Arched floor prefabrication and installation process
By adopting prefabricated floor slabs with arched structures in prefabricated buildings, combined with factory prefabricated and on-site installation methods, the problem of floor slab deformation in prefabricated buildings is solved, and the installation efficiency and quality are improved.
Patent Information
- Application Number
- CN202411071215.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-12
AI Technical Summary
In prefabricated buildings, prefabricated floor slabs are deformed greatly during transportation and installation, resulting in damage to internal decoration. The existing methods mainly control deformation by increasing support and thickness, but affect the decoration quality and project progress.
Prefabricated floor slabs with arched structures are used to increase rigidity and reduce deflection deformation by adding steel bars during factory prefabrication and changing the shape of the floor slabs, and appropriate connections and concrete pouring are carried out on site to reduce installation workload.
It effectively reduces the deflection deformation of prefabricated floor slabs, improves overall operating efficiency, meets the installation requirements of fully prefabricated buildings, and reduces the on-site construction volume.
Smart Images

Figure CN118933250A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of civil engineering and prefabricated buildings, and relates to a process for prefabrication and installation of an arched floor slab. Background Art
[0002] In the construction field, the prefabricated structure is promoted, among which the concrete structure floor is the most widely used. The common method is to use the factory to prefabricate the bottom of the floor, and then cast the upper concrete on the construction site. The two parts are superimposed to form an overall floor structure. In actual application, for the convenience of transportation, the thickness of the prefabricated part of the floor is thin, and the post-cast part of the analysis floor is relatively thick, which leads to large deformation of the prefabricated part of the floor during the construction process. For this reason, the span of the prefabricated floor is often controlled during the design to reduce the deformation of the prefabricated floor. With the application of fully prefabricated buildings, the interior decoration of the building is completed in the factory, and the deformation control requirements during the transportation and on-site installation of the building are greatly improved, otherwise the interior decoration of the building will be damaged due to excessive deformation of the floor and wall panels. At present, it is only controlled by increasing the support and increasing the thickness of the building and wall panels. This makes the fully prefabricated building components have to be supported and dismantled and decorated after installation. The process not only affects the decoration quality, but also affects the progress of the project. Summary of the invention
[0003] In order to overcome the shortcomings of the existing technology, the present invention provides a process for prefabrication and installation of arched floor slabs. During the prefabrication process of the floor slabs in the factory, the prefabrication method of the floor slabs is changed, and the plane structure of the prefabricated platform is changed into an arc structure, so that the prefabricated floor slabs become an arched structure. The arched structure is used to improve the rigidity of the prefabricated floor slabs and reduce their deflection and deformation. At the same time, part of the steel bars added during cast-in-place are added during prefabrication to further enhance the bearing capacity of the prefabricated structure and reduce the amount of engineering work for on-site installation and construction.
[0004] The technical solution adopted by the present invention to solve its technical problem is:
[0005] A process for prefabrication and installation of an arched floor slab, the process comprising the following steps:
[0006] Step 1: Make prefabricated arched floor slabs. The process is as follows:
[0007] First, make the arch truss steel bars, lay the arch truss steel cage on the arc-shaped prefabricated platform, make the curved upper chord of the arch truss steel bars fit the arc of the prefabricated platform, and set up the floor slab perimeter formwork according to the design requirements; secondly, lay the distribution steel bars perpendicular to the truss steel bars, among which the distribution steel bars in the mid-span area orthogonal to the upper chord steel bars and the pre-buried pipelines in the slab are laid first, and then the distribution steel bars orthogonal to the lower chord steel bars are laid; then pour the precast concrete to the top of the formwork, bury all the floor slab steel bars in the concrete and ensure the thickness of the protective layer of the lower chord steel bars;
[0008] Step 2: On-site installation and pouring, the process is as follows:
[0009] 2.1. Inspect the prefabricated floor slabs delivered to the site and classify and stack them according to the construction and installation plan;
[0010] 2.2. Carry out trial lifting operation on site;
[0011] 2.3. Turn the prefabricated floor slab over on the ground so that the bottom is facing downward and the arch is facing upward, and then lift it steadily at four points;
[0012] 2.4. Lift the prefabricated floor slabs to the designed floor and installation position, and place the two ends of the span of the prefabricated floor slabs on the beams or wall supports at both ends; after each floor slab is installed in place, check and adjust the floor elevation, and pre-embed electrical wires and water pipes;
[0013] 2.5. After the prefabricated floor slabs are in place, the connection between the prefabricated floor slabs can be carried out. The connection between the prefabricated floor slabs at the middle support position is carried out by direct connection and indirect connection. The lower chord steel bars in the truss span direction are directly connected, and the sleeve and stud bolt connection method is adopted, that is, one end of the stud bolt is screwed into the bottom of the sleeve at one end, and the other end of the bolt is aligned with the sleeve at the other end, and screwed in reverse and the threads at both ends are adjusted evenly. In the direction perpendicular to the span direction, there is no preset sleeve, and the height of the prefabricated floor slabs between the connection sections is inconsistent. In the mid-span area of the steel truss, the height of the prefabricated floor slab is large, and the mid-span section is the maximum height H of the prefabricated floor slab. The prefabricated floor slabs at both ends are gradually thinned to the support, reaching the minimum height h = (1 / 3 ~ 1 / 2) H, and only at the prefabricated floor slab supports at both ends are bent steel bars used to indirectly connect the support and the lower distributed steel bars of the floor slabs on both sides;
[0014] 2.6. The connection between the upper reinforcements in the span direction of the precast floor slab at the middle support is indirectly connected by negative moment reinforcement. The diameter of the negative moment reinforcement at the upper part of the support is the same as that of the upper chord reinforcement. The length extending into the slab is not less than 1 / 4 of the slab span in this direction, and the distance from the upper surface of the slab is greater than or equal to the thickness of the concrete cover layer;
[0015] 2.7. The connection between the precast floor slab and the side beam or side wall support shall refer to the connection method with the middle beam and wall support; the lower chord along the truss span direction shall be connected to the connection sleeve at the support with a long screw at one end, and the other end shall exceed the center line of the support. The upper chord shall be indirectly connected with negative moment reinforcement, and the length extending into the slab shall not be less than 1 / 4 of the slab span in this direction; the precast floor slab shall be connected to the support only on both sides in the direction perpendicular to the truss span, of which the bottom shall be connected with specially processed curved reinforcement and the upper part shall be connected with negative moment reinforcement;
[0016] 2.8. The surface reinforcement at the support is connected with the corresponding beam or wall reinforcement to ensure the stability of the reinforcement;
[0017] 2.9. After all the floor slab reinforcements are installed in place, pour the floor concrete. Pour the concrete in layers near the supports, and pour the cast-in-place concrete layer in the middle of the span at one time. When the cast-in-place concrete of the entire floor reaches the designed thickness, the structural construction of the composite floor is completed.
[0018] Furthermore, in the above 2.4, when the flatness of the shelf surface is poor, a soft seal is pre-arranged on the shelf surface to prevent leakage of concrete when the shelf surface is cast in situ, or to adjust the flatness of the shelf surface.
[0019] In the above 2.5, at the supports at both ends of the prefabricated floor slab, the lower steel bars are connected by three bent connecting steel bars, and the spacing between the three steel bars is 100 mm.
[0020] The process of step 1 is as follows:
[0021] 1.1. According to the floor design drawings and the platform size of the prefabrication plant, determine the span direction, basic dimensions L, B, and arch curve shape parameters H and h of the upper chord reinforcement of the prefabricated part of the floor; according to the reinforcement of the design drawings and the relevant prefabricated technical regulations, determine the number of truss reinforcements and the diameters of the upper and lower chord reinforcements on each prefabricated floor; determine the length and diameter of the orthogonal distribution reinforcements of the lower chord reinforcement and the upper chord reinforcement perpendicular to the span, and at the same time determine the connection method of the reinforcements in the two directions;
[0022] 1.2. Digitally process each prefabricated floor slab according to the design drawings and splitting plan and send it to the processing plant for processing;
[0023] 1.3. Adjust the curve shape of the upper chord steel bars of the truss steel bar making machine to meet the design requirements; adjust the arc shape of the prefabricated table formwork on the assembly line to match the curve shape of the upper chord steel bars, and adjust the upper opening height of the template to match the concrete pouring height;
[0024] 1.4. Process both ends of the lower chord steel bar into threaded connection ends, sleeve the connecting sleeve at the upper support, and perform thread protection on the sleeve;
[0025] 1.5. Make steel trusses, put the steel bar curve surface of the truss into the arc groove of the prefabricated table formwork, lay out the orthogonal distribution steel bars of the upper chord steel bars and the orthogonal distribution steel bars of the lower chord steel bars; pre-embed the wire tube according to the design requirements;
[0026] 1.6. After adjusting the size of the steel mesh, pour the concrete. After pouring to the height of the upper edge of the formwork, vibrate and level it. The thickness of the concrete cover of the lower chord steel bars shall not be less than 15mm. The concrete mix ratio shall meet the design requirements, and samples shall be kept for testing;
[0027] 1.7. Prefabricated floor slabs enter the curing room for curing, demoulding, inspection, coding, classification, and then are protected as finished products ready for shipment.
[0028] In the above 1.1, when the total thickness of the floor slab is ≥200mm, a weight-reducing block is designed in the precast slab to reduce the amount of concrete and the deadweight of the slab; in the above 1.5, the weight-reducing block is arranged between the orthogonally distributed steel bars of the lower chord steel bars and the orthogonally distributed steel bars of the upper chord steel bars, and close to one side of the orthogonally distributed steel bars of the lower chord steel bars.
[0029] The technical concept of the present invention is: the prefabricated flat floor slab is changed into an arched floor slab, and the whole floor slab is formed after overlapping pouring on site.
[0030] The core of the present invention is to process the upper chord steel bars in the steel trusses in the prefabricated floor into an arch shape, and the lower chord steel bars remain in a straight shape. Similarly, a space truss structure is formed by one upper chord steel bar and two lower chord steel bars. The floor is divided into two directions according to the building bay where the floor is located, namely the span direction and the direction perpendicular to the span. The span direction is also the spanning direction of the space truss, and is also the main control direction of the floor deflection. Each prefabricated floor is arranged with a number of steel trusses in parallel in the span direction, and is formed by a number of prefabricated floor slabs in a direction perpendicular to the span direction. At the same time, distributed steel bars orthogonal to the upper and lower chords are arranged in this direction, and the steel bars in the two directions are connected together by binding or welding. The arched steel mesh is placed on an arc-shaped template platform, so that the arch curve of the upper chord steel bar is close to the arc-shaped template, and the upper mouth of the arc-shaped template is the bottom plane of the prefabricated floor. The prefabricated floor can be transported to the site for installation after being cured, demoulded, and inspected.
[0031] The prefabricated floor slab is vertically reversed during on-site installation, that is, the arch curve faces upward and the flat bottom faces downward. The two ends of the bottom surface are placed on supports (beams or walls) at both ends. During installation, only additional steel bars need to be laid above the supports and then concrete can be poured to the designed total thickness, that is, a concrete protective layer is poured on the upper chord steel bar arch curve.
[0032] The beneficial effects of the present invention are mainly manifested in: changing the shape of the existing prefabricated floor structure, reducing the workload of on-site installation work by appropriately increasing the workload of factory prefabrication, and improving the overall work efficiency. At the same time, the deflection deformation of prefabricated floor slabs of the same span can be greatly reduced, meeting the requirements of fully assembled building structures. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the reinforcement and casting form of the arched precast floor.
[0034] Figure 2 yes Figure 1 Top view of the .
[0035] Figure 3 yes Figure 1 AA cross-section diagram.
[0036] Figure 4This is a schematic diagram of the connection at the middle support in the span direction.
[0037] Figure 5 It is a connection diagram of the lower chord steel bar connection sleeve.
[0038] Figure 6 It is a schematic diagram of the connection relationship on the cross-intersecting supports.
[0039] Figure 7 It is a schematic diagram of the connection at the middle support in the direction perpendicular to the span.
[0040] Figure 8 This is a schematic diagram of the connection at the side supports in the span direction.
[0041] Fig. 9 It is a schematic diagram of the connection with the side supports in the direction perpendicular to the span.
[0042] Explanation of the reference numerals: 1. Upper chord reinforcement; 2. Lower chord reinforcement; 3. Web reinforcement; 4. Concrete protection layer of lower chord reinforcement; 5. Pre-buried wire tube in the slab; 6. Connecting sleeve at the support of lower chord reinforcement; 7. Orthogonal distribution reinforcement of lower chord reinforcement; 8. Orthogonal distribution reinforcement of upper chord reinforcement; 9. Intermediate support in the span direction (beam or wall); 9.1 Side support in the span direction (beam or wall) 10. Negative bending moment reinforcement of support in the span direction; 11. Post-cast concrete; 12. Support in the direction perpendicular to the span Connecting steel bars of bottom reinforcement; 13. Negative moment reinforcement in the direction perpendicular to the span; 14. Intermediate support in the direction perpendicular to the span; 14.1 Side support in the direction perpendicular to the span; 15. Weight-reducing foam block; 6.1 Double-headed connecting bolts matching 6; 6.1.1 Anchor bolts matching 6 at the side support; 10.1 Negative moment reinforcement at the side support in the span direction; 12.1 Anchor steel bars of bottom reinforcement at the side support in the direction perpendicular to the span; 13.1 Negative moment reinforcement at the side support in the direction perpendicular to the span. DETAILED DESCRIPTION
[0043] The present invention will be further described below in conjunction with the accompanying drawings.
[0044] Reference Figures 1 to 9 , a process for prefabrication and installation of an arched floor, comprising the following steps:
[0045] Step 1: Make prefabricated arched floor slabs. The process is as follows:
[0046] 1.1. According to the floor design drawings and the platform size of the prefabricated factory, determine the span direction, basic dimensions L, B and arch curve shape parameters H and h (h = (1 / 3 ~ 1 / 2) H) of the prefabricated floor slab; determine the number of truss steel bars and the diameters of the upper chord steel bars 1 and the lower chord steel bars 2 arranged on each prefabricated floor slab according to the reinforcement of the design drawings and the relevant prefabricated technical regulations; determine the length and diameter of the lower chord steel bars 7 and the upper chord steel bars 8 orthogonal to the span, and determine the connection method of the steel bars in the two directions (binding or spot welding, and automatic spot welding should be used as much as possible if conditions permit). When the total thickness of the floor slab is ≥200mm, consider designing a weight reduction block 15 in the prefabricated slab to reduce the amount of concrete and the deadweight of the slab;
[0047] 1.2. Digitally process each prefabricated floor slab according to the design drawings and splitting plan and send it to the processing plant for processing;
[0048] 1.3. Adjust the curve shape of the upper chord steel bars of the truss steel bar making machine to meet the design requirements; adjust the arc shape of the prefabricated table formwork on the assembly line to match the curve shape of the upper chord steel bars, and adjust the upper opening height of the template to match the concrete pouring height;
[0049] 1.4. Process both ends of the lower chord steel bar into threaded connection ends, sleeve the connection sleeve 6 at the upper support, and perform thread protection on the sleeve 6;
[0050] 1.5. Make a steel truss, put the steel bar curve surface of the truss into the arc groove of the prefabricated table form, and lay out the orthogonal distribution steel bars 7 of the lower chord steel bars and the orthogonal distribution steel bars 8 of the upper chord steel bars; pre-embed the wire tube 5 according to the design requirements; when setting the weight reduction block 15, it should be set between the orthogonal distribution steel bars 7 of the lower chord steel bars and the orthogonal distribution steel bars 8 of the upper chord steel bars, and close to the side of the orthogonal distribution steel bars 7 of the lower chord steel bars;
[0051] 1.6. After adjusting the size of the steel mesh, pour the concrete. After pouring to the height of the upper edge of the formwork, vibrate and level it. The thickness of the concrete protective layer 4 of the lower chord steel bar shall not be less than 15mm. The concrete mix ratio must meet the design requirements, and samples shall be kept for testing;
[0052] 1.7. The prefabricated floor slabs are put into the curing room for curing, demoulding, inspection, coding, classification, and then the finished products are protected and ready for transportation;
[0053] Step 2: On-site installation and pouring, the process is as follows:
[0054] 2.1. Inspect the prefabricated floor slabs delivered to the site and classify and stack them according to the construction and installation plan;
[0055] 2.2. Conduct trial lifting operations on site to check whether the designed lifting points are suitable for the operation, determine whether the lifting, turning, lowering and positioning operations are safe, reliable and efficient, and adjust the operation plan in a timely manner;
[0056] 2.3. In principle, turn the prefabricated floor slab over on the ground so that the bottom is facing downward, and lift it steadily at four points;
[0057] 2.4. Lift the precast floor slabs to the designed floor and installation position, and place the two ends of the span direction of the precast floor slabs on the beams or wall supports at both ends; when the flatness of the shelf surface is poor, soft seals can be set on the shelf surface in advance to prevent leakage of concrete when pouring concrete, and the flatness of the shelf surface can also be adjusted; after each floor slab is installed in place, the floor elevation is checked and adjusted, and pre-buried wires, water pipes, and weight reduction blocks are arranged.
[0058] 2.5. After the prefabricated floor slabs are in place, the connection between the prefabricated floor slabs can be carried out. The connection between the prefabricated floor slabs at the support position is carried out by direct connection and indirect connection. The lower chord reinforcement in the span direction is directly connected, and the sleeve and stud bolt connection method is adopted, that is, one end of the stud bolt 6.1 is screwed into the bottom of the sleeve 6 at one end, and the other end of the bolt is aligned with the sleeve 6 at the other end, and screwed in reverse and the threads at both ends are adjusted evenly, as shown in the attached figure. Figure 4 , 5 In the direction perpendicular to the span direction, the height of the precast floor slabs between the connection sections is inconsistent. In the mid-span area of the steel truss, the height of the precast floor slab is large. The mid-span section is the maximum height H of the precast floor slab. The precast floor slabs at both ends gradually thin to the support, reaching the minimum height h = (1 / 3 ~ 1 / 2) H. Therefore, the method of direct connection of the full side length is not adopted. It is only connected at the supports at both ends of the precast floor slab. The lower part is indirectly connected with 3 curved steel bars 12, such as Figure 6 , 7 , the spacing between the three curved steel bars is 100mm;
[0059] 2.6. The upper reinforcement (reinforcement) of the precast floor slab is connected indirectly at the middle support. In principle, the diameter of the negative moment reinforcement at the upper part of the support is the same as that of the upper chord reinforcement. The length of the reinforcement extending into the slab is not less than 1 / 4 of the slab span in this direction. The distance from the upper surface of the slab is greater than or equal to the thickness of the concrete cover layer. Figure 4 10 and Figure 7 13 of 13;
[0060] 2.7. The connection method between the precast floor slab and the side beam or side wall support is as follows: the lower chord along the truss span direction is connected to the connection sleeve 6 at the support by a long screw 6.1.1 at one end, and the other end must exceed the center line of the support. The upper chord is indirectly connected by a negative bending moment steel bar 10.1, and the length extending into the slab is not less than 1 / 4 of the slab span in this direction; the precast floor slab is connected to the support only at the thinner part of the two sides perpendicular to the truss span, of which the bottom is connected by 3 specially processed curved steel bars 12.1, and the upper part is connected by negative bending moment steel bars 13.1. Figure 8 and Fig. 9 As shown;
[0061] 2.8. The surface reinforcement at the support should be connected with the corresponding beam or wall reinforcement to ensure the stability of the reinforcement;
[0062] 2.9. After all the floor slab reinforcements are installed in place, pour the floor concrete. The concrete at the supports and nearby locations is thicker and should be poured in layers. The cast-in-place concrete layer in the middle of the span is thinner and can be poured at one time. However, the thickness of the concrete protective layer at each location must comply with the requirements of the regulations. After the cast-in-place concrete of the entire floor reaches the designed thickness, the structural construction of the composite floor is completed.
[0063] The method and process involved in this embodiment are applicable to the floor structure of a fully assembled Mic building, and are also applicable to building structures with relatively large spans and strict control of vertical deflection and deformation.
[0064] In this embodiment, only the upper chord steel bars of the steel truss are changed into an arch curve shape, which can effectively improve the rigidity of the assembled composite floor slab, reduce its vertical deflection, and speed up the installation construction.
[0065] The contents described in the embodiments of this specification are merely enumerations of implementation forms of the inventive concept and are for illustrative purposes only. The protection scope of the present invention should not be considered to be limited to the specific forms described in this embodiment, and the protection scope of the present invention also extends to equivalent technical means that can be thought of by ordinary technicians in this field based on the inventive concept.
Claims
1. A prefabrication and installation process for arched floor slabs, It is characterized in that The process comprises the following steps: Step 1: Make prefabricated arched floor slabs. The process is as follows: First, make the arch truss steel bars, lay the arch truss steel cage on the arc-shaped prefabricated platform, make the curved upper chord of the arch truss steel bars fit the arc of the prefabricated platform, and set up the floor slab perimeter formwork according to the design requirements; secondly, lay the distribution steel bars perpendicular to the truss steel bars, among which the distribution steel bars in the mid-span area orthogonal to the upper chord steel bars and the pre-buried pipelines in the slab are laid first, and then the distribution steel bars orthogonal to the lower chord steel bars are laid; then pour the precast concrete to the top of the formwork, bury all the floor slab steel bars in the concrete and ensure the thickness of the protective layer of the lower chord steel bars; Step 2: On-site installation and pouring, the process is as follows: 2.
1. Inspect the prefabricated floor slabs delivered to the site and classify and stack them according to the construction and installation plan; 2.
2. Carry out trial lifting operation on site; 2.
3. Turn the prefabricated floor slab over on the ground so that the bottom is facing downward and the arch is facing upward, and then lift it steadily at four points; 2.
4. Lift the prefabricated floor slabs to the designed floor and installation position, and place the two ends of the span of the prefabricated floor slabs on the beams or wall supports at both ends; after each floor slab is installed in place, check and adjust the floor elevation, and pre-embed electrical wires and water pipes; 2.
5. After the prefabricated floor slabs are in place, the connection between the prefabricated floor slabs can be carried out. The connection between the prefabricated floor slabs at the middle support position is carried out by direct connection and indirect connection. The lower chord steel bars in the truss span direction are directly connected, and the sleeve and stud bolt connection method is adopted, that is, one end of the stud bolt is screwed into the bottom of the sleeve at one end, and the other end of the bolt is aligned with the sleeve at the other end, and screwed in reverse and the threads at both ends are adjusted evenly. In the direction perpendicular to the span direction, there is no preset sleeve, and the height of the prefabricated floor slabs between the connection sections is inconsistent. In the mid-span area of the steel truss, the height of the prefabricated floor slab is large, and the mid-span section is the maximum height H of the prefabricated floor slab. The prefabricated floor slabs at both ends are gradually thinned to the support, reaching the minimum height h = (1 / 3 ~ 1 / 2) H, and only at the prefabricated floor slab supports at both ends are bent steel bars used to indirectly connect the support and the lower distributed steel bars of the floor slabs on both sides; 2.
6. The connection between the upper reinforcements in the span direction of the precast floor slab at the middle support is indirectly connected by negative moment reinforcement. The diameter of the negative moment reinforcement at the upper part of the support is the same as that of the upper chord reinforcement. The length extending into the slab is not less than 1 / 4 of the slab span in this direction, and the distance from the upper surface of the slab is greater than or equal to the thickness of the concrete cover layer; 2.
7. The connection method between the precast floor slab and the side beam or side wall support is as follows: the lower chord along the truss span direction is connected to the connection sleeve at the support by a long screw at one end, and the other end must exceed the center line of the support. The upper chord is indirectly connected by negative moment reinforcement, and the length extending into the slab is not less than 1 / 4 of the slab span in this direction; the precast floor slab is connected to the support only on both sides perpendicular to the truss span, of which the bottom is connected by specially processed curved reinforcement and the upper part is connected by negative moment reinforcement; 2.
8. The surface reinforcement at the support is connected with the corresponding beam or wall reinforcement to ensure the stability of the reinforcement; 2.
9. After all the floor slab reinforcements are installed in place, pour the floor concrete. Pour the concrete in layers near the supports, and pour the cast-in-place concrete layer in the middle of the span at one time. When the cast-in-place concrete of the entire floor reaches the designed thickness, the structural construction of the composite floor is completed.
2. A process for prefabrication and installation of an arched floor as claimed in claim 1, It is characterized in that In the above 2.4, when the flatness of the shelf surface is poor, a soft seal is pre-arranged on the shelf surface to prevent leakage of concrete when the shelf surface is cast in situ, or to adjust the flatness of the shelf surface.
3. A process for prefabrication and installation of an arched floor as claimed in claim 1 or 2, It is characterized in that In 2.5, at the supports at both ends of the prefabricated floor slab, three specially processed curved connecting steel bars are used to indirectly connect the supports, and the spacing between the three steel bars is 100 mm.
4. A process for prefabrication and installation of an arched floor as claimed in claim 1 or 2, It is characterized in that The process of step 1 is as follows: 1.
1. According to the floor design drawings and the platform size of the prefabrication plant, determine the span direction, basic dimensions L, B, and arch curve shape parameters H and h of the upper chord reinforcement of the prefabricated part of the floor; according to the reinforcement of the design drawings and the relevant prefabricated technical regulations, determine the number of truss reinforcements and the diameters of the upper and lower chord reinforcements on each prefabricated floor; determine the length and diameter of the orthogonal distribution reinforcements of the lower chord reinforcement and the upper chord reinforcement perpendicular to the span, and at the same time determine the connection method of the reinforcements in the two directions; 1.
2. Digitally process each prefabricated floor slab according to the design drawings and splitting plan and send it to the processing plant for processing; 1.
3. Adjust the curve shape of the upper chord steel bars of the truss steel bar making machine to meet the design requirements; adjust the arc shape of the prefabricated table formwork on the assembly line to match the curve shape of the upper chord steel bars, and adjust the upper opening height of the template to match the concrete pouring height; 1.
4. Process both ends of the lower chord steel bar into threaded connection ends, sleeve the connecting sleeve at the upper support, and perform thread protection on the sleeve; 1.
5. Make steel trusses, put the steel bar curve surface of the truss into the arc groove of the prefabricated table formwork, lay out the orthogonal distribution steel bars of the upper chord steel bars and the orthogonal distribution steel bars of the lower chord steel bars; pre-embed the wire tube according to the design requirements; 1.
6. After adjusting the size of the steel mesh, pour the concrete. After pouring to the height of the upper edge of the formwork, vibrate and level it. The thickness of the concrete cover of the lower chord steel bars shall not be less than 15mm. The concrete mix ratio shall meet the design requirements, and samples shall be kept for testing; 1.
7. Prefabricated floor slabs enter the curing room for curing, demoulding, inspection, coding, classification, and then are protected as finished products ready for shipment.
5. A process for prefabrication and installation of an arched floor as claimed in claim 4, It is characterized in that In the above 1.1, when the total thickness of the floor slab is ≥200mm, a weight-reducing block is designed in the precast slab to reduce the amount of concrete and the deadweight of the slab; in the above 1.5, the weight-reducing block is arranged between the orthogonally distributed steel bars of the lower chord steel bars and the orthogonally distributed steel bars of the upper chord steel bars, and close to one side of the orthogonally distributed steel bars of the lower chord steel bars.