Continuous expansion reinforcing band construction method

Through the continuous expansion reinforcement belt construction method, the use of waterproof fixtures and concrete pouring with different expansion agents is achieved to achieve seamless construction and self-waterproofing, which solves the problems of long time and many materials in the existing methods, and improves construction efficiency and structural durability sex.

CN118933199AInactive Publication Date: 2024-11-12CHINA MCC20 GRP CORP LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411361588.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing intermittent and post-cast expansion reinforcement belt construction methods have a long cycle time, many turnover materials are used, and the construction period is greatly affected, making it difficult to effectively control cracks caused by concrete shrinkage stress.

Method used

The continuous expansion reinforcement belt construction method is adopted. By installing waterproof fixtures on both sides of the expansion reinforcement belt, the concrete is poured by continuous construction, and the concrete is poured with different expansion agents on the inner and outer sides to achieve seamless construction and self-waterproofing, reducing post-watering Use of the belt.

Benefits of technology

It improves construction efficiency and quality, shortens construction period, enhances structural durability, reduces leakage and cleaning work, reduces costs, and solves the problems of long time and high materials for existing methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933199A_ABST
    Figure CN118933199A_ABST
Patent Text Reader

Abstract

The invention provides a continuous expansion reinforcing band construction method. The construction method comprises the following steps that the position for paying off an expansion reinforcing band is positioned; expansion reinforcing band waterproof fixing devices are installed on the two sides of the expansion reinforcing band positioning pay-off position; and concrete pouring is conducted in a continuous construction mode, and concrete doped with an expanding agent is adopted for pouring the expansion reinforcing band. The expansion reinforcing band waterproof fixing devices are mounted on the two sides of the expansion reinforcing band, so that the waterproof effect is enhanced, the structural durability is improved, the construction efficiency and quality are effectively improved, and the construction cost is easy to draw; concrete pouring is conducted in a continuous construction mode, a post-cast strip is not reserved any more, seamless construction and structural self-waterproofing are achieved, the construction period of mass concrete floor construction is greatly shortened, the waterproof effect is enhanced, and the structural durability is improved; meanwhile, the continuous reinforcing band replaces a post-cast strip for integrated construction, leakage is reduced, and cleaning of the post-cast strip and secondary formwork erecting work are omitted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of installation engineering, and in particular to a continuous expansion reinforcement belt construction method. Background Art

[0002] In recent years, with the continuous development of construction technology, super-long structures have been widely used in the field of industrial construction. However, since ordinary concrete will produce shrinkage stress during the hardening process, which will cause concrete cracking and damage the overall structure, how to control possible foundation settlement and temperature shrinkage cracks during construction is one of the key difficulties in the construction of super-long structures, especially underground engineering construction.

[0003] Nowadays, the shrinkage stress is generally offset by setting expansion reinforcement strips at the maximum position of concrete shrinkage stress (middle position in length direction). Expansion reinforcement strips are a technical measure to reduce or eliminate post-cast strips and expansion joints and extend the length of continuous casting of components by pouring shrinkage compensation concrete at the preset post-cast strip position of the structure. It can be divided into three types: continuous, intermittent and post-cast. If intermittent and post-cast expansion reinforcement strips are used for construction, the cycle time is long, the turnover materials are more, and the progress of the construction period is greatly affected. Summary of the invention

[0004] In view of this, the present invention proposes a continuous expansion reinforcement belt construction method, aiming to solve the problems of the existing intermittent and post-cast expansion reinforcement belts having a long cycle time, a large amount of turnover materials used, and a great impact on the construction schedule.

[0005] The invention proposes a continuous expansion reinforcement belt construction method, which comprises the following steps: a laying-out step, locating and laying out the position of the expansion reinforcement belt; a reinforcement belt fixing step, installing expansion reinforcement belt waterproof fixing devices on both sides of the expansion reinforcement belt positioning and laying-out position; a concrete pouring step, pouring concrete in a continuous construction manner, during pouring, pouring concrete from one side and moving forward successively until pouring to the expansion reinforcement belt, pouring the expansion reinforcement belt with concrete mixed with an expansion agent, and when pouring to the other side outside the expansion reinforcement belt, pouring with the original concrete, and circulating in sequence until the continuous pouring is completed.

[0006] Furthermore, in the above-mentioned continuous expansion reinforcement band construction method, in the concrete pouring step, the concrete used for pouring outside the expansion reinforcement band is small expansion concrete, and the concrete used for pouring inside the expansion reinforcement band is large expansion concrete; wherein the amount of expansion agent in the small expansion concrete is less than the amount of expansion agent in the large expansion concrete.

[0007] Furthermore, in the above-mentioned continuous expansion reinforcement belt construction method, the concrete strength grade of the large expansion concrete is higher than the concrete strength of the small expansion concrete.

[0008] Furthermore, in the above-mentioned continuous expansion reinforcement belt construction method, the concrete strength grade of the large expansion concrete is one grade higher than the concrete strength grade of the small expansion concrete.

[0009] Furthermore, in the above-mentioned continuous expansion reinforcement band construction method, the expansion reinforcement band waterproof fixing device includes: a plurality of fixing rods connected end to end to form a supporting frame structure; a concrete isolation net arranged inside the supporting frame structure, and the outer edge of the concrete isolation net is connected to the fixing rods, and is used to be arranged on the side of the expansion reinforcement band under the support of the fixing rods to separate the concrete inside the reinforcement band and the concrete outside the reinforcement band; a water stop plate is arranged on the concrete isolation net to prevent water seepage at the joints of the expansion reinforcement band.

[0010] Furthermore, in the above-mentioned continuous expansion reinforcement belt construction method, the concrete isolation net includes a double layer of stacked dense-pore steel wire mesh.

[0011] Furthermore, in the above-mentioned continuous expansion reinforcement belt construction method, the fixing rod is a steel bar structure.

[0012] Furthermore, in the above-mentioned continuous expansion reinforcement belt construction method, each layer of concrete is vibrated and compacted during concrete pouring.

[0013] Furthermore, the above-mentioned continuous expansion reinforcement belt construction method, after the concrete pouring step, also includes the following steps: a curing step, before the concrete is finally set, repeatedly smoothing and pressing, and curing the poured concrete.

[0014] Furthermore, in the above-mentioned continuous expansion reinforcement band construction method, the expansion reinforcement band is located at the position where the maximum shrinkage stress of concrete occurs.

[0015] The continuous expansion reinforcement belt construction method provided by the present invention has a waterproof function by installing expansion reinforcement belt waterproof fixing devices on both sides of the expansion reinforcement belt, strengthens the waterproof effect, improves the durability of the structure, effectively improves the construction efficiency and quality, and is easy to reduce the project cost; when pouring concrete, a continuous construction method is adopted to pour concrete, concrete is poured from one side and gradually moved forward until it is poured to the expansion reinforcement belt, and the expansion reinforcement belt is poured with concrete mixed with an expansion agent. When pouring to the other side outside the expansion reinforcement belt, the original concrete is used for pouring, and the cycle is repeated in sequence until the continuous pouring is completed, and no post-casting belt is left, so that seamless construction and structural self-waterproofing are realized, so that the construction period of large-volume concrete floor is greatly shortened, the waterproof effect is strengthened, and the durability of the structure is improved, and the problems of long cycle time required for existing intermittent and post-casting expansion reinforcement belts, large use of turnover materials, and great impact on construction progress are solved; at the same time, the continuous reinforcement belt replaces the post-casting belt for integrated construction, so as to ensure the overall construction of the structure, reduce leakage, save the cleaning of the post-casting belt and the secondary formwork work, simplify the construction process, shorten the construction period, reduce costs, and improve economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings: Figure 1 A flowchart of a continuous expansion reinforcement belt construction method provided by an embodiment of the present invention; Figure 2 A schematic diagram of the structure of a continuous expansion reinforcement belt provided by an embodiment of the present invention; Figure 3 A schematic diagram of the structure of the expansion reinforcement belt waterproof fixing device provided in an embodiment of the present invention; Figure 4 Another flowchart of the continuous expansion reinforcement belt construction method provided by the embodiment of the present invention. DETAILED DESCRIPTION

[0017] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present disclosure and to be able to fully convey the scope of the present disclosure to those skilled in the art. It should be noted that, in the absence of conflict, the embodiments of the present invention and the features described in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0018] See also Figure 1 , which is a structural schematic diagram of a continuous expansion reinforcement belt construction method provided by an embodiment of the present invention. As shown in the figure, the construction method includes the following steps: The wire laying step S1 is to locate the position of the wire laying expansion reinforcement belt.

[0019] Specifically, the expansion reinforcement belt is required to be set at the maximum location of concrete shrinkage stress, that is, the expansion reinforcement belt is located at the maximum location of concrete shrinkage stress, and the location of the expansion reinforcement belt is determined accordingly, and the location of the expansion reinforcement belt is positioned and laid out, and then checked for correctness. In this embodiment, the width of the expansion reinforcement belt is 2000mm.

[0020] The reinforcement belt fixing step S2 is to install the expansion reinforcement belt waterproof fixing device on both sides of the expansion reinforcement belt positioning and laying-out position.

[0021] Specifically, the expansion reinforcement belt waterproof fixing device 2 is installed on both sides of the expansion reinforcement belt. Among them, the expansion reinforcement belt waterproof fixing device 2 can be arranged vertically and installed on the upper and lower fixed steel bars. In this embodiment, the expansion reinforcement belt is outside, that is, on both sides of the expansion reinforcement belt (such as Figure 2 Concrete 1 can be poured on the left and right sides (as shown), and concrete 3 mixed with expansive agent can be poured inside the expansion reinforcement belt, that is, between the two expansion reinforcement belt waterproof fixing devices 2. The arrangement of the expansion reinforcement belt waterproof fixing devices 2 can achieve separation or isolation between the concrete 1 outside the reinforcement belt and the concrete 3 mixed with expansive agent inside the reinforcement belt, and can also prevent water seepage at the joint between the concrete 1 outside the reinforcement belt and the concrete 3 mixed with expansive agent inside the reinforcement belt, thereby achieving a water-stopping effect.

[0022] In the concrete pouring step S3, the concrete is poured in a continuous construction mode. When pouring, the concrete is poured from one side and gradually moved forward until it is poured to the expansion reinforcement zone. The expansion reinforcement zone is poured with concrete mixed with an expansion agent. When pouring to the other side outside the expansion reinforcement zone, the original concrete is used for pouring, and the cycle is repeated in sequence until the continuous pouring is completed.

[0023] Specifically, a continuous construction method is used to pour concrete to form a continuous expansion reinforcement belt. When pouring, concrete is poured from one side and gradually moved forward until it is poured to the expansion reinforcement belt, that is, the waterproof fixing device 2 of the expansion reinforcement belt on the left side. That is to say, when the concrete is poured to about 1000mm of the expansion reinforcement belt, concrete 3 mixed with an expansion agent is used for pouring. When pouring to about 1000mm on the other side of the reinforcement belt, that is, when pouring to the waterproof fixing device 2 of the expansion reinforcement belt on the right side, the original designed concrete is used for pouring on the right side. The pouring sequence is as follows: Figure 2Shown is poured successively from left to right, and circulated successively until continuous pouring is completed. In the present embodiment, when concrete is poured, each layer of concrete is vibrated and compacted.

[0024] In this embodiment, the concrete used for pouring outside the expansion reinforcement zone is small expansion concrete, and the concrete used for pouring inside the expansion reinforcement zone is large expansion concrete; wherein, the amount of expansion agent in the small expansion concrete is less than that in the large expansion concrete, and the specific amount can be determined according to actual conditions, and is not limited in this embodiment. In order to improve the strength of the expansion reinforcement zone, preferably, the concrete strength grade of the large expansion concrete is higher than the concrete strength of the small expansion concrete; further preferably, the concrete strength grade of the large expansion concrete is one level higher than the concrete strength of the small expansion concrete.

[0025] In this embodiment, the continuous expansion reinforcement belt structure form: the continuous expansion reinforcement belt construction method is to first pour the compensating concrete with a small amount of expansion agent outside the reinforcement belt, and then pour the compensating concrete with a large amount of expansion agent inside the reinforcement belt, and no post-pouring strip is left, thereby achieving seamless construction and structural self-waterproofing.

[0026] See also Figure 3 , which is a schematic diagram of the structure of the expansion reinforcement belt waterproof fixing device provided by an embodiment of the present invention. As shown in the figure, the expansion reinforcement belt waterproof fixing device 2 includes: a plurality of fixing rods 21, a concrete isolation net 22 and a water stop plate 23; wherein, the plurality of fixing rods 21 are connected end to end to form a supporting frame structure; the concrete isolation net 22 is arranged inside the supporting frame structure, and the outer edge of the concrete isolation net 22 is connected to the fixing rod 21, and is used to be arranged on the side of the expansion reinforcement belt under the support of the fixing rod 21 to separate the concrete inside the reinforcement belt from the concrete outside the reinforcement belt; the water stop plate 23 is arranged on the concrete isolation net 22 to prevent water seepage at the joint of the expansion reinforcement belt.

[0027] Specifically, the fixing rod 21 can be a fixed steel bar, for example, a steel bar structure with a diameter of 16 mm. There can be four fixing rods 21, and the four fixing rods 21 are connected end to end to form a rectangular support frame structure. The concrete isolation net 22 can include a double-layer stacked dense mesh steel wire mesh. The concrete isolation net 22 is arranged inside the support frame structure surrounded by the four fixing rods 21, and the outer edge is connected to the fixing rods 21 to fix the concrete isolation net 22 through the fixing rods 21. The water stop plate 23 can be a galvanized water stop steel plate to enhance the waterproof effect, realize structural self-waterproofing, and improve the durability of the structure.

[0028] See also Figure 4 , which is another flowchart of the continuous expansion reinforcement belt construction method provided by the embodiment of the present invention. As shown in the figure, the construction method may also include the following steps: The wire laying step S1 is to locate the position of the wire laying expansion reinforcement belt.

[0029] The reinforcement belt fixing step S2 is to install the expansion reinforcement belt waterproof fixing device on both sides of the expansion reinforcement belt positioning and laying-out position.

[0030] In the concrete pouring step S3, the concrete is poured in a continuous construction mode. When pouring, the concrete is poured from one side and gradually moved forward until it is poured to the expansion reinforcement zone. The expansion reinforcement zone is poured with concrete mixed with an expansion agent. When pouring to the other side outside the expansion reinforcement zone, the original concrete is used for pouring, and the cycle is repeated in sequence until the continuous pouring is completed.

[0031] In the curing step S4, before the concrete is finally set, the poured concrete is repeatedly pressed and cured.

[0032] Specifically, before the concrete is finally set, it is repeatedly pressed to prevent the appearance of surface shrinkage cracks. After the pressing is completed, protective work is carried out, for example, the concrete curing time in the expansion reinforcement zone can be greater than or equal to 14 days.

[0033] In summary, the continuous expansion reinforcement belt construction method provided in the present embodiment has a waterproof function by installing expansion reinforcement belt waterproof fixing devices on both sides of the expansion reinforcement belt, which enhances the waterproof effect, improves the durability of the structure, effectively improves the construction efficiency and quality, and is easy to pull the project cost; when pouring concrete, a continuous construction method is adopted to pour concrete, pouring concrete from one side and moving forward gradually until it is poured to the expansion reinforcement belt, and the expansion reinforcement belt is poured with concrete mixed with an expansion agent. When pouring to the other side outside the expansion reinforcement belt, the original concrete is used for pouring, and the cycle is repeated in sequence until the continuous pouring is completed, and no post-casting belt is left, so that seamless construction and structural self-waterproofing are realized, so that the construction period of large-volume concrete floors is greatly shortened, the waterproof effect is enhanced, and the durability of the structure is improved; at the same time, the continuous reinforcement belt replaces the post-casting belt for integrated construction, which ensures the overall construction of the structure, reduces leakage, saves the cleaning of the post-casting belt and the secondary formwork work, simplifies the construction process, shortens the construction period, reduces costs, and improves economic benefits.

[0034] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0035] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0036] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A continuous expansion reinforcement belt construction method, It is characterized in that The steps include: The laying-out step is to locate the position of the laying-out expansion reinforcement belt; The reinforcement belt fixing step includes installing the expansion reinforcement belt waterproof fixing device on both sides of the expansion reinforcement belt positioning and laying-out position; The concrete pouring step adopts a continuous construction method to pour concrete. When pouring, concrete is poured from one side and moved forward gradually until it is poured to the expansion reinforcement zone. The expansion reinforcement zone is poured with concrete mixed with an expansion agent. When pouring to the other side outside the expansion reinforcement zone, the original concrete is used for pouring, and the cycle is repeated in sequence until the continuous pouring is completed.

2. The continuous expansion reinforcement belt construction method according to claim 1, It is characterized in that In the concrete pouring step, the concrete used for pouring outside the expansion reinforcement zone is small expansion concrete, and the concrete used for pouring inside the expansion reinforcement zone is large expansion concrete; wherein the amount of expansion agent in the small expansion concrete is less than that in the large expansion concrete.

3. The continuous expansion reinforcement belt construction method according to claim 2, It is characterized in that The concrete strength grade of the large-expansion concrete is higher than the concrete strength of the small-expansion concrete.

4. The continuous expansion reinforcement belt construction method according to claim 3, It is characterized in that The concrete strength grade of the large expansion concrete is one grade higher than that of the small expansion concrete.

5. The continuous expansion reinforcement belt construction method according to any one of claims 1 to 4, It is characterized in that The expansion reinforcement belt waterproof fixing device comprises: A plurality of fixed rods are connected end to end to form a supporting frame structure; A concrete isolation net is arranged inside the supporting frame structure, and the outer edge of the concrete isolation net is connected to the fixing rod, and is used to be arranged on the side of the expansion reinforcement belt under the support of the fixing rod to separate the concrete inside the reinforcement belt from the concrete outside the reinforcement belt; The water stop plate is arranged on the concrete isolation net and is used to prevent water seepage at the joints of the expansion reinforcement belt.

6. The continuous expansion reinforcement belt construction method according to claim 5, It is characterized in that The concrete isolation net comprises double-layered dense-pore steel wire mesh sheets.

7. The continuous expansion reinforcement belt construction method according to claim 5, It is characterized in that The fixing rod is a steel bar structure.

8. The continuous expansion reinforcement belt construction method according to any one of claims 1 to 4, It is characterized in that When pouring concrete, each layer of concrete is vibrated and compacted.

9. The continuous expansion reinforcement belt construction method according to any one of claims 1 to 4, It is characterized in that After the concrete pouring step, the following steps are also included: Curing steps: Before the concrete finally sets, repeatedly smooth and compact it and cure the poured concrete.

10. The continuous expansion reinforcement belt construction method according to any one of claims 1 to 4, It is characterized in that The expansion reinforcement belt is located at the location where the maximum shrinkage stress of concrete occurs.

Citation Information

Patent Citations

  • Water prevention and crack resistance construction method with expanding agent added into bottom board of underground structure

    CN105064414A

  • Construction structure for controlling concrete cracks and construction method thereof

    CN116623814A

  • Large-volume super-long concrete structure expansion reinforcing band and pouring construction method

    CN116876675A

  • Rapid construction method for large-area super-thick concrete terrace

    CN117646539A

  • Super-long seamless concrete slab doped with MAC magnesium high-performance concrete anti-cracking agent

    CN215484026U