Bridge BIM (Building Information Modeling) information survey and model construction method and system based on video survey

The acquisition of bridge data through video measurement and generation of a full life cycle model is solved, and the problem of insufficient efficiency and accuracy of traditional surveying technologies is achieved, efficient and comprehensive data acquisition of bridge surveys is achieved, and a reliable foundation for bridge management is provided.

CN118940374AInactive Publication Date: 2024-11-12YANCHENG INST OF TECH
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410985865.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing bridge surveying technology is too traditional and relies on manual labor. The measurement project is not comprehensive enough, and the progress period is long, which affects efficiency and quality.

Method used

Using the BIM information survey and model construction method of bridges based on video measurement, the original construction data of the bridge and the survey video data are obtained, and the full life cycle model is generated using BIM modeling software, including the acquisition of data by air and underwater camera components, and the time is carried out. Sequence analysis and object detection to generate accurate bridge full life cycle models.

Benefits of technology

It improves the accuracy and efficiency of bridge surveys, provides a reliable data basis for the maintenance and management of bridges, reduces manual intervention and shortens the measurement cycle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118940374A_ABST
    Figure CN118940374A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge survey, and provides a bridge BIM information survey and model construction method and system based on video metrology, and the method comprises the steps: obtaining the original construction data of a bridge based on a bridge BIM information platform; acquiring survey video data of the bridge, and generating survey period data according to the survey video data; and according to the original construction data and the survey period data of the bridge, performing modeling by using BIM modeling software to generate a bridge full-life-cycle model. According to the invention, modeling is carried out by using the BIM modeling software according to the surveying period data generated according to the original construction data of the bridge and the surveying video data of the bridge, and the bridge full-life-cycle model is generated, so that the accuracy of the bridge full-life-cycle model can be ensured, and a condition and a basis are provided for subsequent maintenance and management of a bridge building.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge surveying, and in particular to a method and system for bridge BIM information surveying and model building based on video metrology. Background Art

[0002] Bridge engineering refers to the process of bridge survey, design, construction, maintenance and verification. Bridge survey mainly involves the investigation, exploration and measurement of bridges, providing comprehensive data basis for bridge maintenance and management.

[0003] When surveying a bridge, it is necessary to obtain the construction data of the bridge in order to discover damaged structures of the bridge and provide targets for maintenance. The existing technical means of bridge survey are relatively traditional and rely too much on manual work. The measured items are not comprehensive enough and the measurement progress cycle is relatively long, which affects the efficiency and quality of bridge survey.

[0004] Therefore, it is necessary to provide a bridge BIM information survey and model building method and system based on video measurement. Summary of the invention

[0005] The present invention provides a method and system for bridge BIM information survey and model building based on video surveying. By modeling according to the original construction data of the bridge and the survey cycle data generated by the survey video data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge, thereby ensuring the accuracy of the full life cycle model of the bridge and providing conditions and basis for the subsequent maintenance and management of the bridge building.

[0006] The present invention provides a bridge BIM information survey and model building method based on video measurement, including:

[0007] Based on the bridge BIM information platform, obtain the original construction data of the bridge;

[0008] Collect and obtain survey video data of the bridge, and generate survey cycle data based on the survey video data;

[0009] Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge.

[0010] Furthermore, based on the set bridge BIM information platform, the original construction data of the bridge is obtained, including:

[0011] Obtain the bridge construction database in the bridge BIM information platform;

[0012] In the bridge construction database, original bridge construction data is obtained.

[0013] Furthermore, the survey video data of the bridge is collected and acquired, and the survey cycle data is generated according to the survey video data, including:

[0014] Based on the aerial camera device component and the underwater camera device component respectively, the survey video data of the bridge is collected and obtained;

[0015] According to the survey video data, based on the time series data analysis template, the survey video data is analyzed periodically to obtain the survey period data.

[0016] Furthermore, based on the aerial camera assembly and the underwater camera assembly, the survey video data of the bridge is collected and obtained, including:

[0017] Using an aerial camera device assembly equipped with a camera and a drone, based on a set flight path, photograph a first structure of the bridge located above the water surface to obtain first structure data;

[0018] Using an underwater camera assembly, photograph a second structure of the bridge below the water surface to obtain second structure data;

[0019] The first structural data and the second structural data are aggregated to obtain survey video data of the bridge.

[0020] Further, according to the survey video data, a template is generated based on the time series data to extract the period of the survey video data to obtain the survey period data, including:

[0021] Generate a sub-template based on the trend item in the time series data generation template, extract the data showing trend changes in the survey video data, and obtain the first survey cycle data;

[0022] Generate a sub-template based on the periodic item in the time series data generation template, extract the data showing periodic changes in the survey video data, and obtain the second survey period data;

[0023] Generate a sub-template based on the difference item in the time series data generation template, extract the data with obvious differences in the survey video data, and obtain the third survey cycle data;

[0024] Generate a sub-template based on the fixed items in the time series data generation template, extract the data that does not show changes in the survey video data, and obtain the fourth survey cycle data;

[0025] The first survey cycle data, the second survey cycle data, the third survey cycle data and the fourth survey cycle data are aggregated to obtain the survey cycle data.

[0026] Furthermore, based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge, including:

[0027] Based on the original construction data of the bridge, the BIM modeling software is used to generate an initial bridge construction model;

[0028] Based on the survey period data, BIM modeling software is used to generate several survey period bridge construction models;

[0029] A full life cycle model of the bridge is generated based on the initial bridge construction model and the survey period bridge construction model.

[0030] Furthermore, based on the initial bridge construction model and the survey period bridge construction model, a bridge life cycle model is generated, including:

[0031] Analyze the variation of bridge construction data of the initial bridge construction model and the bridge construction model of the survey period, and obtain m groups of variation of bridge construction data between the initial bridge construction model and the bridge construction model of the first survey period, the bridge construction model of the first survey period and the bridge construction model of the second survey period, and the bridge construction model of the mth survey period and the bridge construction model of the m+1th survey period, where m ranges from 2 to n-1; n is the last generated bridge construction model of the survey period;

[0032] The m groups of changes are divided into a plurality of change sequence segments according to a plurality of set change thresholds;

[0033] According to the sequence segment of the variation, set the identification segment of the whole life cycle of the bridge;

[0034] After marking the identification sections of the bridge's entire life cycle, a bridge life cycle model consisting of multiple bridge life cycle identification sections with identification markings is generated.

[0035] Furthermore, based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to model and generate a bridge life cycle model, which also includes target detection on the survey cycle data to obtain the maintenance targets of the bridge construction structure and mark them in the generated bridge life cycle model; the specific steps are:

[0036] Based on the survey period data, image extraction is performed on a plurality of first target areas in the set bridge construction structure to obtain first target area images; the first target area is an area where the bridge construction structure is damaged or significantly changed;

[0037] Perform target recognition on the first target area image based on the YOLOv8 model to obtain a first recognition area frame image;

[0038] Based on the first recognition area frame image, extracting a corresponding original recognition frame area from the original construction data of the bridge;

[0039] Comparing the similarity between the first recognition region frame image and the original recognition region frame, and generating first annotation content based on the similarity;

[0040] Based on the survey period data, performing image extraction on a plurality of second target areas in the second structure data to obtain a second target area map;

[0041] Extracting feature data of the second target area map, and based on the feature data, using a neural network prediction model to predict the impact degree of water erosion on the second target area map to obtain a prediction result of the impact degree of water erosion; generating second annotation content based on the prediction result;

[0042] The first annotation content and the second annotation content are annotated in the generated bridge life cycle model to serve as a basis for maintenance judgment of the maintenance targets of the bridge construction structure.

[0043] Furthermore, based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to model and generate a bridge life cycle model, which also includes: monitoring and analyzing the survey cycle data using a bridge construction structure health monitoring model to obtain monitoring results, generating a bridge construction structure health assessment score based on the monitoring results, and using the bridge construction structure health assessment score as the annotation content in the bridge life cycle model; the specific steps are:

[0044] Based on the survey cycle data, multiple data items that affect the health of bridge construction structures are extracted;

[0045] Based on multiple data items, the bridge construction structure aging index, bridge construction structure damage area index and bridge construction structure water erosion rate index corresponding to each survey period are constructed, and a bridge construction structure health monitoring model is constructed using a linear regression algorithm;

[0046] Using the bridge construction structural health monitoring model, the survey cycle data is monitored and analyzed to obtain the monitoring results of each survey cycle;

[0047] According to the monitoring results, the health assessment rules or health assessment models of the set bridge construction structures are used to assess the health of the bridge construction structures and obtain the health assessment scores of the bridge construction structures;

[0048] The bridge construction structure health assessment score is used as the annotation content in the bridge life cycle model.

[0049] The bridge BIM information survey and model building system based on video measurement includes:

[0050] The bridge original construction data acquisition module is used to obtain the original construction data of the bridge based on the bridge BIM information platform;

[0051] A survey cycle data acquisition module is used to collect and acquire survey video data of the bridge and generate survey cycle data based on the survey video data;

[0052] The bridge full life cycle model construction module is used to generate a bridge full life cycle model by modeling based on the original construction data and survey cycle data of the bridge using BIM modeling software.

[0053] Compared with the prior art, the present invention has the following advantages and beneficial effects: by using BIM modeling software to model the original construction data of the bridge and the survey cycle data generated by the survey video data of the bridge, a full life cycle model of the bridge is generated, thereby ensuring the accuracy of the full life cycle model of the bridge and providing conditions and basis for the subsequent maintenance and management of the bridge building.

[0054] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description and the accompanying drawings.

[0055] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0057] Figure 1 This is a schematic diagram of the steps of bridge BIM information survey and model building method based on video measurement;

[0058] Figure 2 A schematic diagram of the method steps for obtaining the original construction data of the bridge;

[0059] Figure 3 This is a schematic diagram of the bridge BIM information survey and model building system based on video measurement. DETAILED DESCRIPTION

[0060] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0061] The present invention provides a bridge BIM information survey and model building method based on video measurement, such as Figure 1 As shown, including:

[0062] Based on the bridge BIM information platform, obtain the original construction data of the bridge;

[0063] Collect and obtain survey video data of the bridge, and generate survey cycle data based on the survey video data;

[0064] Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge.

[0065] The working principle of the above technical solution is: in order to realize the bridge BIM information survey and model building method based on video measurement, the present invention first obtains the original construction data of the bridge based on the bridge BIM information platform; then collects and obtains the survey video data of the bridge, and generates survey cycle data according to the survey video data; finally, according to the original construction data and survey cycle data of the bridge, the BIM modeling software is used to model and generate a full life cycle model of the bridge.

[0066] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, by modeling according to the original construction data of the bridge and the survey cycle data generated by the survey video data of the bridge, using BIM modeling software to generate a full life cycle model of the bridge, the accuracy of the full life cycle model of the bridge can be guaranteed, and the conditions and basis for the subsequent maintenance and management of the bridge building can be provided.

[0067] In one embodiment, Figure 2 As shown in the figure, based on the set bridge BIM information platform, the original construction data of the bridge is obtained, including:

[0068] Obtain the bridge construction database in the bridge BIM information platform;

[0069] In the bridge construction database, original bridge construction data is obtained.

[0070] The working principle of the above technical solution is: in order to obtain the original construction data of the bridge, the present invention first obtains the bridge construction database in the bridge BIM information platform; and then obtains the original construction data of the bridge in the bridge construction database.

[0071] The beneficial effect of the above technical solution is: by adopting the solution provided by this embodiment, the original construction data of the bridge is obtained from the bridge construction database, thereby ensuring the comprehensiveness of the acquisition of the original construction data of the bridge.

[0072] In one embodiment, acquiring survey video data of a bridge and generating survey cycle data according to the survey video data include:

[0073] Based on the aerial camera device component and the underwater camera device component respectively, the survey video data of the bridge is collected and obtained;

[0074] According to the survey video data, based on the time series data analysis template, the survey video data is analyzed periodically to obtain the survey period data.

[0075] The working principle of the above technical solution is: in order to obtain survey periodic data, the present invention collects and acquires survey video data of the bridge based on an aerial camera assembly and an underwater camera assembly respectively; then, based on the survey video data and based on a time series data analysis template, a periodic analysis of the survey video data is performed to obtain survey periodic data.

[0076] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, the survey periodic data is obtained by performing periodic analysis of the survey video data based on the time series data analysis template according to the survey video data, thereby ensuring the accuracy of the generation of the survey periodic data.

[0077] In one embodiment, the survey video data of the bridge is collected and acquired based on the aerial camera assembly and the underwater camera assembly, respectively, including:

[0078] Using an aerial camera device assembly equipped with a camera and a drone, based on a set flight path, photograph a first structure of the bridge located above the water surface to obtain first structure data; the first structure includes a bridge span, a bridge cap beam, a bridge abutment, a bridge tie beam, a bridge cone slope, a bridge guardrail, a bridge slab, etc.;

[0079] Using an underwater camera assembly, photographing a second structure of the bridge below the water surface to obtain second structure data; the second structure includes a bridge pier, a bridge support, etc.;

[0080] The first structural data and the second structural data are aggregated to obtain survey video data of the bridge.

[0081] The working principle of the above technical solution is: in order to collect and obtain the survey video data of the bridge, the present invention first uses an aerial camera device assembly equipped with a camera and a drone to photograph the first structure of the bridge above the water surface based on a set flight path to obtain first structure data; then uses an underwater camera device assembly to photograph the second structure of the bridge below the water surface to obtain second structure data; finally, the first structure data and the second structure data are summarized to obtain the survey video data of the bridge.

[0082] The beneficial effect of the above technical solution is: by adopting the solution provided by this embodiment, the survey video data of the bridge is obtained by aggregating the first structure data and the second structure data, thereby ensuring the comprehensiveness of the survey video data of the bridge.

[0083] In one embodiment, according to the survey video data, a template is generated based on time series data, and period extraction of the survey video data is performed to obtain survey period data, including:

[0084] Generate a sub-template based on the trend item in the time series data generation template, extract the data showing trend changes in the survey video data, and obtain the first survey cycle data;

[0085] Generate a sub-template based on the periodic item in the time series data generation template, extract the data showing periodic changes in the survey video data, and obtain the second survey period data;

[0086] Generate a sub-template based on the difference item in the time series data generation template, extract the data with obvious differences in the survey video data, and obtain the third survey cycle data;

[0087] Generate a sub-template based on the fixed items in the time series data generation template, extract the data that does not show changes in the survey video data, and obtain the fourth survey cycle data;

[0088] The first survey cycle data, the second survey cycle data, the third survey cycle data and the fourth survey cycle data are aggregated to obtain the survey cycle data.

[0089] The working principle of the above technical solution is: in order to obtain survey cycle data, the present invention first generates a sub-template based on the trend item in the time series data generation template, extracts the data showing trend changes in the survey video data, and obtains the first survey cycle data; then, generates a sub-template based on the periodic item in the time series data generation template, extracts the data showing periodic changes in the survey video data, and obtains the second survey cycle data; then, generates a sub-template based on the difference item in the time series data generation template, extracts the data showing obvious differences in the survey video data, and obtains the third survey cycle data; finally, generates a sub-template based on the fixed item in the time series data generation template, extracts the data that does not show changes in the survey video data, and obtains the fourth survey cycle data; summarizes the first survey cycle data, the second survey cycle data, the third survey cycle data and the fourth survey cycle data to obtain the survey cycle data.

[0090] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, the survey cycle data is obtained by aggregating the first survey cycle data, the second survey cycle data, the third survey cycle data and the fourth survey cycle data, thereby ensuring the completeness of the survey cycle data.

[0091] In one embodiment, based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge, including:

[0092] Based on the original construction data of the bridge, the BIM modeling software is used to generate an initial bridge construction model;

[0093] Based on the survey period data, BIM modeling software is used to generate several survey period bridge construction models;

[0094] A full life cycle model of the bridge is generated based on the initial bridge construction model and the survey period bridge construction model.

[0095] The working principle of the above technical solution is: in order to realize the generation of a full life cycle model of a bridge, the present invention first uses BIM modeling software to model according to the original construction data of the bridge to generate an initial bridge construction model; then uses BIM modeling software to model according to the survey cycle data to generate several survey cycle bridge construction models; finally, based on the initial bridge construction model and the survey cycle bridge construction model, a full life cycle model of the bridge is generated.

[0096] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, a bridge life cycle model is generated according to the initial bridge construction model and the survey period bridge construction model, thereby ensuring the accuracy of the bridge life cycle model.

[0097] In one embodiment, a bridge life cycle model is generated based on the initial bridge construction model and the survey period bridge construction model, including:

[0098] Analyze the variation of bridge construction data of the initial bridge construction model and the bridge construction model of the survey period, and obtain m groups of variation of bridge construction data between the initial bridge construction model and the bridge construction model of the first survey period, the bridge construction model of the first survey period and the bridge construction model of the second survey period, and the bridge construction model of the mth survey period and the bridge construction model of the m+1th survey period, where m ranges from 2 to n-1; n is the last generated bridge construction model of the survey period;

[0099] The m groups of changes are divided into a plurality of change sequence segments according to a plurality of set change thresholds;

[0100] According to the sequence segment of the variation, set the identification segment of the whole life cycle of the bridge;

[0101] After marking the identification sections of the bridge's entire life cycle, a bridge life cycle model consisting of multiple bridge life cycle identification sections with identification markings is generated.

[0102] The working principle of the above technical solution is: in order to realize the generation of a full life cycle model of a bridge, the present invention first analyzes the change amount of bridge construction data of the initial bridge construction model and the survey period bridge construction model, and obtains m groups of change amounts of bridge construction data between the initial bridge construction model and the first survey period bridge construction model, the first survey period bridge construction model and the second survey period bridge construction model, and the mth survey period bridge construction model and the m+1th survey period bridge construction model, where m ranges from 2 to n-1; n is the last generated survey period bridge construction model; the m groups of change amounts are divided into multiple change amount sequence segments according to the set multiple change amount thresholds; then, according to the change amount sequence segments, the bridge full life cycle identification segments are set; finally, after marking the bridge full life cycle identification segments, a bridge full life cycle model consisting of multiple bridge full life cycle identification segments with identification marks is generated.

[0103] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, by marking the identification segments of the bridge's entire life cycle, a bridge life cycle model consisting of multiple bridge life cycle identification segments with identification marks is generated, thereby ensuring the accuracy of the bridge life cycle model.

[0104] In one embodiment, based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to model and generate a bridge life cycle model, which also includes performing target detection on the survey cycle data to obtain the targets to be maintained for the bridge construction structure and marking them in the generated bridge life cycle model; the specific steps are:

[0105] Based on the survey period data, image extraction is performed on a plurality of first target areas in the set bridge construction structure to obtain first target area images; the first target area is an area where the bridge construction structure is damaged or significantly changed;

[0106] Perform target recognition on the first target area image based on the YOLOv8 model to obtain a first recognition area frame image;

[0107] Based on the first recognition area frame image, extracting a corresponding original recognition frame area from the original construction data of the bridge;

[0108] Comparing the similarity between the first recognition region frame image and the original recognition region frame, and generating first annotation content based on the similarity;

[0109] Based on the survey period data, performing image extraction on a plurality of second target areas in the second structure data to obtain a second target area map;

[0110] Extracting feature data of the second target area map, and based on the feature data, using a neural network prediction model to predict the impact degree of water erosion on the second target area map to obtain a prediction result of the impact degree of water erosion; generating second annotation content based on the prediction result;

[0111] The first annotation content and the second annotation content are annotated in the generated bridge life cycle model to serve as a basis for maintenance judgment of the maintenance targets of the bridge construction structure.

[0112] The working principle of the above technical solution is: in order to enrich the annotation content of the bridge life cycle model, the present invention also includes, performing target detection on the survey cycle data to obtain the targets to be maintained for the bridge construction structure, and annotating them in the generated bridge life cycle model; the specific steps are: firstly, based on the survey cycle data, performing image extraction on several first target areas in the set bridge construction structure to obtain the first target area image; the first target area is the area where the bridge construction structure is damaged or obviously changed; then, based on the YOLOv8 model, performing target recognition on the first target area image to obtain the first recognition area frame image; based on the first recognition area frame image, extract the relative the corresponding original recognition frame area; compare the similarity between the first recognition frame image and the original recognition frame area, and generate the first annotation content based on the similarity; finally, based on the survey period data, perform image extraction on several second target areas in the second structure data to obtain a second target area map; extract feature data of the second target area map, and based on the feature data, use a neural network prediction model to predict the degree of influence of water erosion on the second target area map to obtain a prediction result of the degree of influence of water erosion; generate the second annotation content based on the prediction result; annotate the first annotation content and the second annotation content in the generated bridge life cycle model to serve as a maintenance judgment basis for the maintenance targets of the bridge construction structure.

[0113] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, by performing target detection on the survey cycle data, the targets to be maintained for the bridge construction structure are obtained, and they are marked in the generated bridge life cycle model, thereby enriching the annotation content of the bridge life cycle model.

[0114] In one embodiment, based on the original construction data and survey period data of the bridge, BIM modeling software is used to model and generate a bridge life cycle model, which also includes: monitoring and analyzing the survey period data using a bridge construction structure health monitoring model to obtain monitoring results, generating a bridge construction structure health assessment score based on the monitoring results, and using the bridge construction structure health assessment score as the annotation content in the bridge life cycle model; the specific steps are:

[0115] Based on the survey cycle data, multiple data items that affect the health of bridge construction structures are extracted;

[0116] Based on multiple data items, the bridge construction structure aging index, bridge construction structure damage area index and bridge construction structure water erosion rate index corresponding to each survey period are constructed, and a bridge construction structure health monitoring model is constructed using a linear regression algorithm;

[0117] Using the bridge construction structural health monitoring model, the survey cycle data is monitored and analyzed to obtain the monitoring results of each survey cycle;

[0118] According to the monitoring results, the health assessment rules or health assessment models of the set bridge construction structures are used to assess the health of the bridge construction structures and obtain the health assessment scores of the bridge construction structures;

[0119] The bridge construction structure health assessment score is used as the annotation content in the bridge life cycle model.

[0120] The working principle of the above technical solution is as follows: in order to enrich the full life cycle model of the bridge, the present invention monitors and analyzes the survey cycle data using the bridge construction structure health monitoring model to obtain monitoring results, generates a bridge construction structure health assessment score based on the monitoring results, and uses the bridge construction structure health assessment score as the annotation content in the full life cycle model of the bridge; the specific steps are as follows: first, based on the survey cycle data, extract multiple data items that affect the health of the bridge construction structure; then, based on the multiple data items, construct the bridge construction structure aging index, bridge construction structure damage area index and bridge construction structure water erosion rate index corresponding to each survey cycle, and use the linear regression algorithm to construct the bridge construction structure health monitoring model; finally, use the bridge construction structure health monitoring model to monitor and analyze the survey cycle data to obtain the monitoring results of each survey cycle; according to the monitoring results, use the set bridge construction structure health assessment rules or health assessment model to assess the health of the bridge construction structure and obtain the bridge construction structure health assessment score; use the bridge construction structure health assessment score as the annotation content in the full life cycle model of the bridge.

[0121] The beneficial effects of the above technical solution are: by adopting the solution provided in this embodiment, the survey cycle data is monitored and analyzed using the bridge construction structure health monitoring model to obtain monitoring results, and a bridge construction structure health assessment score is generated according to the monitoring results. The bridge construction structure health assessment score is used as the annotation content in the bridge life cycle model, which can enrich the annotation content in the bridge life cycle model.

[0122] Bridge BIM information survey and model building system based on video measurement, such as Figure 3 As shown, including:

[0123] The bridge original construction data acquisition module is used to obtain the original construction data of the bridge based on the bridge BIM information platform;

[0124] A survey cycle data acquisition module is used to collect and acquire survey video data of the bridge and generate survey cycle data based on the survey video data;

[0125] The bridge full life cycle model construction module is used to generate a bridge full life cycle model by modeling based on the original construction data and survey cycle data of the bridge using BIM modeling software.

[0126] The working principle of the above technical solution is: in order to obtain a bridge BIM information survey and model building system based on video measurement, the present invention first proposes a bridge original construction data acquisition module, which obtains the original construction data of the bridge based on the bridge BIM information platform; then proposes a survey cycle data acquisition module to collect and obtain the survey video data of the bridge, and generate survey cycle data based on the survey video data; finally, a bridge full life cycle model construction module is proposed, which uses BIM modeling software to model the bridge according to the original construction data and survey cycle data to generate a bridge full life cycle model.

[0127] The beneficial effect of the above technical solution is: by adopting the solution provided in this embodiment, by modeling according to the original construction data of the bridge and the survey cycle data generated by the survey video data of the bridge, using BIM modeling software to generate a full life cycle model of the bridge, the accuracy of the full life cycle model of the bridge can be guaranteed, and the conditions and basis for the subsequent maintenance and management of the bridge building can be provided.

[0128] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A bridge BIM information survey and model building method based on video measurement, characterized in that: include: Based on the bridge BIM information platform, obtain the original construction data of the bridge; Collect and obtain survey video data of the bridge, and generate survey cycle data based on the survey video data; Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge.

2. The bridge BIM information survey and model building method based on video measurement according to claim 1 is characterized in that: Based on the established bridge BIM information platform, the original construction data of the bridge is obtained, including: Obtain the bridge construction database in the bridge BIM information platform; In the bridge construction database, original bridge construction data is obtained.

3. The bridge BIM information survey and model building method based on video measurement according to claim 1 is characterized in that: Collect and obtain the survey video data of the bridge, and generate survey cycle data based on the survey video data, including: Based on the aerial camera device component and the underwater camera device component respectively, the survey video data of the bridge is collected and obtained; According to the survey video data, a template is generated based on the time series data, and the period extraction of the survey video data is performed to obtain the survey period data.

4. The bridge BIM information survey and model building method based on video measurement according to claim 3 is characterized in that: Based on the aerial camera assembly and the underwater camera assembly, the survey video data of the bridge is collected and obtained, including: Using an aerial camera device assembly equipped with a camera and a drone, based on a set flight path, photograph a first structure of the bridge located above the water surface to obtain first structure data; Using an underwater camera assembly, photograph a second structure of the bridge below the water surface to obtain second structure data; The first structural data and the second structural data are aggregated to obtain survey video data of the bridge.

5. The bridge BIM information survey and model building method based on video measurement according to claim 3 is characterized in that: According to the survey video data, a template is generated based on the time series data to extract the period of the survey video data and obtain the survey period data, including: Generate a sub-template based on the trend item in the time series data generation template, extract the data showing trend changes in the survey video data, and obtain the first survey cycle data; Generate a sub-template based on the periodic item in the time series data generation template, extract the data showing periodic changes in the survey video data, and obtain the second survey period data; Generate a sub-template based on the difference item in the time series data generation template, extract the data with obvious differences in the survey video data, and obtain the third survey cycle data; Generate a sub-template based on the fixed items in the time series data generation template, extract the data that does not show changes in the survey video data, and obtain the fourth survey cycle data; The first survey cycle data, the second survey cycle data, the third survey cycle data and the fourth survey cycle data are aggregated to obtain the survey cycle data.

6. The bridge BIM information survey and model building method based on video measurement according to claim 3 is characterized in that: Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a full life cycle model of the bridge, including: Based on the original construction data of the bridge, the BIM modeling software is used to generate an initial bridge construction model; Based on the survey period data, BIM modeling software is used to generate several survey period bridge construction models; A full life cycle model of the bridge is generated based on the initial bridge construction model and the survey period bridge construction model.

7. The bridge BIM information survey and model building method based on video measurement according to claim 1 is characterized in that: Based on the initial bridge construction model and the survey period bridge construction model, a bridge life cycle model is generated, including: Analyze the variation of bridge construction data of the initial bridge construction model and the bridge construction model of the survey period, and obtain m groups of variation of bridge construction data between the initial bridge construction model and the bridge construction model of the first survey period, the bridge construction model of the first survey period and the bridge construction model of the second survey period, and the bridge construction model of the mth survey period and the bridge construction model of the m+1th survey period, where the value of m ranges from 2 to n-1; n is the last generated bridge construction model of the survey period; The m groups of changes are divided into a plurality of change sequence segments according to a plurality of set change thresholds; According to the sequence segment of the variation, set the identification segment of the whole life cycle of the bridge; After marking the identification sections of the bridge's entire life cycle, a bridge life cycle model consisting of multiple bridge life cycle identification sections with identification markings is generated.

8. The method for bridge BIM information survey and model building based on video metrology according to claim 4 is characterized in that: Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to generate a bridge life cycle model, which also includes target detection on the survey cycle data to obtain the maintenance targets of the bridge construction structure and mark them in the generated bridge life cycle model; the specific steps are: Based on the survey period data, image extraction is performed on a plurality of first target areas in the set bridge construction structure to obtain first target area images; the first target area is an area where the bridge construction structure is damaged or significantly changed; Perform target recognition on the first target area image based on the YOLOv8 model to obtain a first recognition area frame image; Based on the first recognition area frame image, extracting a corresponding original recognition frame area from the original construction data of the bridge; Comparing the similarity between the first recognition region frame image and the original recognition region frame, and generating first annotation content based on the similarity; Based on the survey period data, performing image extraction on a plurality of second target areas in the second structure data to obtain a second target area map; Extracting feature data of the second target area map, and based on the feature data, using a neural network prediction model to predict the impact degree of water erosion on the second target area map to obtain a prediction result of the impact degree of water erosion; generating second annotation content based on the prediction result; The first annotation content and the second annotation content are annotated in the generated bridge life cycle model to serve as a basis for maintenance judgment of the maintenance targets of the bridge construction structure.

9. The bridge BIM information survey and model building method based on video metrology according to claim 1 is characterized in that: Based on the original construction data and survey cycle data of the bridge, BIM modeling software is used to model and generate a bridge life cycle model, which also includes: monitoring and analyzing the survey cycle data using the bridge construction structure health monitoring model to obtain monitoring results, generating bridge construction structure health assessment scores based on the monitoring results, and using the bridge construction structure health assessment scores as annotation content in the bridge life cycle model; the specific steps are: Based on the survey cycle data, multiple data items that affect the health of bridge construction structures are extracted; Based on multiple data items, the bridge construction structure aging index, bridge construction structure damage area index and bridge construction structure water erosion rate index corresponding to each survey period are constructed, and a bridge construction structure health monitoring model is constructed using a linear regression algorithm; Using the bridge construction structural health monitoring model, the survey cycle data is monitored and analyzed to obtain the monitoring results of each survey cycle; According to the monitoring results, the health assessment rules or health assessment models of the set bridge construction structures are used to assess the health of the bridge construction structures and obtain the health assessment scores of the bridge construction structures; The bridge construction structure health assessment score is used as the annotation content in the bridge life cycle model.

10. The bridge BIM information survey and model building system based on video measurement is characterized by: include: The bridge original construction data acquisition module is used to obtain the original construction data of the bridge based on the bridge BIM information platform; A survey cycle data acquisition module is used to collect and acquire survey video data of the bridge and generate survey cycle data based on the survey video data; The bridge full life cycle model construction module is used to generate a bridge full life cycle model by modeling based on the original construction data and survey cycle data of the bridge using BIM modeling software.

Citation Information

Patent Citations

  • BIM-FEM-based bridge structure digital twinborn body and method

    CN113806978A

  • Highway bridge management and maintenance PHM system and method based on BIM

    CN114169548A