fixing plate 3, and three groups of steel wire ropes are wound around the traction device. The three groups of steel wire ropes on the traction device all pass through the fixing plate 3, the first group of steel wire ropes pass through the two first fixing rings 4 on the upper side and the middle part and are fixedly connected to the first fixing ring 4 on the lower side, the second group of steel wire ropes pass through the first fixing ring 4 on the upper side and are fixedly connected to the first fixing ring 4 in the middle, and the third group of steel wire ropes are connected to the first fixing ring 4 on the upper side, and the three first fixing rings 4 are driven to move in sequence by the traction device through the three groups of steel wire ropes, and the first fixing ring 4 is internally connected with a The first electric rotating shaft 5 connected to the remote control terminal network is provided with two threaded parts symmetrically distributed up and down. The first electric rotating shaft 5 is threadedly connected to two trigger rings 6 through the two threaded parts thereon. Two groups of extrusion blocks 7 symmetrically distributed up and down are slidably connected inside the first fixed ring 4. Each group of extrusion blocks 7 includes a number of circumferentially distributed. The extrusion blocks 7 and the opposite sides of the adjacent trigger rings 6 are provided with arc-shaped inclined surfaces, and the inclination angles and curvatures of the arc-shaped inclined surfaces of the two are the same. In the process of movement of the trigger ring 6, the trigger ring 6 squeezes the adjacent group of extrusion blocks 7, so that the opposite sides of the adjacent group of extrusion blocks 7 are close to each other, the extrusion blocks 7 are extruded and matched with the adjacent trigger rings 6, and the extrusion blocks 7 are extruded and matched with the steel cage 2. The two adjacent groups of extrusion blocks 7 cooperate with each other to guide the steel cage 2. A rubber layer is provided on the side of the extrusion block 7 close to the center of the adjacent trigger ring 6 to increase the friction between the extrusion block 7 and the steel cage 2, and at the same time prevent the steel cage 2 from being deformed by hard extrusion.

[0023] like Figure 4-Figure 6 As shown, the opposite sides of the two trigger rings 6 on the same first electric rotating shaft 5 are rotatably connected with a plurality of circumferentially distributed fixed columns 8, and the circumferentially distributed fixed columns 8 located on the same trigger ring 6 are set as a group. The trigger ring 6 drives an adjacent group of fixed columns 8 to move synchronously during the movement. A torsion spring is fixedly connected between the rotating shaft of the fixed column 8 and the adjacent trigger ring 6, which is used to drive the fixed column 8 to move to a horizontal position, and in the initial position, the torsion spring between the fixed column 8 and the trigger ring 6 is in a force storage state. Two groups of limit blocks 9 symmetrically distributed up and down are fixedly connected to the middle part of the first fixed ring 4, and each group of limit blocks 9 is set to a plurality of circumferentially evenly distributed. The limit blocks 9 are squeezed and matched with the adjacent fixed columns 8. In the process of the trigger ring 6 driving an adjacent group of fixed columns 8 to move to the initial position, the limit blocks 9 squeeze the adjacent fixed columns 8 to rotate the adjacent fixed columns 8.

[0024] like Figure 2 , Figure 3 , Figure 8 and Fig. 9 As shown, the fixing mechanism includes a positioning ring 10, which is fixed to the fixing plate 3. The positioning ring 10 is located on the outside of the sleeve 1. The outer side of the positioning ring 10 is threadedly connected to a driving ring 11. The lower side of the driving ring 11 is rotatably connected to a moving tube 12. The driving ring 11 drives the moving tube 12 to move downward synchronously during the rotation process. The positioning ring 10 is provided with symmetrical and circumferentially uniformly distributed sliding grooves. A connecting column 13 is rotatably connected in the sliding groove of the positioning ring 10. Two upper and lower adjacent connecting columns 13 are set as a group. The two connecting columns 13 in each group are hinged together with a fixing block 14 on the side away from the positioning ring 10. The fixing block 14 is pressed and matched with the sleeve 1. The circumferentially evenly distributed fixing blocks 14 cooperate with each other to connect the positioning ring 10 and the sleeve 1 together, and at the same time adjust the center of the positioning ring 10 to a position that coincides with the center of the sleeve 1. The connecting column 13 is slidably connected to a hinge seat, and the hinge seat on the connecting column 13 is hinged with a connecting rod 15. The connecting rod 15 is fixedly connected to the moving tube 12. The moving tube 12 drives the circumferentially evenly distributed connecting rods 15 to move synchronously during the downward movement. The connecting rod 15 drives the adjacent connecting columns 13 to move synchronously through the adjacent hinge seats, and then drives the adjacent fixing blocks 14 to move, so that the fixing blocks 14 move synchronously to a position close to the center of the sleeve 1 during the downward movement.

[0025] Before using the device, the staff first uses the existing device to insert the reusable casing 1 into the ground. After the casing 1 is inserted into the ground and the soil inside the casing 1 is cleaned, the staff places the fixing plate 3 and other parts connected thereto on the casing 1 (such as Figure 3 As shown), the staff then rotates the driving ring 11, and through the threaded cooperation between the driving ring 11 and the positioning ring 10, the driving ring 11 moves downward along the positioning ring 10 while rotating, and the driving ring 11 drives the moving tube 12 to move downward synchronously, and the moving tube 12 drives several groups of connecting rods 15 evenly distributed in the circumferential direction to move downward synchronously. The following is a description of the movement process of one group of connecting rods 15 as an example: During the downward movement of the group of connecting rods 15, the two connecting rods 15 respectively drive the adjacent articulated seats to move downward synchronously, and the articulated seats squeeze the adjacent connecting columns 13, so that the connecting columns 13 are under pressure and rotate around the connection between them and the positioning ring 10, thereby gradually reducing the distance between the upper side of the connecting column 13 and the sleeve 1. At the same time, during the rotation of the connecting column 13, the two connecting columns 13 in the same group cooperate with each other to jointly drive the adjacent fixing blocks 14 to move synchronously in the direction close to the sleeve 1 until the fixing blocks 14 are tightly fitted with the outer side of the sleeve 1. The staff stops rotating the drive ring 11 and fixes the fixing blocks 14 at this position (the movement process of the remaining fixing blocks 14 can refer to the above), and the fixing blocks 14 evenly distributed circumferentially cooperate with each other to fix the positioning ring 10 and other parts connected thereto on the sleeve 1.

[0026] After the positioning ring 10 and other parts connected thereto are fixed as described above, the worker lifts the steel cage 2 by the existing lifting machinery, guides the lower end of the steel cage 2 into the casing 1, and then gradually lowers the steel cage 2 into the casing 1 by the existing lifting machinery. At the same time, during the downward movement of the steel cage 2, the steel cage 2 passes through the three first fixing rings 4 until the lower end of the steel cage 2 moves into the casing 1 to a specified length (when the lowest annular steel bar on the steel cage 2 is located below the lowest first fixing ring 4), the worker shuts down the lifting machinery and simultaneously starts the lowest first electric rotating shaft 5 through the remote control terminal. The lowest first electric rotating shaft 5 drives the two adjacent trigger rings 6 to move in opposite directions through the thread. The following is a description of the downward movement of the lowest trigger ring 6 as an example: During the downward movement of the trigger ring 6, the trigger ring 6 squeezes an adjacent group of extrusion blocks 7 through the arc-shaped inclined surface thereon, so that the opposite sides of the lowest group of extrusion blocks 7 approach each other until the opposite sides of the lowest group of extrusion blocks 7 move to contact and fit tightly with the main reinforcement of the steel cage 2. At this time, the upper group of extrusion blocks 7 on the lowest first fixed ring 4 are synchronously moved to a position that is tightly fitted with the main reinforcement of the steel cage 2 (the specific process can be referred to above), and at the same time, the two lowest trigger rings 6 are respectively moved to the extreme positions, and then the remote control terminal shuts down the lowest first electric shaft 5, and connects the lowest first fixed ring 4 with the steel cage 2 through the contact between the two groups of extrusion blocks 7 on the lowest first fixed ring 4 and the steel cage 2.

[0027] During the process of the two trigger rings 6 at the bottom moving backwards, the two trigger rings 6 respectively drive a group of adjacent fixed columns 8 to move synchronously. The following description is based on the process of the bottom group of fixed columns 8 moving downwards as an example: In the process of the downward movement of the lowest group of fixed columns 8, until the lowest group of fixed columns 8 moves downward to a position where the center line of its rotation axis is flush with the intersection of the vertical surface and the inclined surface on the adjacent limit block 9, as the lowest group of fixed columns 8 continues to move downward, the extrusion force of the lowest group of limit blocks 9 on the adjacent fixed columns 8 gradually decreases, so that the lowest group of fixed columns 8 rotate around their rotation axes under the action of adjacent torsion springs, until the lowest group of fixed columns 8 moves to a position where the center line of its rotation axis is flush with the lower edge line of the adjacent limit block 9, the group of fixed columns 8 It rotates to a horizontal state, and at the same time, after the trigger ring 6 at the lowest side moves downward to the extreme position, a group of fixed columns 8 at the lowest side moves downward to a position in contact with the upper side of the adjacent annular steel bar at its lower side, and at the same time, a group of fixed columns 8 located on the trigger ring 6 on the upper side of the first fixing ring 4 at the lowest side moves upward to a position in contact with the lower side of the adjacent annular steel bar at its upper side (the specific process can be referred to above), at this time, the two groups of extrusion blocks 7 on the first fixing ring 4 at the lowest side move synchronously to a position in close contact with the main reinforcement of the steel cage 2, and then the remote control terminal shuts down the first electric rotating shaft 5 at the lowest side.

[0028] Subsequently, the staff started the existing lifting machinery and continued to transport the steel cage 2 to the casing 1. At the same time, the remote control terminal started the traction device on the fixed plate 3, released the first group of steel wire ropes wound on the traction device, and the steel cage 2 drove the first fixing ring 4 at the bottom and other parts connected thereto to move downward synchronously, and the first fixing ring 4 at the bottom and other parts connected thereto cooperated with each other to guide the part of the steel cage 2 located in the casing 1, thereby reducing the shaking amplitude of the steel cage 2 during movement, and preventing the lower end of the steel cage 2 from colliding with the inner wall of the casing 1 during movement, causing the lower end of the steel cage 2 to deform due to a hard collision with the inner wall of the casing 1, making it impossible for the steel cage 2 to be evenly distributed in the concrete column, resulting in a decrease in the bearing capacity of the concrete column, and preventing the inner wall of the casing 1 from being damaged by the collision of the steel cage 2, making the casing 1 unable to be reused.

[0029] In the process of continuing to convey the steel cage 2 into the casing 1, the staff connects the remaining two first fixing rings 4 to the steel cage 2 in sequence according to the distance the steel cage 2 moves downward (the specific process can be referred to above), until the steel cage 2 is completely conveyed into the casing 1, and the three first fixing rings 4 and other parts connected thereto cooperate with each other to support the steel cage 2, so as to prevent the steel cage 2 from being deformed by the pressure generated by its own weight and contacting the inner wall of the casing 1, causing damage to the inner wall of the casing 1, and causing the center of the steel cage 2 to deviate from the center of the casing 1, affecting its uniform distribution with the concrete, and even causing voids or weak points to appear after pouring the concrete, thereby reducing the overall quality of the concrete pile.

[0030] After completing the transportation of the steel cage 2, the staff separates the lifting machinery from the steel cage 2, and pours concrete into the casing 1 through the existing grouting device until a predetermined amount of concrete is poured into the casing 1 (that is, when there is at least a 2-meter concrete column inside the casing 1, the concrete has completed the preliminary fixation of the lower side of the steel cage 2). Then the staff releases the connection between the three first fixing rings 4 and the steel cage 2, and slowly pulls out the casing 1 with the help of the existing pipe pulling device. At the same time, in the process of pulling out the casing 1, the casing 1 drives the three first fixing rings 4 and the other parts connected thereto to move upward synchronously through the transmission of other parts on the fixing plate 3. After the casing 1 is pulled out, the fixing plate 3 and the other parts connected thereto are removed from the casing 1 for subsequent continued use.

[0031] Embodiment 2: Based on embodiment 1, Figure 4-Figure 7As shown, it also includes an axially distributed second electric rotating shaft 16 (the specific number of the second electric rotating shaft 16 is the same as the specific number of the first fixed ring 4, and three are shown as an example in the figure and the text), the second electric rotating shaft 16 is connected to the remote control terminal network, the three second electric rotating shafts 16 are respectively rotatably connected to the adjacent first fixed rings 4, the first electric rotating shaft 5 and the adjacent second electric rotating shaft 16 are symmetrically distributed on the adjacent first fixed ring 4, the second electric rotating shaft 16 is provided with two threaded parts symmetrically distributed up and down, the second electric rotating shaft 16 is threadedly connected to two movable plates symmetrically distributed up and down through the two threaded parts thereon, the second electric rotating shaft 16 drives the two adjacent movable plates 17 to move in the opposite direction, the movable plate 17 is slidably connected to the adjacent first fixed ring 4, the outer side of the first fixed ring 4 is rotatably connected to two groups of connecting shafts 18 symmetrically distributed up and down through a connecting piece, each group of connecting shafts 18 is set to a number of evenly distributed circumferentially, the connecting shaft 18 is fixedly connected to a roller that rotates with the inner wall of the sleeve 1 to reduce the friction between the sleeve 1 and the first fixed ring 4, During the movement of the first fixed ring 4, the roller drives the adjacent connecting shaft 18 to rotate synchronously. The connecting parts on the first fixed ring 4 are all fixedly connected with the first liquid storage ring 19. The interior of the first liquid storage ring 19 is filled with hydraulic oil. The connecting shaft 18 penetrates the adjacent first liquid storage ring 19 and is rotatably connected thereto. The connecting shaft 18 is fixedly connected with a moving block 20. The moving block 20 slides in the adjacent first liquid storage ring 19. The connecting shaft 18 drives the adjacent moving block 20 to rotate synchronously, and the moving block 20 drives the adjacent first liquid storage ring 19 in the process of rotation. The hydraulic oil flows, and the facing sides of the two movable plates 17 on the same second electric rotating shaft 16 are fixedly connected with a plurality of circumferentially evenly distributed blocking blocks 21, and the plurality of blocking blocks 21 on the same movable plate 17 are arranged as a group, and the blocking blocks 21 are slidingly connected with the adjacent first liquid storage ring 19. In the process of the movable plate 17 moving toward the direction approaching the adjacent first fixed ring 4, the movable plate 17 drives a group of adjacent blocking blocks 21 to move synchronously, and the blocking blocks 21 cooperate with the adjacent movable blocks 20 to lock the adjacent connecting shafts 18.

[0032] During the downward movement of the first fixed ring 4, the first fixed ring 4 drives the two groups of rollers thereon to move downward, and the two groups of rollers respectively drive the adjacent connecting shafts 18 to rotate, and the connecting shafts 18 drive the adjacent moving blocks 20 to rotate in the adjacent first liquid storage rings 19, thereby converting the sliding friction between the first fixed ring 4 and the inner wall of the sleeve 1 into rotational friction, reducing the friction between the first fixed ring 4 and the inner wall of the sleeve 1, and increasing the service life of the sleeve 1.

[0033] After the delivery of the steel cage 2 is completed, the staff shuts down the existing hoisting machinery and simultaneously starts the three second electric rotating shafts 16 through the remote control terminal. The following is a description of the rotation process of the second electric rotating shaft 16 at the bottom as an example: During the rotation of the second electric shaft 16 at the bottom, the second electric shaft 16 rotates to drive the two adjacent moving plates 17 to approach each other through thread transmission, and the moving plate 17 drives an adjacent group of blocking blocks 21 to move synchronously, and the blocking blocks 21 are inserted into the adjacent first liquid storage ring 19 until the two moving plates 17 at the bottom move synchronously to the limit position, and the remote control terminal shuts down the second electric shaft 16 at the bottom. At this time, the two groups of blocking blocks 21 at the bottom move to the position of contacting the adjacent connecting shaft 18 respectively, and the blocking blocks 21 cooperate with the adjacent connecting shaft 18 and the adjacent moving blocks 20 to divide the adjacent first liquid storage ring 19 into two closed cavities, and at the same time, the hydraulic oil in the adjacent first liquid storage ring 19 cannot flow, thereby locking the adjacent connecting shaft 18, that is, locking the adjacent rollers, and converting the friction between the first fixing ring 4 at the bottom and the inner wall of the casing 1 from rotational friction to sliding friction, thereby increasing the resistance of the first fixing ring 4 at the bottom when it moves upward, and the rotation process of the remaining second electric shaft 16 can refer to the above.

[0034] After shutting down the three second electric shafts 16 as mentioned above, the staff pours concrete into the casing 1 through the existing grouting device. The three first fixing rings 4 and other parts connected thereto cooperate with each other to increase the resistance of the steel cage 2 when it moves upward, and the steel cage 2 is fixed for a second time to prevent the steel cage 2 from moving upward due to the supporting force generated by the flow of concrete during the concrete pouring process.

[0035] During the process of pouring concrete, until the concrete in the casing 1 reaches 2 meters, the staff slowly pulls out the casing 1 with the help of the existing pipe pulling device. At the same time, the remote control terminal controls the traction device to gradually release the three sets of steel wire ropes on the traction device, so that the three first fixing rings 4 and other parts connected thereto do not move upward synchronously with the casing 1. In the process of pulling out the casing 1, the three first fixing rings 4 and other parts connected thereto jointly guide the casing 1, and at the same time maintain the relative position of the casing 1 and the steel cage 2 to prevent the steel cage 2 from tilting in the casing 1.

[0036] When the upper surface of the concrete rises to a position close to the lowermost movable plate 17, the remote control terminal reversely starts the lowermost first electric rotating shaft 5 and the lowermost second electric rotating shaft 16, resets the parts connected to the two to the initial position and then shuts them down, disconnects the lowermost first fixing ring 4 from the steel cage 2, and starts the traction device on the fixing plate 3, which drives the lowermost first fixing ring 4 to move upward through the first group of steel wire ropes. During this process, the two first fixing rings 4 on the upper side and the middle part do not move upward, and the two first fixing rings 4 on the upper side and the middle part and other parts connected thereto continue to guide the casing 1 and maintain the relative position of the casing 1 and the steel cage 2. In the subsequent pouring of concrete, the remote control terminal moves the three first fixing rings 4 upward to the initial position in sequence according to the position of the upper surface of the concrete (refer to the above for the specific process).

[0037] After the sleeve 1 is completely pulled out, the staff removes the fixing plate 3 and other parts connected thereto from the sleeve 1 for subsequent use.

[0038] Embodiment 3: Based on embodiment 2, Figure 3 and Figure 10-12 As shown, (the following parts are shown in the figure in the state after moving, not in the initial position) also includes a cleaning mechanism, the cleaning mechanism is used to clean the concrete remaining on the inner wall of the casing 1, the cleaning mechanism is arranged on the lower side of the first fixing ring 4 at the lowermost side, the cleaning mechanism includes a mounting ring 22, the mounting ring 22 is arranged on the lower side of the first fixing ring 4 at the lowermost side, a lifting device connected to the remote control terminal network is provided on the fixing plate 3 (it is an existing device, which is not shown in the figure), the connecting rope on the lifting device passes through the fixing plate 3, the three first fixing rings 4 and the six moving plates 17, and is fixedly connected to the mounting ring 22, the left side of the mounting ring 22 is threadedly connected to the third electric shaft 23 connected to the remote control terminal network, the lower side of the third electric shaft 23 is rotatably connected to the second fixing ring 24, the third electric shaft 23 rotates During the process, the second fixing ring 24 is driven to move up and down synchronously along the mounting ring 22. A cleaning ring 25 is fixedly connected to the lower side of the second fixing ring 24. The cleaning ring 25 is squeezed and matched with the casing 1. The cleaning ring 25 is made of elastic deformable material. The cross-section of the cleaning ring 25 is triangular, and the distance between the cleaning ring 25 and the inner wall of the casing 1 gradually decreases from top to bottom. The concrete remaining on the inner wall of the casing 1 is scraped and cleaned by the lower side of the cleaning ring 25. In the process of the second fixing ring 24 moving downward, the cleaning ring 25 is driven to move downward synchronously. The mounting ring 22 is fixedly connected to an extrusion ring 26. The extrusion ring 26 is squeezed and matched with the cleaning ring 25. The extrusion ring 26 squeezes the cleaning ring 25 to make the cleaning ring 25 shrink inwardly. In the initial position, the cleaning ring 25 is in a contracted state. A trigger mechanism is arranged on the upper side of the second fixing ring 24. The trigger mechanism is used to change the position of the extrusion ring 26.

[0039] like Figure 10-13 As shown in the figure, (the following parts are shown in the state after movement, not the initial position) the trigger mechanism includes a second liquid storage ring 27, the second liquid storage ring 27 is filled with hydraulic oil, the second liquid storage ring 27 is fixedly connected to the upper side of the second fixed ring 24, and the second fixed ring 24 drives the second liquid storage ring 27 to move synchronously during the downward movement, and the second liquid storage ring 27 is slidably connected with a moving ring 28, and a tension spring is arranged between the moving ring 28 and the mounting ring 22. During the downward movement of the second liquid storage ring 27, the mounting ring 22 maintains the moving ring 28 in the initial position through the tension spring, so that the second liquid storage ring 27 and the moving ring 28 move relative to each other, thereby squeezing out the hydraulic oil in the second liquid storage ring 27 outwardly, and the upper side of the second fixed ring 24 is rotatably connected with a plurality of mounting shafts 29 evenly distributed in the circumferential direction through a connecting piece, and the mounting shafts 29 are rotatably connected with the second fixed ring 24 through a connecting piece. A torsion spring is arranged between the fixing rings 24, and the torsion spring is used to maintain the initial position of the adjacent mounting shafts 29 and drive the mounting shafts 29 to reset. The mounting shafts 29 are fixedly connected with positioning posts 30. The mounting shafts 29 drive the adjacent positioning posts 30 to rotate synchronously during the rotation process, and in the initial position, the positioning posts 30 are in a vertical state, and the positioning posts 30 are in contact with and cooperate with the annular steel bars of the steel cage 2. The positioning posts 30 evenly distributed circumferentially cooperate with each other to connect the second fixing ring 24 and other parts connected thereto with the steel cage 2. The connecting parts on the second fixing ring 24 are all fixedly connected with a third liquid storage ring 31, and the third liquid storage ring 31 is filled with hydraulic oil. The mounting shaft 29 passes through the adjacent third liquid storage ring 31 and is rotatably connected thereto. A positioning block is fixedly connected to the interior of the third liquid storage ring 31, and the mounting shaft 29 is fixedly connected with a dividing block ( Fig.13 The middle dividing block is located on the upper side of the installation shaft 29, and the positioning block is located on the lower left side of the third liquid storage ring 31). The positioning block in the third liquid storage ring 31 cooperates with the dividing block on the adjacent installation shaft 29 to divide the third liquid storage ring 31 into a first cavity and a second cavity, wherein the volume of the second cavity is larger than the volume of the first cavity in the initial state. A through hole is provided on the lower side of the third liquid storage ring 31, and the through hole on the lower side of the third liquid storage ring 31 is connected with its second cavity. The third liquid storage ring 31 is connected with the second liquid storage ring 27 through a connecting pipe. The hydraulic oil in the second liquid storage ring 27 flows through the connecting pipe into the first cavity of the third liquid storage ring 31 which is evenly distributed circumferentially, so that the evenly distributed circumferentially divided blocks are subjected to pressure and drive the adjacent mounting shaft 29 and other parts connected thereto to rotate synchronously. The elastic coefficient of the tension spring between the movable ring 28 and the mounting ring 22 is greater than the elastic coefficient of the torsion spring between the third liquid storage ring 31 and the adjacent mounting shaft 29, so that the relative movement between the second liquid storage ring 27 and the movable ring 28 occurs only after the evenly distributed circumferentially positioning columns 30 are all moved to a horizontal state.

[0040] In the process that the above-mentioned steel cage 2 drives the lowest first fixing ring 4 to move downward (at this time, the other two first fixing rings 4 are not connected to the steel cage 2), the remote control terminal starts the lifting device on the fixing plate 3, and gradually releases the connecting rope wound on the lifting device, so that the mounting ring 22 moves downward under the action of its own gravity and the gravity of other parts connected to it. At the same time, in the process that the mounting ring 22 moves downward, the remote control terminal controls the release speed of the connecting rope on the lifting device, so that the distance between the upper side of the mounting ring 22 and the lowest moving plate 17 is always maintained at the initial length.

[0041] After the conveying of the reinforcing cage 2 is completed, the control terminal shuts down the lifting device, fixes the mounting ring 22 and other parts connected thereto at the position, and locks the six groups of connecting shafts 18 according to the above operation by the remote control terminal.

[0042] In the above-mentioned process of pulling out the casing 1, the remote control terminal releases the three sets of steel wire ropes on the traction device, and at the same time, the remote control terminal controls the lifting device to synchronously release the connecting ropes wound on the lifting device, so that the mounting ring 22 and other parts connected thereto do not move up synchronously with the casing 1, until the concrete rises to a position close to the lower side of the cleaning ring 25. The remote control terminal shuts down the lifting device, so that the casing 1 drives the mounting ring 22 and other parts connected thereto to move upward synchronously through the fixing plate 3 and the lifting device thereon during the subsequent upward movement.

[0043] While the above-mentioned remote control terminal shuts down the lifting device, the remote control terminal controls the traction device according to the above-mentioned operation to drive the first fixed ring 4 at the bottom to move upward through the first group of steel wire ropes until the circumferentially evenly distributed positioning columns 30 move upward to be located between the first annular steel bar and the second annular steel bar on the upper side of the steel cage 2, and the inner wall of the lower part of the casing 1 is still partially in contact with the concrete. Then, the remote control terminal starts the third electric shaft 23, and the third electric shaft 23 moves downward synchronously through the threaded transmission of the second fixed ring 24 and other parts connected thereto.

[0044] During the downward movement of the second fixed ring 24, the mounting ring 22 drives the moving ring 28 to move upward relative to the second liquid storage ring 27 through the tension spring, and squeezes the hydraulic oil in the second liquid storage ring 27 outward, so that the hydraulic oil in the second liquid storage ring 27 flows through the connecting pipe to the first cavity of the third liquid storage ring 31 evenly distributed in the circumferential direction, thereby causing the circumferentially evenly distributed dividing blocks to respectively drive the adjacent mounting shafts 29 to rotate under the extrusion force, and at the same time, the adjacent positioning columns 30 are driven to rotate synchronously by the mounting shaft 29, and the adjacent torsion springs are rotated and stored in force during the rotation process by the mounting shaft 29, until the moving ring 28 moves upward to the limit position relative to the second liquid storage ring 27, and the circumferentially evenly distributed positioning columns 30 rotate from a vertical state to a horizontal state, at which time the circumferentially evenly distributed positioning columns 30 are all located between the first annular steel bar and the second annular steel bar on the upper side of the steel cage 2.

[0045] After the movable ring 28 moves upward to the limit position relative to the second liquid storage ring 27, the second fixed ring 24 continues to move downward, stretching the tension spring between the movable ring 28 and the mounting ring 22, and the second fixed ring 24 continues to drive the cleaning ring 25 to move downward, so that the contact position of the cleaning ring 25 and the extrusion ring 26 is constantly changed, thereby gradually reducing the extrusion force exerted by the extrusion ring 26 on the cleaning ring 25, and then the cleaning ring 25 opens circumferentially under the action of its own elastic force until the third electric shaft 23 drives the second fixed ring 24 to move downward to the limit position, the remote control terminal shuts down the third electric shaft 23, the tension spring between the movable ring 28 and the mounting ring 22 is stretched to the limit state, and the cleaning ring 25 opens to the limit state, that is, the lower side of the cleaning ring 25 contacts the inner wall of the sleeve 1, and the extrusion ring 26 no longer squeezes the cleaning ring 25.

[0046] After the third electric shaft 23 is shut down as mentioned above, the sleeve 1 frictionally cooperates with the cleaning ring 25 during the process of continuing to move upward, and drives the cleaning ring 25 and other parts connected thereto to move upward through the friction force, until the circumferentially evenly distributed positioning columns 30 move upward to a position in contact with the lower side of the first annular steel bar on the upper side of the steel cage 2, and the first annular steel bar on the upper side of the steel cage 2 exerts a reverse force on the circumferentially evenly distributed positioning columns 30, at which time the cleaning ring 25 no longer continues to move with the sleeve 1, and then the cleaning ring 25 scrapes and cleans the residual concrete on the inner wall of the sleeve 1 during the process of the sleeve 1 moving upward, so as to prevent the residual concrete on the inner wall of the sleeve 1 from solidifying and affecting the flatness of the outer side of the concrete pile when the sleeve 1 is used for the second time.

[0047] After the concrete pouring is completed and the sleeve 1 is completely pulled out by the staff, the remote control terminal starts the third electric shaft 23 in reverse, and the third electric shaft 23 drives the second fixed ring 24 and other parts connected thereto to move upward synchronously, so that the cleaning ring 25 is squeezed by the extrusion ring 26 and gathered toward the middle thereof, thereby separating the cleaning ring 25 from the inner wall of the sleeve 1. After the tension spring between the moving ring 28 and the mounting ring 22 is reset to the initial length, the second fixed ring 24 moves upward to draw the hydraulic oil squeezed out of the second liquid storage ring 27 back therein, so that the circumferentially evenly distributed positioning columns 30 are changed from a horizontal position to a vertical position, and the second fixed ring 24 and other parts connected thereto are disconnected from the steel cage 2.

[0048] When the second fixing ring 24 and other parts connected thereto are disconnected from the steel cage 2, the remote control terminal lifts the mounting ring 22 and other parts connected thereto to the initial position through the lifting device, and then the staff separates the other parts connected to the fixing plate 3 from the casing 1 and cleans the remaining concrete on the cleaning ring 25 for subsequent use.

[0049] The above is a detailed introduction to the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea. At the same time, for general technical personnel in this field, according to the idea of ​​the present application, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.

Claims

1. A building foundation pit support structure, comprising a casing (1), a steel cage (2) installed inside the casing (1), a fixing mechanism provided on the upper part of the casing (1), and a fixing plate (3) provided on the casing (1) through the fixing mechanism, It is characterized in that The invention also comprises first fixing rings (4) uniformly distributed in the axial direction, wherein the first fixing rings (4) uniformly distributed in the axial direction are all arranged inside the sleeve (1), a traction device is arranged on the fixing plate (3), a steel wire rope on the traction device passes through the fixing plate (3) and is fixedly connected to the first fixing ring (4), a first electric rotating shaft (5) is rotatably connected inside the first fixing ring (4), the first electric rotating shaft (5) is threadedly connected to symmetrically distributed trigger rings (6), and two groups of symmetrically distributed extrusion blocks (7) are slidably connected inside the first fixing ring (4), each group of the extrusion blocks (7) comprises a plurality of circumferentially distributed extrusion blocks, the extrusion blocks (7) are extrusion-matched with the adjacent trigger rings (6), and the extrusion blocks (7) are extrusion-matched with the steel cage (2).

2. A building foundation pit support structure according to claim 1, It is characterized in that A rubber layer is provided on one side of the extrusion block (7) close to the center of the adjacent trigger ring (6), so as to increase the friction between the extrusion block (7) and the steel cage (2).

3. A building foundation pit support structure according to claim 2, It is characterized in that The trigger rings (6) symmetrically distributed on the same first electric rotating shaft (5) are rotatably connected to the opposite sides thereof with a plurality of circumferentially distributed fixing columns (8), a torsion spring is fixedly connected between the rotation axis of the fixing column (8) and the adjacent trigger ring (6), and the middle part of the first fixing ring (4) is fixedly connected to two symmetrically distributed groups of limit blocks (9), each group of the limit blocks (9) is arranged to be a plurality of circumferentially evenly distributed, and the limit blocks (9) are pressed and matched with the adjacent fixing columns (8).

4. A building foundation pit support structure according to claim 1, It is characterized in that The fixing mechanism comprises a positioning ring (10), wherein the positioning ring (10) is fixedly connected to the fixing plate (3), the positioning ring (10) is located on the outside of the sleeve (1), the outer side of the positioning ring (10) is threadedly connected to a driving ring (11), the lower side of the driving ring (11) is rotatably connected to a moving tube (12), the positioning ring (10) is provided with symmetrical and circumferentially uniformly distributed sliding grooves, the sliding grooves of the positioning ring (10) are rotatably connected to connecting columns (13), the upper and lower adjacent connecting columns (13) are hingedly connected to a fixing block (14) at a side away from the positioning ring (10), the fixing block (14) is pressed and matched with the sleeve (1), the connecting column (13) is slidably connected to an articulated seat, the articulated seat on the connecting column (13) is hingedly connected to a connecting rod (15), and the connecting rod (15) is fixedly connected to the moving tube (12).

5. A building foundation pit support structure according to claim 4, It is characterized in that The invention also comprises an axially distributed second electric rotating shaft (16), the axially distributed second electric rotating shaft (16) being rotatably connected to the adjacent first fixing ring (4), the first electric rotating shaft (5) and the adjacent second electric rotating shaft (16) being symmetrically distributed on the adjacent first fixing ring (4), the second electric rotating shaft (16) being threadedly connected to a symmetrically distributed moving plate (17), the moving plate (17) being slidably connected to the adjacent first fixing ring (4), the outer side of the first fixing ring (4) being rotatably connected to a symmetrically and circumferentially uniformly distributed connecting shaft (18) through a connecting member, the connecting shaft (18) being fixedly connected to the first fixing ring (4) and ... A roller is connected to the inner wall of the sleeve (1) for rotational cooperation, the connecting parts on the first fixed ring (4) are all fixedly connected to the first liquid storage ring (19), the connecting shaft (18) passes through the adjacent first liquid storage ring (19) and is rotationally connected thereto, the connecting shaft (18) is fixedly connected to a moving block (20), the moving block (20) slides in the adjacent first liquid storage ring (19), and the opposite sides of the moving plates (17) symmetrically distributed on the same second electric rotating shaft (16) are all fixedly connected to a plurality of circumferentially evenly distributed blocking blocks (21), and the blocking blocks (21) are slidably connected to the adjacent first liquid storage ring (19).

6. A building foundation pit support structure according to claim 5, It is characterized in that The invention also comprises a cleaning mechanism, the cleaning mechanism being used to clean the concrete remaining on the inner wall of the casing (1), the cleaning mechanism being arranged at the lower side of the first fixing ring (4) at the lowermost side, the cleaning mechanism comprising a mounting ring (22), the mounting ring (22) being arranged at the lower side of the first fixing ring (4) at the lowermost side, a lifting device being arranged on the fixing plate (3), a connecting rope on the lifting device passing through the fixing plate (3), all the first fixing rings (4) and all the moving plates (17), and being fixedly connected to the mounting ring (22), the mounting ring (22) A third electric rotating shaft (23) is threadedly connected to one side of the mounting ring (22); a second fixing ring (24) is rotatably connected to the lower side of the third electric rotating shaft (23); a cleaning ring (25) is fixedly connected to the lower side of the second fixing ring (24); the cleaning ring (25) is pressed and fitted with the sleeve (1); an extrusion ring (26) is fixedly connected to the mounting ring (22); the extrusion ring (26) is pressed and fitted with the cleaning ring (25); a trigger mechanism is arranged on the upper side of the second fixing ring (24); the trigger mechanism is used to change the position of the extrusion ring (26).

7. A building foundation pit support structure according to claim 6, It is characterized in that The cross section of the cleaning ring (25) is triangular, and the distance between the cleaning ring (25) and the inner wall of the sleeve (1) gradually decreases from top to bottom.

8. A building foundation pit support structure according to claim 6, It is characterized in that The trigger mechanism comprises a second liquid storage ring (27), the second liquid storage ring (27) being fixedly connected to the upper side of the second fixed ring (24), the second liquid storage ring (27) being slidably connected to a movable ring (28), a tension spring being arranged between the movable ring (28) and the mounting ring (22), the upper side of the second fixed ring (24) being rotatably connected to a plurality of circumferentially evenly distributed mounting shafts (29) via a connecting piece, a torsion spring being arranged between the mounting shaft (29) and the second fixed ring (24), the mounting shaft (29) being fixedly connected to a positioning column (30), the positioning column (30) being in contact with and cooperating with the steel cage (2), the connecting pieces on the second fixed ring (24) being fixedly connected to a third liquid storage ring (31), the mounting shaft (29) penetrating through adjacent third liquid storage rings (31) and being rotatably connected thereto, the lower side of the third liquid storage ring (31) being arranged with a through hole, the third liquid storage ring (31) being connected to the second liquid storage ring (27) via a connecting pipe.

9. A building foundation pit support structure according to claim 8, It is characterized in that A positioning block is fixedly connected inside the third liquid storage ring (31), and a dividing block that slides inside an adjacent third liquid storage ring (31) is fixedly connected to the mounting shaft (29).

10. A building foundation pit support structure according to claim 9, It is characterized in that The elastic coefficient of the tension spring between the moving ring (28) and the mounting ring (22) is greater than the elastic coefficient of the torsion spring between the third liquid storage ring (31) and the adjacent mounting shaft (29).