Open hole horizontal well fracturing production integrated pipe column and using method thereof
By designing the integrated pipe column for the production of open-hole horizontal well fracturing and integrating fracturing and production mining functions, the problem that the segmented fracturing filling technology of open-hole horizontal well in the existing technology cannot effectively prevent sand, and the segmented sand prevention of the wellbore is realized and selective mining reduces sand production risks and construction costs.
Patent Information
- Application Number
- CN202411061138.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-05
AI Technical Summary
In the prior art, the segmented fracturing and filling technology of open-hole horizontal wells cannot effectively prevent sand, and there is a risk of premature sand output, and the construction cost is high, which cannot meet the demand for well conditions with low rupture pressure of long horizontal wells and formations.
Design an integrated pipe column for the production of open-hole horizontal well fracturing, integrating fracturing and production and mining functions. It realizes segmented separation and selective mining of the wellbore through multiple naked-hole packers and filling slip sleeves to reduce sand output risk and simplify operational processes.
Effective sectional sand prevention and selective mining and production of the wellbore is achieved, which reduces the risk of sand output, increases the initial production capacity of well completion, reduces construction costs, and does not require additional sand prevention and mining columns.
Smart Images

Figure CN118958936A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of oil and gas exploitation, and in particular relates to an open hole horizontal well fracturing production integrated pipe string and a use method thereof. Background Art
[0002] As some oilfields enter the middle and late stages of production, the water content of production continues to increase, the production pressure difference and the intensity of liquid production continue to increase, the sand production problem of oil wells continues to intensify, and the screen blockage problem becomes more and more serious. Gravel packing sand control has been used more and more widely in recent years. It has achieved good results, especially for open hole horizontal wells. Gravel packing sand control can significantly extend the completion life.
[0003] Horizontal well staged fracturing technology can effectively increase production, but lacks long-term and effective sand control methods, and there is a risk of premature sand production in sand-producing reservoirs. Openhole horizontal well filling and sand control technology is currently the most commonly used openhole horizontal well sand control method. Its principle is that the sand-carrying fluid brings the filling gravel into the annulus between the screen and the well wall. The liquid passes through the screen filter layer and returns to the ground through the flushing pipe. The filling gravel remains in the annulus between the screen and the well wall to support the well wall and prevent sand. However, openhole horizontal well filling and sand control has high requirements on the length of the horizontal well openhole section and the formation fracture pressure. The construction risk is high for long horizontal wells or wells with low formation fracture pressure, and it cannot meet the needs of horizontal well stratified sand control. In addition, for the later refined stratified mining, it is necessary to lower the stratified mining production string for the second time, and the construction cost is high.
[0004] The sliding sleeve packer staged fracturing technology uses multi-stage packers for stratification, with fracturing sleeves between the packers, and provides a fracturing channel through the switch of the fracturing sleeve. The fracturing sleeve is usually opened by throwing a ball. There is a ball seat inside the sleeve. The smallest ball seat is installed in the sleeve at the bottom, and the largest ball seat is installed in the top ball seat. Low-density fracturing balls of different sizes are put in, and then the balls are pumped to the corresponding ball seats. The fracturing sleeve is opened by pressurizing the oil pipe, and the corresponding layer is fractured. Multiple layers of fixed pipe string fracturing can be completed at one time. However, the sliding sleeve packer staged fracturing is only suitable for fracturing construction in medium and low permeability formations, and can only achieve fracturing production increase operations, but cannot achieve effective sand control in the wellbore. It is necessary to specially lower the sand control pipe string to perform sand control operations on the wellbore.
[0005] It can be seen from this that the openhole horizontal well segmented fracturing and filling technology in the related technology is a general filling and sand prevention technology for openhole horizontal wells, which cannot effectively segment the horizontal section, and the edge and bottom water reservoirs will see water prematurely. For oil wells with long horizontal sections and low formation fracture pressure, the filling effect cannot be guaranteed, and there is a risk of premature sand production. At the same time, the openhole horizontal well segmented filling technology cannot perform large-volume extrusion, and the production capacity is limited in the initial stage of production. It needs to be equipped with a separate production string, the inner diameter of the well is small, and the later processing is difficult. In addition, the lower completion production string needs to be lowered separately, and the operation process is complicated and the construction cost is high. Summary of the invention
[0006] In order to solve all or part of the above problems, the purpose of the present invention is to provide an integrated open hole horizontal well fracturing production string and a method of using the same, which integrates fracturing filling and production and mining functions, can achieve effective segmentation, sand control and selective mining and production, ensure the filling effect, reduce the risk of sand production, and improve the initial production capacity of the well completion. There is no need to additionally run sand control strings and production strings, which simplifies the operation process and reduces construction costs.
[0007] In a first aspect, the present invention provides an integrated tubular string for fracturing production of open hole horizontal wells, comprising a center tubular string and a tool tubular string, wherein the center tubular string comprises a top packer, a first sealing cylinder, a quick connector, a filling production assembly, a locking sealing assembly and a floating shoe assembly connected in sequence from top to bottom;
[0008] There are multiple packing production assemblies, and two adjacent packing production assemblies are connected through an open hole packer, and each packing production assembly includes a circulation sleeve, a first double-layer screen, a production sleeve, a second double-layer screen, a second sealing cylinder, a packing sleeve and a positioning collar, which are connected in sequence from top to bottom;
[0009] The tool string includes a top setting tool, a test sealing rod, a tieback rod, a tieback tool, a filling control tool, a filling sleeve closing tool, a positioning tool, a filling sleeve switching tool, a circulation sleeve single closing tool, a circulation sleeve single opening tool, a positioning sealing rod and a shear sleeve, which are connected in sequence from top to bottom;
[0010] The top sealing tool is used to control the sealing of the top packer, the test sealing rod is used to cooperate with the first sealing cylinder to achieve the sealing of the annulus between the center pipe string and the tool pipe string, the tie-back tool is used to connect with the tie-back rod, and the tie-back tool can cooperate with the locking seal assembly to form a temporary lock, the filling control tool is used to control the opening and closing of its own flow channel, the positioning tool is used to cooperate with the positioning joint hoop to achieve the positioning of the center pipe string, and the shear sleeve is used to seal the bottom end of the tool pipe string.
[0011] Optionally, the locking and sealing assembly includes a locking cylinder and a third sealing cylinder, the third sealing cylinder is connected to the bottom of the locking cylinder, the locking cylinder is connected to the positioning collar of the lowest layer, and the locking cylinder can cooperate with the reconnection tool to achieve temporary locking.
[0012] Optionally, the float shoe assembly includes a liquid-proof lock sealing cylinder and a float shoe, the liquid-proof lock sealing cylinder is connected to the bottom of the third sealing cylinder, and the float shoe is connected to the bottom of the liquid-proof lock sealing cylinder.
[0013] In a second aspect, the present invention provides a method for using an open hole horizontal well fracturing production integrated tubing string, comprising the following steps:
[0014] S1, connect the center string and the tool string, lower the center string into the wellbore, and lower the tool string into the center string;
[0015] S2, during the lowering of the tool string, the tool string is pressurized by external pressure equipment to flush the residual sediment in the open hole horizontal well section with liquid;
[0016] S3, controls the setting of the top packer;
[0017] S4, top packer seal inspection;
[0018] S5, controlling the multiple open hole packers to be set separately, so that the multiple open hole packers separate the wellbore into multiple layers from bottom to top;
[0019] S6, bottom open hole packer seal inspection;
[0020] S7, verification of closing of the secondary bottom filling sleeve;
[0021] S8, performing fracturing and filling operations on the bottom area of the wellbore;
[0022] S9, reverse circulation well washing, cleaning the residual mortar in the wellbore;
[0023] S10, bottom filling sleeve closing verification;
[0024] S11, lifting the tool string to the corresponding layer of the oil well, and repeating steps S6-S10 until each layer of the oil well is completed with fracturing filling, reverse circulation well washing, and filling sleeve closing verification;
[0025] S12, through the tool string, the production sleeve and the circulation sleeve of the corresponding layer in the well are controlled to open, so as to realize the selective production and exploitation of the oil well.
[0026] Optionally, in S1:
[0027] Connecting the center string includes: connecting the top packer to the first sealing cylinder, and connecting the floating shoe to the locking cylinder in sequence from bottom to top, selecting a corresponding number of packing production assemblies according to the depth of the oil well, connecting two adjacent packing production assemblies through the open hole packer, connecting the locking cylinder to the bottommost positioning collar, and connecting the quick connector to the topmost circulating sleeve;
[0028] Ensure that the circulation sleeve, production sleeve and filling sleeve in each filling production assembly are in the closed state respectively, fill each first double-layer screen pipe and second double-layer screen pipe with liquid respectively to ensure the balance of internal and external pressures, and conduct pressure test on each filling production assembly respectively to ensure the sealing of the connection;
[0029] Connecting the tool string includes: connecting the shear sleeve to the tieback tool in sequence from bottom to top, and lowering it into the center string until the tieback tool and the locking cylinder are temporarily locked, then connecting the test sealing rod with the tieback rod, and connecting the test sealing rod with the drill rod, using the drill rod to carry the test sealing rod and the tieback rod into the center string until the tieback rod and the tieback tool are connected, and then lifting the tool string to unlock the tieback tool and the locking cylinder;
[0030] When the tie-back tool is unlocked, the tool string is pressure tested, and then the drill pipe is pressurized to the set pressure through external pressure equipment to cut the shear pins in the shear sleeve to achieve communication between the tool string and the center string. Subsequently, the first sealing cylinder is connected to the quick connector and the tool string is lowered.
[0031] Optionally, in S2:
[0032] During the lowering of the tool string, the drill pipe is pressurized by external pressure equipment, so that the liquid flows from the top setting tool to the shear sleeve in sequence, then flows through the float shoe, and returns through the annulus between the center string and the wellbore to flush the residual mud and sand in the open hole horizontal well section.
[0033] Optionally, in S3:
[0034] A steel ball of set size is dropped and the drill pipe is pressurized by an external pressurizing device until the steel ball shears the ball seat in the filling control tool to open the channel in the filling control tool. The pressure is then increased to the set pressure until the top packer is seated. Subsequently, the pressure is increased to the set pressure to release the top sealing tool and the top packer, thereby releasing the lock between the center string and the tool string.
[0035] Optionally, in S4:
[0036] Lift the tool string until the test sealing rod is located in the first sealing cylinder. The test sealing rod and the first sealing cylinder seal the annulus between the tool string and the center string. Pressurize the annulus between the tool string and the center string to the set pressure through external pressurizing equipment, observe whether there is liquid returning from the annulus, and determine whether the top packer is sealed.
[0037] Optionally, in S5:
[0038] The tool string is lifted until the reverse circulation hole of the filling control tool is sealed in the sealing tube of the bottom filling sleeve, and the annulus between the center string and the tool string is pressurized to the set pressure through the external pressure equipment to complete the setting of all open hole packers.
[0039] Optionally, in S6:
[0040] Lift the tool string to make the positioning tool and the secondary bottom positioning collar cooperate and position, mark the secondary bottom filling positioning position, and continue to lift the tool string to make the filling sleeve switch tool be located above the secondary bottom filling sleeve, and at the same time, the circulation sleeve single opening tool be located above the bottom circulation sleeve;
[0041] The tool string is lowered to the secondary bottom filling positioning position, the filling sleeve switch tool controls the secondary bottom filling sleeve to open, the circulating sleeve single opening tool controls the bottom circulating sleeve to open, the drill pipe is pressurized by external pressure equipment, the liquid flows from the drill pipe to the secondary bottom filling sleeve in turn, and then enters the annulus between the center string and the wellbore through the filling channel of the secondary bottom filling sleeve, observe whether there is liquid returning from the annulus, and judge whether the bottom open hole packer is sealed.
[0042] Optionally, in S7:
[0043] Lift the tool string so that the filling sleeve closing tool is located above the secondary bottom filling sleeve, and then lower the tool string to the secondary bottom filling positioning position, so that the filling sleeve closing tool closes the secondary bottom filling sleeve, and pressurizes the drill pipe to the set pressure through external pressure equipment. The liquid flows from the drill pipe to the filling port of the filling control tool in sequence, and then enters the annulus between the bottom filling sleeve and the filling control tool. Observe whether there is liquid returning from the annulus to determine whether the secondary bottom filling sleeve is closed.
[0044] Optionally, in S8:
[0045] The tool string is lowered until the positioning tool and the bottom positioning collar are positioned together, and the bottom filling positioning position is marked. At this time, the filling sleeve switch tool opens the bottom filling sleeve, and the mortar is pumped into the drill pipe through the external pressure equipment. The mortar flows through the drill pipe to the filling port of the filling control tool in sequence, and then enters the bottom filling sleeve, and enters the annulus between the center string and the wellbore through the filling channel of the bottom filling sleeve. As the filling operation continues, the mortar is gradually filled upwards until the mortar completely fills the bottom area of the wellbore.
[0046] Optionally, in S9:
[0047] Lift the tool string, and pump the well-washing fluid into the annulus between the center string and the tool string through the external pressure equipment. The well-washing fluid enters the inner wall channel through the reverse circulation hole of the filling control tool, and then enters the backwashing ball valve through the double-through interlayer of the filling control tool, and enters the annulus between the center string and the tool string through the discharge channel of the filling control tool, and then enters the inner cavity through the filling port of the filling control tool, and then flows upward and returns to the wellhead through the drill pipe, preliminarily backwashing the excess mortar in the annulus between the filling control tool and the bottom filling sleeve;
[0048] Continue to lift the tool string until the reverse circulation hole of the filling control tool is sealed in the sealing tube of the secondary bottom circulation sleeve. At this time, the filling sleeve closing tool closes the bottom filling sleeve, and the circulation sleeve single closing tool closes the bottom circulation sleeve. A large amount of well washing fluid is pumped into the annulus between the center string and the tool string through the external pressure equipment. The large-volume well washing fluid enters the inner cavity of the filling control tool through the filling port, then flows upward and returns to the wellhead through the drill pipe, completely cleaning the residual mortar in the well.
[0049] Optionally, in S10:
[0050] Lower the tool string to the bottom filling positioning position, pressurize the drill pipe to the set pressure through the external pressure equipment, observe whether there is liquid return in the annulus, and determine whether the bottom filling sleeve is closed.
[0051] Optionally, in S11:
[0052] According to the number of filling production assemblies, lift the tool string to position the positioning tool and the third-to-last positioning collar, mark the third-to-last filling positioning position, repeat S6-S10 until the second-to-last layer area of the wellbore completes fracturing filling, reverse circulation well washing and filling sleeve closure verification, repeat this process until the top layer area of the oil well completes fracturing filling, reverse circulation well washing and filling sleeve closure verification, then execute S12.
[0053] It can be seen from the above technical scheme that the open hole horizontal well fracturing production integrated pipe string and its use method provided by the present invention have the following advantages:
[0054] The device integrates fracturing filling and production and mining functions, and can achieve effective segmentation, sand prevention and selective mining and production of the wellbore, ensure the filling effect, reduce the risk of sand production, and improve the initial production capacity of the well completion. At the same time, this design does not require the additional insertion of sand prevention and sub-production strings, reducing construction costs. Not only that, the simple operation of external pressure and lifting and releasing the tool string can realize the control of the setting of the packer and the opening and closing of the filling sleeve and other components, simplifying the operation process and improving work efficiency.
[0055] Other features and advantages of the present invention will be set forth in the description which follows. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] The accompanying drawings are used to provide a further understanding of the technical solution of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the technical solution of the present invention and do not constitute a limitation on the technical solution of the present invention.
[0057] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present invention;
[0058] Figure 2 Schematic diagram of the structure of the central column in an embodiment of the present invention;
[0059] Figure 3 A schematic diagram of the structure of a tool string in an embodiment of the present invention;
[0060] Figure 4 It is a structural schematic diagram of an embodiment of the present invention, showing the positional relationship between the tie-back tool and the locking cylinder;
[0061] Figure 5 It is a structural schematic diagram of an embodiment of the present invention, showing the fracturing filling state;
[0062] Figure 6 It is a schematic diagram of the structure of an embodiment of the present invention, showing the initial backwashing state;
[0063] Figure 7 It is a schematic diagram of the structure of an embodiment of the present invention, showing a large-displacement backwash state.
[0064] Description of reference numerals:
[0065] 1. Top packer; 2. First sealing cylinder; 3. Quick connector; 4. Filling production assembly; 41. Circulation sleeve; 411. Filling channel; 42. First double-layer screen; 43. Production sleeve; 44. Second double-layer screen; 45. Second sealing cylinder; 46. Filling sleeve; 47. Positioning collar; 5. Locking seal assembly; 51. Locking cylinder; 52. Third sealing cylinder; 6. Floating shoe assembly; 61. Liquid-proof lock sealing cylinder; 62. Floating shoe; 7. Open hole packer; 8. Top setting tool; 9. Test sealing rod; 10. Tieback rod ; 11. Tieback tool; 111. Shear pin; 112. Elastic sleeve; 12. Filling control tool; 121. Filling port; 122. Reverse circulation hole; 123. Sandwich wall channel; 124. Double-through interlayer; 125. Backwash ball valve; 126. Drain channel; 13. Filling sleeve closing tool; 14. Positioning tool; 15. Filling sleeve switching tool; 16. Circulation sleeve single closing tool; 17. Circulation sleeve single opening tool; 18. Positioning sealing rod; 19. Shear sleeve; 100. Center pipe string; 200. Tool pipe string. DETAILED DESCRIPTION
[0066] To make the purpose, technical solution and advantages of the present invention more clear, the embodiments of the present invention will be described in detail with reference to the accompanying drawings. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other arbitrarily without conflict.
[0067] like Figure 1-Figure 7The embodiment of the present invention is shown, which discloses an integrated pipe string for fracturing production of open hole horizontal wells, including a center pipe string 100 and a tool pipe string 200. The center pipe string 100 is used to be lowered into the wellbore, and the tool pipe string 200 is used to be lowered into the center pipe string 100 and used as a service tool for the center pipe string 100. In this embodiment, in order to more clearly show the liquid flow direction in the annulus between the center pipe string 100 and the tool pipe string 200, the size of the tool pipe string 200 in the figure is appropriately reduced.
[0068] In one embodiment, Figure 1 , Figure 2 As shown, the central pipe string 100 includes a top packer 1, a first sealing cylinder 2, a quick connector 3, a packing production assembly 4, a locking sealing assembly 5 and a floating shoe assembly 6 which are sequentially connected from top to bottom. There are multiple packing production assemblies 4, and two adjacent packing production assemblies 4 are connected through an open hole packer 7. The number of packing production assemblies 4 can be selected according to the actual wellbore depth. This embodiment only shows the state of two packing production assemblies 4.
[0069] In one embodiment, Figure 1 , Figure 2 As shown, each filling production assembly 4 includes a circulation sleeve 41, a first double-layer screen pipe 42, a production sleeve 43, a second double-layer screen pipe 44, a second sealing cylinder 45, a filling sleeve 46 and a positioning collar 47 which are connected in sequence from top to bottom. The quick connector 3 is connected to the uppermost circulation sleeve 41, and the locking seal assembly 5 is connected to the lowermost positioning collar 47.
[0070] In one embodiment, Figure 1 , Figure 3 As shown, the tool string 200 includes a top sealing tool 8, a test sealing rod 9, a tie-back rod 10, a tie-back tool 11, a filling control tool 12, a filling sleeve closing tool 13, a positioning tool 14, a filling sleeve switching tool 15, a circulation sleeve single closing tool 16, a circulation sleeve single opening tool 17, a positioning sealing rod 18 and a shear sleeve 19, which are connected in sequence from top to bottom.
[0071] In one embodiment, Figure 1 , Figure 2 , Figure 3As shown, the top sealing tool 8 is used to control the sealing of the top packer 1, and the test sealing rod 9 is used to cooperate with the first sealing cylinder 2 to achieve the sealing of the annulus between the central pipe string 100 and the tool pipe string 200, so as to facilitate the subsequent sealing test of the top packer 1. The tie-back tool 11 is used to connect with the tie-back rod 10, and the tie-back tool 11 can cooperate with the locking seal assembly 5 to form a temporary lock, the filling control tool 12 is used to control the opening and closing of its own flow channel, the positioning tool 14 is used to cooperate with the positioning collar 47 to achieve the positioning of the central pipe string 100, and the shear sleeve 19 is used to seal the bottom end of the tool pipe string 200, so as to facilitate the pressure test of the tool pipe string 200.
[0072] The open hole horizontal well fracturing production integrated tubing string in this embodiment integrates the functions of fracturing filling and production and exploitation. By setting the open hole packer 7, effective segmentation of the wellbore and selective exploitation and production can be achieved. At the same time, effective segmentation of the wellbore can improve the sand control effect, ensure the filling effect, reduce the risk of sand production in the oil well, and improve the initial production capacity of the well completion.
[0073] In one embodiment, Figure 1 , Figure 2 As shown, the locking sealing assembly 5 includes a locking cylinder 51 and a third sealing cylinder 52. The third sealing cylinder 52 is connected to the bottom of the locking cylinder 51. The locking cylinder 51 is connected to the bottommost positioning collar 47, and the locking cylinder 51 can cooperate with the reconnection tool 11 to achieve temporary locking.
[0074] In one embodiment, Figure 1 , Figure 2 As shown, the float shoe assembly 6 includes a liquid-proof lock sealing cylinder 61 and a float shoe 62. The liquid-proof lock sealing cylinder 61 is connected to the bottom of the third sealing cylinder 52, and the float shoe 62 is connected to the bottom of the liquid-proof lock sealing cylinder 61. The liquid-proof lock sealing cylinder 61 can effectively prevent the liquid from forming a liquid lock inside the sealing cylinder, thereby avoiding equipment failure or operation failure caused by liquid lock, so that the tool string 200 can be flushed and lowered (for details on the flushing and lowering operation, see the usage method section).
[0075] This embodiment also discloses a method for using an integrated pipe string for fracturing production in an open hole horizontal well, comprising the following steps:
[0076] S1 , connecting the central pipe string 100 and the tool pipe string 200 , lowering the central pipe string 100 into the wellbore, and lowering the tool pipe string 200 into the central pipe string 100 .
[0077] Connecting the center pipe string 100 includes: connecting the top packer 1 to the first sealing cylinder 2, and connecting the floating shoe 62 to the locking cylinder 51 from bottom to top, selecting a corresponding number of filling production assemblies 4 according to the depth of the oil well, and connecting two adjacent filling production assemblies 4 through the open hole packer 7 respectively, then connecting the locking cylinder 51 to the bottommost positioning collar 47, and connecting the quick connector 3 to the topmost circulating sleeve 41.
[0078] During the connection process of the center pipe column 100, the circulation sleeve 41, the production sleeve 43 and the filling sleeve 46 in each filling production assembly 4 are ensured to be in a closed state respectively. At the same time, each first double-layer screen pipe 42 and the second double-layer screen pipe 44 are respectively filled with liquid to ensure the balance of internal and external pressures, and each filling production assembly 4 is pressure tested respectively to ensure the sealing of the connection.
[0079] The connecting tool string 200 includes: connecting the shear sleeve 19 to the tie-back tool 11 in sequence from bottom to top, and lowering it into the center string 100 until the tie-back tool 11 and the locking cylinder 51 are temporarily locked, and then connecting the test sealing rod 9 to the tie-back rod 10, and connecting the test sealing rod 9 to the drill pipe.
[0080] like Figure 4 As shown, the test sealing rod 9 and the tie-back rod 10 are carried by the drill pipe and lowered into the central pipe column 100 until the tie-back rod 10 is connected to the tie-back tool 11, and then the tool column 200 is lifted to cut off the shear pin 111 in the tie-back tool 11 and move the elastic sleeve 112 in the tie-back tool 11 downward to unlock the tie-back tool 11.
[0081] When the tie-back tool 11 is unlocked, the tool string 200 is pressure tested by an external pressure test device. During the pressure test, the shear pins are sheared off to seal the bottom port of the tool string 200. After the pressure test, the drill pipe is pressurized to a set pressure by an external pressure test device to shear off the shear pins in the shear sleeve 19 to achieve communication between the tool string 200 and the center string 100. Subsequently, the first sealing cylinder 2 is connected to the quick connector 3, and the tool string 200 is lowered.
[0082] S2, during the lowering of the tool string 200, the tool string 200 is pressurized by an external pressurizing device, and the residual sediment in the open hole horizontal well section is flushed with liquid.
[0083] When the tool string is lowered, the drill pipe is pressurized by an external pressurizing device, so that the liquid flows downward from the top sealing tool 8 to the shear sleeve 19 in sequence, then flows through the float shoe 62, and returns through the annulus between the center string 100 and the wellbore to flush the residual sediment in the open hole horizontal well section.
[0084] S3, control the top packer 1 to be set.
[0085] A steel ball of a set size is dropped, and the drill pipe is pressed by an external pressurizing device until the steel ball shears the ball seat in the filling control tool 12, so that the channel in the filling control tool 12 is opened. Subsequently, the pressure is continuously increased to the set pressure until the top packer 1 is set. Next, the pressure is continuously increased to the set pressure, so that the top setting tool 8 and the top packer 1 are released, so as to release the lock between the center string 100 and the tool string 200.
[0086] S4, top packer 1 seal inspection.
[0087] The tool string 200 is lifted until the test sealing rod 9 is located in the first sealing cylinder 2. At this time, the test sealing rod 9 and the first sealing cylinder 2 seal the annulus between the tool string 200 and the center string 100. Subsequently, the annulus between the tool string 200 and the center string 100 is pressurized to a set pressure by an external pressurizing device to observe whether there is liquid return in the annulus. If there is no liquid return in the annulus, it proves that the top packer 1 is well sealed. Otherwise, it proves that the top packer 1 is not completely sealed and the top packer 1 needs to be re-sealed.
[0088] S5, controlling the multiple open hole packers 7 to be set separately, so that the multiple open hole packers 7 separate the wellbore into multiple layers from bottom to top.
[0089] The tool string 200 is lifted up until the reverse circulation hole 122 of the filling control tool 12 is sealed in the sealing tube of the bottom filling sleeve 46, and the annulus between the center string 100 and the tool string 200 is pressurized to the set pressure through the external pressurizing equipment. At this time, all the open hole packers 7 can be sealed under the action of pressure.
[0090] S6, bottom open hole packer 7 seal inspection.
[0091] Lift the tool string 200 to position the positioning tool 14 and the secondary bottom positioning collar 47, and mark the secondary bottom filling positioning position. Continue to lift the tool string 200 to position the filling sleeve switch tool 15 above the secondary bottom filling sleeve 46, and at the same time, the circulation sleeve single opening tool 17 above the bottom circulation sleeve 41.
[0092] Then, the tool string 200 is lowered to the secondary bottom filling positioning position. During this process, the filling sleeve switch tool 15 controls the secondary bottom filling sleeve 46 to open, and the circulation sleeve single opening tool 17 controls the bottom circulation sleeve 41 to open. Next, the drill pipe is pressurized by an external pressure device, and the liquid flows from the drill pipe to the secondary bottom filling sleeve 46 in sequence, and then enters the annulus between the central string 100 and the wellbore through the filling channel 411 of the secondary bottom filling sleeve 46. It is observed whether there is liquid return in the annulus. If there is no liquid return in the annulus, it proves that the bottom open hole packer 7 is well sealed. Otherwise, it proves that the bottom open hole packer 7 is not completely sealed, and the open hole packer 7 needs to be re-sealed.
[0093] S7, the secondary bottom filling sliding sleeve 46 is closed and verified.
[0094] The tool string 200 is lifted up to position the filling sleeve closing tool 13 above the secondary bottom filling sleeve 46, and then the tool string 200 is lowered to the secondary bottom filling positioning position, so that the filling sleeve closing tool 13 closes the secondary bottom filling sleeve 46. Subsequently, the drill pipe is pressurized to the set pressure through an external pressure device, and the liquid flows from the drill pipe to the filling port 121 of the filling control tool 12 in sequence, and then enters the annulus between the bottom filling sleeve 46 and the filling control tool 12, and observes whether there is liquid return in the annulus. If there is no liquid return in the annulus, the secondary bottom filling sleeve 46 is closed, otherwise it proves that the bottom filling sleeve 46 is not closed, and it is necessary to lift and lower the tool string 200 again to close the bottom filling sleeve 46.
[0095] S8, performing fracturing and filling operations on the bottom area of the wellbore.
[0096] like Figure 5 As shown, the tool string 200 is lowered until the positioning tool 14 and the bottom positioning collar 47 are positioned together to mark the bottom filling positioning position. During this process, the filling sleeve switch tool 15 opens the bottom filling sleeve 46. Subsequently, the mortar is pumped into the drill pipe through an external pressure device, and the mortar flows through the drill pipe to the filling port 121 of the filling control tool 12 in sequence, then enters the bottom filling sleeve 46, and enters the annulus between the central string 100 and the wellbore through the filling channel 411 of the bottom filling sleeve 46. As the filling operation continues, the mortar is gradually filled upward until the mortar completely fills the bottom area of the wellbore, completing the fracturing filling operation.
[0097] S9, reverse circulation well washing, to clean the residual mortar in the wellbore.
[0098] like Figure 6As shown, the tool string 200 is lifted up to ensure that the packing sleeve closing tool 13 is located below the bottom packing sleeve 46, and then the well washing fluid is pumped into the annulus between the central string 100 and the tool string 200 through the external pressure device. The well washing fluid enters the inner wall channel 123 through the reverse circulation hole 122 of the packing control tool 12, and then enters the backwashing ball valve 125 through the double-through body interlayer 124 of the packing control tool 12. Subsequently, the well washing fluid enters the annulus between the central string 100 and the tool string 200 through the discharge channel 126 of the packing control tool 12, and then enters the inner cavity through the packing port 121 of the packing control tool 12, and then flows upward and returns to the wellhead through the drill pipe, preliminarily backwashing the excess mortar in the annulus between the packing control tool 12 and the bottom packing sleeve 46.
[0099] like Figure 7 As shown, the tool string 200 is continuously lifted until the reverse circulation hole 122 of the packing control tool 12 is sealed in the sealing tube of the secondary bottom circulation sleeve 41. During this process, the packing sleeve closing tool 13 closes the bottom packing sleeve 46, and the circulation sleeve single closing tool 16 closes the bottom circulation sleeve 41. Next, a large amount of well washing fluid is pumped into the annulus between the center string 100 and the tool string 200 through an external pressure device. The large amount of well washing fluid enters the inner cavity of the packing control tool 12 through the packing port 121, then flows upward and returns to the wellhead through the drill pipe, and the residual mortar in the well is completely cleaned.
[0100] S10, bottom filling sliding sleeve 46 closing verification.
[0101] Lower the tool string 200 to the bottom filling positioning position, pressurize the drill pipe to the set pressure through external pressure equipment, observe whether there is liquid returning from the annulus, and judge whether the bottom filling sleeve 46 is closed in the same way as the closing judgment method of the secondary bottom filling sleeve 46.
[0102] S11, lifting the tool string 200 to the corresponding layer of the oil well, and repeating steps S6-S10 until each layer of the oil well is respectively completed with fracturing filling, reverse circulation well washing, and closing verification of the filling sleeve 46.
[0103] According to the number of packing production assemblies 4, the tool string 200 is lifted to position the positioning tool 14 and the third-to-last positioning collar 47, and the third-to-last packing positioning position is marked. Then, S6-S10 are repeated until the second-to-last layer of the wellbore is completed with fracturing packing, reverse circulation well washing, and packing sleeve 46 closure verification, and this is repeated until the top layer of the oil well is completed with fracturing packing, reverse circulation well washing, and packing sleeve 46 closure verification.
[0104] S12, by controlling the opening of the production sleeve 43 and the circulation sleeve 41 of the corresponding layer in the well through the tool string 200, the selective production and exploitation of the oil well can be achieved.
[0105] As can be seen from the above, the pipe string integrates the functions of fracturing filling and production and mining, and can realize effective segmentation, sand prevention and selective mining and production of the wellbore, ensure the filling effect, reduce the risk of sand production, and improve the initial production capacity of the well completion. At the same time, this design does not require the additional insertion of sand prevention pipe strings and sub-production pipe strings, which reduces the construction cost. Moreover, only through the simple operation of external pressure and lifting and releasing the tool pipe string 200, the control of the setting of the packer and the opening and closing of the filling sleeve 46 and other components can be realized, simplifying the operation process and improving the work efficiency.
[0106] Compared with the existing technology, it can improve the formation conductivity, reduce the friction resistance near the wellbore, and effectively prevent sand for medium and low permeability sandstone reservoirs. For the blockage of the formation near the wellbore, it can complete the extrusion and unblocking, and improve the initial production capacity of the well completion. At the same time, it can also optimize the sand control construction parameters in sections according to the physical property differences of the horizontal sections, realize the balanced transformation of the horizontal sections, and effectively extend the life of the sand control.
[0107] Moreover, the open hole packer 7 can effectively segment the horizontal section to achieve selective production, and for oil reservoirs with edge and bottom water, it can avoid premature flooding, which causes problems such as reduced production capacity and shortened sand control life. This design enables oil wells to be exploited in layers, and the production sleeve 43 in the well can be selectively opened or closed by the production sleeve 43 switch tool according to the water output in the later stage of horizontal well exploitation, so as to achieve segmented water control of the horizontal well production layer.
[0108] It should be noted that, unless otherwise specified, the technical terms or scientific terms used in the present invention should have the common meanings understood by those skilled in the art to which the present invention belongs.
[0109] In addition, the terms "first", "second", etc. are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. In the description of the present invention, the meaning of "plurality" is more than two, unless otherwise clearly and specifically defined.
[0110] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in each embodiment can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.
Claims
1. An integrated pipe string for fracturing production of open hole horizontal wells, characterized in that: The invention comprises a central pipe string (100) and a tool pipe string (200), wherein the central pipe string (100) comprises a top packer (1), a first sealing cylinder (2), a quick connector (3), a filling production assembly (4), a locking sealing assembly (5) and a floating shoe assembly (6) which are sequentially connected from top to bottom; The packing production assembly (4) is provided in plurality, and two adjacent packing production assemblies (4) are connected via an open hole packer (7), and each packing production assembly (4) comprises a circulation sleeve (41), a first double-layer screen pipe (42), a production sleeve (43), a second double-layer screen pipe (44), a second sealing cylinder (45), a packing sleeve (46), and a positioning collar (47) which are sequentially connected from top to bottom; The tool string (200) comprises a top setting tool (8), a test sealing rod (9), a tie-back rod (10), a tie-back tool (11), a filling control tool (12), a filling sleeve closing tool (13), a positioning tool (14), a filling sleeve switching tool (15), a circulation sleeve single closing tool (16), a circulation sleeve single opening tool (17), a positioning sealing rod (18) and a shear sleeve (19) which are sequentially connected from top to bottom; The top sealing tool (8) is used to control the sealing of the top packer (1); the test sealing rod (9) is used to cooperate with the first sealing tube (2) to achieve the sealing of the annulus between the central pipe string (100) and the tool pipe string (200); the tie-back tool (11) is used to connect with the tie-back rod (10), and the tie-back tool (11) can cooperate with the locking seal assembly (5) to form a temporary lock; the filling control tool (12) is used to control the opening and closing of its own flow channel; the positioning tool (14) is used to cooperate with the positioning collar (47) to achieve the positioning of the central pipe string (100); and the shear sleeve (19) is used to seal the bottom end of the tool pipe string (200).
2. The open hole horizontal well fracturing production integrated tubing string according to claim 1, characterized in that: The locking seal assembly (5) comprises a locking cylinder (51) and a third sealing cylinder (52), wherein the third sealing cylinder (52) is connected to the bottom of the locking cylinder (51), the locking cylinder (51) is connected to the bottommost positioning collar (47), and the locking cylinder (51) can cooperate with the reconnection tool (11) to achieve temporary locking.
3. The open hole horizontal well fracturing production integrated tubing string according to claim 2, characterized in that: The float shoe assembly (6) comprises a liquid-proof lock sealing cylinder (61) and a float shoe (62), wherein the liquid-proof lock sealing cylinder (61) is connected to the bottom of the third sealing cylinder (52), and the float shoe (62) is connected to the bottom of the liquid-proof lock sealing cylinder (61).
4. A method for using the open hole horizontal well fracturing production integrated tubing string according to any one of claims 1 to 3, characterized in that: The steps include: S1, connecting the central pipe string (100) and the tool pipe string (200), lowering the central pipe string (100) into the wellbore, and lowering the tool pipe string (200) into the central pipe string (100); S2, during the lowering process of the tool string (200), the tool string (200) is pressurized by an external pressurizing device to flush the residual sediment in the open hole horizontal well section with liquid; S3, controlling the top packer (1) to be set; S4, top packer (1) seal inspection; S5, controlling the multiple open hole packers (7) to be set respectively, so that the multiple open hole packers (7) separate the wellbore into multiple layers from bottom to top; S6, bottom open hole packer (7) seal inspection; S7, verification of closing of the secondary bottom filling sleeve (46); S8, performing fracturing and filling operations on the bottom area of the wellbore; S9, reverse circulation well washing, cleaning the residual mortar in the wellbore; S10, bottom filling sleeve (46) closing verification; S11, lifting the tool string (200) to the corresponding layer of the oil well, and repeating steps S6-S10 until each layer of the oil well is completed with fracturing filling, reverse circulation well washing, and closing verification of the filling sleeve (46); S12, controlling the opening of the production sleeve (43) and the circulation sleeve (41) at the corresponding layer in the well by means of the tool string (200), so as to realize the selective production and exploitation of the oil well.
5. The method of use according to claim 4, characterized in that: In S1: Connecting the center pipe column (100) comprises: connecting the top packer (1) to the first sealing cylinder (2), and sequentially connecting the floating shoe (62) to the locking cylinder (51) from bottom to top, selecting a corresponding number of packing production assemblies (4) according to the depth of the oil well, connecting two adjacent packing production assemblies (4) respectively through the open hole packer (7), connecting the locking cylinder (51) to the bottommost positioning collar (47), and connecting the quick connector (3) to the topmost circulating sleeve (41); Ensure that the circulation sleeve (41), production sleeve (43) and filling sleeve (46) in each filling production assembly (4) are in a closed state, fill each first double-layer screen tube (42) and second double-layer screen tube (44) with liquid to ensure internal and external pressure balance, and perform pressure testing on each filling production assembly (4) to ensure connection sealing; The connecting tool column (200) comprises: sequentially connecting the shear sleeve (19) to the tie-back tool (11) from bottom to top, and lowering the tool into the central column (100) until the tie-back tool (11) and the locking cylinder (51) are temporarily locked, then connecting the test sealing rod (9) to the tie-back rod (10), and connecting the test sealing rod (9) to the drill pipe, using the drill pipe to carry the test sealing rod (9) and the tie-back rod (10) to lower into the central column (100) until the tie-back rod (10) and the tie-back tool (11) are connected, and then lifting the tool column (200) to unlock the tie-back tool (11) and the locking cylinder (51); After the tie-back tool (11) is unlocked, the tool string (200) is pressure tested, and then the drill pipe is pressurized to a set pressure through an external pressure device, so that the shear pins in the shear sleeve (19) are sheared off, thereby achieving communication between the tool string (200) and the center string (100). Subsequently, the first sealing cylinder (2) is connected to the quick connector (3), and the tool string (200) is lowered.
6. The method of use according to claim 5, characterized in that: In S2: During the lowering of the tool string, the drill pipe is pressurized by an external pressurizing device, so that the liquid flows from the top setting tool (8) to the shear sleeve (19) in sequence, then flows through the floating shoe (62), and returns through the annulus between the center string (100) and the wellbore to flush the residual mud and sand in the open hole horizontal well section.
7. The method of use according to claim 6, characterized in that: In S3: A steel ball of a set size is dropped, and the drill pipe is pressurized by an external pressurizing device until the steel ball shears the ball seat in the filling control tool (12), so that the channel in the filling control tool (12) is opened, and the pressure is continuously increased to the set pressure until the top packer (1) is completely set. Subsequently, the pressure is continuously increased to the set pressure, so that the top setting tool (8) and the top packer (1) are released, so as to release the lock between the center pipe string (100) and the tool pipe string (200).
8. The method of use according to claim 7, characterized in that: In S4: The tool string (200) is lifted until the test sealing rod (9) is located in the first sealing tube (2). The test sealing rod (9) and the first sealing tube (2) seal the annulus between the tool string (200) and the center string (100). The annulus between the tool string (200) and the center string (100) is pressurized to a set pressure by an external pressurizing device. Whether there is liquid flowing out of the annulus is observed to determine whether the top packer (1) is sealed.
9. The method of use according to claim 8, characterized in that: In S5: The tool string (200) is lifted until the reverse circulation hole (122) of the filling control tool (12) is sealed in the sealing tube of the bottom filling sleeve (46), and the annulus between the center string (100) and the tool string (200) is pressurized to a set pressure through an external pressurizing device, so that all open hole packers (7) are sealed.
10. The method of use according to claim 9, characterized in that: In S6: The tool column (200) is lifted up, so that the positioning tool (14) and the secondary bottom layer positioning collar (47) are matched and positioned, and the secondary bottom layer filling positioning position is marked, and the tool column (200) is further lifted up, so that the filling sleeve switch tool (15) is located above the secondary bottom layer filling sleeve (46), and at the same time, the circulation sleeve single opening tool (17) is located above the bottom layer circulation sleeve (41); The tool string (200) is lowered to the secondary bottom filling positioning position, the filling sleeve switch tool (15) controls the secondary bottom filling sleeve (46) to open, the circulation sleeve single opening tool (17) controls the bottom circulation sleeve (41) to open, and the drill pipe is pressurized by an external pressurizing device. The liquid flows from the drill pipe to the secondary bottom filling sleeve (46) in sequence, and then enters the annulus between the central string (100) and the wellbore through the filling channel (411) of the secondary bottom filling sleeve (46). It is observed whether there is liquid flowing back in the annulus to determine whether the bottom open hole packer (7) is sealed.
11. The method of use according to claim 10, characterized in that: In S7: The tool string (200) is lifted up so that the filling sleeve closing tool (13) is located above the secondary bottom filling sleeve (46), and then the tool string (200) is lowered to the secondary bottom filling positioning position so that the filling sleeve closing tool (13) closes the secondary bottom filling sleeve (46). The drill pipe is pressurized to a set pressure through an external pressurizing device, and the liquid flows from the drill pipe to the filling port (121) of the filling control tool (12) in sequence, and then enters the annulus between the bottom filling sleeve (46) and the filling control tool (12). It is observed whether there is liquid flowing back from the annulus to determine whether the secondary bottom filling sleeve (46) is closed.
12. The method of use according to claim 11, characterized in that: In S8: The tool string (200) is lowered until the positioning tool (14) and the bottom positioning collar (47) are matched and positioned, and the bottom filling positioning position is marked. At this time, the filling sleeve switch tool (15) opens the bottom filling sleeve (46), and the mortar is pumped into the drill pipe through the external pressure device. The mortar flows through the drill pipe to the filling port (121) of the filling control tool (12), and then enters the bottom filling sleeve (46), and enters the annulus between the central string (100) and the wellbore through the filling channel (411) of the bottom filling sleeve (46). As the filling operation continues, the mortar is gradually filled upward until the mortar completely fills the bottom area of the wellbore.
13. The method of use according to claim 12, characterized in that: In S9: Lift the tool string (200), and pump a well-washing fluid into the annulus between the central string (100) and the tool string (200) through an external pressure device. The well-washing fluid enters the inner wall channel (123) through the reverse circulation hole (122) of the filling control tool (12), and then enters the backwashing ball valve (125) through the double-through body interlayer (124) of the filling control tool (12), and enters the annulus between the central string (100) and the tool string (200) through the discharge channel (126) of the filling control tool (12), and then enters the inner cavity through the filling port (121) of the filling control tool (12), and then flows upward and returns to the wellhead through the drill pipe, and initially backwashes the excess mortar in the annulus between the filling control tool (12) and the bottom filling sleeve (46); Continue to lift the tool string (200) until the reverse circulation hole (122) of the filling control tool (12) is sealed in the sealing tube of the secondary bottom circulation sleeve (41). At this time, the filling sleeve closing tool (13) closes the bottom filling sleeve (46), and the circulation sleeve single closing tool (16) closes the bottom circulation sleeve (41). A large amount of well washing fluid is pumped into the annulus between the central string (100) and the tool string (200) through the external pressure equipment. The large-volume well washing fluid enters the inner cavity of the filling control tool (12) through the filling port (121), then flows upward and returns to the wellhead through the drill pipe, so as to completely clean the residual mortar in the well.
14. The method of use according to claim 13, characterized in that: In S10: The tool string (200) is lowered to the bottom filling positioning position, and the drill pipe is pressurized to a set pressure through an external pressure device to observe whether there is liquid return in the annulus to determine whether the bottom filling sleeve (46) is closed.
15. The method of use according to claim 14, characterized in that: In S11: According to the number of filling production assemblies (4), the tool string (200) is lifted to position the positioning tool (14) and the third-to-last positioning collar (47) in coordination, and the third-to-last filling positioning position is marked, and S6-S10 are repeated until the second-to-last layer area of the wellbore completes the fracturing filling, reverse circulation well washing, and filling sleeve (46) closure verification. This is repeated until the top layer area of the oil well completes the fracturing filling, reverse circulation well washing, and filling sleeve (46) closure verification, and then S12 can be executed.
Citation Information
Patent Citations
Integrated tubular column for conducting well completion fracturing on open hole horizontal well
CN103422846A
Completion and fracture integrated pipe column of offshore openhole horizontal well and construction method of pipe column
CN103643931A
Segmented gravel packing pipe column and method for open hole horizontal well
CN116398097A
High-temperature graded well cementation and sand prevention integrated pipe column and using method thereof
CN117307050A
Gravel pack inner string adjustment device
WO2013103786A2