Safety construction method for tunnel close to construction sensitive area

By using technologies such as advance grouting of the periphery and palm surfaces, leading support of the top arch and mechanical excavation in tunnel construction, the problems of structural deformation and foundation settlement in tunnel construction near sensitive areas are solved, ensuring the safety of construction and Progress has achieved protection for sensitive areas.

CN118933899APending Publication Date: 2024-11-12CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411258322.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the tunnel construction process, when approaching sensitive areas (such as military management areas), there are environmental risks and their own risks, resulting in structural deformation, uneven foundation settlement, cracking and other problems, affecting military activities and construction safety, and the existing technology is difficult to be effective Meet these challenges.

Method used

Adopt grouting around the hole and palm surface, top arch forward large pipe shed and small conduit support, mechanical excavation, joint initial support of anchor spray hanging net and steel support, simple trest trest secondary lining and grouting after lining Measures to ensure the safety and stability of tunnel construction.

Benefits of technology

It effectively avoids adverse effects on sensitive areas, ensures the safety and progress of tunnel construction, reduces structural deformation and ground settlement, and improves the control capability and safety of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933899A_ABST
    Figure CN118933899A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel construction methods, and discloses a safe construction method for a tunnel close to a construction sensitive area. Comprising the following steps that (1) advance grouting is conducted on the periphery of a tunnel and a tunnel face, the length of each cycle of grouting is 30 m, 3 m is reserved for each cycle to serve as a grouting stopping rock tray, the grouting range is 3 m outside a tunnel excavation contour line and in front of the tunnel face, advance grouting is conducted according to the grout diffusion radius of 2 m and the hole bottom interval of 3 m, 76 holes are formed in each cycle, the diameter of each grouting hole is not smaller than 89 mm, and the diameter of a final hole is not smaller than 75 mm; (2) a top arch advance large pipe shed and a top arch advance small pipe are adopted for advance supporting; the construction method comprises the steps of (1) carrying out primary lining, (2) carrying out secondary lining, (3) carrying out mechanical excavation, (4) carrying out primary support on IV-class surrounding rock and V-class surrounding rock through combination of an anchoring and shotcreting hanging net and a steel support, (5) carrying out secondary lining through a simple trestle trolley, and (6) carrying out grouting after lining.The safe construction method special for the tunnel close to the sensitive area is provided, adverse effects on the sensitive area can be avoided, and guidance suggestions can be provided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of safe tunnel construction, and in particular to a safe tunnel construction method near a sensitive construction area. Background Art

[0002] During the tunnel construction process, the tunnel may be close to some sensitive areas, such as military management areas, etc. This kind of tunnel construction near sensitive areas has environmental risks and inherent risks. The risk level of environmental risk is high, and its main risks are local deformation of the structure, uneven settlement and cracking of the foundation, resulting in damage to military facilities and affecting normal military activities. The inherent risks include excessive deformation of the tunnel, and even tunnel collapse, instability, water gushing, mud bursting, etc., which in turn threaten the safety of construction personnel and seriously affect the construction progress.

[0003] Compared with the ordinary tunnel construction process, since the tunnel construction is close to sensitive areas, it is necessary to consider the existing environmental risks to avoid adverse effects on sensitive areas. At present, it is relatively rare to encounter sensitive areas during tunnel construction, and construction personnel are not fully aware of the impact of tunnel construction on sensitive areas. Therefore, it is necessary to provide a safe construction method for tunnels near sensitive areas to avoid adverse effects on sensitive areas and cause more serious consequences. Summary of the invention

[0004] The purpose of the present invention is to provide a safe construction method for a tunnel near a sensitive construction area.

[0005] The present invention is implemented by the following technical solution: A method for safe construction of a tunnel near a sensitive construction area comprises the following steps: (1) Pre-grouting is adopted around the tunnel and the face. The length of each grouting cycle is 30m, of which 3m is reserved as a grouting rock plate in each cycle. The grouting range is 3m outside the tunnel excavation contour line and in front of the face. Pre-grouting is arranged according to the slurry diffusion radius of 2m and the hole bottom spacing of 3m. There are 76 holes in each cycle. The diameter of the grouting hole opening is not less than 89mm, and the final hole diameter is not less than 75mm; (2) Use the top arch advance large pipe shed and top arch advance small pipe for advance support; (3) Mechanical excavation; (4) For Class IV and V surrounding rock, anchor spraying and mesh hanging are used in combination with steel support for initial support; (5) Use a simple trestle trolley for secondary lining; (6) Grouting after lining.

[0006] In order to better implement the method of the present invention, further, in step (1), the specific process of performing advance grouting on the tunnel periphery and the tunnel face includes the following steps: (1.1) Sealing the tunnel face: hang a double-layer steel mesh and use 20 cm thick shotcrete for sealing; (1.2) Measure the hole layout; (1.3) Drilling: First drill the grouting holes arranged on the top arch of the tunnel, then drill the holes on both sides of the tunnel, and finally drill the low arch holes; (1.4) Borehole flushing: After each section of drilling is completed, the borehole is opened and a large flow of water is used to flush out the rock powder and other materials in the hole. The depth of the borehole after flushing is measured and recorded. The thickness of the sediment at the bottom of the hole after flushing should not exceed 20 cm. (1.5) Pulping; (1.6) Grouting: At least one of the following methods: segmented forward grouting, segmented backward grouting, or full-hole one-time pressure grouting, whichever is more appropriate, should be selected based on the actual situation; (1.7) Slurry transformation; (1.8) Grouting and sealing.

[0007] In order to better implement the method of the present invention, further, in the step (2), the construction process of the top arch advance large pipe shed is: (2.1.1) Build a pipe shed studio; (2.1.2) Drilling of pipe shed holes; (2.1.3) Install pipe shed; (2.1.4) Carry out grouting of pipe roof.

[0008] In order to better implement the method of the present invention, further, in the step (2), the construction process of the top arch advance small duct is: (2.2.1) Seal the excavation surface with sprayed concrete; (2.2.2) Arrange holes along the perimeter of the excavation surface; (2.2.3) Process and manufacture a small grouting tube, and insert the processed small tube into the hole; (2.2.4) Prepare slurry and carry out grouting; (2.2.5) Carry out excavation work.

[0009] In order to better implement the method of the present invention, further, in the step (3), the specific process of mechanical excavation is as follows: mechanical excavation is used for tunnel V-type surrounding rock, and the excavation cycle footage is 0.8-1.2m. The tunnel V-type surrounding rock conditions are poor. Due to the large cross-section, the V-type surrounding rock adopts the up and down step method. The special section adopts the step reserved core soil method for excavation. Mechanical excavation is used, and the excavation cycle footage is 0.5-0.7m. Before mechanical excavation, the surveying team will lay out the excavation contour line, use red paint to mark the points, and draw the excavation contour line to avoid over-excavation or under-excavation. The surveying team should also review the excavation in time to prevent over-excavation and under-excavation. After the excavation is completed, the loose stones on the excavation surface should be processed to avoid being hit by objects.

[0010] In order to better implement the method of the present invention, further, in step (4), the specific process of performing the initial support is as follows: (4.1) Drilling of anchor holes; (4.2) Installation of anchor bolts and grouting; (4.3) Install steel mesh; (4.4) Carry out steel support construction; (4.5) Shotcrete.

[0011] In order to better implement the method of the present invention, further, in the step (4.2), the specific process of installing the anchor rod and grouting is as follows: (4.2.1) Preparation work before installing anchor bolts; (4.2.2) Drilling; (4.2.3) Washing holes; (4.2.4) Insert the anchor rod and plastic anchor head assembly; (4.2.5) Insert the trachea and perform orifice processing; (4.2.6) Install the gasket and nuts; (4.2.7) Grouting; (4.2.8) Nut loading.

[0012] In order to better implement the method of the present invention, further, in step (5), the specific process of using a simple trestle trolley for secondary lining is as follows: (5.1) Bottom slab concrete construction; (5.2) Concrete lining of side and top arch.

[0013] In order to better implement the method of the present invention, further, in the step (6), the grouting after lining is divided into backfill grouting and consolidation grouting.

[0014] In order to better implement the method of the present invention, further, the backfill grouting range is 110° of the arch, the grouting hole diameter is φ50, the row spacing is 3m, the rock penetration is 0.1m, the backfill grouting uses cement slurry, the water-cement ratio is 0.6:1~1:1, and the grouting pressure is 0.3Mpa; The consolidation grouting arrangement is PG6, and the grouting material is silicate cement. Medium-resistant sulfate cement is used in the tunnel section where groundwater has acid corrosion. The grouting hole diameter of PG6 consolidation grouting is φ56, the hole depth is 6m, the circumferential spacing is 2m, and the longitudinal spacing is 2.5m.

[0015] Compared with the prior art, the present invention has the following advantages and beneficial effects: The present invention provides a safe construction method specifically for tunnels near sensitive areas, filling the gap in this construction situation. It can not only avoid adverse effects on sensitive areas and lead to more serious consequences, but also provide guidance for future construction processes with similar working conditions, ensuring the safe and normal construction of this special tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The present invention is further described in conjunction with the following drawings and embodiments, and all the concepts and innovations of the present invention should be regarded as the disclosed contents and the protection scope of the present invention.

[0017] Figure 1 It is a longitudinal section diagram of the advance grouting around the tunnel and the tunnel face in the present invention; Figure 2 It is a cross-sectional view of the advance grouting around the tunnel and the tunnel face in the present invention; Figure 3 This is a structural diagram of a large pipe shed in the present invention; Figure 4 This is a schematic diagram of the structure of the advanced small catheter in the present invention; Figure 5 Schematic diagram of the construction process of the advanced small-pipe grouting in the present invention; Figure 6 Schematic diagram of the wet spraying concrete construction process in the present invention; Figure 7 This is a cross-sectional view of the PG6 type consolidation grouting in the present invention. DETAILED DESCRIPTION

[0018] In order to make the purpose, process conditions and advantages of the present invention more clearly understood, the present invention is further described in detail in conjunction with the following embodiments, but the embodiments of the present invention are not limited thereto. Without departing from the above-mentioned technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the field, which should all be included in the scope of the present invention. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0019] Embodiment 1: This embodiment provides a method for safe construction of a tunnel near a sensitive construction area, comprising the following steps: (1) Pre-grouting is adopted around the tunnel and the face. The length of each grouting cycle is 30m, of which 3m is reserved as a grouting rock plate in each cycle. The grouting range is 3m outside the tunnel excavation contour line and in front of the face. Pre-grouting is arranged according to the slurry diffusion radius of 2m and the hole bottom spacing of 3m. There are 76 holes in each cycle. The diameter of the grouting hole opening is not less than 89mm, and the final hole diameter is not less than 75mm; (2) Use the top arch advance large pipe shed and top arch advance small pipe for advance support; (3) Mechanical excavation; (4) For Class IV and V surrounding rock, anchor spraying and mesh hanging are used in combination with steel support for initial support; (5) Use a simple trestle trolley for secondary lining; (6) Grouting after lining.

[0020] During construction, the ground and buildings in the section near the military management area are monitored for safety. A monitoring network is set up within 25m on the left and right sides of the tunnel centerline, with a grid spacing of 5m. During construction, settlement monitoring is carried out on the monitoring points. If a large settlement of the ground is found, support is immediately strengthened, the monitoring frequency is increased, and relevant units are notified in time for processing. In order to reduce the impact on adjacent facilities, support measures such as large and small pipe sheds, steel supports, and digging and lining are adopted. During construction, the deformation monitoring of the tunnel and the monitoring of ground settlement are carried out well, and the effects of advanced support, primary support and secondary lining of tunnel construction are timely grasped. Problems should be solved in time, and work should be stopped first for processing, and construction can be continued after processing. If the ground deformation is large, stop the tunnel excavation immediately and carry out concrete lining in time. At the same time, master the construction methods, be proficient in the construction procedures, reduce the exposure time of surrounding rocks, and support in time during the construction within 200m from the face of the head to ensure that the ground settlement deformation does not exceed the requirements of the specification. It is planned to use the method of advanced grouting to consolidate the rock in the unexcavated area, use I18a steel I-beam (spacing 0.5m / frame), medium 108 large pipe shed, medium 42 small pipe advance support, and follow the permanent lining joint support system to strengthen the support measures. The specific excavation construction measures are as follows: (1) Pre-grouting is used on the face and around the tunnel, L=30m, spacing 2m, overlap 3m; (2) The J arch is reinforced by a combination of Φ108 large pipe shed and small pipe shed. The spacing between large pipe sheds is 50 cm × 9 m (L = 12 m). The small pipe sheds are Φ42 steel pipes with a spacing of 50 cm × 2 m (L = 4.5 m). Grouting is performed using cement + water glass: (3) The excavation of the cavern is carried out by digging and lining at the same time and mechanical excavation.

[0021] According to the geological conditions, the excavation and support procedures mainly include: advance grouting, advance support, mechanical excavation, steel support, shotcrete support, reinforced concrete lining and other methods.

[0022] The overall construction procedure is as follows: advance grouting and advance support → mechanical excavation → steel support → shotcrete support → lining. The advance grouting construction process: close the tunnel face → measure and arrange holes → drill holes → grouting.

[0023] Embodiment 2: Based on the above embodiment, this embodiment further defines that in step (1), the process of pre-grouting the tunnel periphery and tunnel face is as follows: the length of each cycle of tunnel periphery + tunnel face grouting is 30m, of which 3m is reserved as a grouting rock plate in each cycle, and the grouting range is 3m outside the tunnel excavation contour line and in front of the tunnel face. The pre-grouting is arranged according to the slurry diffusion radius of 2 and the hole bottom spacing of 3m, with a total of 76 holes in each cycle. The opening diameter of the grouting hole is not less than 89mm, and the final hole diameter is not less than 75mm.

[0024] The specific steps include: (1.1) Sealing the tunnel face: hang a double-layer steel mesh and use 20cm thick shotcrete for sealing; the advance grouting around the tunnel and the tunnel face is mainly used for advance water blocking and pre-reinforcement of the surrounding rock to ensure construction safety; the length of each cycle of advance grouting around the tunnel and the tunnel face is 30m, of which each cycle is 27m, and 3m is reserved as a grouting rock plate. The grouting range is 3m outside the tunnel excavation outline and in front of the tunnel face; (1.2) Measure the hole layout; Figure 1 , Figure 2 As shown; (1.3) Drilling: First drill the grouting holes arranged on the top arch of the tunnel, then drill the holes on both sides of the tunnel, and finally drill the low arch holes; the grouting hole positioning is measured and laid out according to the coordinate values ​​of the design drawings, marked with spray paint, and the elevation and horizontal angles of the drill rod are adjusted. Move the drill rig and align the drill bit with the marked hole position. Place the prism at the tail end of the drill rod, and use a total station to check the posture of the drill rod and adjust it; According to the geology, a down-the-hole drill is selected to drill holes. The diameter of the grouting hole is 89mm, and the final hole diameter is 75mm. According to the prediction results of the detection hole, it is decided whether to use a hole pipe. For areas with predicted water pressure (P≥1.OMPa) and large water volume (Q≥20m3 / h), hole pipe grouting is used, otherwise grouting is stopped by grouting plugs; When backward segmented grouting is adopted, the hole can be directly drilled to the designed depth, and segmented grouting can be carried out from the bottom of the hole to the hole mouth; when forward segmented grouting is adopted, the method of drilling and grouting one section at a time is adopted until the designed hole depth; when full-hole one-time pressure-injection grouting is adopted, if mudstone interlayers, fault structures, or water gushing are encountered during the drilling process, drilling should be stopped immediately and forward grouting should be adopted until the end of the hole.

[0025] The drilling is carried out in the order of outer circle first and inner circle later. The inner circle drilling can refer to the order of outer circle drilling, and the subsequent holes can check the grouting effect of the previous holes. Gradually increasing the density of grouting can adjust the grouting parameters according to the drilling situation. On the other hand, if the drilling situation proves that the grouting effect has met the design requirements, the next circle of holes can be drilled to reduce the workload of drilling and speed up the construction progress. When drilling, strictly keep drilling records, including hole number, footage, start and end time, rock fissure development, water gushing location, water gushing amount and water gushing pressure. During the drilling process, if the water output of a single hole is less than 30L / mi, drilling can continue; if the water output of a single hole is greater than 30L / min, stop drilling immediately and carry out grouting.

[0026] (1.4) Borehole flushing: After each section of drilling is completed, the borehole is opened and a large flow of water is used to flush out the rock powder and other materials in the hole. The depth of the borehole after flushing is measured and recorded. The thickness of the bottom sediment after flushing should not exceed 20cm. In the special case of the dissolution area, a flower pipe is used for flushing. When flushing, the borehole is opened and the L=1.5m flower pipe is first sent to the bottom of the hole. The grouting pump is flushed at a large flow rate with its own maximum pressure. When flushing, the flower pipe is slowly rotated and lifted to the borehole mouth. The flushing time is not more than 1 hour until the return water is clean. Then remove the flower pipe, use a six-point steel braided pipe to go down to the bottom of the hole, and flush at a large flow rate until the return water is clean.

[0027] (1.5) Slurry preparation: The slurry materials must be weighed, and the weighing error should be less than 5%. Solid materials such as cement should be weighed by weight. The mixing time of pure cement slurry: when using an ordinary mixer, it should be no less than 3 minutes; when using a high-speed mixer, it should be no less than 30 seconds. The slurry should be sieved before use, and the time from preparation to use should be less than 4 hours.

[0028] Mix fine cement slurry and stabilized slurry, add water reducing agent and use high-speed mixer. The stirring speed of high-speed mixer is greater than 1200r / min (r is one rotation), and the stirring time is determined by experiment. The stirring time of fine cement slurry from preparation to use up shall not exceed 2h. Centralized slurry making station: The cement slurry is pure cement slurry with a water-cement ratio of 0.5:1, and the slurry delivery flow rate is 1.4~2.0m / s. Each grouting point is used according to the density of the incoming slurry and the different needs of each grouting point. The slurry temperature is maintained at 5~40℃. If it is lower than or higher than this standard, it will be regarded as waste slurry. After the slurry is made, the slurry volume is tested with a hydrometer to ensure the slurry water-cement ratio.

[0029] (1.6) Grouting: At least one of the following methods shall be adopted: staged forward grouting, staged backward grouting, and full-hole one-time pressure grouting. The specific grouting method shall be determined on site. Regardless of the grouting method adopted, the grouting effect shall be guaranteed.

[0030] The grouting water-cement ratio is 1:1~0.6:1 pure cement slurry. According to the on-site geological conditions, if there is a large amount of water gushing and high groundwater pressure in the tunnel section, cement slurry and water glass double slurry is used. The volume ratio of cement slurry and water glass double slurry is 1:0.5. The specific mix ratio of pure cement ash and double slurry is determined based on on-site tests.

[0031] The grouting pressure is 0.5MPa~1.0MPa. For the hole section with water gushing pressure greater than 0.5MPa, P=(1.52) times the measured external water pressure is adopted. The specific pressure is determined through on-site grouting test based on the surrounding rock geological conditions and external water pressure.

[0032] In order to prevent groundwater from surging to the construction surface during grouting, the face at the start of grouting should be sealed with 20cm thick C20 sprayed coarse fiber concrete and hung with a double-layer steel mesh (Φ6.0m@0.15m×0.15m).

[0033] First, drain the water outlet of the face, clean the bottom, and pour the concrete grouting wall. During the concrete construction process, embed the orifice pipe and the advance small guide tube for grouting to build the grouting rock plate. Finally, shut off the water of the drainage pipe.

[0034] (1.7) Grout changes: The water-cement ratio shall not be changed when the grouting pressure remains constant and the injection rate continues to decrease, or when the injection rate remains constant and the pressure continues to increase.

[0035] When the injection volume of a certain grade of slurry reaches more than 300L or the injection time reaches 30min, and the grouting pressure and injection rate do not change or change insignificantly, change to a higher concentration.

[0036] When the injection rate is greater than 30L / min or the slurry leaks, the concentration can be increased according to the situation.

[0037] Single hole termination standard: grouting can be terminated after the injection rate of the grouting section is no more than 1Lmin under the final hole pressure and grouting continues for 30min.

[0038] The end standard of the whole section: all grouting holes have met the single-hole end conditions and there is no leakage. The effective injection range of the slurry is not less than the design range. The permeability requirement of the grouting area after grouting is not more than 5L. After analysis and evaluation, the safety hazards of surrounding rock stability have been eliminated, the tunnel excavation construction safety is met, and landslides and other losses will not occur.

[0039] (1.8) Grouting and sealing. After the grouting is completed, remove the water and dirt in the borehole, use the "full hole grouting method" to seal the hole, and fill and smooth the remaining part of the hole with dry hard mortar.

[0040] (1.9) Handling of special situations (1.9.1) If mud burst occurs during the drilling process, stop drilling immediately, pull out the drill rod, install the orifice pipe and high-pressure valve, and carry out grouting.

[0041] (1.9.2) If there is grout leakage from small cracks on the face of the tunnel, first fill the cracks with hemp soaked in cement slurry, and adjust the slurry ratio to shorten the gel time; if there is still slurry leakage, use a common air drill to drill shallow holes at the leakage site for grouting consolidation. If there is slurry leakage or leakage from large cracks in front of the face of the tunnel, use a grout stopper to penetrate the crack and perform backward grouting.

[0042] (1.9.3) When the grouting pressure suddenly increases, only pure cement slurry or clean water should be injected. When the pump pressure returns to normal, double-liquid grouting can be carried out. If the pressure does not return to normal, stop grouting and check whether the pipeline is blocked.

[0043] (1.9.4) When the slurry input volume is large and the pressure does not increase for a long time, adjust the slurry concentration and mix ratio, shorten the gel time, and carry out small pump volume and low pressure grouting to allow the slurry to have a relative residence time in the rock formation cracks to facilitate gelation; intermittent grouting can also be carried out, but the stop time cannot exceed the slurry gel time.

[0044] Embodiment 3: Based on the above embodiment, this embodiment further defines that in step (2), the construction of the top arch advance large pipe shed is specifically as follows: The parameters of the advanced large pipe shed are: hot-rolled seamless steel pipe, 12m long, 3m overlap, 108mm outer diameter, 6mm wall thickness, 50cm spacing, and the external insertion angle is preferably 710°.

[0045] The pipe shed is 12m long, and the steel pipe is made of hot-rolled seamless steel pipe, with a diameter of 108mm and a wall thickness of not less than 6mm. The standard section length is 3m or 6m, and the front end is processed into a cone. The large pipe shed is made in a component processing plant, and the front end is made into a cone of about 20cm long, with a hole diameter of 10mm, a hole spacing of 15cm, and a plum blossom arrangement. The tail is not drilled for a length of 3m (as a stop grout section). Figure 3 shown.

[0046] The following steps are involved: (2.1.1) Build a pipe-roof studio; the top of the pipe-roof studio is 50cm outward, the studio length is 3m, the construction length of each cycle is 12m, and the overlap is 3m.

[0047] (2.1.2) Drilling of pipe shed holes; (2.1.2.1) Determine the hole position and mark it according to the design requirements. The allowable deviation of the hole is 40mm; (2.1.2.2) The axial direction of the drill rod should be strictly controlled during drilling to ensure the accuracy of the drilling direction of the pipe rack construction. The scaffolding should be erected reliably, the drilling rig should be firmly fixed, and inclinometers should be used during the drilling process.

[0048] (2.1.2.3) The drilling sequence is from high hole position to low hole position, and the holes are staggered. When drilling to a certain depth, an inclinometer is used to check whether the inclination of the hole is correct so that it can be corrected in time.

[0049] (2.1.2.4) The depth of the pipe support hole should meet the design requirements and should not exceed 200mm.

[0050] (2.1.2.5) The drilling sequence should be from high hole position to low hole position. The drilling diameter should be 20mm~30mm larger than the designed pipe rack diameter.

[0051] (2.1.2.6) After drilling is completed, the rock powder and accumulated water in the hole should be washed and blown clean, and the hole mouth should be protected.

[0052] (2.1.3) Install pipe shed; (2.1.3.1) Before installing the pipe rack, the pipe rack holes should be inspected and those that do not meet the requirements should be handled.

[0053] (2.1.3.2) Steel pipe joints are connected by threaded connections with a thread length of 15 cm. To prevent the steel pipes from being staggered, steel pipes with odd numbers of holes are connected by three sections, using standard lengths of 3 m, 6 m, and 3 m respectively; steel pipes with even numbers of holes are connected by two sections of 6 m standard length.

[0054] (2.1.3.3) The lap length of two longitudinal groups of pipe racks is generally 3m.

[0055] (2.1.3.4) The end of the steel pipe should be firmly welded to the arch guide pipe or steel arch frame.

[0056] (2.1.3.5) After the pipe shed is installed, it shall be sealed with quick-setting mortar. Before the mortar strength reaches the design requirements, the pipe shed shall not be knocked, collided or pulled.

[0057] (2.1.4) Carry out grouting of pipe roof.

[0058] (2.1.4.1) Pure cement slurry is generally used for grouting.

[0059] (2.1.4.2) Before grouting, a grouting test should be conducted and the grouting parameters should be adjusted according to the test results. During the initial grouting test, the water-cement ratio of cement slurry can be 1:0.5~1:1.

[0060] (2.1.4.3) Grouting can be carried out by forward grouting during the drilling process or by orifice tube grouting after the drilling is completed.

[0061] (2.1.4.4) The initial grouting pressure should be 0.5~1.0MPa, and the final pressure should be 2.0MPa. The specific pressure should be determined by on-site grouting test according to the surrounding rock geological conditions and external water pressure. When the grouting volume of each hole reaches the designed grouting volume or the grouting pressure reaches 2.0MPa, the grouting can be stopped after maintaining it for more than 10 minutes.

[0062] (2.1.4.5) After grouting, the slurry in the pipe should be removed promptly and filled tightly with M30 cement mortar to enhance the rigidity of the steel pipe.

[0063] Embodiment 4: Based on the above embodiment, this embodiment further defines that in step (2), the construction process of the top arch advance small duct is: The parameters of the advance small conduit are: hot-rolled seamless steel pipe, 4.5m long, 1.5m overlap, 42mm outer diameter, 3.5mm wall thickness. This section is used together with the large pipe rack, with an external insertion angle of 15~20° and a spacing of 50cm.

[0064] The advance small conduit is set along the outer side of the tunnel top arch contour line. The tunnel fault fracture zone is pre-supported by grouting with the advance small conduit, and the small conduit is made of Φ42 hot-rolled seamless steel pipe.

[0065] Use YT-28 pneumatic rock drill to drill holes, manually install small advance guide tubes and weld them to the steel frame. The external insertion angle of the small guide tube meets the design. Use a grouting pump to carry out grouting operations and inject single-liquid cement slurry. The grouting pressure is generally 0.5-1.0MPa. Reasonable grouting parameters are determined based on field tests during construction.

[0066] The small conduit is made in the component processing factory. The front end is made into a cone shape of about 10cm long. The tail is welded with a 8mm steel reinforcement hoop. The tail is not drilled for a length of 1m (as a grout stop section). The rest of the pipe wall is arranged with 6mm grout outlet holes in a plum blossom pattern at 15cm intervals. The structure of the advanced small conduit is as follows: Figure 4 shown.

[0067] After drilling, insert the small conduit into the hole according to the design requirements. In areas with weak surrounding rock, use a jackhammer or rock drill to directly drive the small conduit into the middle of the grid steel frame, and weld the tail to the steel frame to form a pre-support system. When the grouting volume of a single hole reaches the designed grouting volume, the grouting is terminated. The grouting parameters should be adjusted according to the grouting test results and on-site conditions. Fill in the grouting records carefully during the grouting operation, analyze and improve the operation at any time, and pay attention to the status of the construction support working surface.

[0068] The construction process of advanced small-duct grouting, such as Figure 5 shown.

[0069] Embodiment 5: Based on the above embodiment, this embodiment further defines that in step (3), the specific process of mechanical excavation is as follows: mechanical excavation is used for tunnel V-type surrounding rock, and the excavation cycle footage is 0.8-1.2m. The tunnel V-type surrounding rock conditions are poor. Due to the large cross-section, the V-type surrounding rock adopts the up and down step method. The special section adopts the step reserved core soil method for excavation. Mechanical excavation is used, and the excavation cycle footage is 0.5-0.7m. Before mechanical excavation, the surveying team will stake out the excavation contour line, use red paint to mark the points, and draw the excavation contour line to avoid over-excavation or under-excavation. The surveying team should also review the excavation in time to prevent over-excavation and under-excavation. After the excavation is completed, the loose stones on the excavation surface should be processed to avoid being hit by objects.

[0070] Embodiment 6: Based on the above embodiment, this embodiment further defines that in step (4), the IV and V type surrounding rocks are supported by anchor spraying and hanging nets, steel support combined support, and combined with auxiliary construction methods such as advanced large pipe shed and advanced grouting small pipe for advanced support. The specific process of initial support is: Use 25 hollow grouting anchor rods to reinforce the J top arch on the opposite side, L=4.5m@1.5m×1.5m.

[0071] (4.1) Drilling of anchor holes; The anchor holes are arranged according to the drilling positions in the construction drawings, and the hole position deviation is controlled to be no more than 100mm.

[0072] The anchor holes should be inspected before installation, and those that do not meet the requirements should be handled according to the supervisor's requirements.

[0073] (4.2) Anchor bolt installation and grouting (4.2.1) Preparation before installation Check whether the inner hole of the hollow anchor rod and the outlet hole of the plastic grouting anchor head are blocked by foreign objects. If there is any blockage, it should be cleaned up.

[0074] Screw the plastic grouting anchor head onto one end of the hollow anchor rod body until it can no longer be turned.

[0075] Check whether the diameter of the drill bit used meets the design requirements and select the appropriate drill bit type, using a cross drill bit.

[0076] (4.2.2) Drilling Use a rock drill or a down-the-hole drill to drill holes at the designated locations for installing anchor rods. Supply water and air before drilling.

[0077] (4.2.3) Hole washing After drilling is completed, pull the drill rod and drill bit out of the borehole, flush the borehole with compressed air, and blow out the accumulated water and rock powder in the hole.

[0078] (4.2.4) Insert anchor rod and plastic anchor head assembly Insert the anchor rod and plastic anchor head assembly into the drilled hole.

[0079] (4.2.5) Insert the air inlet (exhaust) pipe and process the orifice (or insert a stop plug) Anchor system with air inlet (exhaust) pipe: insert the air inlet (exhaust) pipe into the hole about 12~15mm, seal the hole with quick-drying cement slurry and smooth the end surface of the hole.

[0080] Anchor system with grout stop plug: Insert the grout stop plug and push it into the drilled hole to press against the end face of the hole.

[0081] (4.2.6) Install the gasket and nuts Insert the backing plate into the exposed end of the hollow anchor rod body, make sure that the air inlet (exhaust) pipe is aligned with the hole on the backing plate and passes through the hole, screw in the nut until the nut is in contact with the backing plate to prevent the hollow anchor rod body from being pulled out of the hole.

[0082] (4.2.7) Grouting Screw the grouting joint on the exposed end of the hollow anchor body; connect the grouting hose to the grouting joint; stir the slurry in the mixer according to the water-cement ratio (0.3~0.45):1 (0.35:1 is recommended), the grouting liquid is pure cement slurry, and cement mortar is strictly prohibited; pour the cement slurry mixed in the mixer into the hopper of the grouting machine; start the grouting with a grouting pressure of .8~1MPa and a pump flow rate of 0.3~0.6m3. The grouting process is continuous and non-stop and must be completed in one go. Stop the pump when the slurry overflows from the exhaust pipe or the end hole of the hollow anchor body.

[0083] (4.2.8) Nut loading After the slurry dries, the nut can be slightly tightened. The loading force is applied according to the test results.

[0084] (4.3) Install the steel mesh; the specifications and mesh size of the steel mesh are: medium 6 @ 0.15m × 0.15m. The steel mesh is processed and formed in the steel processing yard outside the tunnel. Before processing, the steel bars must be straightened, rusted and degreased to ensure the construction quality. The mesh must be placed flat or upright during stacking and transportation to ensure that the mesh does not deform. The steel mesh is hung after the system anchor rod is installed. When hanging, the mesh is laid according to the actual ups and downs of the initial concrete spraying surface to ensure that the steel mesh is closely attached to the supported rock surface. The joints of the steel mesh and the connection between the steel mesh and the anchor rod are tied or spot welded together with lead wire to prevent the steel mesh from shaking during concrete spraying.

[0085] (4.4) Carry out steel support construction; the steel support of the side J top arch adopts I18@0.5m, Φ6@0.15×0.15m, and the side J top arch is sprayed with 0.2m thick C20 concrete. The thickness of the C20 concrete cushion is 0.2m. This is carried out after the anchor rod hanging mesh construction.

[0086] The steel support is welded with the positioning reinforcement. Before the steel support is processed in the steel component factory outside the tunnel, the processing site is first hardened with C15 concrete, and the processing sample is released according to the design. The steel section is cold-formed by a cold bending machine according to the processing sample, and the sections are connected with bolts through 16mm steel plates. The processed steel support requires accurate size and smooth arc shape, and before being transported into the tunnel for installation, it must be tested and assembled correctly.

[0087] To ensure that the steel support is placed on a solid foundation, 0.15m~0.2m of original foundation is reserved at the foot of the steel support during construction; trenches are dug into place when the steel support is erected, and channel steels are installed at the foot of the steel support in soft areas to increase the bearing capacity of the base.

[0088] The steel support plane should be perpendicular to the tunnel centerline, with an inclination of no more than 2°, and any part of the steel support should not deviate from the plumb plane by more than 5 cm.

[0089] The steel support is installed according to the designed position. During the installation process, when there is a large gap between the steel support and the initial sprayed layer, riding pads should be installed. The contact distance between the steel support and the surrounding rock (or pads) should not be greater than 50mm.

[0090] To enhance the overall stability of the steel support, the steel support is welded to the anchor rod. Longitudinal connecting steel bars are arranged along the steel support and are arranged at a circumferential spacing of 1.2m.

[0091] In order to accurately position the steel support, the steel support must be pre-installed with a foot tie bar. One end of the tie bar is welded to the steel support, and the other end is anchored into the surrounding rock 0.5~1m and anchored with mortar. When there are anchor rods at the steel support installation location, try to use the anchor rods for positioning.

[0092] The steel support connection joints must be firmly connected. The arch foot is prone to plastic shear failure, so in addition to tensile testing, the joints in this area should also be welded on all four sides to ensure the rigidity and strength of the joints.

[0093] After the steel support is erected, spray concrete as soon as possible and cover the entire steel support so that the steel support and the spray concrete are under stress together. Spray concrete in layers with each layer being about 5cm to 6cm thick. Spray concrete upward from the arch foot or wall foot first to prevent the upper spray material from covering the arch foot (wall foot) loosely, resulting in insufficient strength and instability of the arch foot (wall foot).

[0094] (4.5) Shotcrete, the specific construction process is as follows Figure 6As shown. The shotcrete is mixed by an automatic metering mixing station outside the tunnel and is constructed by wet shotcrete. Wet shotcrete can reduce rebound, reduce dust, and improve work efficiency and construction quality.

[0095] After excavation, spray concrete 3cm~5cm thick to seal the surrounding rock to shorten the exposure time of the surrounding rock, control the deformation of the surrounding rock, and prevent the surrounding rock from loosening and peeling in a short period of time. After the installation of anchor rods, hanging nets, and steel frame supports, spray concrete to the designed thickness. The spray concrete is sprayed by a wet spraying machine, and the spray material is mixed at a concrete mixing station and transported to the spraying operation point by a concrete mixer truck.

[0096] Before jet support, pry off the loose soil and under-excavated parts on the surface, and use high-pressure air to remove debris; when there is a large amount of water on the excavation surface, take measures to centrally drain the water.

[0097] Before spraying, check and test-run the equipment; provide adequate lighting and ventilation equipment on the sprayed surface and in various mechanical equipment operation areas.

[0098] According to the designed thickness, existing parts such as the exposed length of anchor rods can be used, or short steel bars can be driven into the rock surface and marked with scales as marks.

[0099] Coarse aggregate should be screened again before adding to the mix to prevent oversized aggregate from mixing in and causing pipe blockage. Fine aggregate should be stored in a rainproof material storage to control the moisture content.

[0100] The maximum particle size of gravel in shotcrete should not be greater than 10mm, and continuous grading should be adopted for aggregate grading. Concrete mixing should preferably adopt the method of dry mixing cement and aggregate first and then wet mixing with water, and the dry mixing time shall not be less than 1.5min.

[0101] After the concrete spraying machine is debugged, install a vibrating screen (sieve hole 10mm) on the hopper to prevent oversized aggregate from entering the spraying machine.

[0102] When spraying, turn on the metering pump before supplying air, and adjust the air pressure after supplying air to control it between 0.45 and 0.70 MP. If the air pressure is too high, the coarse aggregate will rebound after hitting the surrounding rock; if the air pressure is low, the spraying kinetic energy is small, and the coarse aggregate cannot rush into the mortar layer and falls off, which will lead to an increase in the rebound amount. Control the spraying pressure to ensure that the concrete rebounds little, the surface is moist and shiny, and easy to adhere.

[0103] The spraying direction is perpendicular to the sprayed surface. During operation, the nozzle and the sprayed surface are automatically controlled by a computer, and the spraying is perpendicular to the rock surface and equidistant. If the sprayed surface is covered by a steel frame or a steel mesh, the nozzle can be slightly tilted, but not less than 70°.

[0104] The thickness of one spraying should not exceed 56cm. If it is too thick, it will weaken the cohesion between concrete particles, causing the sprayed layer to fall off due to its own weight, or forming a gap between the sprayed layer at the vault and the surrounding rock surface; if it is too thin, the coarse aggregate will rebound easily. Spray in batches to the designed thickness, and the time interval between two spraying layers is 15~20min. The main reasons affecting the thickness of the sprayed layer are the effect of the accelerator and the temperature.

[0105] To improve work efficiency and ensure quality, the spraying operation should be carried out in sections. To prevent rebound objects from adhering to the unsprayed rock surface and affecting the bonding force between the sprayed layer and the rock surface, the construction process of spraying from bottom to top and the spiral trajectory spraying should be followed; before spraying, the concave part of the sprayed surface should be leveled first, and then the nozzle should be moved slowly and evenly in a spiral shape to ensure that the concrete surface is smooth.

[0106] Not only the raw materials and mix ratio (including the amount of accelerator added) of shotcrete must meet the requirements, but also the setting time of the accelerator, its compatibility with cement, and its effect on strength must meet the requirements.

[0107] The on-site mix ratio of shotcrete should appropriately increase its strength grade to ensure the design strength of the shotcrete layer attached to the surrounding rock surface.

[0108] Shotcrete is carried out immediately after the excavation of the face. When the surrounding rock is broken and the stability is poor, the initial spraying (thickness of more than 4cm), anchor rods, steel mesh, steel frame, and re-spraying (second and third spraying) can be carried out continuously until the design requirements are met. After the grid steel frame is erected, it is quickly sealed with shotcrete to give full play to its support capacity. When the surrounding rock is relatively complete and has been stable for a long time, excavation operations can be carried out after the initial spraying, anchor rods, steel mesh, etc., and re-spraying can be carried out after the initial support time of the next cycle. The spraying layer of designed thickness can be completed in two or three times.

[0109] Embodiment 7: Based on the above embodiment, this embodiment is further limited to that in step (5), a simple trestle trolley is used for secondary lining, the effective working length of the simple trestle trolley is 12m, and the total length is 31m. The tunnel side arch lining is lined with a hydraulic steel mold trolley, the effective working length of the trolley is 12m, and the total length is 12.1m.

[0110] The excavation and lining method is adopted: the bottom plate is cast first and then the side arch is cast. The casting length of each chamber is 12. The tunnel excavation and bottom plate casting are carried out simultaneously to solve the problem of mechanical equipment passing through the excavation working face. This section adopts a simple trestle to cross the bottom plate casting working face to ensure the passage of mechanical equipment and realize the synchronization of tunnel excavation and lining. The side arch is lined with a hydraulic steel mold trolley.

[0111] The distance between the concrete pouring of the excavation and lining tunnel section and the excavation face shall be controlled according to the following requirements: The length of the tunnel section with poor geological conditions (V special category) shall not exceed 50m.

[0112] The lining concrete grade of the ordinary tunnel section of the main tunnel is: C30W8F100, and the concrete grade of the groundwater corrosion tunnel section is: C30W10F100 or C35W10F100.

[0113] The specific construction process is: (5.1) Bottom slab concrete construction; Specifically, it includes the construction processes of cleaning and washing the gravel surface, steel bar binding, concrete pouring, etc.

[0114] include: (5.1.1) Formwork construction The base plate is constructed using a self-propelled long trestle type sliding formwork trolley, and the head formwork uses a wooden formwork.

[0115] (5.1.2) Bottom cleaning The surface of the gravel is cleaned manually with high-pressure air and water, partially assisted by brushing with a wire brush and then mopping dry.

[0116] (5.1.3) Steel bar installation After being processed and shaped in the steel bar processing plant, the steel bars are transported to the construction site by 10t trucks. The slabs are manually tied, raised with concrete pads, and connected and fixed.

[0117] (5.1.4) Waterstop construction The construction of the waterstop strip is carried out simultaneously with the construction of the formwork and steel bars, and the waterstop strip is fixed using processed supports.

[0118] A. Rubber water stop construction method During construction, materials are cut manually according to the design requirements and transported to the construction site, where they are installed and fixed according to the design and specification requirements. The joints of rubber waterstop strips are vulcanized and welded to ensure that the joints are watertight. When pouring concrete, a special person is assigned to be on duty to ensure the accurate position of the rubber waterstop strips.

[0119] B. Construction method of copper water stop The processing plant makes copper sheet pressing molds according to the design requirements, and puts the copper sheets that meet the requirements into the molds for pressing. On-site manual installation is carried out according to the design and specification requirements, and the copper sheet water-stop connection is manually welded on-site. The surface of the water-stop copper sheet is flat, clean, without sand holes and nail holes, and the overlap length is not less than 20mm. Double-sided welding is adopted, and the installed water-stop sheet is reinforced and protected. A special person is assigned to be on duty during pouring to ensure the accurate position of the water-stop sheet.

[0120] (5.1.5) Concrete pouring Before pouring the bottom bedrock, a 2-3 cm thick mortar layer is evenly spread. The concrete is centrally mixed at a concrete mixing station, transported by a concrete truck, pumped into the mold, and compacted manually using a 100-type insert vibrator.

[0121] (5.1.6) Observation of formwork deformation during pouring During the concrete pouring process, formwork deformation observation is an important link. Before concrete pouring, special formwork inspection control points are arranged at appropriate locations. During the concrete pouring process, technicians with rich construction experience are assigned to inspect the entire process. If there are signs of formwork or arch deformation, the treatment measures are immediately determined according to the specific situation, and the concrete pouring speed is slowed down or the material is stopped, and the formwork is adjusted and reinforced according to the control points.

[0122] (5.1.7) Concrete curing Watering maintenance shall be carried out within 6 to 18 hours after the concrete pouring is completed, and the maintenance time shall comply with the requirements of the bidding documents and relevant specifications.

[0123] After the surface treatment of the crushed stone is inspected, care should be taken to keep the surface clean. Before pouring concrete, drain the water in the pit and mop it dry. Pour the concrete from one end to the other using the parallel push method, fix the concrete delivery pipe with a steel support, and vibrate and compact it with an inserted vibrator.

[0124] (5.2) Concrete lining of side and top arch.

[0125] (5.2.1) Steel bar binding construction In the steel bar binding section, first measure and lay out the lines, determine 9 points at the edge and top, and install 1m deep anchor rods. After reaching the required strength, weld the longitudinal steel bars according to the measured points to form the fixed circle of the steel bars, and then bind the circumferential steel bars and longitudinal steel bars in turn according to the designed spacing, and stagger the joints as required by the specifications until everything is completed.

[0126] The steel bar processing shed outside the tunnel is used to bend and process arc-shaped and straight wall steel bars of a certain length.

[0127] Use a steel bar trolley to weld steel bars in the hole according to design standards to ensure that the joints are <50% in the same section.

[0128] (5.2.2) Trolley in place Lay the trolley running rails, use 50kg / m standard rails, remove residual concrete on the trolley surface, apply release agent, adjust the rail surface elevation, then move the trolley into position, adjust the center line and elevation of the trolley until the clearance fully meets the design requirements.

[0129] Send professional technicians to inspect the trolley and strictly check whether the center line, elevation and clearance of the trolley meet the requirements of the design section. The dimensional accuracy indicators are: Trolley arch elevation: +10mm; The deviation between the center line of the trolley and the center line of the diversion tunnel is 10mm; Clearance size error: +20mm.

[0130] Lining trolley reinforcement, running rails are reinforced with I20 I-beam bracing, and the trolley is reinforced with fulcrum diagonal bracing and bracing. The arch form and side form are tightened against the rock surface with steel pipes or wooden bracing. Positioning is guided by STZ laser collimator.

[0131] According to the design drawings, use PVC pipes to pre-embed backfill grouting holes, consolidation grouting holes, drainage holes, etc.

[0132] Install the rigid head plate firmly according to the actual excavation section and install water stop strips, water stop belts, etc. according to the design.

[0133] (5.2.3) Concrete pouring The quality inspector will check and the engineer will re-check. After passing the inspection, the concrete opening notice will be issued. Select qualified raw materials and use the mixing station to mix the concrete. Use concrete mixer trucks for transportation.

[0134] Concrete pouring is pumped into the warehouse using a concrete delivery pump.

[0135] Concrete is poured in layers and symmetrically, and the thickness of each layer shall not exceed 30cm. The height difference on both sides shall be controlled within 50cm, and the vertical distance from the delivery pipe mouth to the pouring surface shall be controlled within 1.5m to prevent concrete segregation. The pouring process should be continuous to avoid pauses causing "cold joints". The intermittent time shall generally not exceed 45min, otherwise it will be treated as a construction joint.

[0136] When the concrete is poured to 50cm below the working window, scrape off the dirt near the window, apply the release agent, close the window, and apply putty to the joints between the window and the panel to ensure a close fit and prevent leakage.

[0137] The top is capped by connecting the top mold center capping device to the conveying pipe, and the top is capped gradually from the inside to the outside. When slurry overflows from the observation hole on the head plate, the capping is completed.

[0138] Demolding: When the on-site pressure test of the last capping concrete specimen reaches 5MPa, the mold can be removed. Be careful when removing the mold to avoid missing edges and corners.

[0139] Curing: Curing starts 10 to 20 hours after lining pouring, using covering and watering method, and the curing time is not less than 14 days.

[0140] Embodiment 8: Based on the above embodiment, this embodiment further defines that in step (6), the grouting after lining is divided into backfill grouting and consolidation grouting.

[0141] The backfill grouting range is 110° for the vault, the grouting hole diameter is φ50, the row spacing is 3m, the rock penetration is 0.1m, the backfill grouting uses cement slurry, the water-cement ratio is 0.6:1~1:1, and the grouting pressure is 0.3Mpa; The consolidation grouting arrangement is PG6, and the grouting material is silicate cement. Medium-resistance sulfate cement is used in the tunnel section where there is acid corrosion in the groundwater. The grouting hole diameter of PG6 consolidation grouting is φ56, the hole depth is 6m, the annular spacing is 2m, and the longitudinal spacing is 2.5m. Figure 7 shown.

[0142] The consolidation grouting will start 7 days after the lining concrete strength reaches the designed compressive strength and the backfill grouting within 20m is completed. The concentration of the consolidation grouting slurry can be gradually controlled from a water-cement ratio of 3:10.5:1, and the specific concentration should be determined through on-site production tests in combination with the surrounding rock conditions.

[0143] Use micro-expansive cement mortar of the same grade to seal the holes.

[0144] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.

Claims

1. A method for safe construction of a tunnel near a sensitive construction area, characterized in that: The following steps are involved: (1) Pre-grouting is adopted around the tunnel and the face. The length of each grouting cycle is 30m, of which 3m is reserved as a grouting rock plate in each cycle. The grouting range is 3m outside the tunnel excavation contour line and in front of the face. Pre-grouting is arranged according to the slurry diffusion radius of 2m and the hole bottom spacing of 3m. There are 76 holes in each cycle. The diameter of the grouting hole opening is not less than 89mm, and the final hole diameter is not less than 75mm; (2) Use the top arch advance large pipe shed and top arch advance small pipe for advance support; (3) Mechanical excavation; (4) For Class IV and V surrounding rock, anchor spraying and mesh hanging are used in combination with steel support for initial support; (5) Use a simple trestle trolley for secondary lining; (6) Grouting after lining.

2. A method for safe construction of a tunnel near a sensitive construction area according to claim 1, characterized in that: In step (1), the specific process of performing advance grouting on the tunnel periphery and the tunnel face includes the following steps: (1.1) Sealing the tunnel face: hang a double-layer steel mesh and use 20 cm thick shotcrete for sealing; (1.2) Measure the hole layout; (1.3) Drilling: First drill the grouting holes arranged on the top arch of the tunnel, then drill the holes on both sides of the tunnel, and finally drill the low arch holes; (1.4) Borehole flushing: After each section of drilling is completed, the borehole is opened and a large flow of water is used to flush out the rock powder and other materials in the hole. The depth of the borehole after flushing is measured and recorded. The thickness of the sediment at the bottom of the hole after flushing should not exceed 20 cm. (1.5) Pulping; (1.6) Grouting: At least one of the following methods: segmented forward grouting, segmented backward grouting, or full-hole one-time pressure grouting, whichever is more appropriate, should be selected based on the actual situation; (1.7) Slurry transformation; (1.8) Grouting and sealing.

3. A method for safe construction of a tunnel near a sensitive construction area according to claim 1 or 2, characterized in that: In step (2), the construction process of the top arch advance large pipe shed is as follows: (2.1.1) Build a pipe shed studio; (2.1.2) Drilling of pipe shed holes; (2.1.3) Install pipe shed; (2.1.4) Carry out grouting of pipe roof.

4. A method for safe construction of a tunnel near a sensitive construction area according to claim 1 or 2, characterized in that: In step (2), the construction process of the top arch advance small duct is as follows: (2.2.1) Seal the excavation surface with sprayed concrete; (2.2.2) Arrange holes along the perimeter of the excavation surface; (2.2.3) Process and manufacture a small grouting tube, and insert the processed small tube into the hole; (2.2.4) Prepare slurry and carry out grouting; (2.2.5) Carry out excavation work.

5. A method for safe construction of a tunnel near a sensitive construction area according to claim 1 or 2, characterized in that: In the step (3), the specific process of mechanical excavation is as follows: mechanical excavation is used for tunnel V-type surrounding rock, and the excavation cycle footage is 0.8-1.2m. The tunnel V-type surrounding rock conditions are poor. Due to the large cross-section, the V-type surrounding rock adopts the up and down step method. Special sections adopt the step reserved core soil method for excavation. Mechanical excavation is used, and the excavation cycle footage is 0.5-0.7m. Before mechanical excavation, the surveying team shall stake out the excavation contour line, use red paint to mark the points, and draw the excavation contour line to avoid over-excavation or under-excavation. The surveying team shall also review the excavation in time to prevent over-excavation or under-excavation. After excavation is completed, the loose rocks on the excavation surface should be processed to avoid being hit by objects.

6. A method for safe construction of a tunnel near a sensitive construction area according to claim 1 or 2, characterized in that: In step (4), the specific process of performing the initial support is as follows: (4.1) Drilling of anchor holes; (4.2) Installation of anchor bolts and grouting; (4.3) Install steel mesh; (4.4) Carry out steel support construction; (4.5) Shotcrete.

7. A method for safe construction of a tunnel near a sensitive construction area according to claim 6, characterized in that: In the step (4.2), the specific process of installing the anchor rod and grouting is as follows: (4.2.1) Preparation work before installing anchor bolts; (4.2.2) Drilling; (4.2.3) Washing holes; (4.2.4) Insert the anchor rod and plastic anchor head assembly; (4.2.5) Insert the trachea and perform orifice processing; (4.2.6) Install the gasket and nuts; (4.2.7) Grouting; (4.2.8) Nut loading.

8. A method for safe tunnel construction near sensitive construction areas according to claim 1 or 2, characterized in that: In step (5), the specific process of using the simple trestle trolley for secondary lining is as follows: (5.1) Bottom slab concrete construction; (5.2) Concrete lining of side and top arch.

9. A method for safe construction of a tunnel near a sensitive construction area according to claim 1 or 2, characterized in that: In the step (6), the grouting after lining is divided into backfill grouting and consolidation grouting.

10. A method for safe construction of a tunnel near a sensitive construction area according to claim 9, characterized in that: The backfill grouting range is 110° for the vault, the grouting hole diameter is φ50, the row spacing is 3m, the rock penetration is 0.1m, the backfill grouting uses cement slurry, the water-cement ratio is 0.6:1~1:1, and the grouting pressure is 0.3Mpa; The consolidation grouting arrangement is PG6, and the grouting material is silicate cement. Medium-resistant sulfate cement is used in the tunnel section where groundwater has acid corrosion. The grouting hole diameter of PG6 consolidation grouting is φ56, the hole depth is 6m, the circumferential spacing is 2m, and the longitudinal spacing is 2.5m.