Connecting structure used between wall formworks on two sides of shear wall and shear wall
By designing the connecting structure of embedded steel plates and connectors between the wall molds on both sides of the shear wall, the problem of prefabricated wall panels not participating in the on-site binding of structural stress and steel bars is solved, the installation efficiency and material utilization are improved, and the installation efficiency and material utilization are achieved. Efficient shear wall construction.
Patent Information
- Application Number
- CN202411288409.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-09-14
AI Technical Summary
In the prior art, prefabricated wall panels do not participate in structural stress, waste materials, and the cast shear wall steel bars need to be tied on site, which limits the improvement of production efficiency.
A connection structure is designed for the wall molds on both sides of the shear wall. The first prefabricated wall mold is connected with the second prefabricated wall mold through embedded steel plates and connectors, replacing longitudinal steel bars to achieve prefabricated and rapid Connect and reduce the workload of on-site binding.
It improves installation efficiency and material utilization, reduces on-site workload, increases the available indoor building area, and realizes the performance of traditional steel mesh.
Smart Images

Figure CN118933236A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of concrete modular buildings, and in particular relates to a connection structure between wall forms on both sides of a shear wall and a shear wall. Background Art
[0002] Prefabricated shear walls can be divided into two types of technologies: composite shear walls and prefabricated solid walls. When prefabricated technology is upgraded to modular buildings, composite shear walls are more suitable for interior walls than prefabricated solid walls.
[0003] Modular construction refers to the modularization of a single building according to spatial structure, apartment type and functional zoning, and then the prefabrication of spatial modules in the factory, and then the transportation of each module to the construction site for modular installation and construction, and finally the formation of a building entity that meets the safety, reliability and related functional requirements. Compared with traditional construction methods, modular integrated construction methods have the advantages of high construction efficiency, resource conservation, environmental protection, and civilized construction.
[0004] There will be main structures such as load-bearing walls between adjacent modules of modular buildings. The composite shear wall structure has the characteristics of good overall performance, high rigidity, and small lateral deformation under horizontal action. It is widely used in load-bearing walls. The modules of modular buildings use concrete wall panels as the on-site concrete pouring formwork to make composite shear walls, which greatly reduces the on-site formwork and interior decoration time, and minimizes the impact on surrounding residents.
[0005] However, patent CN218522010U discloses a prefabricated wall structure in an integrated building. The prefabricated wall panel used as a formwork for pouring concrete is only used as a formwork and is not a part of the shear wall. It does not participate in the structural force, which wastes materials and encroaches on the indoor usable area. In addition, the steel bars of the shear wall after pouring need to be tied on site, which limits the improvement of production efficiency. Summary of the invention
[0006] 1. Technical issues to be resolved
[0007] In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a connection structure and a shear wall for use between the wall formworks on both sides of the shear wall, thereby solving the technical problems that the prefabricated wall panels do not participate in the structural stress, occupy the indoor usable area, and the steel bars of the shear wall after casting need to be tied on site.
[0008] (II) Technical solution
[0009] In order to achieve the above object, the main technical solutions adopted by the present invention include:
[0010] On the one hand, an embodiment of the present invention provides a connection structure for wall formworks on both sides of a shear wall, including a first connection component and a second connection component, the first connection component including a first steel plate and a first connection member, the first steel plate including a first embedded end, the first embedded end being used to be embedded in a first prefabricated wall formwork forming a shear wall, and the first connection member being fixed to an end of the first steel plate away from the first embedded end; the second connection component including a second steel plate and a second connection member, the second steel plate including a second embedded end, the second embedded end being used to be embedded in a second prefabricated wall formwork forming a shear wall, and the second connection member being fixed to an end of the second steel plate away from the second embedded end; the first connection component and the second connection component are connected by fixing the first connection member to the second connection member.
[0011] Furthermore, the first steel plate is consistent in height with the first prefabricated wall formwork, the second steel plate is consistent in height with the second prefabricated wall formwork, and a plurality of vertical through holes are provided on the first steel plate and the second steel plate for accommodating transverse reinforcement of the beam connected to the shear wall.
[0012] Furthermore, the cross-sections of the first steel plate and the second steel plate are both L-shaped, the cross-section of the first steel plate is a horizontal portion and the connected cross-section is a partially vertical portion to form a first embedded end, the cross-section of the first steel plate is a vertical portion with a plurality of first groove-type slide rails fixed at the end, the plurality of first groove-type slide rails are arranged along the height direction of the first prefabricated wall formwork, and the first groove-type slide rails are the first connecting member; the cross-section of the second steel plate is a horizontal portion and the connected cross-section is a partially vertical portion to form a second embedded end, the cross-section of the second steel plate is a vertical portion with a third steel plate welded at the end, the third steel plate is consistent in height with the second steel plate, the plane where the third steel plate is located is perpendicular to the plane where the cross-section of the second steel plate is a vertical portion, and the third steel plate is the second connecting member; the third steel plate is locked with all the first groove-type slide rails.
[0013] Furthermore, first chamfers are formed on the inner sides of the upper and lower openings of the first groove-shaped slide rail to form a trumpet-mouth shape.
[0014] Furthermore, first connecting plates extend from both sides of the first groove-shaped slide rail, and the two first connecting plates are welded to the vertical portion of the cross section of the first steel plate.
[0015] Furthermore, the first connecting component and the second connecting component have the same structure, and the first connecting component and the second connecting component are symmetrically arranged about the center of the shear wall; the first steel plate and the second steel plate both include an integrally formed vertical plate and horizontal plates respectively connected to the two ends of the vertical plate, and the extension directions of the two horizontal plates are opposite, and a plurality of second groove-type slide rails are welded on a part of the vertical plate connected to one of the horizontal plates, and the plurality of second groove-type slide rails are arranged along the height direction of the wall formwork; the horizontal plate of the first steel plate away from the second groove-type slide rail and the connected part of the vertical plate form a first embedded end, and the second groove-type slide rail on the first steel plate is a first connecting member; the horizontal plate of the second steel plate away from the second groove-type slide rail and the connected part of the vertical plate form a second embedded end, and the second groove-type slide rail on the second steel plate is a second connecting member; the plurality of second groove-type slide rails of the first steel plate cooperate and lock with the horizontal plate of the second steel plate close to the second groove-type slide rail, and at the same time, the plurality of second groove-type slide rails of the second steel plate cooperate and lock with the horizontal plate of the first steel plate close to the second groove-type slide rail.
[0016] Furthermore, the inner sides of the upper and lower openings of the second groove-shaped slide rail are both provided with second chamfers to form a trumpet shape.
[0017] Furthermore, the second groove-shaped slide rail extends out a second connecting plate, and the second connecting plate of the second groove-shaped slide rail of the first steel plate is welded to the vertical plate of the first steel plate; the second connecting plate of the second groove-shaped slide rail of the second steel plate is welded to the vertical plate of the second steel plate.
[0018] On the other hand, an embodiment of the present invention provides a shear wall, including a first prefabricated wall formwork, a second prefabricated wall formwork and a plurality of connecting structures, the first prefabricated wall formwork and the second prefabricated wall formwork are both L-shaped, and the openings of the first prefabricated wall formwork and the second prefabricated wall formwork are arranged back to back to form a T-shaped shear wall; the first prefabricated wall formwork is provided with a first horizontal steel bar of the shear wall, the first prefabricated wall formwork at the long wall position forming the shear wall is pre-embedded with a first connecting component, the first horizontal steel bar is located on the side of the first connecting component away from the second prefabricated wall formwork and is welded to the first embedded end; the second prefabricated wall formwork is provided with a second horizontal steel bar of the shear wall, the second prefabricated wall formwork at the long wall position forming the shear wall is pre-embedded with a second connecting component, the second horizontal steel bar is located on the side of the second connecting component away from the first prefabricated wall formwork and is welded to the second embedded end; the first prefabricated wall formwork and the second prefabricated wall formwork are connected by a plurality of connecting structures to achieve counter-tensioning.
[0019] Furthermore, two fourth steel plates are fixed to the top of the first connecting component and the second connecting component, and the fourth steel plates are L-shaped. The open ends of the two fourth steel plates are relatively arranged and fixed on both sides of the first steel plate or the second steel plate, and a receiving groove is formed between the two fourth steel plates; when the two shear walls are vertically stacked, the first steel plate or the second steel plate located above is inserted into the corresponding receiving groove located below.
[0020] (III) Beneficial effects
[0021] The beneficial effects of the present invention are:
[0022] The present invention provides a connection structure between wall molds on both sides of a shear wall. A first connection component embedded in a first prefabricated wall mold forming the shear wall and a second connection component embedded in a second prefabricated wall mold forming the shear wall are provided, and the first steel plate in the first connection component is connected to the second steel plate in the second connection component by fixing the first connection member and the second connection member. This can achieve an effective connection between the first connection component and the second connection component, making the installation of the first connection component and the second connection component convenient, fast and highly accurate, and greatly improving the installation efficiency.
[0023] A shear wall of the present invention has a plurality of connection structures for the wall forms on both sides of the shear wall arranged between the first prefabricated wall formwork and the second prefabricated wall formwork, wherein the first steel plate and the second steel plate in the connection structure replace the longitudinal reinforcement of the shear wall and are respectively welded to the first horizontal reinforcement and the second horizontal reinforcement of the shear wall, and the first connection assembly is connected to the second connection assembly to realize the opposite pulling of the first prefabricated wall formwork and the second prefabricated wall formwork. The first horizontal reinforcement and the second horizontal reinforcement of the shear wall do not need to be tied on site, but are directly buried in the first prefabricated wall formwork and the second prefabricated wall formwork respectively, so that the first horizontal reinforcement and the second horizontal reinforcement of the shear wall do not need to be tied on site, but are directly buried in the first prefabricated wall formwork and the second prefabricated wall formwork respectively, thereby having the same performance as the traditional steel mesh, and the installation is convenient, fast and high-precision, which greatly improves the installation efficiency and greatly reduces the workload on site.
[0024] In addition, the connection structure enables the first precast wall form, the second precast wall form and the cast-in-place concrete to be effectively superimposed to form a part of the shear wall to form a complete force-bearing whole, so that the first precast wall form and the second precast wall form can jointly participate in the structural force, reducing the use of materials and increasing the indoor available building area. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 is a structural schematic diagram of the connection structure in Example 1;
[0026] Figure 2 It is a structural schematic diagram of the connection structure in Embodiment 1 from another perspective;
[0027] Figure 3 is a top view of the connection structure in Example 1;
[0028] Figure 4 It is a structural schematic diagram of the connection structure in the shear wall in the first embodiment;
[0029] Figure 5 It is a schematic diagram of the internal local structure of the shear wall in the first embodiment;
[0030] Figure 6 It is a schematic diagram of the local structure of the connection between two adjacent layers of shear walls in the first embodiment;
[0031] Figure 7 It is a structural schematic diagram of the connection structure in the second embodiment;
[0032] Figure 8 This is a structural schematic diagram of the connection structure in Embodiment 2 from another perspective;
[0033] Fig. 9 is a top view of the connection structure in Example 2;
[0034] Fig.10 It is a structural schematic diagram of the connection structure in the shear wall in the second embodiment;
[0035] Fig.11 It is a schematic diagram of the internal local structure of the shear wall in the second embodiment;
[0036] Fig.12 It is a schematic diagram of the local structure of the connection between two adjacent layers of shear walls in the second embodiment.
[0037] [Description of Reference Numerals]
[0038] 1: first connecting assembly; 11: first steel plate; 111: vertical plate; 112: horizontal plate; 12: first grooved slide rail; 121: first chamfer; 122: first connecting plate; 13: second grooved slide rail; 131: second chamfer; 132: second connecting plate;
[0039] 2: second connecting assembly; 21: second steel plate; 22: third steel plate;
[0040] 3: Through hole;
[0041] 4: first precast wall form; 41: first horizontal reinforcement;
[0042] 5: second precast wall form; 51: second horizontal reinforcement;
[0043] 7: Beam; 71: Transverse reinforcement;
[0044] 8: fourth steel plate; 81: receiving groove. DETAILED DESCRIPTION
[0045] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below through specific implementation modes in conjunction with the accompanying drawings.
[0046] On the one hand, if Figure 1-12 As shown, the present invention provides a shear wall, such as Figure 4-6 , Figure 10-12As shown, it includes a first prefabricated wall form 4, a second prefabricated wall form 5, a plurality of connection structures and cast-in-place concrete. The first prefabricated wall form 4 and the second prefabricated wall form 5 are both concrete slabs cast from fiber concrete materials, and are both L-shaped. The openings of the first prefabricated wall form 4 and the second prefabricated wall form 5 are arranged opposite to each other, and concrete is poured into the cavity between the first prefabricated wall form 4 and the second prefabricated wall form 5 to form a T-shaped shear wall. The first prefabricated wall form 4 and the second prefabricated wall form 5 are connected by a plurality of connection structures to achieve tension. The connection structure enables the first prefabricated wall form 4 and the second prefabricated wall form 5 to be effectively connected, thereby improving the integration and installation efficiency of the first prefabricated wall form 4 and the second prefabricated wall form 5. The connection structure enables the first prefabricated wall form 4 and the second prefabricated wall form 5 to be combined with the cast-in-place concrete to form a complete force-bearing whole, becoming a part of the shear wall, thereby improving the material utilization rate and increasing the indoor available building area.
[0047] The shear wall consists of a long wall part and a short wall part. The short wall part contains a steel cage formed by traditional longitudinal bars and stirrups. The upper end of the longitudinal bars is a mechanical sleeve used for overlapping the longitudinal bars when two shear walls are vertically stacked.
[0048] like Figure 4-5 , Figure 10-11 As shown, the first prefabricated wall formwork 4 of the long wall portion is provided with the first horizontal steel bar 41 of the shear wall, and the first prefabricated wall formwork 4 at the long wall position forming the shear wall is pre-embedded with the first connecting component 1, and the first horizontal steel bar 41 is located on the side of the first connecting component 1 away from the second prefabricated wall formwork 5 and is welded to the first embedded end of the first steel plate 11.
[0049] like Figure 4 , Fig.10 As shown, the second prefabricated wall formwork 5 is provided with the second horizontal steel bar 51 of the shear wall, and the second prefabricated wall formwork 5 at the long wall position forming the shear wall is pre-embedded with the second connecting component 2, and the second horizontal steel bar 51 is located on the side of the second connecting component 2 away from the first prefabricated wall formwork 4 and is welded to the second embedded end of the second steel plate 21.
[0050] The first steel plate 11 and the second steel plate 21 make it unnecessary to tie the first horizontal steel bars 41 and the second horizontal steel bars 51 of the shear wall on site, but directly bury them in the first prefabricated wall formwork 4 and the second prefabricated wall formwork 5. At the same time, by respectively setting the first connecting component 1 and the second connecting component 2, the first steel plates 11 and the second steel plates 21 therein replace the longitudinal steel bars of the shear wall, thereby reducing the binding of the longitudinal steel bars and greatly reducing the workload of on-site binding.
[0051] It can be seen that the first connecting assembly 1 and the second connecting assembly 2 play the role of longitudinal reinforcement and tighten the first prefabricated wall formwork 4 and the second prefabricated wall formwork 5, thereby achieving the same performance as the traditional steel mesh. The wall formwork on both sides of the shear wall can be installed conveniently, quickly and with high precision, greatly improving the installation efficiency.
[0052] Since the long wall portion uses the first steel plate 11 and the second steel plate 21 to replace the longitudinal reinforcement of the shear wall, a fourth steel plate 8 is set as a lap steel plate. When the two shear walls are vertically stacked, the first steel plate 11 and the second steel plate 21 of the same layer are overlapped with the corresponding first steel plates 11 and the second steel plates 21 of the adjacent layer.
[0053] Specifically, Figure 5-6 , Figure 11-12 Two fourth steel plates 8 are fixed to the top of the first connecting component 1 and the second connecting component 2. The fourth steel plate 8 is L-shaped. The opening ends of the two fourth steel plates 8 are relatively arranged and fixed on both sides of the first steel plate 11 or the second steel plate 21. A receiving groove 81 is formed between the two fourth steel plates 8.
[0054] When two shear walls are vertically stacked, the first steel plate 11 or the second steel plate 21 located on the upper side is inserted into the corresponding receiving groove 81 located on the lower side.
[0055] Installation method:
[0056] First, a first prefabricated wall formwork 4 and a second prefabricated wall formwork 5 are produced, wherein the first connection component 1 and the second connection component 2 are pre-embedded in the long wall portion of the first prefabricated wall formwork 4 and the second prefabricated wall formwork 5, and then the first connection component 1 and the second connection component 2 are installed, and then a steel cage formed by traditional longitudinal bars and stirrups is pre-embedded in the short wall portion of the first prefabricated wall formwork 4 and the second prefabricated wall formwork 5.
[0057] Finally, concrete is poured into the cavity between the first precast wall form 4 and the second precast wall form 5 to complete the construction of the shear wall.
[0058] On the other hand, the present invention provides a connection structure between wall forms on both sides of a shear wall and a shear wall. The specific structure of the first connection component 1 and the second connection component 2 provides two embodiments in the present invention, which are as follows:
[0059] Embodiment 1
[0060] like Figure 1-6As shown, the present invention provides a connection structure for wall forms on both sides of a shear wall, including a first connection component 1 and a second connection component 2. The first connection component 1 includes a first steel plate 11 and a first connection member, the first steel plate 11 includes a first embedded end, the first embedded end is used to be embedded in a first prefabricated wall formwork 4 forming a shear wall, and the first connection member is fixed to an end of the first steel plate 11 away from the first embedded end. The cross-section of the first steel plate 11 is L-shaped, and the cross-section of the first steel plate 11 is a horizontal portion and the connected cross-section is a partially vertical portion to form the first embedded end. In this embodiment, the first connection member is a first groove-type slide rail 12. A plurality of first groove-type slide rails 12 are fixed to the end of the vertical portion of the cross-section of the first steel plate 11 and are arranged along the height direction of the first prefabricated wall formwork 4.
[0061] The second connecting assembly 2 includes a second steel plate 21 and a second connecting member, the second steel plate 21 includes a second embedded end, the second embedded end is used to be embedded in the second prefabricated wall form 5 forming the shear wall, and the second connecting member is fixed to the end of the second steel plate 21 away from the second embedded end. The cross section of the second steel plate 21 is L-shaped, the cross section of the second steel plate 21 is a horizontal portion and the connected cross section is a partial vertical portion to form the second embedded end. In this embodiment, the second connecting member is a third steel plate 22. The third steel plate 22 is welded to the end of the vertical portion of the cross section of the second steel plate 21, the plane where the third steel plate 22 is located is perpendicular to the plane where it is located, and the height of the third steel plate 22 is consistent with that of the second steel plate 21.
[0062] The first connecting assembly 1 and the second connecting assembly 2 are inserted into all the first grooved slide rails 12 through the third steel plate 22 and locked with all the first grooved slide rails 12 .
[0063] Preferably, if Figure 3 As shown, the first grooved slide rail 12 has first chamfers 121 formed into a trumpet shape on the inner sides of the upper and lower openings, so that the second prefabricated wall form 5 can be matched with the already placed first prefabricated wall form 4 or the first prefabricated wall form 4 can be matched with the already placed second prefabricated wall form 5 accurately and quickly. Figure 2 , Figure 3 As shown, in order to strengthen the connection between the first grooved rail 12 and the first steel plate 11 and prevent the first grooved rail 12 from deforming and shifting after being subjected to force, first connecting plates 122 are extended on both sides of the first grooved rail 12, and the two first connecting plates 122 are welded to the vertical portion of the cross section of the first steel plate 11.
[0064] Preferably, the thickness of the first steel plate 11 and the second steel plate 21 ranges from 3 mm to 10 mm, and the material is steel with a strength grade of Q235 or above.
[0065] like Figure 5-6As shown, the first steel plate 11 is at the same height as the first prefabricated wall formwork 4, and the second steel plate 21 is at the same height as the second prefabricated wall formwork 5. A plurality of vertical through holes 3 are provided on the first steel plate 11 and the second steel plate 21 for accommodating the transverse reinforcement 71 of the beam 7 connected to the shear wall.
[0066] Embodiment 2
[0067] like Figure 7-12 As shown, the present invention provides a connection structure between wall forms on both sides of a shear wall, including a first connection component 1 and a second connection component 2. The first connection component 1 has the same structure as the second connection component 2, and the first connection component 1 and the second connection component 2 are symmetrically arranged about the center of the shear wall. The first connection component 1 includes a first steel plate 11 and a first connecting member. The first steel plate 11 includes a first embedded end, and the first embedded end is used to be embedded in a first prefabricated wall form 4 forming a shear wall. The first connecting member is fixed to an end of the first steel plate 11 away from the first embedded end. The first steel plate 11 includes an integrally formed vertical plate 111 and horizontal plates 112 respectively connected to both ends of the vertical plate 111. The two horizontal plates 112 extend in opposite directions. A plurality of second groove-type slide rails 13 are welded on a portion of the vertical plate 111 to which one of the horizontal plates 112 is connected, and the plurality of second groove-type slide rails 13 are arranged along the height direction of the wall form. The horizontal plate 112 of the first steel plate 11 away from the second grooved rail 13 and the connected part of the vertical plate 111 form a first embedded end. In this embodiment, the first connecting member is the second grooved rail 13 on the first steel plate 11 .
[0068] The second connecting assembly 2 includes a second steel plate 21 and a second connecting member. The second steel plate 21 includes a second embedded end, and the second embedded end is used to be embedded in the second prefabricated wall form 5 forming the shear wall. The second connecting member is fixed to the end of the second steel plate 21 away from the second embedded end. The second steel plate 21 also includes an integrally formed vertical plate 111 and horizontal plates 112 respectively connected to the two ends of the vertical plate 111. The extension directions of the two horizontal plates 112 are opposite. A plurality of second grooved rails 13 are welded on a portion of the vertical plate 111 connected to one of the horizontal plates 112. The plurality of second grooved rails 13 are arranged along the height direction of the wall form. The horizontal plate 112 of the second steel plate 21 away from the second grooved rail 13 and the connected portion of the vertical plate 111 form the second embedded end. In this embodiment, the second connecting member is the second grooved rail 13 on the second steel plate 21.
[0069] The first connecting component 1 and the second connecting component 2 are inserted into the multiple second grooved rails 13 of the first steel plate 11 through the horizontal plate 112 of the second steel plate 21 close to the second grooved rail 13 and locked with the multiple second grooved rails 13. At the same time, the horizontal plate 112 of the first steel plate 11 close to the second grooved rail 13 is inserted into the multiple second grooved rails 13 of the second steel plate 21 and locked with the multiple second grooved rails 13.
[0070] Preferably, if Fig. 9 As shown, the inner sides of the upper and lower openings of the second grooved slide rail 13 are both provided with second chamfers 131 to form a bell-mouth shape. This allows for precise and quick matching of the second prefabricated wall form 5 with the already placed first prefabricated wall form 4 or the first prefabricated wall form 4 with the already placed second prefabricated wall form 5. Figure 7 , Fig. 9 As shown, in order to strengthen the connection between the second grooved rail 13 and the first steel plate 11 and the connection between the second grooved rail 13 and the second steel plate 21, and to prevent the first grooved rail 12 from deforming and shifting after being stressed, a second connecting plate 132 is extended from the second grooved rail 13, and the second connecting plate 132 of the second grooved rail 13 of the first steel plate 11 is welded to the vertical plate 111 of the first steel plate 11. The second connecting plate 132 of the second grooved rail 13 of the second steel plate 21 is welded to the vertical plate 111 of the second steel plate 21.
[0071] Preferably, the thickness of the first steel plate 11 and the second steel plate 21 ranges from 3 mm to 10 mm, and the material is steel with a strength grade of Q235 or above.
[0072] like Figure 11-12 As shown, the first steel plate 11 is at the same height as the first prefabricated wall formwork 4, and the second steel plate 21 is at the same height as the second prefabricated wall formwork 5. A plurality of vertical through holes 3 are provided on the first steel plate 11 and the second steel plate 21 for accommodating the transverse reinforcement 71 of the beam 7 connected to the shear wall.
[0073] The thickness of the first grooved slide rail 12 and the second grooved slide rail 13 ranges from 8 mm to 16 mm.
[0074] Compared with the second embodiment, the first embodiment has one more welding process than the second embodiment because the second steel plate 21 is also welded with the third steel plate 22. However, from the perspective of installation, since only one side of the third steel plate 22 needs to be aligned and inserted into all the first grooved rails 12, the installation is simpler than the second embodiment.
[0075] In the second embodiment, since the first connecting assembly 1 and the second connecting assembly 2 have the same structure, they can be made into standard parts for batch processing, and the first steel plate 11 and the second steel plate 21 are both integrally formed bending parts, which reduces welding and makes processing simpler. However, from the perspective of installation, since the horizontal plates 112 on both sides need to be aligned and inserted into the corresponding second grooved slide rails 13, the installation is more complicated than that of the first embodiment, but the tensioning strength will also be higher.
[0076] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0077] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0078] In the present invention, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.
[0079] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0080] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may alter, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A connection structure between wall forms on both sides of a shear wall, characterized in that: The invention comprises a first connection assembly (1) and a second connection assembly (2), wherein the first connection assembly (1) comprises a first steel plate (11) and a first connection piece, wherein the first steel plate (11) comprises a first embedded end, wherein the first embedded end is used to be embedded in a first prefabricated wall form (4) forming the shear wall, and the first connection piece is fixed to an end of the first steel plate (11) away from the first embedded end; The second connection assembly (2) comprises a second steel plate (21) and a second connection piece, the second steel plate (21) comprises a second embedded end, the second embedded end is used to be embedded in a second prefabricated wall form (5) forming the shear wall, and the second connection piece is fixed to an end of the second steel plate (21) away from the second embedded end; The first connecting component (1) and the second connecting component (2) are connected by fixing the first connecting member to the second connecting member.
2. The connection structure between the wall forms on both sides of the shear wall according to claim 1 is characterized in that: The first steel plate (11) is at the same height as the first prefabricated wall form (4), the second steel plate (21) is at the same height as the second prefabricated wall form (5), and the first steel plate (11) and the second steel plate (21) are both provided with a plurality of vertical through holes (3) for accommodating transverse reinforcement (71) of a beam (7) connected to the shear wall.
3. The connection structure between the wall forms on both sides of the shear wall according to claim 2 is characterized in that: The cross-sections of the first steel plate (11) and the second steel plate (21) are both L-shaped, the cross-section of the first steel plate (11) is a horizontal portion and the connected cross-section is a partially vertical portion to form the first embedded end, a plurality of first grooved slide rails (12) are fixed to the end of the vertical portion of the cross-section of the first steel plate (11), the plurality of first grooved slide rails (12) are arranged along the height direction of the first prefabricated wall form (4), and the first grooved slide rails (12) are the first connecting member; The cross section of the second steel plate (21) is a horizontal portion and the connected cross section is a partially vertical portion to form the second embedded end, the end of the cross section of the second steel plate (21) is a vertical portion and a third steel plate (22) is welded thereto, the height of the third steel plate (22) is consistent with that of the second steel plate (21), the plane where the third steel plate (22) is located is perpendicular to the plane where the cross section of the second steel plate (21) is a vertical portion, and the third steel plate (22) is the second connecting member; The third steel plate (22) cooperates and locks with all of the first groove-shaped slide rails (12).
4. The connection structure between the wall forms on both sides of the shear wall according to claim 3 is characterized in that: The inner sides of the upper and lower openings of the first groove-shaped slide rail (12) are both provided with first chamfers (121) to form a bell-mouth shape.
5. The connection structure between wall forms on both sides of a shear wall according to claim 3, characterized in that: First connecting plates (122) extend from both sides of the first groove-shaped slide rail (12), and the two first connecting plates (122) are welded to the vertical portion of the cross section of the first steel plate (11).
6. The connection structure between wall forms on both sides of a shear wall according to claim 2, characterized in that: The first connection component (1) and the second connection component (2) have the same structure, and the first connection component (1) and the second connection component (2) are symmetrically arranged with respect to the center of the shear wall; The first steel plate (11) and the second steel plate (21) each include an integrally formed vertical plate (111) and horizontal plates (112) respectively connected to both ends of the vertical plate (111), the two horizontal plates (112) extending in opposite directions, a plurality of second groove-shaped slide rails (13) being welded to a portion of the vertical plate (111) connected to one of the horizontal plates (112), the plurality of second groove-shaped slide rails (13) being arranged along the height direction of the wall formwork; The horizontal plate (112) of the first steel plate (11) away from the second grooved slide rail (13) and the connected part of the vertical plate (111) form the first embedded end, and the second grooved slide rail (13) on the first steel plate (11) is the first connecting member; The horizontal plate (112) of the second steel plate (21) away from the second grooved slide rail (13) and the connected part of the vertical plate (111) form the second embedded end, and the second grooved slide rail (13) on the second steel plate (21) is the second connecting member; The plurality of second grooved rails (13) of the first steel plate (11) are locked in cooperation with the horizontal plate (112) of the second steel plate (21) close to the second grooved rails (13). At the same time, the plurality of second grooved rails (13) of the second steel plate (21) are locked in cooperation with the horizontal plate (112) of the first steel plate (11) close to the second grooved rails (13).
7. The connection structure between wall forms on both sides of a shear wall according to claim 6, characterized in that: The inner sides of the upper and lower openings of the second groove-shaped slide rail (13) are both provided with second chamfers (131) to form a bell-mouth shape.
8. The connection structure between wall forms on both sides of a shear wall according to claim 6, characterized in that: The second groove-shaped slide rail (13) extends out a second connecting plate (132), and the second connecting plate (132) of the second groove-shaped slide rail (13) of the first steel plate (11) is welded to the vertical plate (111) of the first steel plate (11); The second connecting plate (132) of the second groove-shaped slide rail (13) of the second steel plate (21) is welded to the vertical plate (111) of the second steel plate (21).
9. A shear wall, characterized in that: It comprises a first prefabricated wall form (4), a second prefabricated wall form (5) and a plurality of connection structures according to any one of claims 1 to 8, wherein the first prefabricated wall form (4) and the second prefabricated wall form (5) are both L-shaped, and the openings of the first prefabricated wall form (4) and the second prefabricated wall form (5) are arranged back to back to form a T-shaped shear wall; The first prefabricated wall form (4) is provided with a first horizontal steel bar (41) of the shear wall, the first prefabricated wall form (4) at the long wall position forming the shear wall is pre-embedded with the first connection component (1), the first horizontal steel bar (41) is located on a side of the first connection component (1) away from the second prefabricated wall form (5) and is welded to the first pre-embedded end; The second prefabricated wall form (5) is provided with a second horizontal steel bar (51) of the shear wall, the second prefabricated wall form (5) at the long wall position forming the shear wall is pre-embedded with the second connection component (2), the second horizontal steel bar (51) is located on a side of the second connection component (2) away from the first prefabricated wall form (4) and is welded to the second pre-embedded end; The first prefabricated wall form (4) and the second prefabricated wall form (5) are connected via a plurality of connection structures to achieve tension.
10. The shear wall according to claim 9, characterized in that: Two fourth steel plates (8) are fixed at the top of each of the first connecting component (1) and the second connecting component (2); the fourth steel plates (8) are L-shaped, and the open ends of the two fourth steel plates (8) are arranged oppositely and fixed on both sides of the first steel plate (11) or the second steel plate (21); a receiving groove (81) is formed between the two fourth steel plates (8); When the two shear walls are stacked vertically, the first steel plate (11) or the second steel plate (21) located at the top is inserted into the corresponding receiving groove (81) located at the bottom.
Citation Information
Patent Citations
Prefabricated wall surface structure in integrated building
CN218522010U
Splicing type template system
CN114351907A
Splicing structure of laminated plate type shear wall
CN213204449U
Steel tube bundle combined shear wall structure
CN215519355U
Fabricated prefabricated part
CN217811771U