Deformation joint construction method of disassembly-free assembly type formwork
Through the disassembly and assembly-type formwork construction method, the use of components such as steel bar frames and polyethylene foam boards has solved the problem of difficult to take into account both the construction period and quality in the existing technology, and achieved ultra-long, ultra-thick and large-volume concrete deformation joints. Rapid and high-quality construction.
Patent Information
- Application Number
- CN202411344323.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-11-12
AI Technical Summary
When the existing deformation joint construction methods are used to treat ultra-long, super-thick and large volumes of concrete, they cannot meet the construction period and quality requirements at the same time. The traditional method requires dismantling and assemblage, resulting in a long construction cycle and poor quality.
Adopt the construction method of disassembly and assembly-type formwork. By cutting the scrap steel bars into a rectangular steel bar frame, and installing polyethylene foam boards and quick-to-sink nets inside it, combining rubber water stops to form a stable steel bar frame structure to avoid concrete. The offset caused by impact force realizes a formwork design without removal.
It achieves shortening the construction period, reducing steel bar losses, and improving the stability of the formwork while ensuring quality and appearance. It is suitable for the construction of deformation joints of ultra-long, ultra-thick and large-volume concrete, saving construction period and reducing labor costs.
Smart Images

Figure CN118933089A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction engineering, and in particular to a method for constructing a deformation joint of a disassembly-free assembled formwork. Background Art
[0002] In the traditional construction process of expansion joints, for smaller expansion joints, a foam board is usually stuffed in the expansion joint in advance as a template. However, this technology is limited by the material itself and cannot be applied to expansion joints of ultra-long, ultra-thick, and large-volume concrete, because the foam board cannot be effectively fixed, and the foam board cannot meet the impact and lateral pressure generated during concrete pouring. At the same time, the foam board cannot meet the vibration force generated by the concrete vibrator.
[0003] Therefore, the existing method is to use wooden formwork + skip-bin method for construction. The skip-bin method is effective in reducing cracks in ultra-long, ultra-thick, and ultra-thin large-volume concrete. The skip-bin method divides the concrete floor into multiple bins, usually four bins, and first pours the two bins on the diagonal. After the concrete in the two bins solidifies to a certain strength, the wooden formwork is removed, and then the concrete bins on the other two diagonals are poured. Since the wooden formwork needs to be removed, the four bins cannot be poured at the same time, resulting in a long construction period, which cannot meet the on-site work surface and project schedule. It is not economical for this project and the labor cost will also increase at the same time.
[0004] During the construction of the raft expansion joint of a sewage treatment plant, our company could only construct one side of the raft first to ensure that the design requirements were met. After the concrete strength reached the design strength requirements, the formwork was removed and then the other side of the raft was constructed. Although the quality could be guaranteed, it did not meet the construction period requirements. If the construction period requirements were to be met, extruded boards could only be directly added as formwork, and concrete was poured directly on both sides of the extruded boards at the same time. Although the construction period could be met, the quality could not meet the requirements; the above two construction technologies could not meet the construction period and quality requirements of this project. Therefore, this project invented a non-disassembly assembled formwork and construction method for expansion joints through research. This method can solve the adverse effects of construction period and quality at the same time. Summary of the invention
[0005] The invention provides a method for constructing a deformation joint of a disassembly-free assembled formwork, which solves the above-mentioned problem.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is: a method for constructing a deformation joint of a non-disassembly assembled formwork, the construction method is as follows:
[0007] Step S1, cutting the waste steel bars on site into transverse steel bars and longitudinal steel bars, and welding the transverse steel bars and longitudinal steel bars into a plurality of rectangular steel bar skeletons;
[0008] Step S2, placing a polyethylene foam board in the rectangular inner frame of the steel frame, and tying the polyethylene foam board around and fixing it on the steel frame;
[0009] Step S3, setting quick-closing nets on the left and right sides of the steel skeleton, wherein the quick-closing nets are welded to the steel skeleton and placed for standby;
[0010] Step S4, laying raft slab reinforcement, when laying to a certain height, insert a reinforcement skeleton along the length direction of the deformation joint as the lower reinforcement skeleton, and weld and fix adjacent lower reinforcement skeletons, when the raft slab reinforcement is laid to half the height, lay the embedded rubber water stop above the deformation joint, and then continue to bundle the raft slab reinforcement, and insert a reinforcement skeleton again in the length direction of the deformation joint as the upper reinforcement skeleton, and weld and fix adjacent upper reinforcement skeletons, and then continue to bundle the raft slab reinforcement until the laying of the raft slab reinforcement is completed;
[0011] Step S5: After the raft slab reinforcement is laid, concrete is poured simultaneously on both sides of the expansion joint until it covers the upper reinforcement skeleton;
[0012] Step S6: After the concrete is completely solidified, the construction project is completed.
[0013] Preferably, in step S1, the steel bar skeleton is welded by two transverse steel bars and three longitudinal steel bars, the transverse steel bars are arranged horizontally and in parallel, and the longitudinal steel bars are vertically welded between the two transverse steel bars, two of which are welded at both ends of the transverse steel bars, and one is welded in the middle of the transverse steel bars.
[0014] Preferably, the transverse reinforcements are made of grade 3 steel with a diameter of 28 mm, the length of the transverse reinforcements is 3000 mm, and the length of the longitudinal reinforcements is 272 or 442 mm.
[0015] Preferably, in step S2, the polyethylene foam board is rectangular and matches the rectangular inner frame shape of the steel skeleton. The polyethylene foam board is fixed to the steel skeleton with wire binding at binding points every 500 mm around it.
[0016] Preferably, in step S3, the quick-closing net is welded and fixed to the steel frame at a welding point every 500 mm, and the welding points are staggered with the binding points.
[0017] Preferably, in step S5, when pouring concrete, the final pouring height is 30 mm below the upper steel frame.
[0018] Preferably, in step S5, when pouring the last 30 mm of concrete, a 30 mm thick closed-cell foam board is laid above the deformation joint.
[0019] Compared with the prior art, the advantages of the present invention are:
[0020] (1) The present invention designs a disassembly-free assembled formwork, which can effectively avoid the impact force caused by concrete pouring during the expansion joint concrete pouring process, thereby preventing the construction method from being offset, resulting in poor expansion joint forming quality, unsightly appearance and other quality problems. While ensuring the quality and appearance requirements, it can also save the concrete pouring period and the construction period of the subsequent construction method. The method can realize rapid concrete construction and can be carried out without waiting for the technical interval of the construction joint, thus saving construction period.
[0021] (2) By adopting the green and low-carbon technical concept of prefabricated buildings and using on-site steel waste, the steel loss rate of this project can be reduced, thereby reducing investment costs.
[0022] (3) Compared with the non-disassembly assembled formwork, it has been designed to be miniaturized and faster. The upper steel frame, rubber water stop and lower steel frame are installed independently and can be placed separately during the laying and pouring of raft slab reinforcement, which greatly reduces the difficulty of installation.
[0023] (4) The steel skeleton can increase the stability of the formwork, which can better bear the lateral pressure caused by the pouring of concrete on both sides, thus improving the overall quality.
[0024] (5) Through the design of polyethylene foam board, the concrete on both sides of the expansion joint can be separated. Its chemical properties are stable and not easily corroded. It can be placed in the expansion joint as a buffer material without removal. After being reinforced with a steel skeleton, it can be used in the construction of expansion joints of ultra-long, ultra-thick, and large-volume concrete.
[0025] (6) The design of the quick-closing net can block the concrete and disperse the lateral pressure caused by pouring concrete, making the force more uniform and reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 A flow chart of the construction process of the invention;
[0027] Figure 2 A schematic diagram of the structure of the invented steel bar skeleton unit;
[0028] Figure 3 A schematic diagram of the structure of the invented steel reinforcement skeleton;
[0029] Figure 4 The invention is an assembly diagram of a non-disassembly assembled formwork;
[0030] Figure 5 The invention is a structural schematic diagram of a non-disassembly assembled formwork in a deformation joint of concrete.
[0031] In the figure: 1. Steel skeleton; 11. Horizontal steel bars; 12. Longitudinal steel bars; 2. Polyethylene foam board; 3. Rubber waterstop; 4. Quick-closing net; 5. Closed-cell foam board; 6. Concrete; 7. Expansion joint. DETAILED DESCRIPTION
[0032] The present invention will be further described below.
[0033] Embodiment: A method for constructing a deformation joint of a non-disassembly assembled formwork, see Figure 1 , the specific construction methods are as follows:
[0034] Step S1, cutting the waste steel bars on site into transverse steel bars 11 and longitudinal steel bars 12, welding the transverse steel bars 11 and the longitudinal steel bars 12 into a plurality of rectangular steel bar skeletons 1, wherein the transverse steel bars 11 are made of grade 3 steel with a diameter of 28 mm, the length of the transverse steel bars 11 is 3000 mm, and the length of the longitudinal steel bars 12 is 272 or 442 mm, depending on the casting height; to ensure the supporting stability effect, the steel bar skeleton 1 is made of grade 3 steel with a diameter of 28 mm, and the steel bar skeleton 1 is made of the waste steel bars on site, which can reduce the steel bar loss rate of this project and reduce the investment cost.
[0035] The steel bar skeleton 1 improves the overall stability of the formwork and provides good support strength for the polyethylene foam board 2, thereby avoiding the problem of building deviation and poor forming quality of the deformation joint 7 caused by the impact force caused by pouring concrete 6;
[0036] Step S2, a polyethylene foam board 2 is arranged in the rectangular inner frame of the steel skeleton 1, and the polyethylene foam board 2 is tied and fixed on the steel skeleton 1 on all sides; the concrete 6 on both sides of the deformation joint 7 is separated by the polyethylene foam board 2. The polyethylene foam board 2 has stable chemical properties and is not easily corroded. It can be placed in the deformation joint 7 as a buffer material without being removed. After being reinforced by the steel skeleton 1, it can be suitable for the construction of the deformation joint 7 of super-long, super-thick, and large-volume concrete 6.
[0037] The polyethylene foam board 2 is rectangular and matches the rectangular inner frame of the steel frame 1. In order to better connect the polyethylene foam board 2 to the steel frame 1 and prevent local breakage, the polyethylene foam board 2 is tied at 500mm intervals around the edges and fixed to the steel frame 1 with wire.
[0038] Step S3, quick-closing nets 4 are arranged on the left and right sides of the steel skeleton 1, and the quick-closing nets 4 are welded to the steel skeleton 1 and placed for standby; the quick-closing nets 4 can block the concrete 6 and also disperse the lateral pressure caused by pouring the concrete 6, so that the force is more uniform and reliable.
[0039] In order to better connect the quick-closing net 4 with the steel frame 1, the quick-closing net 4 is welded to the steel frame 1 with a welding point every 500 mm. The welding points and the binding points are staggered, which can further disperse the lateral pressure caused by pouring concrete 6 and avoid breakage of the polyethylene foam board 2 at the binding points.
[0040] The upper steel frame 1, the lower steel frame 1 and the rubber water stop 3 of the steel frame unit of the present invention are fixed into a whole in advance. In the process of laying the raft steel bars, the steel frame unit needs to be pre-buried as a whole, and each section of the steel frame unit is welded in sequence, which is very inconvenient to carry and weld, and the installation, laying and fixing of the polyethylene foam board 2 and the quick-closing net 4 are also very troublesome and inefficient. Therefore, the invention has modularized the steel frame unit, and the upper steel frame 1, the lower steel frame 1 and the rubber water stop 3 are not fixed. Before construction, it is only necessary to fix the polyethylene foam board 2 and the quick-closing net 4 in the steel frame 1 in advance and put them aside for use. In the process of laying the raft steel bars, the lower steel frame 1, the rubber water stop 3 and the upper steel frame 1 are placed synchronously, and the lower steel frame 1, the rubber water stop 3 and the upper steel frame are installed and limited by the trapped raft steel bars. As the height of the raft steel bars is increased, the assembly of the steel frame unit is completed, which is very convenient to operate, and after the modular design, it is very convenient to carry it easily by one person.
[0041] Step S4, laying raft slab steel bars, when laying to a certain height, insert a steel bar skeleton 1 along the length direction of the deformation joint 7 as the lower steel bar skeleton 1, and weld and fix adjacent lower steel bar skeletons 1, when the raft slab steel bars are laid to half the height, lay the embedded rubber water stop 3 above the deformation joint 7, and then continue to bundle the raft slab steel bars, and insert the steel bar skeleton 1 again in the length direction of the deformation joint 7 as the upper steel bar skeleton 1, and weld and fix adjacent upper steel bar skeletons 1, and then continue to bundle the raft slab steel bars until the laying of the raft slab steel bars is completed; since the steel bar skeleton 1 has been miniaturized and modularly designed, the upper steel bar skeleton 1, the rubber water stop 3, and the lower steel bar skeleton 1 are independently installed, and can be placed separately during the pouring process of laying the raft slab steel bars, and the deformation joint 7 formed by the laid raft slab steel bars can be used to achieve the clamping installation of the upper steel bar skeleton 1 and the lower steel bar skeleton 1 on both sides, and can be installed synchronously with the installation progress of laying the raft slab steel bars, which greatly reduces the difficulty of its installation. The entire formwork not only has good structural strength and good appearance, but also does not need to be dismantled after pouring. It can be poured on both sides at the same time, which can realize the rapid construction of concrete 6, and there is no need to wait for the technical interval time of the construction joint to carry out the operation, thus saving construction time.
[0042] Step S5, after the laying of the raft slab reinforcement is completed, concrete 6 is poured on both sides of the deformation joint 7 at the same time. When the pouring height is flush with the top of the upper reinforcement skeleton 1, a 30mm thick closed-cell foam board 5 is laid above the deformation joint 7 until it reaches the top, and then pouring is continued. The final pouring height is flush with the upper surface of the closed-cell foam board 5; the closed-cell foam board 5 has an independent closed-cell bubble structure, and the honeycomb-like holes are evenly distributed in appearance, and are firmly and tightly integrated with the cement adhesive. When placed on the surface of the deformation joint 7, it can naturally adapt to the expansion and contraction changes, and enhance the expansion and water-stopping effect;
[0043] Step S6: After the concrete 6 is completely solidified, the construction project is completed.
[0044] The structure of the non-disassembly assembled template of the present invention is shown in Figures 2 to 5 The non-disassembly assembled formwork is formed by welding multiple sections of rectangular steel frame units end to end. The steel frame unit is mainly composed of a rectangular steel frame 1, a polyethylene foam board 2, a quick-closing net 4 and a rubber waterstop 3. The steel frame 1 is divided into an upper steel frame 1 and a lower steel frame 1. The rubber waterstop 3 is horizontally laid between the upper steel frame 1 and the lower steel frame 1. The polyethylene foam board 2 is laid in the rectangular inner frame of the steel frame 1, and the four sides of the polyethylene foam board 2 are tied and fixed to the steel frame 1. The quick-closing net 4 is welded to the left and right sides of the steel frame 1, and is tightly attached to the two side surfaces of the polyethylene foam board 2.
[0045] The upper steel frame 1 and the lower steel frame 1 have the same shape and are both welded by two transverse steel bars 11 and three longitudinal steel bars 12. The transverse steel bars 11 are arranged horizontally and in parallel, and the longitudinal steel bars 12 are vertically welded between the two transverse steel bars 11, two of which are welded at the two ends of the transverse steel bars 11, and one is welded in the middle of the transverse steel bars 11. A stable supporting frame structure is formed by the transverse steel bars 11 and the longitudinal steel bars 12, and at the same time its stability can be increased, and it can better bear the lateral pressure brought by the pouring of concrete 6 on both sides.
[0046] The above is a detailed introduction to the expansion joint construction method of the non-disassembly assembled formwork provided by the present invention. Specific examples are used in this article to illustrate the principle and implementation mode of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation mode and application scope, and changes and improvements to the present invention will be possible without exceeding the concept and scope specified in the attached claims. In summary, the content of this specification should not be understood as a limitation on the present invention.
Claims
1. A method for constructing a deformation joint of a non-disassembly assembled formwork, characterized in that: The construction method is as follows: Step S1, cutting the waste steel bars on site into transverse steel bars and longitudinal steel bars, and welding the transverse steel bars and longitudinal steel bars into a plurality of rectangular steel bar skeletons; Step S2, placing a polyethylene foam board in the rectangular inner frame of the steel frame, and tying the polyethylene foam board around and fixing it on the steel frame; Step S3, setting quick-closing nets on the left and right sides of the steel skeleton, wherein the quick-closing nets are welded to the steel skeleton and placed for standby; Step S4, laying raft slab reinforcement, when laying to a certain height, insert a reinforcement skeleton along the length direction of the deformation joint as the lower reinforcement skeleton, and weld and fix adjacent lower reinforcement skeletons, when the raft slab reinforcement is laid to half the height, lay the embedded rubber water stop above the deformation joint, and then continue to bundle the raft slab reinforcement, and insert a reinforcement skeleton again in the length direction of the deformation joint as the upper reinforcement skeleton, and weld and fix adjacent upper reinforcement skeletons, and then continue to bundle the raft slab reinforcement until the laying of the raft slab reinforcement is completed; Step S5: After the raft slab reinforcement is laid, concrete is poured simultaneously on both sides of the expansion joint until it covers the upper reinforcement skeleton; Step S6: After the concrete is completely solidified, the construction project is completed.
2. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 1, characterized in that: In step S1, the steel bar skeleton is welded by two transverse steel bars and three longitudinal steel bars, the transverse steel bars are arranged horizontally and in parallel, and the longitudinal steel bars are vertically welded between the two transverse steel bars, two of which are welded at both ends of the transverse steel bars, and one is welded in the middle of the transverse steel bars.
3. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 2, characterized in that: The transverse reinforcements are all made of grade 3 steel with a diameter of 28 mm, the length of the transverse reinforcements is 3000 mm, and the length of the longitudinal reinforcements is 272 or 442 mm.
4. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 1, characterized in that: In step S2, the polyethylene foam board is rectangular and matches the rectangular inner frame shape of the steel frame. The polyethylene foam board is fixed to the steel frame with wire binding at binding points every 500 mm around it.
5. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 1, characterized in that: In step S3, the quick-closing net is welded and fixed to the steel frame at a welding point every 500 mm, and the welding points are staggered with the binding points.
6. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 1, characterized in that: In step S5, when pouring concrete, the final pouring height is 30 mm below the upper steel frame.
7. The method for constructing a deformation joint of a non-disassembly assembled formwork according to claim 6, characterized in that: In step S5, when pouring the last 30 mm of concrete, a 30 mm thick closed-cell foam board is laid above the deformation joint.