Box culvert reinforcing method

By driving piles on both sides of the box culvert to form a closed curtain and grouting and reinforcement, the problem of inaccurate reinforcement of the box culvert in the prior art is solved, the foundation bearing capacity and waterproofing effect are improved, and the box culvert settlement and cracking are avoided.

CN118958258APending Publication Date: 2024-11-15XINJIANG BEIXIN ROAD & BRIDGE GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411256579.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In the box culvert reinforcement, due to the influence of terrain and the large slurry fluidity in the box culvert reinforcement, it is difficult to achieve accurate reinforcement of the foundation foundation, resulting in difficult to effectively solve the problem of box culvert settlement and cracking.

Method used

By digging out the working surfaces on both sides of the box culvert, piles form a plurality of first pile bodies arranged at intervals, and inclined grouting holes are drilled along the bottom of the box culvert for grouting, forming a closed curtain to increase the foundation bearing capacity and prevent water seepage.

Benefits of technology

The foundation foundation of the sinking section box culvert is achieved accurately reinforced, the bearing capacity of the foundation at the bottom of the box culvert is raised, the outer water is avoided, the grouting liquid is expanded, and the pressure is formed is formed, which effectively prevents the box culvert from further settlement and cracking.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958258A_ABST
    Figure CN118958258A_ABST
Patent Text Reader

Abstract

The invention relates to a box culvert reinforcing method, and relates to the field of civil engineering. The invention provides a box culvert reinforcing method. The box culvert reinforcing method comprises the steps that working faces are dug in the positions of the side walls of the two sides of a box culvert correspondingly, a plurality of piling holes distributed at intervals are formed along the working faces, piling is conducted on the multiple piling holes to form multiple first pile bodies, and the multiple first pile bodies form closed curtains on the two sides of the box culvert correspondingly. Half of the first pile body formed by piling is in the side wall of the box culvert, and the other half of the first pile body is in the foundation, so that a supporting system is formed for the bottom plate of the box culvert, the foundation of the sinking section of the box culvert is accurately reinforced through the reinforcing mode, the sinking box culvert is lifted within a certain range, and the bearing capacity of the foundation at the bottom of the box culvert can be improved; meanwhile, the multiple first pile bodies effectively enclose and block the area, needing to be reinforced, of the box culvert, the multiple first pile bodies can form a closed curtain for the box culvert foundation, and the closed curtain can prevent water from entering the box culvert foundation and can also seal grouting liquid to be freely spread outwards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of civil engineering, and in particular to a box culvert reinforcement method. Background Art

[0002] At the end of the 40-meter box culvert of the first phase of the water inlet box culvert of a certain city's channel rainwater regulation project, a large amount of rainwater leaked into the foundation soil due to the poor flow of rainwater and sewage in the surrounding area, causing varying degrees of settlement in the completed box culvert, especially varying degrees of cracking at the expansion joints.

[0003] Since the site is a thick fill foundation formed by recent ditch filling and land reclamation, the unevenness of the fill foundation and the heavy rain that soaked the foundation caused the uneven settlement of the box culvert as the main reasons.

[0004] According to the on-site sampling and test data analysis, the engineering properties of the lime soil cushion and soil samples within the range of 0.0-8.5m below the box culvert base can basically meet the requirements. According to the data analysis of the uneven settlement of the box culvert, the water content of the box culvert and the base below 8.5m increases, and the compressibility is large.

[0005] The inventors have found that reinforcing the box culvert foundation by grouting can increase the bearing capacity of the box culvert foundation. However, the existing technology of grouting reinforcement of the foundation is greatly affected by the terrain, the slurry has high fluidity, and it is impossible to accurately reinforce the reinforcement area. Summary of the invention

[0006] The objects of the present invention include, for example, providing a box culvert reinforcement method which can accurately increase the foundation bearing capacity of the box culvert.

[0007] The embodiments of the present invention can be implemented as follows:

[0008] The present invention proposes a box culvert reinforcement method, comprising:

[0009] Working surfaces are dug out at the side walls of both sides of the box culvert, and a plurality of pile holes arranged at intervals are drilled along the working surfaces. The plurality of pile holes are piled to form a plurality of first pile bodies, and the plurality of first pile bodies form closed curtains on both sides of the box culvert.

[0010] Optionally, a plurality of inclined and spaced grouting holes are drilled along both sides of the box culvert toward the bottom of the box culvert;

[0011] The plurality of grouting holes are formed by grouting.

[0012] Optionally, the step of grouting the plurality of grouting holes comprises:

[0013] The grouting holes are grouted in sections from bottom to top using a grouting pipe with a diameter of 50 cm;

[0014] The grouting pipe is at least 0.5m away from the bottom of the grouting hole for grouting.

[0015] Optionally, a plurality of grouting holes are drilled at intervals along the axis of the closed curtain, and a single grouting hole is located between two adjacent first pile bodies.

[0016] Optionally, the hole spacing between the multiple grouting holes is 0.7m-1m;

[0017] The grouting hole is inclined at 40°-50°;

[0018] The grouting pressure is 1.0-1.5MPa.

[0019] Optionally, the width of the working surface ranges from 4 to 5 m, and the depth of the working surface ranges from 5 to 6 m.

[0020] Optionally, the plurality of piling holes are arranged in sequence and at equal intervals along the extension direction of the working surface, the interval between adjacent piling holes is 0.7-0.9 m, and the diameter of the piling holes is 0.7-0.9 m;

[0021] The depth of the first pile body is 10-12m.

[0022] Optionally, a horizontal layout is performed on the working surface, and a plurality of the piling holes are drilled at intervals along the horizontal layout using a drilling rig, the drill rod head of the drilling rig is perpendicular to the working surface, and the center of the drill rod head is coaxial with the center of the piling hole.

[0023] Optionally, the step of driving piles into the plurality of pile holes to form a plurality of first pile bodies comprises:

[0024] Move the rotary spraying machine, insert the rotary spraying pipe into the piling hole, and perform test spraying;

[0025] After the test spraying is completed, the rotary spraying pipe is inserted into the pile hole to carry out high-pressure rotary spraying grouting;

[0026] The rotary jet grouting machine is moved to the next piling hole until high-pressure rotary jet grouting is completed for all the piling holes.

[0027] Optionally, the step of inserting the rotary jet pipe into the piling hole for high-pressure rotary jet grouting includes:

[0028] Inserting the rotary spraying pipe into the pile hole, and when the rotary spraying pipe reaches a predetermined spraying pressure, lifting the rotary spraying pipe from bottom to top to perform rotary spraying on the pile hole;

[0029] The rotary spraying pipe is first sprayed, and then rotated and lifted;

[0030] When the jet spraying pipe is lifted to a depth of at least 1 m below the designed top of the first pile body, the lifting speed is slowed down until the designed elevation of the first pile body is reached.

[0031] The beneficial effects of the embodiments of the present invention include, for example:

[0032] The present invention provides a box culvert reinforcement method, which comprises the following steps: by arranging a plurality of first pile bodies, half of the first pile bodies formed by piling are in the side walls of the box culvert, and the other half are in the foundation at the bottom of the box culvert, so that a support system can be formed for the bottom plate of the box culvert. This reinforcement method can accurately reinforce the foundation of the sunken section of the box culvert, and lift the sunken box culvert within a certain range, thereby increasing the bearing capacity of the foundation at the bottom of the box culvert; at the same time, the plurality of first pile bodies form an effective blockade for the area of ​​the box culvert that needs to be reinforced, and the plurality of first pile bodies can form a closed curtain for the box culvert foundation, which can prevent water from entering from the outside, and can also block the grouting liquid from spreading outward at will, and form pressure within the range of the box culvert foundation. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0034] Figure 1 It is a schematic diagram of punching a plurality of pile holes along the working surface of a box culvert in an embodiment of the present invention;

[0035] Figure 2 It is a schematic diagram of setting a first pile body and a second pile body in a box culvert according to an embodiment of the present invention.

[0036] Icons: 100-box culvert; 110-side wall; 120-working surface; 130-pile hole; 140-grouting hole; 200-first pile body; 300-second pile body. DETAILED DESCRIPTION

[0037] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0038] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0040] In the description of the present invention, it should be noted that if the terms "upper", "lower", "inside", "outside", etc. appear to indicate an orientation or position relationship, they are based on the orientation or position relationship shown in the accompanying drawings, or are the orientation or position relationship in which the product of the invention is usually placed when used. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0041] In addition, the terms “first”, “second”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0042] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0043] Please refer to Figure 1 The present embodiment provides a method for reinforcing a box culvert 100, comprising: digging out working surfaces 120 at the positions of the side walls 110 on both sides of the box culvert 100, punching a plurality of pile holes 130 arranged at intervals along the working surfaces 120, and driving piles through the plurality of pile holes 130 to form a plurality of first pile bodies 200, and the plurality of first pile bodies 200 respectively form closed curtains on both sides of the box culvert 100.

[0044] It can be understood that half of the first pile body 200 formed by piling is in the side wall of the box culvert 100, and the other half is in the foundation at the bottom of the box culvert 100, so that a support system can be formed for the bottom plate of the box culvert 100. This reinforcement method can accurately reinforce the foundation of the box culvert 100 in the sunken section, and lift the sunken box culvert 100 within a certain range, which can increase the bearing capacity of the foundation at the bottom of the box culvert 100; at the same time, multiple first pile bodies 200 form an effective blockade for the area of ​​the box culvert 100 that needs to be reinforced, and multiple first pile bodies 200 can form a closed curtain for the foundation of the box culvert 100. The closed curtain can prevent water from entering from the outside, and can also block the grouting liquid from spreading outward at will, and form pressure within the foundation range of the box culvert 100.

[0045] Please refer to Figure 1 and Figure 2 In this embodiment, a box culvert 100 reinforcement method includes the following steps:

[0046] S1: Working surfaces 120 are excavated at the side walls 110 of the box culvert 100, and a plurality of pile holes 130 arranged at intervals are drilled along the working surfaces 120. The plurality of pile holes 130 are piled to form a plurality of first pile bodies 200. The plurality of first pile bodies 200 form closed curtains on both sides of the box culvert 100.

[0047] S2: drilling a plurality of inclined and spaced grouting holes 140 along both sides of the box culvert 100 toward the bottom of the box culvert 100 ; grouting the plurality of grouting holes 140 to form a plurality of second pile bodies 300 .

[0048] It can be understood that the multiple second pile bodies 300 can consolidate and reinforce the bottom parts of the box culvert 100, and the multiple first pile bodies 200 and the multiple second pile bodies 300 can form a support system for the bottom plate of the box culvert 100. This reinforcement method can accurately reinforce the foundation of the sunken section of the box culvert 100 and lift the sunken box culvert 100 within a certain range, which can increase the bearing capacity of the foundation at the bottom of the box culvert 100.

[0049] It is worth mentioning that the steps of S1 and S2 can be replaced. S1 can be performed first and then S2, or S2 can be performed first and then S1.

[0050] Specifically, S1 includes the following steps:

[0051] S11: digging out working surfaces 120 at the side walls 110 on both sides of the box culvert 100 respectively. The width of the working surface 120 is 4-5 m, and the depth of the working surface 120 is 5-6 m.

[0052] S12: Horizontal layout is performed on the working surface 120 , and a plurality of pile holes 130 are drilled at intervals along the horizontal layout using a drilling rig, with the drill rod head of the drilling rig being perpendicular to the working surface 120 , and the center of the drill rod head being coaxial with the center of the pile hole 130 .

[0053] It is understood that the drilling machine is moved according to the horizontal layout on the on-site working surface 120, so that the drill rod head is aligned with the hole position center of the pile hole 130. The drill rod is drilled into the hole, and the hole diameter of the pile hole 130 is 800mm. The hole is drilled strictly according to the predetermined pile position, and the plane position deviation shall not be greater than 50mm. The original soil slurry is used to protect the wall.

[0054] At the same time, in order to ensure that the drilling rig reaches the required verticality, the drilling rig must be horizontally corrected after it is in place so that the axis of the drill rod is vertically aligned with the position of the pile hole 130 to ensure the verticality of the drill hole.

[0055] At the same time, during the straightening and correction inspection, use a plumb ball to check from two vertical directions. If deflection is found, add a thin wooden block under the base of the drill rig for adjustment. The height of the plumb ball must not be less than 2 meters.

[0056] In this embodiment, a plurality of pile holes 130 are arranged in a equidistant manner along the extension direction of the working surface 120. The distance between adjacent pile holes 130 can be 0.7m, 0.75m, 0.8m, 0.85m, 0.9m, etc. The diameter of the pile holes 130 can be 0.7m, 0.75m, 0.8m, 0.85m, 0.9m, etc.

[0057] S13: Move the jet spraying machine, insert the jet spraying pipe into the piling hole 130, and perform test spraying.

[0058] It is understandable that a test spray is conducted to determine the construction technical parameters. In this embodiment, the rotary spray pipe adopts a double pipe, and the grouting materials are silicate cement and compressed air; wherein the silicate cement can adopt ordinary silicate cement of No. 42.5; wherein the compressed air pressure is 0.7-0.8MPa; wherein the water-cement ratio of the cement slurry (single liquid) is: 0.8-1.2; wherein the slurry pressure of the double pipe method is 20-40MPa.

[0059] Optionally, the jet spray pipe can be a single pipe, a double pipe, or a triple pipe. The grouting material of the single pipe is cement slurry; the grouting material of the double pipe is cement slurry and compressed air; the grouting material of the triple pipe is cement slurry, air, and high-pressure water.

[0060] S14: After the test spraying is completed, the rotary spraying pipe is inserted into the pile hole 130 to perform high-pressure rotary spraying grouting.

[0061] S15: Move the jet grouting machine to the next piling hole 130 until the high-pressure jet grouting is completed for all the piling holes 130 .

[0062] In this embodiment, S14 further includes the following steps:

[0063] S141: Before construction, prepare drainage ditches and mud pools in advance. During construction, waste slurry is directed or discharged into the mud pool. After sedimentation and condensation, it is transported to off-site storage or disposal.

[0064] S142: Before conducting high-pressure rotary jet grouting, check the high-pressure equipment and piping system. The pressure and flow must meet the design requirements.

[0065] Among them, there must be no debris in the grouting pipe and nozzle, and the sealing ring of the grouting pipe joint must be in good condition.

[0066] S143: Record the hole position of each pile hole 130, and record the actual hole position, hole depth, underground obstacles in each borehole, grouting volume and other data of the pile hole 130.

[0067] S144: inserting the rotary spraying pipe into the pile hole 130, and when the rotary spraying pipe reaches a predetermined spraying pressure, lifting the rotary spraying pipe from bottom to top to perform rotary spraying on the pile hole 130.

[0068] Among them, high-pressure jet grouting is carried out according to the determined construction parameters; after the amount of high-pressure jet grouting is normal, the grouting pipe is gradually lifted, and high-pressure rotary jet grouting is carried out from bottom to top.

[0069] In case of interruption of slurry or gas supply, the nozzle will be immediately lowered to 0.3m below the supply stop point and will be lifted again after supply is resumed.

[0070] S145: The rotary jet nozzle first sprays the slurry, then rotates and lifts.

[0071] During each high-pressure rotary spraying, the slurry is sprayed first and then rotated and lifted to prevent the slurry pipe from twisting off.

[0072] S146: When the jet nozzle is lifted to a depth of at least 1 m below the designed top of the first pile body 200, the lifting speed is slowed down until the designed elevation of the first pile body 200 is reached.

[0073] S147: After the high-pressure rotary jet grouting operation is completed, the slurry that emerges is back-injected into the pile hole 130 until it stops sinking.

[0074] It is understandable that the depth of the first pile body 200 is 10-12 meters, because the bottom of the box culvert 100 is about 10 meters from the bottom elevation of the fill, and the treatment depth is initially set to 12 meters, so the first pile body 200 extends to about 2 meters below the foundation. The depth of the first pile body 200 can be selected according to the actual depth of the bottom of the box culvert 100 from the foundation.

[0075] It is worth mentioning that when preparing cement slurry, the water-cement ratio is required to be in accordance with the design regulations and cannot be changed at will. During the spraying process, the cement slurry should be prevented from settling to reduce the concentration. The mixing time after each feeding should not be less than 3 minutes. The slurry should be poured into the collection hopper before pressing. The cement slurry should be used as soon as it is mixed.

[0076] Among them, when abnormal situations such as sudden drop, rise or large amount of slurry appear during high-pressure injection, the cause should be found out and timely measures should be taken.

[0077] In this embodiment, the waste slurry treatment is as follows: a lot of waste slurry will be generated during the high-pressure rotary jet grouting construction. In order to ensure the cleanliness of the site and smooth construction, a mud pool is planned to be set up in the site before construction. The mud is pumped into the mud pool during construction and transported out for treatment after the mud solidifies.

[0078] In this embodiment, when the high-pressure rotary jet grouting is completed, the grouting pipe should be quickly pulled out to thoroughly clean the rotary jet pipe and the grouting pump to prevent the rotary jet pipe and the grouting pump from being blocked by the solidification of the grouting liquid.

[0079] In this embodiment, the quality control measures for the first pile body 200 are as follows:

[0080] 1. Before jet grouting construction, the drilling rig should be placed stably and firmly, positioned accurately, the inclination of the jet grouting pipe should not exceed 1.5%, and the deviation of the pile center should not exceed 5 cm.

[0081] 2. Before the formal construction, a test pile should be made to determine the reasonable jet grouting parameters and slurry mix ratio. The jet grouting depth, diameter and compressive strength should meet the design requirements.

[0082] 3. In order to prevent the slurry from settling and segregating due to delayed treatment and to improve the strength of the composite consolidated body as soon as possible, 3% clay and an appropriate amount of early strength agent should be added.

[0083] 4. During the rotary jet grouting process, it is normal for the amount of slurry to be less than 20% of the grouting amount. If it exceeds 20% or no slurry is emitted at all, the cause should be found out, and the rotary jetting parameters should be adjusted or the nozzle diameter should be changed.

[0084] 5. The rotation and lifting of the drill rod must be continuous and uninterrupted. When disassembling and extending the drill rod or continuing the rotary spraying, the drill rod must have an overlap length of 10-20cm to avoid broken piles.

[0085] 6. During the high-pressure rotary jet grouting process, if the rotary jet grouting is interrupted due to mechanical failure, the pile should be re-drilled to the designed elevation of the bottom and the rotary jet grouting should be restarted.

[0086] 7. When making slurry, the water-cement ratio must be designed and strictly controlled and must not be changed at will. During the rotary spraying process, the slurry should be prevented from settling and concentration reduction, and damp or expired cement should not be used. When the slurry is sent to the suction bucket after stirring, it should be filtered with a filter screen, and the filter mesh should be smaller than 1 / 2 of the nozzle diameter.

[0087] 8. During the high-pressure rotary jet grouting process, if isolated rocks or large boulders are encountered, the pile position can be appropriately adjusted (according to the stress conditions, add columns if necessary) to avoid deformed piles and broken piles.

[0088] 9. Keep records of rotary grouting construction in accordance with regulations.

[0089] 10. Carry out quality inspection according to regulations, which can be carried out by methods such as core drilling, standard penetration, static load test, etc. The number of inspection points shall be handled in accordance with relevant specifications. Quality inspection shall be carried out 28 days after the completion of grouting, and those that fail the inspection shall be re-sprayed.

[0090] In this embodiment, the emergency measures for the first pile body 200 during construction are as follows:

[0091] 1. According to experience: it is normal for the amount of grouting from the hole to be less than 20% of the grouting amount. If it exceeds 20% or there is no grouting at all, the cause should be identified and corresponding measures should be taken.

[0092] 2. If the grouting is not caused by large gaps in the stratum, an appropriate amount of quick-setting agent can be added to the grout to shorten the time so that the grout solidifies within a certain range of the soil layer. In addition, the grouting volume can be increased in the gap area, and normal rotary spraying can be continued after the gaps are filled.

[0093] 3. The main reasons for excessive slurry bubbling are generally: the effective spraying range is not compatible with the grouting, and the grouting volume exceeds the slurry volume required for rotary grouting consolidation. There are three measures to reduce slurry bubbling: ① Increase the rotary grouting pressure. ② Appropriately reduce the nozzle aperture. ③ Speed ​​up the rotary grouting speed.

[0094] 4. During jet grouting, the pressure, flow rate and slurry volume should be measured, and the jet grouting and lifting of the drill rod must be continuous. When the drill rod is disassembled and the jet grouting is continued, it is necessary to keep the overlap length of the drill rod at 0.5m, and the jet consolidation body must not be disconnected.

[0095] In this embodiment, S2 includes the following steps:

[0096] S21: drilling a plurality of grouting holes 140 which are inclined and arranged at intervals along both sides of the box culvert 100 toward the bottom of the box culvert 100 .

[0097] S22: Grouting is performed on the plurality of grouting holes 140 to form a plurality of second pile bodies 300 .

[0098] S23: When the injection rate of the grouting section of the grouting hole 140 is not greater than 1 / min under the designed grouting pressure, grouting is continued for 30 minutes, and the grouting is terminated.

[0099] It is worth mentioning that, regarding S21: a plurality of grouting holes 140 are drilled at intervals along the axis of the closed curtain, and a single grouting hole 140 is located between two adjacent first pile bodies 200, and the interval between the two second pile bodies 300 is the diameter of the first pile body 200. In this way, the second pile body 300 formed by grouting the grouting hole 140 can cooperate with the first pile body 200 to form a support system on the bottom plate of the box culvert 100.

[0100] Among them, the grouting holes 140 are measured and placed by manual ruler to ensure that the error between the opening position and the designed hole position is less than 10 cm; the hole spacing between the multiple grouting holes 140 can be 0.7m, 0.75m, 0.8m, 0.85m, 0.9m and 1m, etc.

[0101] The grouting hole 140 is inclined at 40°, 43°, 45°, 47°, 50°, etc. relative to the bottom of the box culvert 100; the inclination angle of the grouting hole 140 relative to the box culvert 100 is selected according to actual conditions.

[0102] The grouting hole 140 is drilled with a 50 cm diameter diamond drill alloy drill to make the hole depth the same as the actual drilling depth, and then grouting is performed. After the slurry in the grouting hole 140 solidifies for 24 hours, the next stage of hole making and grouting is performed in the same manner as the contact stage.

[0103] Specifically, S22 includes the following steps:

[0104] S221: Use a grouting pipe with a diameter of 50 cm to perform segmented grouting of the grouting hole 140 from bottom to top.

[0105] Among them, the grouting pipe can be a metal grouting pipe made of steel pipe material with a diameter of 50cm; among them, the water-cement ratio of cement slurry is 1.0, and the grouting volume and grouting effective range should be determined through on-site grouting tests.

[0106] S222: Grouting is performed at a distance of at least 0.5 m between the grouting pipe and the bottom of the grouting hole 140 .

[0107] Among them, when the grouting pipe is 0.5m away from the bottom of the grouting hole 140, a grouting plug is inserted 0.5m away from the grouting bottom to prevent leakage.

[0108] It is worth mentioning that the grouting pressure is 1.0-1.5MPa. When grouting, the design pressure should be reached as soon as possible. Pay attention to controlling the pressure during the grouting process: the pressure during grouting should be adapted to the injection rate. The grouting pressure is based on the pressure gauge reading of the orifice return grouting pipe, and the pressure gauge reading is the median value of the pressure gauge pointer swing.

[0109] In this embodiment, regarding the grouting method and grouting mode for grouting the grouting hole 140, this grouting adopts a circular, top-down segmented grouting. At the same time, after each segment of grouting is completed, it must be set for 24 hours before the next segment of construction can be carried out.

[0110] In this embodiment, regarding the slurry and changes for grouting the grouting hole 140: A. the water-cement ratio (weight ratio) of the cement slurry is 1:1, and the water-cement ratio of the initial injection is 2:1.

[0111] B. During the grouting process, the grouting pressure remains unchanged and the injection rate continues to decrease, or when the injection rate remains unchanged and the pressure continues to increase, the water-cement ratio of the slurry does not change.

[0112] C. When the injection volume of a certain level of slurry reaches more than 300L or the grouting time has reached more than 1h, and the grouting pressure or injection rate has not changed or the change is not significant, the grouting can be changed to a slurry with a higher water-cement ratio.

[0113] D. When the injection rate is greater than 301 / min, the water-cement ratio can be increased step by step.

[0114] E. Grouting uses pure cement slurry. When the injection volume of the grouting section is large and it is difficult to complete the grouting, you can use: 1. Low pressure, thick slurry, limited flow, limited quantity, intermittent grouting. 2. The slurry can be mixed with accelerators, such as water glass. 3. Stable slurry or mixed slurry can be poured.

[0115] In this embodiment, regarding the grouting end standard: A. When the injection rate of the grouting section of the grouting hole 140 is not greater than 1 / min under the designed grouting pressure, continue to grout for 30 minutes, and the grouting is ended. B. When the end standard is not met for a long time, it should be reported to the on-site construction personnel in time, and the project department should issue a treatment plan. C. The "pressure grouting sealing method" is used to seal the grouting hole 140. After the cement slurry in the hole solidifies, the upper mortar is smoothed.

[0116] In this embodiment, regarding the quality inspection of the grouting of the flower tube: A. The water pressure test of the inspection hole of the flower tube grouting should be carried out 14 days after the grouting of the part is completed. B. The quality inspection is based on the water permeability of the water pressure test, and is comprehensively evaluated in combination with the grouting records and results analysis. C. The layout of the inspection hole is determined by the on-site technicians based on the comprehensive analysis of the grouting data. D. The number of inspection holes should be 5% of the total number of grouting holes 140. At least one inspection hole should be arranged in a section or a process.

[0117] In this embodiment, the quality measures for the second pile body 300 are as follows:

[0118] A. Drilling quality control:

[0119] 1. Hole position layout: first use a measuring instrument to measure the axis of the closed curtain, and set control points every 50m along the axis of the closed curtain, and then use a ruler to layout. The hole position deviation should not exceed 10cm.

[0120] 2. Ensure the accuracy of the direction of the curtain grouting hole 140. After drilling each grouting section, measure the inclination and correct it in time if deviation occurs.

[0121] B. Slurry quality control:

[0122] 1. Strictly control the accuracy of water-cement ratio at all levels. After the slurry delivered by the centralized slurry station is diluted, the slurry specific gravity is measured. The measured slurry specific gravity meets the standard specific gravity of slurry at each level of water-cement ratio before use.

[0123] 2. After grouting of the grouting hole 140 begins, when the return slurry pipe appears, measure the return slurry density in time. When the return slurry density is close to that of the incoming slurry, increase the pressure for grouting.

[0124] 3. During the grouting process of the grouting hole 140, measure the return slurry density every 10 minutes and observe the change of the return slurry density in time. If it is found that the return slurry becomes thicker, find out the reason immediately and take timely measures.

[0125] 4. Pressure control during grouting of grouting hole 140: During the grouting process, ensure that the grouting pressure meets the designed grouting pressure and take the following control measures: a. Select a suitable pressure gauge; the maximum value of the pressure gauge is 1.5 times the grouting pressure, and the use range of the pressure gauge pointer is 1 / 3-2 / 3 of the maximum range: during high-pressure grouting, the maximum range of the pressure gauge is 2-2.5 times the grouting pressure. b. The pressure gauge is used after identification and calibration to ensure accurate measurement. c. The grouting pressure is based on the pressure on the return grouting pipe to control the grouting pressure. d. During the grouting process, when the return grouting has the same slurry specific gravity as the incoming grouting, immediately increase the pressure to ensure that the toe plate mixed soil is not lifted and deformed, and increase to the designed pressure in a relatively short time.

[0126] 5. Strictly control the end standard of grouting: under the designed grouting pressure, the injection rate meets the standard and reaches the prescribed grouting time before grouting is ended. Grouting shall not be ended prematurely.

[0127] 6. Before grouting with water gushing pressure, measure the water gushing pressure, correct the grouting pressure, and plug the grouting for 24 hours after the grouting is completed.

[0128] In this embodiment, the structure of the box culvert 100 and the deformation joint are processed as follows:

[0129] 1. Clean the base layer, remove all the original materials and impurities in the expansion joint to the rubber water stop, and remove the irregular parts of the expansion joint until they are consistent from top to bottom.

[0130] 2. If there is a deformation joint where the rubber waterstop is cracked in the settlement culvert 100, a 30mm thick wooden block should be used to intercept the crack inside the culvert 100, and then the water should be filled to the inside of the rubber waterstop with water. After completion, a water-expandable waterstop strip should be placed, and the waterstop strip should be trimmed and placed in the center according to the width of the deformation joint.

[0131] 3. After fixing the expansion waterstop strip, fill the upper part with watertight material. Leave 30mm outside as required by the drawing. When the watertight material reaches the required strength, remove the internal wood.

[0132] 4. Use low modulus two-component polysulfide sealing paste material to seal both the inside and outside according to the requirements of the drawings.

[0133] 5. After the sound sealing is completed, the height difference between the bottom plate and the top plate of the two box culverts with a settlement of 100 is filled with C20 fine stone concrete to make a gentle slope.

[0134] 6. The uneven settlement of box culvert 100 caused local sinking at the deformation joint, resulting in depressions. After the foundation reinforcement of box culvert 100 was completed, the depressions were filled with C20 concrete with a single-layer bidirectional steel mesh with a diameter of 6 cm to level the slope.

[0135] In summary, the embodiment of the present invention provides a method for reinforcing a box culvert 100, by setting a first pile body 200, half of the first pile body 200 formed by piling is in the side wall of the box culvert 100, and the other half is in the foundation at the bottom of the box culvert 100, so that a support system can be formed for the bottom plate of the box culvert 100, and this reinforcement method can accurately reinforce the foundation of the sunken section of the box culvert 100, and lift the sunken box culvert 100 within a certain range, which can increase the bearing capacity of the foundation at the bottom of the box culvert 100; at the same time, multiple first pile bodies 200 form an effective blockade for the area of ​​the box culvert 100 that needs to be reinforced, and multiple first pile bodies 200 can form a closed curtain for the foundation of the box culvert 100, and the closed curtain can prevent water from entering from the outside, and can also block the grouting liquid from spreading outward at will, and form pressure within the foundation range of the box culvert 100.

[0136] At the same time, this reinforcement method uses simple equipment, has high reinforcement efficiency, and can accurately reinforce weak points of the foundation; the existing materials of the foundation are used for mixed reinforcement, which saves materials and reduces carbon energy.

[0137] Furthermore, by inserting oblique steel flower pipes on both sides of the box culvert 100 for double-liquid grouting reinforcement, this reinforcement method can further accurately reinforce the foundation of the sunken section of the box culvert 100, and the sunken box culvert 100 can be lifted within a certain range.

[0138] The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims

1. A box culvert reinforcement method, characterized in that: include: Working surfaces are dug out at the side walls of both sides of the box culvert, and a plurality of pile holes arranged at intervals are drilled along the working surfaces. The plurality of pile holes are piled to form a plurality of first pile bodies, and the plurality of first pile bodies form closed curtains on both sides of the box culvert.

2. The box culvert reinforcement method according to claim 1, characterized in that: Drilling a plurality of inclined and spaced grouting holes along both sides of the box culvert toward the bottom of the box culvert; The plurality of grouting holes are formed by grouting.

3. The box culvert reinforcement method according to claim 2, characterized in that: The step of grouting the plurality of grouting holes comprises: The grouting holes are grouted in sections from bottom to top using a grouting pipe with a diameter of 50 cm; The grouting pipe is at least 0.5m away from the bottom of the grouting hole for grouting.

4. The box culvert reinforcement method according to claim 2, characterized in that: A plurality of grouting holes are drilled at intervals along the axis of the closed curtain, and a single grouting hole is located between two adjacent first pile bodies.

5. The box culvert reinforcement method according to claim 2, characterized in that: The hole spacing between the plurality of grouting holes is 0.7m-1m; The grouting hole is inclined at 40°-50°; The grouting pressure is 1.0-1.5MPa.

6. The box culvert reinforcement method according to claim 1, characterized in that: The width of the working surface ranges from 4 to 5 m, and the depth of the working surface ranges from 5 to 6 m.

7. The box culvert reinforcement method according to claim 1, characterized in that: The plurality of piling holes are arranged in sequence and at equal intervals along the extension direction of the working surface, the interval between adjacent piling holes is 0.7-0.9 m, and the diameter of the piling holes is 0.7-0.9 m; The depth of the first pile body is 10-12m.

8. The box culvert reinforcement method according to claim 1, characterized in that: Horizontal layout is performed on the working surface, and a plurality of pile holes are drilled at intervals along the horizontal layout by a drilling rig, the drill rod head of the drilling rig is perpendicular to the working surface, and the center of the drill rod head is coaxial with the center of the pile hole.

9. The box culvert reinforcement method according to claim 8, characterized in that: The step of driving piles into the plurality of pile holes to form a plurality of first pile bodies comprises: Move the rotary spraying machine, insert the rotary spraying pipe into the piling hole, and perform test spraying; After the test spraying is completed, the rotary spraying pipe is inserted into the pile hole to carry out high-pressure rotary spraying grouting; The rotary jet grouting machine is moved to the next piling hole until high-pressure rotary jet grouting is completed for all the piling holes.

10. The box culvert reinforcement method according to claim 9, characterized in that: The step of inserting the jet grouting pipe into the piling hole for high-pressure jet grouting comprises: Inserting the rotary spraying pipe into the pile hole, and when the rotary spraying pipe reaches a predetermined spraying pressure, lifting the rotary spraying pipe from bottom to top to perform rotary spraying on the pile hole; The rotary spraying pipe is first sprayed, and then rotated and lifted; When the jet spraying pipe is lifted to a depth of at least 1 m below the designed top of the first pile body, the lifting speed is slowed down until the designed elevation of the first pile body is reached.