Cast-in-place box type channel self-propelled integral type internal mold trolley construction method
Through the construction method of self-organized internal mold trolley, the problems of low efficiency and poor quality in traditional box channel construction are solved, efficient, safe and environmentally friendly construction results are achieved, and construction quality and economic benefits are improved.
Patent Information
- Application Number
- CN202411206553.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-12
AI Technical Summary
The traditional box channel construction method has problems such as low construction efficiency, easy deformation of the formwork, poor flatness, mismatched joints and slurry leakage, which makes it difficult to guarantee the appearance quality.
The construction method of self-organized internal mold trolley includes measurement and layout, foundation construction, steel bar processing, formwork engineering, concrete pouring and mold removal maintenance. The combination of hydraulic pulley walking module, integral body structure and external mold system ensures the formwork Accurate installation and vibration, combined with customized steel molds and large flat molds, achieve efficient concrete pouring and rapid disassembly and assembly.
It improves construction efficiency and quality, reduces personnel investment and material consumption, ensures the flatness and appearance quality of concrete, and significantly improves construction safety and economic and social benefits.
Smart Images

Figure CN118933330A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of cast-in-place box-type channel construction, and in particular to a method for constructing a self-propelled integral inner mold trolley for a cast-in-place box-type channel. Background Art
[0002] The box-type channel is a closed reinforced concrete thin-walled structure with the advantages of simple structure, easy construction, integrity, high rigidity, good durability, and low maintenance cost. It is widely used for pedestrians and vehicles in highway projects. The traditional construction method of the box-type channel is to set up a full-floor support formwork and cast concrete in situ. The support erection and dismantling cycle is long, the construction efficiency is low, and it consumes a lot of manpower. This disadvantage is more obvious in projects with large box-type channel engineering. At the same time, the box-type channel constructed using traditional technology is prone to poor concrete surface flatness, misaligned joints, and slurry leakage due to the reasons such as easy deformation of the formwork and uneven construction level, and the appearance quality is difficult to guarantee. Summary of the invention
[0003] The purpose of the present invention is to address the above-mentioned problems and provide a construction method for a self-propelled integral inner mold trolley for a cast-in-place box-type channel, so as to improve work efficiency, quality and safety. At the same time, it has a high turnover number and can be recycled, thereby reducing engineering costs, promoting energy conservation and environmental protection, and achieving higher economic and social benefits.
[0004] In order to achieve the above purpose, the technical solutions provided are as follows:
[0005] The construction method of a self-propelled integral inner mold trolley for a cast-in-place box-type channel is characterized by comprising the following steps:
[0006] Step 1: Measurement and Staking
[0007] The box-type channel construction adopts the two-person observation method to ensure the accuracy of the measurement data, and adopts the cement nail and hanging line marking method to ensure that the measurement results are directly reflected in the process control; for the oblique block at the end of the oblique box-type channel, the steel bar line is marked on the cushion surface according to the position of the gradual change of the steel bar spacing to ensure the steel bar spacing;
[0008] Step 2: Foundation Construction
[0009] The box-type channel foundation pit is excavated by excavators and manual excavation, with a 20-30cm thick base reserved for manual cleaning. After the base bearing capacity is tested and qualified, a gravel cushion layer is filled according to the design requirements and concrete is poured to seal the bottom.
[0010] Step 3: Steel bar processing
[0011] (1) The steel bars are processed in a centralized processing center, the bottom plate and top plate steel bars are processed into skeleton pieces, and the steel bars are welded and tied at the construction site;
[0012] (2) The bottom plate of the box-type channel adopts plum blossom-shaped pads for stable support, and the top plate and culvert body adopt circular serrated pads and formwork support strips, with 4 pads arranged per square meter;
[0013] (3) The spacing of the steel bars is controlled by slots, and the overall structure of the steel bars is fixed by steel pipe brackets to prevent deformation;
[0014] Step 4: Baseboard construction
[0015] The contour lines on both sides of the culvert, the positioning line of the protective layer and the center line are accurately laid out on the cushion layer, and a customized steel mold is used to complete the pouring of the bottom slab concrete;
[0016] Step 5: Template Engineering
[0017] The self-propelled integral inner mold trolley is composed of three parts: bottom hydraulic pulley walking module, integral main structure and outer mold system. The self-propelled integral inner mold trolley is assembled in parallel while the bottom plate is being constructed, and finally assembled according to the modules. The main steps are as follows:
[0018] (1) Select a wide area, first assemble the pulley 1, beam 2 and other components, connect them with high-strength bolts, and complete the assembly of the hydraulic pulley travel module; then assemble the "door" frame structure, and also use high-strength bolts to connect the support column 3 and the main beam 4; finally, assemble the top truss 5 and the flat mold 6;
[0019] (2) The elevation and direction of track 7 are key factors to ensure the positioning of the inner mold trolley. The surveying personnel accurately lay out the track, mark points on the bottom plate at 2m horizontally, lay out the track installation line, and adjust the track elevation and direction;
[0020] (3) The self-propelled integral inner mold trolley is assembled in modules. The weight of each module is different. The largest module belongs to the gantry structure, which is about 5 tons. The entire assembly process is hoisted by a 25-ton crane. After the bottom hydraulic pulley walking module is hoisted into place, a 1-2m long steel pipe is used as a temporary support to stabilize the pulley walking module. Then the gantry structure is hoisted. The gantry structure and the bottom hydraulic pulley walking module are connected with 24 high-strength bolts. After hoisting, the gantry is promptly connected with rods. Finally, the top distribution beam and flat mold are hoisted;
[0021] (4) After each module is hoisted in place, the screw rod and hydraulic system are installed. The screw rod 8 and the hydraulic system are the core components for adjusting the self-propelled inner mold trolley, and are also the main process for controlling the overall linearity and flatness of the box-shaped channel; according to the overall fixation of the large flat mold, according to the three-point leveling principle, three screw rods are used to adjust and stabilize the template. The screw rod and the template are fixed with pins. Finally, the hydraulic system is accurately installed in the pre-made card slot. Using the "reverse pressure" principle, the hydraulic system is started to accurately adjust the trolley up and down and left and right to improve the accuracy of template installation;
[0022] (5) The outer mold adopts a customized integral large flat mold, which is fastened to the back rib of the template by the tie rod 9 using a pad, and the tie rods are arranged in a staggered manner at a spacing of 60 cm; the plug template is a key process for controlling the quality of the plug, and is also one of the key factors affecting the appearance quality of the box-type channel opening. The plug template uses a double-row steel pipe method with back ribs, and uses double-row square wood with back ribs at intervals. When fixing, it fully utilizes the back ribs on the edge of the large flat mold and is horizontally locked with the large flat mold by pulling screws;
[0023] Step 6: Concrete pouring
[0024] Concrete pouring is transported by pump trucks, and vibrated by insert vibrators in combination with flat plate vibrators. Concrete pouring is based on the principle of longitudinal segmentation and horizontal layering. The layer thickness is generally not more than 30cm. The bottom plate is vibrated by insert vibrators in combination with flat plate vibrators, and the box body is vibrated by insert vibrators. The vibration process should be done quickly and slowly, to ensure the vibration time, pay attention to the bottom vibration effect, and avoid vibration leakage, over-vibration and other phenomena;
[0025] Step 7: Demolding and Maintenance
[0026] Following the order of removing the outer formwork first and then the inner formwork, after the concrete reaches 70% of the design strength, the formwork trolley is adjusted by the jack and the bottom top screw to make the trolley formwork as a whole 10cm away from the concrete surface before it can be moved by the pulley; curing begins after the formwork is removed. The curing method adopts the combined process of "film covering + dripping", which makes full use of the "capillary" effect between the film and the concrete, which can not only keep the concrete moist for a long time, but also avoid the adverse effects of strong winds in the Hexi region, effectively keep warm and moist, reduce cracks in the concrete due to uneven shrinkage, save water and protect the environment, and greatly reduce the curing cost;
[0027] Step 8: Waterproof layer and settlement joint construction
[0028] (1) Settlements joints are set every 4 to 6 meters, with a width of 2 cm. The settlement joints of the bottom plate, culvert body and top plate are kept consistent. The settlement joints are constructed in one go using bakelite boards;
[0029] (2) Before backfilling, ensure that the outer side of the culvert and the contact surface with the fill are painted with three coats of hot asphalt;
[0030] (3) The top, bottom and side walls of the structure are equipped with embedded rubber waterstop strips at the settlement joints, and the bottom and side walls of the structure are equipped with back-adhered waterproof tapes to effectively prevent water seepage in the culvert.
[0031] The beneficial effects of the present invention are:
[0032] 1. Obvious quality advantage: The self-propelled integral inner mold trolley has excellent strength, rigidity and stability. It is equipped with large flat molds and combined with the milling process to improve the quality and flatness of the template joints, and the finished concrete product has excellent linear shape and appearance quality.
[0033] 2. Improve inherent safety: This method is used for cast-in-place box-type channel construction, which reduces the input of personnel, reduces the frequency of lifting operations, avoids a large number of cross operations, and improves inherent safety during disassembly and assembly and mobile transportation.
[0034] 3. High construction efficiency: The integral inner mold trolley designed with modular concept is quick and easy to install and dismantle, with fast turnover, and the jack-assisted trolley movement realizes its rapid assembly; at the same time, its fast translation speed significantly saves the time for moving and assembling the inner mold, achieving the purpose of rapid construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 is a process flow chart of the present invention;
[0036] Figure 2 The structure of the self-propelled integral inner mold trolley in the present invention is shown in FIG. Figure 1 ;
[0037] Figure 3 The structure of the self-propelled integral inner mold trolley in the present invention is shown in FIG. Figure 2 ;
[0038] Figure 4 The structure of the self-propelled integral inner mold trolley in the present invention is shown in FIG. Figure 3 . DETAILED DESCRIPTION
[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0040] Embodiment 1
[0041] The construction method of a self-propelled integral inner mold trolley for a cast-in-place box-type channel is characterized by comprising the following steps:
[0042] Step 1: Measurement and Staking
[0043] The box-type channel construction adopts the two-person observation method to ensure the accuracy of the measurement data, and adopts the cement nail and hanging line marking method to ensure that the measurement results are directly reflected in the process control; for the oblique block at the end of the oblique box-type channel, the steel bar line is marked on the cushion surface according to the position of the gradual change of the steel bar spacing to ensure the steel bar spacing;
[0044] Step 2: Foundation Construction
[0045] The box-type channel foundation pit is excavated by excavators and manual excavation, with a 20-30cm thick base reserved for manual cleaning. After the base bearing capacity is tested and qualified, a gravel cushion layer is filled according to the design requirements and concrete is poured to seal the bottom.
[0046] Step 3: Steel bar processing
[0047] (1) The steel bars are processed in a centralized processing center, the bottom plate and top plate steel bars are processed into skeleton pieces, and the steel bars are welded and tied at the construction site;
[0048] (2) The bottom plate of the box-type channel adopts plum blossom-shaped pads for stable support, and the top plate and culvert body adopt circular serrated pads and formwork support strips, with 4 pads arranged per square meter;
[0049] (3) The spacing of the steel bars is controlled by slots, and the overall structure of the steel bars is fixed by steel pipe brackets to prevent deformation;
[0050] Step 4: Baseboard construction
[0051] The contour lines on both sides of the culvert, the positioning line of the protective layer and the center line are accurately laid out on the cushion layer, and a customized steel mold is used to complete the pouring of the bottom slab concrete;
[0052] Step 5: Template Engineering
[0053] The self-propelled integral inner mold trolley is composed of three parts: bottom hydraulic pulley walking module, integral main structure and outer mold system. The self-propelled integral inner mold trolley is assembled in parallel while the bottom plate is being constructed, and finally assembled according to the modules. The main steps are as follows:
[0054] (1) Select a wide area, first assemble the pulley, beam and other components, connect them with high-strength bolts, and complete the assembly of the hydraulic pulley travel module; then assemble the "door" frame structure, and also use high-strength bolts to connect the support column and the main beam; finally, assemble the top truss and flat mold;
[0055] (2) The elevation and direction of the track are key factors to ensure the positioning of the inner mold trolley. The surveying personnel accurately lay out the track, mark points on the bottom plate at 2m horizontally, lay out the track installation line, and adjust the track elevation and direction;
[0056] (3) The self-propelled integral inner mold trolley is assembled in modules. The weight of each module is different. The largest module belongs to the gantry structure, which is about 5 tons. The entire assembly process is hoisted by a 25-ton crane. After the bottom hydraulic pulley walking module is hoisted into place, a 1-2m long steel pipe is used as a temporary support to stabilize the pulley walking module. Then the gantry structure is hoisted. The gantry structure and the bottom hydraulic pulley walking module are connected with 24 high-strength bolts. After hoisting, the gantry is promptly connected with rods. Finally, the top distribution beam and flat mold are hoisted;
[0057] (4) After each module is hoisted in place, the screw rod and hydraulic system are installed. The screw rod and hydraulic system are the core components for adjusting the self-propelled inner mold trolley, and are also the main process for controlling the overall linearity and flatness of the box-shaped channel; according to the overall fixation of the large flat mold, according to the three-point leveling principle, three screw rods are used to adjust and stabilize the template. The screw rod and the template are fixed with pins. Finally, the hydraulic system is accurately installed in the pre-made card slot. Using the "reverse pressure" principle, the hydraulic system is started to accurately adjust the trolley up and down and left and right to improve the accuracy of template installation;
[0058] (5) The outer mold adopts a customized integral large flat mold, which is fastened to the back rib of the template by using a pad to tie the rod. The tie rods are staggered at a spacing of 60 cm. The plug template is a key process to control the quality of the plug, and it is also one of the key factors affecting the appearance quality of the box-type channel opening. The plug template uses a double-row steel pipe method with back ribs, and uses double-row square wood with back ribs at intervals. When fixing, it fully utilizes the back ribs on the edge of the large flat mold and is locked horizontally with the large flat mold by pulling screws.
[0059] Step 6: Concrete pouring
[0060] Concrete pouring is transported by pump trucks, and vibrated by insert vibrators in combination with flat plate vibrators. Concrete pouring is based on the principle of longitudinal segmentation and horizontal layering. The layer thickness is generally not more than 30cm. The bottom plate is vibrated by insert vibrators in combination with flat plate vibrators, and the box body is vibrated by insert vibrators. The vibration process should be done quickly and slowly, to ensure the vibration time, pay attention to the bottom vibration effect, and avoid vibration leakage, over-vibration and other phenomena;
[0061] Step 7: Demolding and Maintenance
[0062] Following the order of removing the outer formwork first and then the inner formwork, after the concrete reaches 70% of the design strength, the formwork trolley is adjusted by the jack and the bottom top screw to make the trolley formwork as a whole 10cm away from the concrete surface before it can be moved by the pulley; curing begins after the formwork is removed. The curing method adopts the combined process of "film covering + dripping", which makes full use of the "capillary" effect between the film and the concrete, which can not only keep the concrete moist for a long time, but also avoid the adverse effects of strong winds in the Hexi region, effectively keep warm and moist, reduce cracks in the concrete due to uneven shrinkage, save water and protect the environment, and greatly reduce the curing cost;
[0063] Step 8: Waterproof layer and settlement joint construction
[0064] (1) Settlements joints are set every 4 to 6 meters, with a width of 2 cm. The settlement joints of the bottom plate, culvert body and top plate are kept consistent. The settlement joints are constructed in one go using bakelite boards;
[0065] (2) Before backfilling, ensure that the outer side of the culvert and the contact surface with the fill are painted with three coats of hot asphalt;
[0066] (3) The top, bottom and side walls of the structure are equipped with embedded rubber waterstop strips at the settlement joints, and the bottom and side walls of the structure are equipped with back-adhered waterproof tapes to effectively prevent water seepage in the culvert.
[0067] Embodiment 2
[0068] The use of self-propelled integral inner mold trolley construction technology has greatly improved the quality and appearance of the box culvert, saved construction time, and created benefits for the project during the construction of Fengma Construction Project No. 2.
[0069] 1. Economic benefits
[0070] The box-type channel self-propelled integral inner mold trolley is used for construction, which has fast construction progress, high turnover times, low cost and obvious economic benefits. Take 1-6×5 box culvert as an example:
[0071] (1) Template fee
[0072] The trolley formwork is customized by the formwork factory, and the material is mainly steel. The price of one section of trolley formwork (6m) is 55,000 yuan. The rental price of one section (6m) of box culvert support method buckle support is 0.34 yuan per cubic meter / day. The total price is 5483.52 yuan, and the formwork price is 36,000 yuan.
[0073] (2) Construction period, labor costs, and equipment costs
[0074] The 1-6×5 box culvert is 227 meters in total. The trolley method and the support method have 2 sets of templates each. The construction period of the trolley method is 227÷2÷6×4=76 days. The construction period of the support method is 227÷2÷6×6=114 days. The number of people for the trolley method is 6, and the labor cost is 6××76×260=118,600 yuan. The number of people for the support method is 8, and the labor cost is 8×114×260=237,100 yuan. The trolley method saves 76 days (about 2.5 months) in construction period compared to the support method, and can save 2.5×24300=61,000 yuan in crane rental fees.
[0075] Table 10.1.2 Comparison of the efficacy of the bracket method and the trolley method
[0076] Serial number project Bracket method Trolley method effect quantity 1 Labor cost 237,100 yuan 118,600 yuan reduce 118,600 yuan 2 Template Fee 72,000 yuan 110,000 yuan Increase 38,000 yuan 3 Total construction progress 114 days 76 days reduce 76 days 4 equipment 114 days 76 days reduce 61,000 yuan
[0077] Through economic benefit, construction period, labor cost, safety and quality analysis and application, the box-type channel self-propelled integral inner mold trolley has good concrete appearance, basically no consumption of consumable materials, short construction period, and total cost savings of 141,600 yuan. The construction period is saved by about 50%.
[0078] (3) Construction comparison
[0079] Compared with traditional scaffolding construction, construction progress and quality are significantly improved, and safety hazards are reduced.
[0080] Table 10.1.3 Comparison of the bracket method and the trolley method
[0081]
[0082]
[0083] 2. Social Benefits
[0084] The innovation and application of the rapid construction method of self-propelled integral inner mold for box-type channels has a reasonable process structure design and is easy to implement. The overall inner mold is highly flexible and can be raised and lowered as well as retracted left and right. The mobile mold frame can be quickly and lightly moved with the assistance of a jack trolley. It can be repeatedly used in other projects and is easy to be mastered by engineering and technical personnel and on-site construction workers. It speeds up the construction progress of the box-type channel, reduces construction safety risks, shortens the construction period, and has great social benefits.
[0085] Embodiment 3 Application Example
[0086] 1Project name: G312 Line Fengle to Mayingkou Section (including Yongchang Transit) Project FMSG-2
[0087] 1.1 Project location: Yongchang County, Jinchang City, Gansu Province
[0088] 1.2 Project cost: 640 million yuan
[0089] 1.3 Contract period: December 10, 2022 - December 10, 2024
[0090] 1.4 Project Overview: The project route starts at stake number K26+800 and ends at stake number K51+600, with a total length of 25km. The main projects include roadbed engineering, bridge engineering, pavement engineering, and greening engineering. There are 68 culverts, including 31 box culverts, and 8 of them are 6×5 box culverts that adopt this construction method.
[0091] 2 Project name: G569 line Mandela to Datong Wuwei to Xianmi Temple section WXTJ-2 project
[0092] 2.2 Project cost: 1.57 billion yuan
[0093] 2.3 Contract period: October 25, 2021 - April 25, 2024
[0094] 2.4 Project Overview: The starting and ending pile numbers of the WXTJ-2 project of the G569 line Mandela to Datong Highway Wuwei to Xianmi Temple section are K239+000-K260+000, and the total length of the route is 21km. The main projects are roadbed engineering, bridge engineering, and tunnel engineering. There are 74 culverts, including 39 box culverts, and 5 of them are 6×5 box culverts that adopt this construction method.
[0095] 3 Application Effects
[0096] The self-propelled integral inner formwork trolley construction method for cast-in-place box-type channels in highway projects has been applied in the construction of box-type channels in the FMSG-2 project of the Fengle to Mayingkou section of G312 (including Yongchang transit) and the WXTJ-2 project of the Mandela to Datong Wuwei to Xianmi Temple section of G569. It has effectively solved the problems of slow construction progress, poor appearance quality, and uneven lines of the wall and top plate of the box-type channels, improved the construction quality, accelerated the construction progress, reduced material turnover, which is both energy-saving and environmentally friendly, reduced labor input, and saved construction costs through trolley turnover. The self-propelled integral inner formwork of the box-type channel adopts the advantages of high strength, high rigidity and good stability of the integral main structure, configures a large flat formwork, and combines the milling process to significantly improve the appearance quality of the template joint quality, flatness, wall line type, etc. At the same time, this method sets up three "construction sections" for a box-type channel for skipping and pouring: curing area, steel bar pre-binding area and construction preparation area. According to the section division, it achieves streamlined construction, fully utilizes the working surface of the box-type channel, and realizes the purpose of rapid construction. At the same time, the use of streamlined construction effectively avoids the cross-operation of steel bar binding and template installation; compared with the steel structure mobile formwork used in other industries, this device adopts an integral truss structure, a small hydraulic system, and a modular design assembly concept, which overcomes the disadvantages of requiring a large number of skilled technicians, effectively reduces the frequency of use of large equipment such as car cranes, and improves inherent safety during disassembly and assembly and mobile transportation. In addition, the integral main support structure is quick and easy to install and disassemble, and has a fast turnover rate, which enables rapid assembly. The bottom hydraulic pulley walking module enables the formwork device to quickly switch from the "integral ground support state" during concrete pouring construction to the "roller walking state" after formwork removal. Its construction period, efficiency, quality, and safety are effectively guaranteed, and it has a high promotion value and application prospects.
[0097] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
Claims
1. A construction method for a self-propelled integral inner mold trolley for a cast-in-place box-type channel, characterized in that: The steps include: Step 1: Measurement and Stakeout The box-type channel construction adopts the two-person observation method to ensure the accuracy of the measurement data, and adopts the cement nail and hanging line marking method to ensure that the measurement results are directly reflected in the process control; for the oblique block at the end of the oblique box-type channel, the steel bar line is marked on the cushion surface according to the position of the gradual change of the steel bar spacing to ensure the steel bar spacing; Step 2: Foundation Construction The box-type channel foundation pit is excavated by excavators and manual excavation, with a 20-30cm thick base reserved for manual cleaning. After the base bearing capacity is tested and qualified, a gravel cushion layer is filled according to the design requirements and concrete is poured to seal the bottom. Step 3: Steel bar processing (1) The steel bars are processed in a centralized processing center, the bottom plate and top plate steel bars are processed into skeleton pieces, and the steel bars are welded and tied at the construction site; (2) The bottom plate of the box-type channel adopts plum blossom-shaped pads for stable support, and the top plate and culvert body adopt circular serrated pads and formwork support strips. And 4 are arranged per square meter; (3) The spacing of the steel bars is controlled by slots, and the overall structure of the steel bars is fixed by steel pipe brackets to prevent deformation; Step 4: Baseboard construction The contour lines on both sides of the culvert, the positioning line of the protective layer and the center line are accurately laid out on the cushion layer, and a customized steel mold is used to complete the pouring of the bottom slab concrete; Step 5: Template Engineering The self-propelled integral inner mold trolley is composed of three parts: bottom hydraulic pulley walking module, integral main structure and outer mold system. The self-propelled integral inner mold trolley is assembled in parallel with the bottom plate construction, and finally assembled according to the modules. Step 6: Concrete pouring Concrete pouring is transported by pump trucks, and vibrated by insert vibrators in combination with flat plate vibrators. Concrete pouring is based on the principle of longitudinal segmentation and horizontal layering. The layer thickness is generally not more than 30cm. The bottom plate is vibrated by insert vibrators in combination with flat plate vibrators, and the box body is vibrated by insert vibrators. The vibration process should be done quickly and slowly, to ensure the vibration time, pay attention to the bottom vibration effect, and avoid vibration leakage, over-vibration and other phenomena; Step 7: Demolding and Maintenance Following the order of removing the outer formwork first and then the inner formwork, after the concrete reaches 70% of the design strength, the formwork trolley is adjusted by the jack and the bottom screw to make the trolley formwork as a whole 10cm away from the concrete surface before it can be moved by the pulley; curing begins after the formwork is removed. The curing adopts the combined process curing method of "film covering + dripping", which makes full use of the "capillary" effect between the film and the concrete, which can not only keep the concrete moist for a long time, but also avoid the adverse effects of strong winds in the Hexi region, effectively keep warm and moist, reduce cracks caused by uneven shrinkage of concrete, save water and protect the environment, and greatly reduce the curing cost; Step 8: Waterproof layer and settlement joint construction (1) Settlements joints are set every 4 to 6 meters, with a width of 2 cm. The settlement joints of the bottom plate, culvert body and top plate are kept consistent. The settlement joints are constructed in one go using bakelite boards; (2) Before backfilling, ensure that the outer side of the culvert and the contact surface with the fill are painted with three coats of hot asphalt; (3) The top, bottom and side walls of the structure are equipped with embedded rubber waterstop strips at the settlement joints, and the bottom and side walls of the structure are equipped with back-adhered waterproof tapes to effectively prevent water seepage in the culvert.
2. The method for constructing a self-propelled integral inner mold trolley for a cast-in-place box-type channel according to claim 1 is characterized in that: In step five, the template engineering mainly includes the following steps: (1) Select a wide area, first assemble the pulley and beam, connect them with high-strength bolts, and complete the assembly of the hydraulic pulley travel module; then assemble the "door" frame structure, and also use high-strength bolts to connect the support column and the main beam; finally, assemble the top truss and flat mold; (2) The elevation and direction of the track are key factors to ensure the positioning of the inner mold trolley. The surveying personnel accurately lay out the track, mark points on the bottom plate at 2m horizontally, lay out the track installation line, and adjust the track elevation and direction; (3) The self-propelled integral inner mold trolley is assembled in modules. The weight of each module is different. The largest module belongs to the gantry structure, which is about 5 tons. The entire assembly process is hoisted by a 25-ton crane. After the bottom hydraulic pulley walking module is hoisted into place, a 1-2m long steel pipe is used as a temporary support to stabilize the pulley walking module. Then the gantry structure is hoisted. The gantry structure and the bottom hydraulic pulley walking module are connected with 24 high-strength bolts. After hoisting, the gantry is promptly connected with rods. Finally, the top distribution beam and flat mold are hoisted; (4) After each module is hoisted in place, the screw rod and hydraulic system are installed. The screw rod and hydraulic system are the core components for adjusting the self-propelled inner mold trolley, and are also the main process for controlling the overall linearity and flatness of the box-shaped channel; according to the overall fixation of the large flat mold, according to the three-point leveling principle, three screw rods are used to adjust and stabilize the template. The screw rod and the template are fixed with pins. Finally, the hydraulic system is accurately installed in the pre-made card slot. Using the "reverse pressure" principle, the hydraulic system is started to accurately adjust the trolley up and down and left and right to improve the accuracy of template installation; (5) The outer mold adopts a customized integral large flat mold, which is fastened to the back rib of the mold by using a pad through the tie rod. The tie rod is staggered at a spacing of 60 cm. The plug template is a key process for controlling the quality of the plug, and it is also one of the key factors affecting the appearance quality of the box-type channel opening. The plug template uses a double-row steel pipe method with back ribs and double-row square wood with back ribs at intervals. When fixing, it fully utilizes the back ribs on the edge of the large flat mold and is horizontally locked with the large flat mold by pulling screws.
Citation Information
Patent Citations
Formworking jumbo construction process for long and large box culvert
CN102704948A
Movable modular box culvert rapid construction device
CN110042771A
Heavy component transportation system and method for transporting heavy component by using combined type tire trolley
CN110406917A
Fabricated trolley for box culvert construction and construction method thereof
CN111424570A
Movable internal mold trolley for box culvert construction
CN210068192U