Deck cabin penetrating piece sealing structure and construction method thereof

By designing the deck through-cabin sealing structure, using the combination of semi-ring plates and sealing profiles, combined with grouting technology, the airtightness and paint protection problems during deck sealing are solved, and efficient sealing and load transfer are achieved, reducing the Cost and risk.

CN118935103APending Publication Date: 2024-11-12CHINA ENERGY ENG GRP GUANGDONG ELECTRIC POWER DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411219385.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, when the deck is bolted or welded, there is a problem of insufficient airtightness and deck paint being damaged, resulting in corrosion risks and potential use risks.

Method used

Design a deck through-cabin seal structure, including half-ring plate, sealing profile and connecting ring. By welding and assembling half-ring plate, sealing profile and connecting ring onshore, the sealing space is installed and grouted at sea to form a sealing layer , avoid offshore welding operations and transfer horizontal loads.

Benefits of technology

It realizes airtight sealing, saves offshore welding work, protects deck paint, reduces corrosion risks, and improves the horizontal load constraint capability of the cabin pipe, which is low in cost and high reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118935103A_ABST
    Figure CN118935103A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of ocean engineering structures, and discloses a deck cabin-penetrating piece sealing structure and a construction method thereof.The deck cabin-penetrating piece sealing structure comprises a deck and a cabin-penetrating pipeline, the deck is provided with a cabin-penetrating opening, and the cabin-penetrating pipeline penetrates through the cabin-penetrating opening; the device further comprises two semi-ring plates, the two semi-ring plates are arranged on the outer side of the cabin penetrating pipeline in a sleeving mode, and the two semi-ring plates cover the cabin penetrating opening. The structure further comprises a plugging profile, the plugging profile is arranged on the side, away from the cabin penetrating pipeline, of the semi-ring plate, the plugging profile is of a circumferential closed structure arranged around the center of the cabin penetrating pipeline, a plugging space is defined by the plugging profile and the cabin penetrating pipeline, and the plugging space is filled with a grouting layer. The plugging space is filled with the grouting layer, the cabin penetrating opening is sealed, the airtight effect is achieved, meanwhile, offshore welding operation is avoided, and no damage is caused to existing anti-corrosion measures; the grouting layer is connected with the cabin penetrating pipeline and the blocking profile, the horizontal load of the cabin penetrating pipeline can be transmitted to the deck through the grouting layer, the good restraining effect on the cabin penetrating pipeline is achieved, reliability is high, and cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of marine engineering structures, and in particular to a deck penetration sealing structure and a construction method thereof. Background Art

[0002] There are a large number of cable J-tubes and pump pipes in offshore substations. These pipes need to be installed after the upper modules are installed, so there are a large number of openings on the first deck of the substation. After installing the J-tubes and pump pipes at sea, the openings need to be sealed to prevent people or objects from falling into the sea.

[0003] There are currently two main methods for sealing the openings on the first deck. One is to seal them by bolting two prefabricated half-ring plates. This solution is mainly used in environments where there are no airtight requirements and cannot provide horizontal support for pipelines. It is suitable for situations with low process requirements. The other is to seal them by welding two prefabricated half-ring plates. This solution is mainly used for indoor penetrations.

[0004] Among the above-mentioned blocking methods, Solution 1 cannot be used in indoor spaces with airtightness requirements because there is a gap between the ring plate and the deck after the bolt connection; Solution 2 requires welding operations at sea, and the paint on the bottom of the deck will inevitably be damaged after welding. However, the area under the deck is an inaccessible area, so the paint on the bottom of the deck cannot be repaired after welding, which poses a huge risk of corrosion and poses a hidden danger for later use. Summary of the invention

[0005] The purpose of the present invention is to provide a deck penetration sealing structure to solve the problems in the prior art that when the deck is connected by semi-ring plate bolts or welded, the bolt connection has no airtightness and welding will damage the deck paint; the present invention also provides a construction method for the deck penetration sealing structure.

[0006] In order to achieve the above-mentioned object, the present invention provides a deck penetration member sealing structure, comprising a deck and a penetration pipe, wherein the deck has a penetration opening, and the penetration pipe passes through the penetration opening;

[0007] It also includes a semi-ring plate, wherein there are two semi-ring plates, the two semi-ring plates are sleeved on the outside of the cabin penetration pipe, the two semi-ring plates are connected to form a complete circular ring structure, and the two semi-ring plates cover the cabin penetration opening;

[0008] It also includes a blocking profile, which is arranged on a side of the semi-ring plate away from the through-cabin pipe, and the blocking profile is a circumferentially closed structure arranged around the center of the through-cabin pipe, and a blocking space is enclosed between the blocking profile and the through-cabin pipe, and the blocking space is filled with a grouting layer.

[0009] Preferably, the blocking profile is fixed to the deck by welding.

[0010] Preferably, the blocking profile comprises a vertical plate and a baffle, the vertical plate is vertically welded to the deck, and the baffle is provided at one end of the vertical plate away from the deck and arranged toward the through-cabin pipe.

[0011] Preferably, each of the semi-ring plates is provided with a connecting plate, and the connecting plates on two semi-ring plates are connected by bolts.

[0012] Preferably, each of the semi-annular plates is further provided with a reinforcing rib plate, and a plurality of the reinforcing rib plates are arranged at intervals along the circumference of the semi-annular plate, and one end of the reinforcing rib plate abuts against the cabin penetration pipe.

[0013] Preferably, the angle between two adjacent reinforcing rib plates on a single semi-annular plate is in the range of 75-85 degrees.

[0014] Preferably, it also includes connecting rings, and a plurality of the connecting rings are evenly distributed on the deck and the through-tank pipe at circumferential intervals along the through-tank pipe, and the connecting rings on the deck and the through-tank pipe correspond one to one, and tensioning ropes are detachably connected between the connecting rings on the deck and the connecting rings on the through-tank pipe.

[0015] Preferably, the tensioning cable is a turnbuckle.

[0016] The present invention also provides a construction method for a deck penetration component sealing structure, which is used for the deck penetration component sealing structure described in any of the above technical solutions, and comprises the following steps:

[0017] S1, onshore production stage, determine the position and size of the hatch opening on the deck, the position of the blocking profile, and the position of the connecting ring according to the size of the through-deck pipe;

[0018] S2, welding connecting rings on the deck and through-hatch pipes, opening through-hatch holes on the deck, and welding blocking profiles on the deck;

[0019] S3, manufacturing two semi-ring plates, wherein the inner diameter of the semi-ring plates is the same as the outer diameter of the through-hatch pipe, and the outer diameter of the semi-ring plates is larger than the inner diameter of the through-hatch opening;

[0020] S4, offshore installation stage, the through-tank pipe passes through the through-hatch on the deck and the half-ring plate is installed;

[0021] S5, assemble a tensioning cable between the deck and the connecting ring on the through-tank pipe, and apply force to the tensioning cable to tighten the through-tank pipe;

[0022] S6, grouting is performed on the sealed space, and a grouting layer is formed after the grouting dries.

[0023] Preferably, in step S3, when manufacturing the semi-annular plate, the connecting plate and the reinforcing rib plate are simultaneously welded on the semi-annular plate.

[0024] Compared with the prior art, a deck penetration sealing structure and a construction method thereof according to an embodiment of the present invention have the following beneficial effects: a semi-ring plate is arranged to cover the penetration hatch of the deck, and a sealing profile with a circumferentially closed structure is arranged on the deck around the center of the penetration pipe, so that a sealing space is enclosed between the sealing profile and the penetration pipe to be filled with a grouting layer. The grouting layer is filled in the sealing space to seal the penetration hatch to achieve an airtight effect, while avoiding offshore welding operations, saving work such as offshore cable splicing, saving time and welding materials, and also avoiding damage to the deck paint, without any damage to existing anti-corrosion measures; in addition, the grouting layer connects the penetration pipe and the sealing profile, and the horizontal load of the penetration pipe can be transmitted to the deck via the grouting layer, which has a good restraining effect on the penetration pipe, has high reliability and low cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 2 is a schematic structural diagram of a deck penetration sealing structure of the present invention;

[0026] Figure 2 yes Figure 1 A cross-sectional view of the sealing structure of the deck penetration component;

[0027] Figure 3 yes Figure 1 A schematic diagram of the assembly structure of the deck, the connecting ring and the blocking profile of the deck penetration sealing structure;

[0028] Figure 4 yes Figure 1 A schematic diagram of the assembly structure of the penetration pipe and the connecting ring of the deck penetration sealing structure;

[0029] Figure 5 yes Figure 1 Schematic diagram of the assembly structure of the semi-ring plate, connecting plate and stiffener plate of the deck penetration sealing structure.

[0030] In the figure, 1, deck, 11, hatch opening, 2, hatch pipe, 3, semi-ring plate, 4, blocking profile, 41, vertical plate, 42, baffle, 5, connecting plate, 6, reinforcing rib plate, 7, connecting ring, 8, tensioning cable, 9, grouting layer. DETAILED DESCRIPTION

[0031] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0032] A preferred embodiment of a deck penetration sealing structure of the present invention is as follows: Figures 1 to 5As shown, the deck penetration component sealing structure includes a deck 1, a penetration pipe 2, a semi-ring plate 3 and a blocking profile 4. The deck 1 is the first-layer structural plate of the offshore substation. The deck 1 has a hatch 11. The hatch 11 is a circular structure for installing the penetration component. The penetration pipe 2 forms the penetration component in this embodiment.

[0033] There are two semi-ring plates 3, which are sleeved on the outside of the through-cabin pipe 2. The two semi-ring plates 3 are connected to form a complete circular ring structure, that is, the two semi-ring plates 3 are connected to form a full circle. The two semi-ring plates 3 cover the through-cabin opening 11, and the through-cabin opening 11 can be initially covered and sealed. In this embodiment, the inner diameter of the semi-ring plate 3 is the same as the outer diameter of the through-cabin pipe 2, and the outer diameter is larger than the inner diameter of the through-cabin opening 11, so as to ensure that the two semi-ring plates 3 can completely cover the entire through-cabin opening 11 after being connected and sleeved on the through-cabin pipe 2. And after the two semi-ring plates 3 are connected, a gap of 5 mm is retained, which can compensate for the position deviation of the through-cabin pipe 2 during assembly, and ensure that the semi-ring plate 3 can be sleeved on the outside of the through-cabin pipe 2.

[0034] The blocking profile 4 is fixedly arranged on the deck 1, and is arranged on the side of the semi-annular plate 3 away from the through-tank pipe 2, that is, the blocking profile 4 is located on the outside of the semi-annular plate 3. The blocking profile 4 is a circumferentially closed structure arranged around the center of the through-tank pipe 2, that is, the blocking profile 4 surrounds the through-tank pipe 2 360 degrees on the deck 1. In this embodiment, the blocking profile 4 is an octagonal structure as a whole, surrounding the through-tank pipe 2 at the center. In other embodiments, the blocking profile 4 can also be circular or other shapes.

[0035] A blocking space is formed between the blocking profile 4 and the through-cabin pipe 2, and the blocking space is filled with a grouting layer 9. After the grouting layer 9 fills the blocking space, it can completely cover the gaps between the through-cabin pipe 2, the semi-ring plate 3, and the deck 1 inside the blocking profile 4, thereby sealing the through-cabin opening 11, and having an airtight effect while blocking the through-cabin opening 11. In this embodiment, the grouting layer 9 is made of cement, which has high strength after solidification, and connects the through-cabin pipe 2 and the deck 1 as a whole. Any horizontal load of the through-cabin pipe 2 can be transmitted to the deck 1 through the cement, which plays a good restraining role.

[0036] The deck penetration sealing structure is provided with a semi-annular plate 3 covering the hatch opening 11 of the deck 1, and a sealing profile 4 with a circumferentially closed structure is provided on the deck 1 around the center of the penetration pipe 2, so that a sealing space is enclosed between the sealing profile 4 and the penetration pipe 2 to be filled with a grouting layer 9, and the grouting layer 9 is filled in the sealing space to seal the hatch opening 11 to achieve an airtight effect, while avoiding offshore welding operations, saving work such as offshore cable splicing, saving time and welding materials, and also avoiding damage to the paint of the deck 1, without any damage to existing anti-corrosion measures; in addition, the grouting layer 9 connects the penetration pipe 2 and the sealing profile 4, and the horizontal load of the penetration pipe 2 can be transmitted to the deck 1 via the grouting layer 9, which has a good restraining effect on the penetration pipe 2, high reliability and low cost.

[0037] Preferably, the blocking profile 4 is fixed to the deck 1 by welding.

[0038] After welding, there is no gap between the blocking profile 4 and the deck 1, which can prevent the grouting layer 9 from leaking during grouting and increase the structural strength between the blocking profile 4 and the deck 1. In other embodiments, the blocking profile 4 can also be assembled and connected to the deck 1 by bolts or other means.

[0039] Preferably, the blocking profile 4 includes a vertical plate 41 and a baffle 42 . The vertical plate 41 is vertically welded to the deck 1 . The baffle 42 is disposed at one end of the vertical plate 41 away from the deck 1 and arranged toward the through-cabin pipe 2 .

[0040] The plugging profile 4 is formed by a vertical plate 41 and a baffle 42. The vertical plate 41 and the through-tank pipe 2 enclose a plugging space. The baffle 42 is located on the top of the vertical plate 41 and faces the through-tank pipe 2. The baffle 42 can prevent the slurry from overflowing during grouting. In this embodiment, the vertical plate 41 and the baffle 42 are integrally formed, and the vertical plate 41 and the baffle 42 are angle steels. The plugging profile 4 can be made of shipyard scraps, which is low in cost.

[0041] Preferably, each semi-ring plate 3 is provided with a connecting plate 5 , and the connecting plates 5 on two semi-ring plates 3 are connected by bolts.

[0042] The semi-ring plate 3 is connected by a connecting plate 5 and bolts, and the connecting plate 5 has a positioning function for the semi-ring plate 3, which facilitates the positioning and assembly of the semi-ring plate 3. In this embodiment, the connecting plate 5 is specifically an angle steel.

[0043] Preferably, each semi-annular plate 3 is further provided with a reinforcing rib plate 6 , and a plurality of reinforcing rib plates 6 are arranged at intervals along the circumference of the semi-annular plate 3 , and one end of the reinforcing rib plate 6 abuts against the cabin-penetrating pipe 2 .

[0044] A reinforcing rib plate 6 is arranged on the semi-annular plate 3, and one end of the reinforcing rib plate 6 is in contact with the through-cabin pipe 2. The reinforcing rib plate 6 can increase the structural strength of the semi-annular plate 3 to ensure that the semi-annular plate 3 will not be concave before the slurry solidifies. At the same time, after the slurry solidifies, the reinforcing rib plate 6 is connected to the grouting layer 9 as a whole, and any horizontal load of the through-cabin pipe 2 is transmitted to the grouting layer 9 through the reinforcing rib plate 6, and then transmitted to the deck 1.

[0045] Preferably, the angle between two adjacent reinforcing rib plates 6 on a single semi-ring plate 3 is in the range of 75-85 degrees.

[0046] The angle between adjacent reinforcing ribs 6 on the semi-ring plate 3 is 75-85 degrees, and two to three reinforcing ribs 6 can be made on each semi-ring plate 3, so that each semi-ring plate 3 is subjected to balanced force. In this embodiment, the angle between two adjacent reinforcing ribs 6 on a single semi-ring plate 3 is 80 degrees, and three reinforcing ribs 6 are made on a single semi-ring plate 3, and the angle between the two reinforcing ribs 6 at the edges of the two semi-ring plates 3 is small, which has a significant reinforcing effect on the semi-ring plate 3.

[0047] Preferably, it also includes a connecting ring 7. A plurality of connecting rings 7 are evenly distributed on the deck 1 and the through-tank pipe 2 at circumferential intervals along the through-tank pipe 2. The connecting rings 7 on the deck 1 and the through-tank pipe 2 correspond one to one. A tensioning rope 8 is detachably connected between the connecting rings 7 on the deck 1 and the connecting rings 7 on the through-tank pipe 2.

[0048] Connecting rings 7 are provided on the deck 1 and the through-cabin pipe 2, and tensioning cables 8 are detachably connected between the connecting rings 7. After the through-cabin pipe 2 is assembled, the tensioning cables 8 have a good horizontal restraining effect on the through-cabin pipe 2 after being tightened. Some through-cabin pipes 2 of marine engineering may be equipped with equipment such as water pumps. Under the restraining effect of the tensioning cables 8, the equipment can be used before the grouting layer 9 is completely solidified, without waiting for the grouting layer 9 to be completely solidified. In this embodiment, three connecting rings 7 are respectively installed on the through-cabin pipe 2 and the deck 1, and the connecting rings 7 are located in the blocking space. After grouting, the connecting rings 7 and the tensioning cables 8 are covered by the grouting layer 9; the circumferential angle between two adjacent connecting rings 7 is about 120 degrees, so that the restraining force of the tensioning cables 8 on the through-cabin pipe 2 is balanced.

[0049] Preferably, the tensioning cable 8 is a turnbuckle.

[0050] As a standard structural part, the turnbuckle is widely used on ships and is easy to operate. In other embodiments, if the horizontal load of the equipment is small, the tensioning rope 8 can also be a steel wire rope.

[0051] The present invention also provides a preferred embodiment of a construction method of a deck penetration component sealing structure, which is used for the deck penetration component sealing structure of any of the above embodiments, comprising the following steps:

[0052] S1, onshore production stage, determining the position and size of the hatch opening 11 on the deck 1, the position of the blocking profile 4, and the position of the connecting ring 7 according to the size of the through-trap pipe 2;

[0053] S2, welding connecting rings 7 on the deck 1 and the through-hatch pipe 2, opening a through-hatch opening 11 on the deck 1, and welding a blocking profile 4 on the deck 1;

[0054] S3, manufacturing two semi-annular plates 3, wherein the inner diameter of the semi-annular plates 3 is the same as the outer diameter of the through-hatch pipe 2, and the outer diameter of the semi-annular plates 3 is larger than the inner diameter of the through-hatch opening 11;

[0055] S4, offshore installation stage, the through-tank pipe 2 passes through the through-hatching 11 on the deck 1 and the semi-ring plate 3 is installed;

[0056] S5, assembling a tensioning cable 8 between the deck 1 and the connecting ring 7 on the through-tank pipe 2, and applying a force to the tensioning cable 8 to tighten the through-tank pipe 2;

[0057] S6, grouting is performed on the sealed space, and a grouting layer 9 is formed after the grouting dries.

[0058] In steps S1, S2, and S3, the manufacture or installation of the connecting ring 7, the semi-ring plate 3, the hatch 11, and the blocking profile 4 are all carried out in the onshore manufacturing stage. The operations in this process can be completed in the workshop. After the welding operation, the anti-corrosion structure of the deck 1 can be repaired, which is convenient to use.

[0059] In step S3, after the connecting ring 7 is assembled, a suitable tensioning rope 8 is selected according to the equipment on the through-cabin pipe 2 and the horizontal load it may be subjected to.

[0060] In step S4 , when assembling the half-ring plates 3 , a gap of about 5 mm is reserved between the two half-ring plates 3 .

[0061] The construction method of the deck penetration sealing structure is that the grouting layer 9 is filled in the sealing space to seal the penetration hatch 11 to achieve an airtight effect, while avoiding offshore welding operations, saving work such as offshore cable splicing, saving time and welding materials, and also avoiding damage to the paint of the deck 1, without any damage to existing anti-corrosion measures; in addition, the grouting layer 9 connects the penetration pipe 2 and the sealing profile 4, and the horizontal load of the penetration pipe 2 can be transmitted to the deck 1 via the grouting layer 9, which has a good restraining effect on the penetration pipe 2, with high reliability and low cost.

[0062] Preferably, in step S3 , when manufacturing the semi-annular plate 3 , the connecting plate 5 and the reinforcing rib plate 6 are simultaneously welded on the semi-annular plate 3 .

[0063] The connecting plate 5 and the reinforcing rib plate 6 are simultaneously welded to the semi-ring plate 3 when the semi-ring plate 3 is manufactured to form an integral structure, which makes it more convenient to assemble the semi-ring plate 3; after the connecting plate 5 is connected by bolts, it has the function of temporarily fixing the semi-ring plate 3 before grouting, and the reinforcing rib plate 6 and the grouting layer 9 play the purpose of transferring the load after solidification.

[0064] In summary, an embodiment of the present invention provides a deck penetration sealing structure and a construction method thereof, wherein a semi-ring plate is arranged to cover the penetration opening of the deck, and a sealing profile with a circumferentially closed structure is arranged on the deck around the center of the penetration pipe, so that a sealing space is enclosed between the sealing profile and the penetration pipe to be filled with a grouting layer. The grouting layer is filled in the sealing space to seal the penetration opening to achieve an airtight effect, while avoiding offshore welding operations, saving work such as offshore cable splicing, saving time and welding materials, and avoiding damage to the deck paint, without any damage to existing anti-corrosion measures; in addition, the grouting layer connects the penetration pipe and the sealing profile, and the horizontal load of the penetration pipe can be transmitted to the deck via the grouting layer, which has a good restraining effect on the penetration pipe, with high reliability and low cost.

[0065] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.

Claims

1. A deck penetration sealing structure, characterized in that: It comprises a deck (1) and a through-hatch pipe (2), wherein the deck (1) has a through-hatch opening (11), and the through-hatch pipe (2) passes through the through-hatch opening (11); It also includes a semi-ring plate (3), wherein there are two semi-ring plates (3), the two semi-ring plates (3) are sleeved on the outer side of the cabin penetration pipe (2), the two semi-ring plates (3) are connected to form a complete circular ring structure, and the two semi-ring plates (3) cover the cabin penetration opening (11); The invention also comprises a plugging profile (4), wherein the plugging profile (4) is arranged on a side of the semi-annular plate (3) away from the through-cabin pipe (2), and the plugging profile (4) is a circumferentially closed structure arranged around the center of the through-cabin pipe (2), and a plugging space is enclosed between the plugging profile (4) and the through-cabin pipe (2), and the plugging space is filled with a grouting layer (9).

2. The deck penetration sealing structure according to claim 1, characterized in that: The blocking profile (4) is fixed to the deck (1) by welding.

3. The deck penetration sealing structure according to claim 2, characterized in that: The blocking profile (4) comprises a vertical plate (41) and a baffle (42); the vertical plate (41) is vertically welded to the deck (1); and the baffle (42) is arranged at one end of the vertical plate (41) away from the deck (1) and is arranged toward the through-cabin pipe (2).

4. The deck penetration sealing structure according to any one of claims 1 to 3, characterized in that: Each of the semi-ring plates (3) is provided with a connecting plate (5), and the connecting plates (5) on the two semi-ring plates (3) are connected by bolts.

5. The deck penetration sealing structure according to any one of claims 1 to 3, characterized in that: Each of the semi-annular plates (3) is also provided with a reinforcing rib plate (6), and a plurality of the reinforcing rib plates (6) are arranged at intervals along the circumference of the semi-annular plate (3), and one end of the reinforcing rib plate (6) is in contact with the cabin penetration pipe (2).

6. The deck penetration sealing structure according to claim 5, characterized in that: The angle between two adjacent reinforcing rib plates (6) on a single semi-ring plate (3) is in the range of 75-85 degrees.

7. The deck penetration sealing structure according to any one of claims 1 to 3, characterized in that: It also includes a connecting ring (7). A plurality of the connecting rings (7) are evenly distributed on the deck (1) and the through-tank pipe (2) at intervals along the circumference of the through-tank pipe (2). The connecting rings (7) on the deck (1) and the through-tank pipe (2) correspond one to one. A tensioning rope (8) is detachably connected between the connecting ring (7) on the deck (1) and the connecting ring (7) on the through-tank pipe (2).

8. The deck penetration sealing structure according to claim 7, characterized in that: The tensioning rope (8) is a turnbuckle.

9. A construction method for a deck penetration sealing structure, used for the deck penetration sealing structure according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1, onshore production stage, determining the position and size of the hatch opening (11) on the deck (1), the position of the blocking profile (4), and the position of the connecting ring (7) according to the size of the hatch-penetrating pipe (2); S2, welding connecting rings (7) on the deck (1) and the through-hatch pipe (2), opening a through-hatch opening (11) on the deck (1), and welding a blocking profile (4) on the deck (1); S3, manufacturing two semi-annular plates (3), wherein the inner diameter of the semi-annular plates (3) is the same as the outer diameter of the through-hatch pipe (2), and the outer diameter of the semi-annular plates (3) is larger than the inner diameter of the through-hatch opening (11); S4, offshore installation stage, the through-tank pipe (2) passes through the through-hatching (11) on the deck (1) and the half-ring plate (3) is installed; S5, assembling a tensioning cable (8) between the deck (1) and the connecting ring (7) on the through-tank pipe (2), and applying a force to the tensioning cable (8) to tighten the through-tank pipe (2); S6, grouting is performed on the sealed space, and a grouting layer (9) is formed after the grouting dries.

10. The construction method of the deck penetration sealing structure according to claim 9, characterized in that: In step S3, when manufacturing the semi-ring plate (3), the connecting plate (5) and the reinforcing rib plate (6) are simultaneously welded on the semi-ring plate (3).