Inland river shallow water inclined bank land and water conversion moving large steel box girder engineering buoyancy tank system
By designing a floating box system for large steel box girders in the inland water and land conversion and transportation in the ancient canal heritage area, it uses a diamond floating box platform and I-shaped steel lattice beam, combining hydraulic retractable legs and belt clips The jack of the rail device solves the bearing capacity and safety problems of steel box girder transportation in shallow water, realizes efficient and safe water-land conversion and transportation, and reduces operating costs.
Patent Information
- Application Number
- CN202411249715.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-15
AI Technical Summary
During the construction of the ancient canal heritage area, the transportation of steel box girders faces the problem of large bearing capacity under shallow water conditions but concentrated loads. The half-land and half-water box girder cannot be lifted in place, and the large-tonnage box girder requires large-shaped mechanical equipment to cooperate, resulting in Large investment in equipment and high safety risks.
Design a floating box system for large steel box girders for water and land conversion and transportation in inland shallow water and inclined banks, adopting diamond floating box platform and I-shaped steel grid beam, equipped with hydraulic retractable legs and a jack with rail clamping device to realize floating box The stable positioning of the system is directly connected to the rail, and large-scale cranes are abolished, and rail beams and beam transport platforms are used to transport steel box beams.
It realizes efficient and safe water-land conversion and transportation of steel box girders in shallow water, improves operating efficiency and system reliability, reduces operating costs, and enhances the transportation safety and stability of steel box girders.
Smart Images

Figure CN118953603A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel box girder transportation, in particular to a floating box system for land-water conversion and transportation of large steel box girder projects on inland shallow water and inclined banks. Background Art
[0002] The construction process for assembling large-span river-crossing bridge segments usually involves using large barges to transport large-tonnage box girder segments to the bottom of the designed installation position of the bridge, and then using a bridge deck crane to lift them to the predetermined position of the bridge segment for accurate cantilever assembly.
[0003] Since the project bridge is specially designed to protect the ancient canal (cultural heritage), the bridge is located within the river heritage protection area and is constructed using the cantilever assembly method to ensure that the ancient canal heritage area control line (the canal planned river protection area control line) is not occupied by any engineering facilities.
[0004] Issues that need to be addressed during the specific construction phase: 1. The riverbank of the ancient canal and the centerline of the bridge are at an oblique angle, with a small included angle; 2. The overall water depth of the ancient canal (less than 1.5m) is relatively shallow, and the transportation of box girder segments by barge is restricted; 3. Excavation and destruction are not allowed during construction in the canal heritage area; 4. Some bridge segments are half land and half water, and the box girders in water and on land alone cannot be lifted in place; 5. Steel box girders for high-section bridges need to be processed and pre-assembled in a processing plant, then dismantled and transported in sections to the construction site for secondary assembly, and then transported from land to the river channel to the predetermined installation bridge location; 6. The problem of uniform force on the floating body when providing large bearing capacity but concentrated load under shallow water conditions (small effective load projection area of the segment box girder); 7. Large-tonnage box girders require large-scale mechanical equipment to cooperate with the box girder transportation, and the box girder transportation equipment requires large investment and high safety risks.
[0005] Therefore, a means of transportation that can float in shallow waters, carry large-tonnage steel beam segments, and achieve transfer and transfer between land and water is of great practical significance to the project. Summary of the invention
[0006] In view of the above-mentioned prior art, the present invention proposes a pontoon system for the water-to-land transfer and transportation of large steel box girder projects on shallow inland water and inclined banks.
[0007] The present invention provides a pontoon system for inland shallow water sloping bank water-land transfer and transportation of large steel box girder projects, comprising a pontoon platform, the pontoon platform is composed of a plurality of pontoon units spliced together, a reinforcement beam is arranged at the upper end of the pontoon platform, two parallel track beams are arranged at the upper end of the reinforcement beam, a beam transport platform is arranged at the upper ends of the two track beams, and the beam transport platform is connected to the two track beams via a jack with a track clamp.
[0008] Preferably, the pontoon platform is formed by splicing a plurality of pontoon units into a diamond structure.
[0009] Preferably, the reinforcement beam is made of I-beam.
[0010] Preferably, the track beam is made of I-beam, and two track beams are connected by a plurality of connecting beams, and the connecting beams are made of I-beam.
[0011] Preferably, a plurality of first retractable legs are provided at the lower end of the track beam, and the first retractable legs are arranged in a straight-line structure.
[0012] Preferably, a plurality of second retractable legs are provided at the lower end of the connecting beam, and the second retractable legs are arranged in an H-shaped structure.
[0013] Compared with the prior art, the beneficial effects of the present invention are: 1. The present invention provides a pontoon system for the land-water transfer and transportation of large steel box girders on shallow inland river sloping banks. In order to adapt the steel box girders to be precisely located directly below the bridge deck crane, a diamond-shaped rather than square-shaped assembly is adopted to adapt to the force and to be close to the river bank line, thereby ensuring safe and smooth transportation on water and on shore. The diamond-shaped pontoon system is adopted to realize the upper and lowering of steel box girders on both sides of the river bank without turning around, which improves the overall operation efficiency.
[0014] 2. Standard engineering pontoon assembly pontoon system provides engineering performance with small draft (measured by shore water depth) but large load-bearing capacity; I-beam lattice beams are used to reinforce the assembled pontoons with large area and small stiffness to ensure balanced load-bearing of each pontoon unit under large load and concentrated force conditions, thereby improving the operational reliability of the pontoon system.
[0015] 3. The pontoon system is equipped with hydraulically retractable legs to provide accurate positioning, anchoring and bearing capacity for the floating and berthing steel box girders of the pontoon system, thereby improving the safety and stability of the pontoon system during the transportation of steel box girders.
[0016] 4. The use of track beams and track-transferred steel box beams enables the track to directly connect the onshore operation point (beam installation point) with the pontoon, eliminating the need for large onshore cranes to lift the steel box onto the pontoon, thereby reducing operating costs.
[0017] 5. When moving the steel box girder on the pontoon system, a jack with a track clamp is used to push and move it, and the reaction force between the track and the beam transport platform is applied to avoid external force dragging the beam transport platform and causing the pontoon system to shake, thereby improving overall safety and reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a structural schematic diagram of a pontoon system for a large-scale steel box girder engineering water-to-land transfer and transportation project in an inland shallow water inclined bank in an embodiment of the present invention.
[0019] Figure 2 Schematic diagram of the structure of the pontoon unit in an embodiment of the present invention.
[0020] Figure 3 It is a schematic diagram of the structure of the reinforcement beam in an embodiment of the present invention.
[0021] Figure 4 Schematic diagram of the structure of the first telescopic leg in an embodiment of the present invention.
[0022] Figure 5 Schematic diagram of the structure of the second telescopic leg in an embodiment of the present invention.
[0023] Figure 6 It is a schematic diagram of the structure of the beam transport platform in an embodiment of the present invention.
[0024] In the figure: 1. pontoon platform; 2. pontoon unit; 3. reinforcement beam; 4. track beam; 5. connecting beam; 6. first retractable leg; 61. first hydraulic mechanism; 62. support plate; 7. second retractable leg; 71. second hydraulic mechanism; 72. support rod; 73. telescopic support rod; 8. beam transport platform; 9. jack with track clamp; 10. steel box beam segment; 11. pontoon towing point; 12. tugboat force application point. DETAILED DESCRIPTION
[0025] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below with reference to specific diagrams.
[0026] Example: Figure 1-6 The pontoon system of a large steel box girder engineering for water-land conversion and transportation of shallow inland water and inclined banks shown in the figure comprises a pontoon platform 1, which is formed by splicing a number of pontoon units 2 of standard engineering into a diamond structure, a reinforcing beam 3 is fixed to the upper end of the pontoon platform 1, the reinforcing beam 3 is an I-beam lattice beam, two parallel track beams 4 are fixed to the upper end of the reinforcing beam 3, the track beam 4 is made of I-beam, the two track beams 4 are connected by a number of connecting beams 5, the connecting beams 5 are made of I-beam, and the lower end of the track beam 4 is provided with a number of first retractable legs 6, which are arranged I-shaped structure, the first retractable leg 6 includes a first hydraulic mechanism 61, the upper and lower ends of the first hydraulic mechanism 61 are provided with support plates 62, the lower end of the connecting beam 5 is provided with several second retractable legs 7, the second retractable legs 7 are arranged as an H-shaped structure, the second retractable leg 7 includes a second hydraulic mechanism 71, the upper and lower ends of the second hydraulic mechanism 71 are provided with support rods 72, both ends of the two support rods 72 are provided with telescopic support rods 73, the upper ends of the two track beams 4 are provided with beam transport platforms 8, and the beam transport platforms 8 are connected to the two track beams 4 through jacks 9 with track clamps.
[0027] The buoyancy system, when used in a specific application, includes the following steps: S1. The pontoon system is positioned at the upper beam point, and the retractable legs are adjusted to position and anchor the pontoon platform 1, keeping the track beam 4 in an uphill state toward the center of the pontoon platform 1.
[0028] S2. Move the steel box girder segment 10 after secondary assembly to the beam transport platform 8 through the assembly gantry crane, and adjust the height of the retractable legs with the assistance of the assembly gantry crane to keep the track beam 4 in an uphill state toward the center of the pontoon platform 1.
[0029] S3. Under the action of the reaction jack of the jack 9 with track clamp, the beam transport platform 8 transfers and transports the steel box beam segment 10 to the predetermined central position of the pontoon system, and adjusts the height of the steel box beam segment 10 on the retractable legs while moving, so as to maintain a slight upward slope of the pontoon system to balance the change in track slope caused by the increase in draft as the load of the pontoon platform 1 gradually increases.
[0030] S4. After the steel box girder segment 10 is moved to the center of the pontoon system, the beam transport platform 8 is locked, and the retractable legs on the shore are gradually retracted using the hydraulic system. After observing that the overall force of the pontoon platform 1 reaches a stable state, the pontoon system is dragged (pushed) forward.
[0031] S5. The pontoon platform 1 is advanced by towing with anchors on the shore or by pushing with tugboats on both sides. Before the pontoon platform 1 is in place, it is better to be close to the river bank line. After it is in place, all the legs are extended to position and anchor the pontoon platform 1, and the slope toward the shore is maintained by adjusting the height of the legs on the shore to prepare for the conversion of the shifting beam.
[0032] S6. Release the lock between the beam transport platform 8 and the track beam 4, use the jack 9 with the track clamp as the power and brake to move the box beam from the pontoon platform 1 to the shore to achieve the conversion from water to shore, and use the bridge deck crane to install the beam after it is in place.
[0033] The above are only implementation modes of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure made using the contents of the present invention's specification and drawings, directly or indirectly used in other related technical fields, are also within the patent protection scope of the present invention.
Claims
1. A floating tank system for large-scale steel box girder engineering for water-land transfer and transportation on shallow inland water and inclined banks, characterized in that: It includes a pontoon platform, which is composed of several pontoon units. A reinforcement beam is arranged at the upper end of the pontoon platform, and two parallel track beams are arranged at the upper end of the reinforcement beam. A beam transport platform is arranged at the upper ends of the two track beams, and the beam transport platform is connected to the two track beams through a jack with a track clamp.
2. The pontoon system for large-scale steel box girder engineering for water-land transfer and transportation on shallow inland water and inclined banks as claimed in claim 1 is characterized in that: The pontoon platform is formed by splicing a plurality of pontoon units into a diamond structure.
3. The pontoon system for large-scale steel box girder engineering for water-land transfer and transportation in shallow water and inclined banks of inland rivers as claimed in claim 1 or 2, characterized in that: The reinforcement beam is an I-beam lattice beam.
4. The pontoon system for large-scale steel box girder engineering for water-land transfer and transportation in shallow inland water and inclined banks as claimed in claim 1 or 2, characterized in that: The track beam is made of I-beam, and two track beams are connected by a plurality of connecting beams, and the connecting beams are made of I-beam.
5. The pontoon system for large-scale steel box girder engineering for water-land transfer and transportation in shallow inland water and inclined banks as claimed in claim 1 or 2, characterized in that: A plurality of first retractable legs are arranged at the lower end of the track beam, and the first retractable legs are arranged in a straight-line structure.
6. The pontoon system for large-scale steel box girder engineering for water-land transfer and transportation in shallow inland water and inclined banks as claimed in claim 4 is characterized in that: A plurality of second retractable legs are arranged at the lower end of the connecting beam, and the second retractable legs are arranged in an H-shaped structure.