Shield tunneling machine receiving and disassembling construction method
By optimizing the structure on the shield receiving well and using jacks to achieve the translation of the shield, the problem of the shield machine being unable to be hoisted after dismantling is solved, the construction cost and construction period risks are reduced, and the safe and economic dismantling of the shield machine is achieved. and hoisting.
Patent Information
- Application Number
- CN202411077913.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-11-12
AI Technical Summary
There are obstacles above the shield receiving well that the shield machine cannot be lifted after dismantling, resulting in high construction costs and uncertain construction period.
A shield machine receiving and dismantling construction method is adopted, and the shield machine is decomposed by moving the hoisting port, planning the translation path, optimizing the receiving well structure, and using jacks to realize the horizontal and vertical translation and hoisting of the shield body and the receiving bracket. The shield and the rear supporting trolley are moved to the relocated hoisting port through a jack in the receiving well.
It effectively solves the problem that the shield machine cannot be lifted after dismantling, reduces construction costs, ensures safety during construction periods, and reduces friction through limiting steel plates and lubricating oil, realizing large-volume and large-weight objects in limited space environments Free translation under.
Smart Images

Figure CN118933809A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of shield construction, and in particular relates to a shield machine receiving and disassembling construction method. Background Art
[0002] The shield method is a fully mechanized construction method in the dark excavation method. It pushes the shield machine into the ground, supports the surrounding rock with the shield shell and segments to prevent collapse into the tunnel, and uses a cutting device to excavate the soil in front of the excavation face. The soil is transported out of the cave by the excavation machinery, and is pressurized and pushed forward at the rear by jacks. The precast concrete segments are assembled to form a mechanized construction method of the tunnel structure.
[0003] The shield machine is mainly composed of the shield machine and the supporting system. The shield construction process can be roughly divided into the following parts: shield machine start, shield machine excavation, shield machine reception. If there are obstacles above the shield receiving shaft, such as 110V high-voltage lines, the shield machine will be unable to be hoisted after dismantling.
[0004] Therefore, there is an urgent need for a shield machine receiving and disassembly construction method with low cost and controllable construction period, so as to solve the problem that the shield machine cannot be hoisted after disassembly due to obstacles above the shield receiving shaft. Summary of the invention
[0005] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a shield machine receiving and disassembly construction method with low cost and controllable construction period, so as to solve the problem that the shield machine cannot be hoisted after disassembly due to obstacles above the shield receiving shaft.
[0006] In order to achieve the above objectives, this application adopts the following technical methods:
[0007] A shield machine receiving and disassembling construction method comprises the following steps:
[0008] S1: Move the hoisting port to a place without obstacles, plan the translation path of the shield machine and optimize the structure of the receiving shaft;
[0009] S2: After the shield body of the shield machine is completely on the receiving bracket, the shield machine is disassembled into the shield body and the rear supporting trolley, and the rear supporting trolley is transported to the starting station and hoisted out of the well;
[0010] S3: Use several jacks to achieve horizontal and vertical translation and lifting of the shield body and the receiving bracket; after pushing the shield body to the lifting port position, disassemble and lift the shield body;
[0011] In S3, the shield body and the receiving bracket are first translated horizontally along the direction perpendicular to the shield body axis by a plurality of jacks; and then translated longitudinally along the shield body axis;
[0012] When moving horizontally, first temporarily weld the shield body and the receiving bracket, and then use a number of horizontal jacks to move the shield body and the receiving bracket horizontally as a whole along the direction perpendicular to the shield body axis;
[0013] During longitudinal translation, the temporary welding between the shield body and the receiving bracket is released, and the receiving bracket is temporarily fixed to the steel plate laid in the receiving well by fixing bolts, and then the shield body is longitudinally translated along the shield axis by a number of longitudinal jacks, and then the shield body is lifted up by a number of lifting jacks and the receiving bracket is longitudinally translated;
[0014] The plurality of lifting jacks are axially symmetrically arranged on both sides of the shield body with the shield body axis as the center, the lifting jack cylinder is fixedly connected to the shield body, and when the extended end of the lifting jack is recovered, the extended end of the lifting jack is higher than the bottom surface of the receiving bracket;
[0015] The plurality of longitudinal jacks are coaxially arranged between the shield body and the receiving bracket, and the longitudinal jack cylinder body is fixedly connected to the receiving bracket, and the protruding end is fixedly connected to the shield body; when the protruding end of the longitudinal jack is extended, the shield body translates longitudinally, and after the jacking jack lifts up the shield body, the fixing bolts are removed, and then the protruding end of the longitudinal jack retracts, and the receiving bracket translates longitudinally with the longitudinal jack.
[0016] By adopting the above technical method, the shield machine is disassembled into two parts, the shield body and the rear supporting trolley, after receiving, and the rear supporting trolley is withdrawn to the starting station and hoisted out, and the shield body and the receiving bracket are translated to the relocated hoisting outlet in the receiving well through the cooperation of several jacks, which can solve the problem that the shield machine cannot be hoisted after dismantling due to obstacles above the shield receiving well;
[0017] When the shield is moved horizontally, the shield body and the receiving bracket are temporarily welded first, and then the shield body and the receiving bracket are moved horizontally as a whole along the direction perpendicular to the shield body axis by a number of horizontal jacks;
[0018] During longitudinal translation, the temporary welding between the shield body and the receiving bracket is released, and the receiving bracket is temporarily fixed to the steel plate laid in the receiving well by fixing bolts, and then the shield body is translated longitudinally along the receiving bracket by a number of longitudinal jacks, and then the shield body is lifted up by a number of lifting jacks and the receiving bracket is translated longitudinally;
[0019] A plurality of lifting jacks are symmetrically arranged on both sides of the shield body with the shield body axis as the center axis, and the lifting jack cylinder is fixedly connected to the shield body. When the extended end of the lifting jack is recovered, the extended end of the lifting jack is higher than the bottom surface of the receiving bracket; in this way, the lifting jack will not affect the lateral movement of the shield body and the receiving bracket as a whole.
[0020] The setting of the longitudinal jack realizes the longitudinal translation of the shield body and the receiving bracket; during the longitudinal translation, the fixing bolts temporarily fix the receiving bracket to the steel plate laid in the receiving well, and when the extended end of the longitudinal jack is extended, the shield body can be longitudinally translated. After the jacking jack lifts the shield body, the fixing bolts are removed, and then the extended end of the longitudinal jack is retracted, and the receiving bracket can be longitudinally translated with the longitudinal jack; then the telescopic end of the jacking jack is retracted, and the shield body and the receiving bracket contact the steel plate laid in the receiving well again, and the fixing bolts are reinstalled, and the longitudinal jack and the jacking jack are repeated to realize the longitudinal translation of the shield body and the receiving bracket. In this way, the cooperation of the longitudinal jack and the jacking jack can realize the free translation of the large-volume and heavy-weight shield body and the receiving bracket in the receiving well with limited space.
[0021] Moreover, compared with the methods of dismantling the machine in the receiving well and withdrawing the shield machine as a whole to the starting station and relocating obstacles, the present application provides a shield machine receiving and disassembly construction method, which has the advantages of low cost and controllable construction period and safety.
[0022] Furthermore, in S1, CAD is used to simulate the shield translation route to avoid the structural columns.
[0023] Furthermore, the optimization of the receiving well structure in S1 includes changing the upward-flipped beam into a downward-flipped beam.
[0024] By adopting the above technical method, the construction difficulty in the process of moving the shield body to the lifting port after the relocation can be effectively reduced, so that the shield body can be moved smoothly.
[0025] Furthermore, in the S3, a plurality of limiting steel plates are welded to the outer shell of the shield.
[0026] Furthermore, lubricating oil is applied on the limiting steel plate in S3.
[0027] By adopting the above technical method, the setting of the limiting steel plate reduces the possibility of the shield body overturning, and the lubricating oil reduces the friction between the limiting steel plate and the receiving bracket.
[0028] Furthermore, the number of the lifting jacks is four, and the four lifting jacks are arranged in groups of two and are symmetrically distributed on both sides of the shield body with the shield body axis as the center; the lifting jack cylinder is fixedly connected to the shield body through a supporting bracket.
[0029] Furthermore, the longitudinal jack cylinder is fixedly connected to the receiving bracket via a mounting seat, and the extended end is fixedly connected to the shield body via a connecting seat.
[0030] By adopting the above technical method, the support bearing realizes the connection between the lifting jack and the shield body, and the setting of the mounting seat and the connecting seat respectively realizes the connection between the longitudinal jack and the receiving bracket and the shield body.
[0031] Compared with the prior art, this application has the following technical effects:
[0032] 1. The present application discloses a shield machine receiving and disassembling construction method, which disassembles the shield machine into two parts, a shield body and a rear supporting trolley, after receiving the shield machine, and withdraws the rear supporting trolley to the starting station and hoists it out, and translates the shield body and the receiving bracket to the relocated hoisting outlet in the receiving well through the cooperation of a number of jacks, which can solve the problem that the shield machine cannot be hoisted after being disassembled due to obstacles above the shield receiving well;
[0033] During the specific translation, several transverse jacks realize the transverse translation of the shield body and the receiving bracket as a whole along the direction perpendicular to the axis of the shield body; and when the extended end of the jacking jack is retracted, the extended end of the jacking jack is higher than the bottom surface of the receiving bracket; in this way, the jacking jack will not affect the transverse movement of the shield body and the receiving bracket as a whole; in addition, the cooperation of the longitudinal jack and the jacking jack can realize the free translation of the large-volume and heavy-weight shield body and the receiving bracket in the receiving well with limited space.
[0034] In this way, the present application provides a shield machine receiving and disassembly construction method, which can not only solve the problem that the shield machine cannot be hoisted after being dismantled due to obstacles above the shield receiving shaft, but also has the advantages of low cost and controllable construction period safety compared to methods such as dismantling the machine in the receiving shaft and withdrawing the shield machine as a whole to the starting station and relocating obstacles.
[0035] 2. In this application S1, CAD is used to simulate the shield body translation route, avoid structural columns, and change the upper flip beam to a lower flip beam and other optimization measures, which can effectively reduce the construction difficulty during the translation of the shield body to the lifting port after the relocation, so that the shield body can be translated smoothly.
[0036] 3. The setting of the limit steel plate reduces the possibility of the shield overturning, and the lubricating oil reduces the friction between the limit steel plate and the receiving bracket.
[0037] 4. The support bracket realizes the connection between the lifting jack and the shield body, and the setting of the mounting seat and the connecting seat realizes the connection between the longitudinal jack and the receiving bracket and the shield body respectively. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 This is an overall flow chart of an embodiment of a shield machine receiving and disassembling construction method of the present application;
[0039] Figure 2 This is a plan view of the receiving well bottom plate of Liuxiang Road Station in the embodiment of the present application. DETAILED DESCRIPTION
[0040] The specific contents of this application are further explained in detail below in conjunction with embodiments.
[0041] The present application discloses a shield machine receiving and disassembling construction method, referring to Figure 1 , including the following steps: S1: move the lifting port to a place without obstacles, plan the translation path of the shield machine and optimize the structure of the receiving well; S2: after the shield body of the shield machine is completely on the receiving bracket, disassemble the shield machine into the shield body and the rear supporting trolley, and transport the rear supporting trolley to the starting station for lifting out of the well; S3: use a number of jacks to realize the lateral and longitudinal translation and lifting of the shield body and the receiving bracket; after pushing the shield body to the lifting port position, disassemble and lift the shield body.
[0042] Thus, the present application provides a shield machine receiving and disassembling construction method, which disassembles the shield machine into two parts, a shield body and a rear supporting trolley, after receiving, and withdraws the rear supporting trolley to the starting station and hoist it out, and in the receiving well, the shield body and the receiving bracket are translated to the relocated hoisting outlet through the cooperation of a number of jacks; it can solve the problem that the shield machine cannot be hoisted after disassembly due to obstacles above the shield receiving well, and compared with the method of disassembling the machine in the receiving well and withdrawing the shield machine as a whole to the starting station, relocating obstacles, etc., it has the advantages of low cost and controllable construction period and safety.
[0043] Among them, S1 uses CAD to simulate the shield body translation route, avoids structural columns, and changes the upper flip beam to a lower flip beam and other optimization measures, which can effectively reduce the construction difficulty during the translation of the shield body to the lifting port after the relocation, so that the shield body can be translated smoothly.
[0044] In addition, the shield body and the receiving bracket in S3 are first translated horizontally along the direction perpendicular to the shield body axis by several jacks; and then translated longitudinally along the shield body axis; during the horizontal translation, the shield body and the receiving bracket are first temporarily welded, and the shield body and the receiving bracket are translated horizontally along the direction perpendicular to the shield body axis as a whole by several horizontal jacks. The outer shell of the shield body in S3 is welded with several limit steel plates coated with lubricating oil, and the number of limit steel plates is 6, 2 of which are welded to the front shield, the middle shield, and the tail of the shield; further, the size of the limit steel plate is: 20×100×200mm. By setting the limit steel plate, the possibility of the shield body overturning is reduced, and the lubricating oil reduces the friction between the limit steel plate and the receiving bracket.
[0045] In addition, when the receiving bracket translates on the steel plate, it is a sliding friction, and the friction force F=μFn, where F is the sliding friction force, μ is the sliding friction coefficient between steel and steel, and Fn is the pressure; in the presence of lubricant, μ is 0.05-0.10. In the specific implementation process, considering that it is difficult to make the surface of the laid steel plate completely clean and smooth, a larger value of 0.2 is taken as the sliding friction coefficient; the total weight of the shield body + receiving bracket takes the maximum value of 350t, then the friction force is F=0.2×3500=700kN; the thrust that a 200t hydraulic jack can provide is 2000kN> friction force 700kN, so a 200t hydraulic jack is sufficient to meet the thrust requirements for the lateral translation of the shield body.
[0046] In addition, the maximum weight of the shield machine + receiving bracket is 350t, the receiving bracket specification is 9000×3960mm, and the bearing capacity of C30 concrete is 30MPa. The uniform force on the receiving bracket is calculated according to the following formula:
[0047] F=3500kN / (3.96×9)=98.2Kpa;
[0048] And 98.2KPa<30MPa, the bearing capacity of the foundation meets the design requirements.
[0049] During the specific construction, the shield body starts from rest, and the initial thrust of lateral sliding is controlled within 1000kN, and then the translation thrust is controlled between 300 and 500kN. Each time the lateral jack cylinder is pushed forward, the distance is controlled within 30mm. After each advancement of 30mm, the quality of the welds in key parts is checked, and construction is continued after safety is confirmed. At the same time, at least two emergency stop switches are installed on the hydraulic propulsion equipment, one at each of the two jack observation points, to prevent timely stopping in case of emergency.
[0050] During longitudinal translation, the temporary welding between the shield body and the receiving bracket is released, and the shield body is first longitudinally translated along the length direction of the receiving bracket by using a number of longitudinal jacks, that is, the shield body is longitudinally translated along the axis direction of the shield body, and then the shield body is lifted up by a number of jacking jacks and then longitudinally translated to the receiving bracket. The shield body is connected to four vertically arranged jacking jacks through a support bracket, and the four jacking jacks are arranged in groups of two and are axially symmetrically distributed on both sides of the shield body with the axis of the shield body as the center; the jacking jack cylinder is fixedly connected to the shield body through the support bracket, and when the extended end of the jacking jack is recovered, the extended end of the jacking jack is higher than the bottom surface of the receiving bracket. In this way, the jacking jack will not affect the overall lateral movement of the shield body and the receiving bracket.
[0051] In addition, in order to enhance the stability of the installation of the lifting jack, two angle steels are welded to the support bracket. The support bracket is located between the two angle steels. The specific size of the angle steel is 50×50×5mm. Reinforcing ribs are also welded on both sides of the support bracket.
[0052] Several longitudinal jacks are arranged on both sides of the shield body along the shield body axis direction and are located between the shield body receiving brackets, and the longitudinal jack cylinder is fixedly connected to the receiving bracket through the mounting seat, and the extended end is fixedly connected to the shield body through the connecting seat. During longitudinal translation, the receiving bracket is temporarily fixed to the steel plate laid in the receiving well by the fixing bolts. When the extended end of the longitudinal jack is extended, the shield body can be longitudinally translated. After the jacking jack lifts the shield body, the fixing bolts are removed, and then the extended end of the longitudinal jack is retracted, and the receiving bracket can be longitudinally translated with the longitudinal jack; then the telescopic end of the jacking jack is retracted, and the shield body and the receiving bracket contact the steel plate laid in the receiving well again, and the fixing bolts are reinstalled, and then the telescopic cooperation of the longitudinal jack and the jacking jack is repeated, and the longitudinal translation of the shield body and the receiving bracket can be realized. In this way, the cooperation of the longitudinal jack and the jacking jack can realize the free translation of the large-volume and heavy-weight shield body and the receiving bracket in the receiving well with limited space.
[0053] During the specific construction, the stroke difference of the longitudinal jacks on both sides of the shield body shall not exceed 10mm; during the shield lifting process, the stroke difference of the four lifting jacks shall not exceed 10mm; the receiving bracket shall move forward along the center line of the line with a deviation of no more than 50mm; and the receiving bracket shall not affect the lifting jacks when moving forward.
[0054] In this way, the cooperation of the lifting jack and the longitudinal jack can realize the longitudinal translation of the shield body and the receiving bracket.
[0055] In addition, in order to improve the construction efficiency of shield machine reception, the relevant steps in the shield machine reception process can be carried out as follows:
[0056] 1) When the shield machine reaches the tunnel entrance, it is advanced slowly and steadily, the cutter head speed and excavation thrust are appropriately reduced, the advancement speed is controlled at 5-15mm / min, the thrust is controlled at about 5000kN, and the cutter head speed is controlled within 1rpm. In this way, it can ensure that the shield machine can move forward normally under small thrust conditions, and at the same time reduce the amount of debris cleaning when exiting the tunnel, thereby improving construction efficiency;
[0057] 2) Since the lateral force and longitudinal thrust of the receiving bracket are large and unevenly stressed during translation, in order to prevent the receiving bracket from cracking during advancement, 10mm thick steel plates are used to strengthen the welding reception at weak locations such as the bottom and bolt connections around the receiving bracket; the receiving bracket is positioned according to the design drawing, and is fixed with welded blocks and steel supports around it to prevent the receiving bracket from displacement during the advancement of the shield machine.
[0058] In addition, when the shield machine exits the tunnel, after the debris in the cutterhead is cleaned up, the shield machine continues to advance and assemble the segments in the shortest time possible; to ensure the thrust between the segment rings, reaction points are set between the receiving platform and the shield body to increase the reaction force of the shield machine when it moves forward, to prevent water leakage caused by insufficient compression of the segments close to the tunnel gate when arriving at the station, and to shorten the time it takes for the shield machine to exit the tunnel, reducing the loss of water, soil and slurry.
[0059] In summary, the present application provides a shield machine receiving and disassembly construction method, which can solve the problem that the shield machine cannot be hoisted after disassembly due to obstacles above the shield receiving shaft, and has the advantages of low cost and controllable construction period.
[0060] The implementation principle of a shield machine receiving and disassembling construction method in this application is:
[0061] S1: Move the hoisting port to a place without obstacles, plan the translation path of the shield machine and optimize the structure of the receiving shaft; the structural optimization measures include using CAD to simulate the translation route of the shield, avoiding structural columns, and changing the upward beam to a downward beam;
[0062] S2: After the shield body of the shield machine is completely on the receiving bracket, the shield machine is disassembled into the shield body and the rear supporting trolley, and the rear supporting trolley is transported to the starting station and hoisted out of the well;
[0063] S3: Use several jacks to achieve horizontal and vertical translation and lifting of the shield body and the receiving bracket; after pushing the shield body to the lifting port position, disassemble and lift the shield body;
[0064] Among them, the shield body and the receiving bracket in S3 are first translated horizontally along the direction perpendicular to the shield body axis by a number of jacks; then translated longitudinally along the shield body axis; and when translated horizontally, the shield body and the receiving bracket are first temporarily welded, and the shield body and the receiving bracket are translated horizontally as a whole along the direction perpendicular to the shield body axis by a number of horizontal jacks; and the outer shell of the shield body in S3 is welded with a number of limit steel plates coated with lubricating oil to reduce the possibility of the shield body overturning;
[0065] When moving longitudinally, the temporary welding between the shield body and the receiving bracket is released, and the shield body is first moved longitudinally along the receiving bracket by a number of longitudinal jacks, and then the shield body is lifted up by a number of jacking jacks and then moved longitudinally to the receiving bracket; and the shield body is connected to four vertically arranged jacking jacks through a supporting support, and when the extended ends of the jacking jacks are recovered, the extended ends of the jacking jacks are higher than the bottom surface of the receiving bracket;
[0066] A plurality of longitudinal jacks are arranged between the shield body and the receiving bracket along the shield body axis direction, and the longitudinal jack cylinder is fixedly connected to the receiving bracket, and the extended end is fixedly connected to the shield body; when the extended end of the longitudinal jack is extended, the shield body moves longitudinally, and after the jacking jack lifts up the shield body, the extended end of the longitudinal jack retracts, and the receiving bracket moves longitudinally with the longitudinal jack;
[0067] In this way, the lifting jack and the longitudinal jack cooperate to achieve the longitudinal translation of the shield body and the receiving bracket.
[0068] In summary, the present application provides a shield machine receiving and disassembly construction method, which can solve the problem that the shield machine cannot be hoisted after dismantling due to obstacles above the shield receiving shaft. Compared with the method of dismantling the machine in the receiving shaft and withdrawing the shield machine as a whole to the starting station, and relocating obstacles, it has the advantages of low cost and controllable construction period and safety.
[0069] Specifically, taking the receiving shaft of Hangzhou Metro Liuxiang Road Station as an example, the project overview is as follows: The section between Wushanqian Village Station and Liuxiang Road Station of the northern extension section of Hangzhou Metro Line 3 is a single-circular shield section. The line runs from Wushanqian Village Station to the south along the existing 202 County Road. The left and right lines start from Wushanqian Village Station and are received at Liuxiang Road Station. The right line of the tunnel is 415m long, the left line is 412m long, and the buried depth of the section tunnel is 11.72~17.35m. Liuxiang Road Station is a three-story, two-span frame structure. The standard section width of the station is 23.5m, and the net width of the shield shaft section is 25.6m. The main body of Liuxiang Road Station is constructed by open-cut method; the shield machines in this section are Herrenknecht S-1117 earth pressure balance shield machine and Herrenknecht S-1096 earth pressure balance shield machine.
[0070] However, there is a 110kV high-voltage line above the receiving shaft (north end of Liuxiang Road Station) of the Wushanqian Village Station-Liuxiang Road Station section of the northern extension of Hangzhou Metro Line 3, 25m above the ground. The existing safety protection frame is 18m above the ground, making it impossible to hoist the Wuliu section shield machine after receiving and dismantling it. In addition, the 110kV high-voltage line supplies electricity to Hangzhou West Station of the Shanghai-Hangzhou High-speed Railway. If the high-voltage line is moved, the impact range will be large and the cost will be high. If the shield machine is dismantled in the receiving shaft of Liuxiang Road Station after receiving it, and the shield machine is disassembled, it will be transported in parts to the starting shaft Wushanqian Village Station for hoisting out of the shaft, the dismantling cost will be high and the construction period will be difficult to guarantee.
[0071] According to a shield machine receiving and disassembling construction method in this application, combined with the actual project overview, refer to Figure 2 , optimize the receiving well, move the left-line shield hoisting hole 34.8m southward as a whole, move the right-line shield hoisting hole 31.1m southward as a whole, lengthen the north end well of Liuxiang Road Station by 40m, change the upper flip beam to the lower flip beam, and avoid the translation path of the shield machine. When receiving the shield machine, separate the shield body and the rear supporting trolley, and withdraw the rear supporting trolley back to Wushanqian Village Station, and hoist it out of the well at the starting well of Wushanqian Village Station. Finally, move the shield machine to the southward lifting port for dismantling and hoisting; the receiving and disassembling of the shield machine can be completed.
[0072] The present application discloses a shield receiving and disassembly construction method which has been successfully applied to the shield receiving of Liuxiang Road Station in Hangzhou. The application has proved that when there is a 110kV high-voltage line above the shield receiving shaft and the shield disassembly and hoisting are restricted, the structure and size of the shield shaft are designed and optimized according to the characteristics of the surrounding environment of the shield receiving shaft, and the shield hoisting port is moved southward to outside the influence range of the 110kV high-voltage line. The shield body translation technology of the shield machine is adopted, and the optimized hydraulic cylinder assembly is used. The shield body of the shield machine is moved horizontally in the lateral and longitudinal directions, and the shield body is moved to the hoisting hole of the shield machine after the southward movement. According to the shield disassembly method, the shield machine is disassembled and hoisted, which can effectively avoid the 110kV high-voltage line obstacle while ensuring the node target of the subway line track laying period, and provides a reference for similar projects with obstacles above the receiving shaft. In this scenario of the present embodiment, the shield translation route is simulated by CAD and the influence of electromagnetic radiation is comprehensively considered to design an optimized shield translation path. The electromagnetic radiation monitoring device is installed at the key position of the shield machine to monitor the radiation signal of the 110kV high-voltage line in real time. These signals are transmitted to the control device of the longitudinal jack and the lifting jack through a dedicated transmission system. The control device can accurately analyze and interpret the radiation signal to adjust and optimize the operation of the jack. This design ensures that the shield machine operates according to the set path during translation and lifting, avoiding orientation errors and unnecessary adjustments, and significantly improving the accuracy and reliability of engineering construction. This intelligent solution not only effectively responds to the safety risks that may be caused by electromagnetic radiation, but also provides innovative technical support for the construction of subway tunnels in complex environments.
[0073] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A shield machine receiving and disassembling construction method, It is characterized in that The following steps are involved: S1: Move the hoisting port to a place without obstacles, plan the translation path of the shield machine and optimize the structure of the receiving shaft; S2: After the shield body of the shield machine is completely on the receiving bracket, the shield machine is disassembled into the shield body and the rear supporting trolley, and the rear supporting trolley is transported to the starting station and hoisted out of the well; S3: Use several jacks to achieve horizontal and vertical translation and lifting of the shield body and the receiving bracket; after pushing the shield body to the lifting port position, disassemble and lift the shield body; In S3, the shield body and the receiving bracket are first translated horizontally along the direction perpendicular to the shield body axis by a plurality of jacks; and then translated longitudinally along the shield body axis; When moving horizontally, first temporarily weld the shield body and the receiving bracket, and then use a number of horizontal jacks to move the shield body and the receiving bracket horizontally as a whole along the direction perpendicular to the shield body axis; During longitudinal translation, the temporary welding between the shield body and the receiving bracket is released, and the receiving bracket is temporarily fixed to the steel plate laid in the receiving well by fixing bolts, and then the shield body is longitudinally translated along the shield axis by a number of longitudinal jacks, and then the shield body is lifted up by a number of lifting jacks and the receiving bracket is longitudinally translated; The plurality of lifting jacks are axially symmetrically arranged on both sides of the shield body with the shield body axis as the center, the lifting jack cylinder is fixedly connected to the shield body, and when the extended end of the lifting jack is recovered, the extended end of the lifting jack is higher than the bottom surface of the receiving bracket; The plurality of longitudinal jacks are coaxially arranged between the shield body and the receiving bracket, and the longitudinal jack cylinder body is fixedly connected to the receiving bracket, and the protruding end is fixedly connected to the shield body; when the protruding end of the longitudinal jack is extended, the shield body translates longitudinally, and after the jacking jack lifts up the shield body, the fixing bolts are removed, and then the protruding end of the longitudinal jack retracts, and the receiving bracket translates longitudinally with the longitudinal jack.
2. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that In S1, CAD is used to simulate the shield translation route to avoid the structural columns.
3. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that The optimization of the receiving well structure in S1 includes changing the upward-flipping beam into a downward-flipping beam.
4. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that The shield shell in S3 is welded with a plurality of limiting steel plates.
5. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that The limit steel plate in S3 is coated with lubricating oil.
6. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that The number of the jacking jacks is four, and the four jacking jacks are arranged in groups of two and are symmetrically distributed on both sides of the shield body with the shield body axis as the center; the cylinder of the jacking jack is fixedly connected to the shield body through a supporting bracket.
7. A shield machine receiving and disassembling construction method as claimed in claim 1, It is characterized in that The longitudinal jack cylinder is fixedly connected to the receiving bracket through a mounting seat, and the extended end is fixedly connected to the shield body through a connecting seat.
Citation Information
Cited By
Construction method for segmental transfer of shield tunneling machine in limited space
CN119686757A
A construction method for sectional transfer of a shield machine in a confined space
CN119686757B
Underground translation dismantling construction method for large-diameter shield tunneling machine
CN121066604A