Tunnel excavation section automatic three-dimensional scanning trolley device and using method thereof
By setting up a total station and reflective patch at the tunnel excavation section, combined with an automated three-dimensional scanner, the problem of difficulty in setting scan points and inaccurate calculations in the existing technology is solved, and the accurate collection of three-dimensional information on the tunnel excavation section is achieved. Data provision has improved the evaluation of tunnel blasting excavation effect.
Patent Information
- Application Number
- CN202411009468.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-15
AI Technical Summary
In the prior art, three-dimensional scanning equipment is used to provide difficulties in setting scanning points during tunnel excavation and inaccurate calculation of actual scanning profiles, which affects the evaluation of tunnel blasting excavation effect.
By setting the total station as the reference point, the coordinates of the automated three-dimensional scanner are determined using the reflective patch on the back of the automatic scanner protection box, and the actual contour lines of the tunnel excavation section are calculated in combination with the control module to realize automated three-dimensional scanning.
It improves the accuracy of the three-dimensional information of the tunnel excavation section, reduces the difficulty of operation, and provides reliable data support for tunnel blasting and excavation.
Smart Images

Figure CN118958990A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to an automatic three-dimensional scanning trolley device for a tunnel excavation section and a method for using the same, and belongs to the field of tunnel construction. Background Art
[0002] In recent years, the scale of high-speed rail construction in my country has continued to expand, and the number of high-speed rail tunnels has increased dramatically. In order to realize the modernization of tunnel construction, improve the level of construction technology, and ensure the modeling and visualization of construction scenes in each stage of tunnel excavation, support, and lining, a three-dimensional laser scanner is used to collect three-dimensional laser point cloud data of the tunnel. By performing three-dimensional laser scanning on the excavation surface, the actual contour of the surrounding rock after tunnel excavation can be obtained. By comparing the contour obtained by the three-dimensional scanning of the excavation surface with the designed contour, the over-excavation value of the blasting excavation can be calculated, thereby evaluating the tunnel blasting excavation effect. However, when using three-dimensional scanning equipment for scanning in the prior art, there are problems such as difficulty in setting scanning points and inaccurate calculation process of scanning the actual contour. Therefore, a new automatic three-dimensional scanning trolley device for tunnel excavation section and its use method have become a problem that technicians in this field need to solve urgently. Summary of the invention
[0003] According to one aspect of the present application, a tunnel excavation section automatic three-dimensional scanning trolley device and a method for using the same are provided. The method sets a measurement point with a total station as a reference point, finds the coordinate point of a reflective patch on the back of an automatic scanner protection box provided on the excavation trolley, calculates the coordinates of an automatic three-dimensional scanner inside the automatic scanner protection box, and enables the automatic three-dimensional scanner to obtain the actual contour line of the tunnel excavation section by calculating and uploading it to a controller.
[0004] The present application provides a trolley device for automatic three-dimensional scanning of tunnel excavation sections, comprising:
[0005] The excavation trolley is set close to the tunnel excavation section;
[0006] An automatic scanner protection box is located at one end of the excavation trolley close to the tunnel excavation section. The automatic scanner protection box is a hollow box with an opening and closing cover at one end. An automatic three-dimensional scanner is arranged inside the automatic scanner protection box.
[0007] The opening and closing cover is hinged to the automatic scanner protection box, and the opening and closing cover and two inner sides of the automatic scanner protection box are connected by an arc-shaped pull rod;
[0008] A reflective patch is arranged on the outer side of one end of the automatic scanner protection box relative to the opening and closing cover, and the reflective patch is also arranged on the top and both sides of the excavation trolley;
[0009] A total station, wherein the total station is placed in an area in the tunnel where the secondary lining construction is completed and the deformation is stable, and the placement position is used as a reference point, and the reference point is used as a reference point for positioning of the automated three-dimensional scanner;
[0010] A control module receives and feeds back the contour coordinates of the tunnel excavation section scanned by the automated three-dimensional scanner, and calculates the coordinates transmitted by the automated three-dimensional scanner and the coordinates of the reference point, so that the tunnel excavation section forms an actual tunnel contour line in the control module according to the calculated coordinates.
[0011] Optionally, the arc-shaped pull rod is in the shape of a quarter of a circle, one end of the arc-shaped pull rod is connected to the inner side of the opening and closing cover, and the other end of the arc-shaped pull rod is connected to the inner side of the opening and closing cover.
[0012] Optionally, a slide groove is provided on the arc-shaped pull rod, a fixed slide block is provided on the inner side of the automatic scanner protection box, one end of the arc-shaped pull rod is hinged to the opening and closing cover, and the other end slides along the fixed slide block.
[0013] Optionally, tracks are provided at the inner bottom end of the automatic scanner protection box and the inner side of the opening and closing cover. When the opening and closing cover is fully opened by the arc-shaped pull rod, the tracks on the opening and closing cover are combined into a long track for the automatic three-dimensional scanner to slide.
[0014] Optionally, the track at the bottom end of the automatic scanner protection box and the connection between the track on the opening and closing cover are provided with relative 45° inclined surfaces, so that when the opening and closing cover is closed, the ends of the tracks are exactly combined at 90° and no collision occurs.
[0015] Optionally, a sliding connecting plate is provided on the two rails, the automated three-dimensional scanner is located on the top of the connecting plate, a pulley is provided at the bottom of the connecting plate, the pulley is driven by a motor, the motor is connected to the control module, and the control module controls the start and stop of the motor.
[0016] A method for using a tunnel excavation section automatic three-dimensional scanning trolley, comprising:
[0017] Step 1: Determine the reference point. By measuring the control point outside the tunnel, determine the reference point in the area where the secondary lining construction is completed and the deformation is basically stable in the tunnel, and place a total station on the reference point. The reference point is used as the reference point for positioning the automated 3D scanning trolley.
[0018] Step 2: Determine the reference coordinates. According to the reference points confirmed in step 1, use a total station to determine the four reflective patches in front to obtain the position coordinates of the automatic scanner protection box, and provide reference coordinates for the automatic three-dimensional scanner;
[0019] Step 3: Open the automatic scanner protection box, and open the opening and closing cover at one end of the automatic scanner protection box so that the opening and closing cover and the bottom of the automatic scanner protection box form a horizontal position, so that the automatic three-dimensional scanner inside the automatic scanner protection box can be driven out to the opening and closing cover in a horizontal state;
[0020] Step 4: Calculate the position of the scanner, start the automated three-dimensional scanner that has completed step 4, and calculate the position of the automated three-dimensional scanner according to the distance of the automated three-dimensional scanner on the track and the position coordinates measured in step 2;
[0021] Step 5: Start scanning, so that the automatic three-dimensional scanner is turned on and performs a full-scale scan of the surrounding rock of the tunnel excavation section, and obtains the coordinate position of each point of the tunnel excavation section and saves and uploads it to the control module;
[0022] Step 6: Return to the operation. After the control module in step 5 successfully saves the coordinate positions of each point on the tunnel excavation section, feedback closing information is sent to the automated 3D scanner and the automated scanner protection box to restore the automated 3D scanner to its initial position.
[0023] The beneficial effects of this application include:
[0024] 1) The present application provides an automatic three-dimensional scanning trolley device for a tunnel excavation section, wherein an automatic scanner protection box is arranged at the top of the excavation trolley near the tunnel section, and an automatic three-dimensional scanner that can enter and exit is arranged inside the automatic scanner protection box. A section of track is arranged at the bottom end of the interior of the automatic scanner protection box, and then a section of the internal track is spliced together to form a long track after the opening and closing cover on the automatic scanner protection box is opened, so that the automatic three-dimensional scanner can slide out of the interior of the automatic scanner protection box, scan the coordinates of each point on the tunnel excavation section, and upload them to the controller, so as to accurately collect the three-dimensional information of the tunnel excavation surface. The automatically controlled scanner and the scanner protection box can not only reduce the operating difficulty of the workers, but also effectively protect the scanner part, and provide reliable data for the evaluation of tunnel blasting excavation.
[0025] 2) The present application provides a method for using an automatic three-dimensional scanning trolley for tunnel excavation sections. By placing a total station in an area in the tunnel where the secondary lining construction is completed and the deformation is basically stable, and the placement position is used as a reference point, it is safer for workers to operate in the area where the secondary lining construction is completed. The total station scans the automatic scanner protection box set in front on the excavation trolley. Because a reflective patch is affixed to the back of the automatic scanner protection box, the coordinates of its reflective points can be found in a dark environment. Then, an automated three-dimensional scanner that can enter and exit the automatic scanner protection box is set inside the automatic scanner protection box to complete the coordinates of each point on the tunnel excavation section, and the actual contour line of the tunnel excavation section is obtained by calculation. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a schematic diagram of the structure of the automatic three-dimensional scanning trolley device for tunnel excavation sections;
[0027] Figure 2 This is a schematic diagram of the internal structure of the automatic scanner protection box;
[0028] Figure 3 This is a schematic diagram of the back structure of the automatic scanner protection box;
[0029] Figure 4 This is a schematic diagram of total station scanning;
[0030] Figure 5 Schematic diagram for total station placement;
[0031] Figure 6 This is a schematic diagram of the installation structure of the excavation trolley and the automatic scanner protection box;
[0032] List of parts and reference numerals: 1. Excavation trolley; 2. Automated 3D scanner; 3. Automatic scanner protection box; 4. Track; 5. Arc pull rod; 6. Hinge; 7. Connecting rod; 8. Reflective patch; 9. Opening and closing cover; 10. Total station. DETAILED DESCRIPTION
[0033] The present application is described in detail below with reference to embodiments, but the present application is not limited to these embodiments.
[0034] Please refer to Figure 1-Figure 6As shown, the present application provides a tunnel excavation section automatic three-dimensional scanning trolley device and a method of using the same, which scans the excavation section of the tunnel after the second lining construction in the tunnel is completed, comprising: an excavation trolley 1, the excavation trolley 1 is a door-shaped steel frame structure, an automatic scanner protection box 3 is installed on the top of one side of the excavation trolley 1, an automatic three-dimensional scanner 2 is arranged inside the automatic scanner protection box 3, the model of the automatic three-dimensional scanner 2 is Leica MS60, and the automatic scanner protection box 3 is hollow inside and has an opening and closing The cover 9 has a cubic structure, and a reflective patch 8 is arranged on the outer side of one end of the automatic scanner protection box 3 relative to the opening and closing cover 9. The reflective patch 8 is also arranged on the top and both sides of the excavation trolley 1. The reflective patch 8 is bonded to the automatic scanner protection box 3, and the reflective patch 8 is bonded to the surface of the excavation trolley 1, that is, a total of four reflective patches are arranged. The function of the reflective patch 8 is to find the position of the reflective patch 8 by illumination in a dark tunnel environment, thereby determining the position of the automatic scanner protection box 3;
[0035] One end of the automatic scanner protection box 3 is provided with an opening and closing cover 9, and the opening and closing cover 9 is connected to the automatic scanner protection box 3 through an arc-shaped pull rod 5, and a slide groove is provided on the arc-shaped pull rod 5. A fixed slider is provided inside the automatic scanner protection box 3, and one end of the arc-shaped pull rod 5 is fixedly connected to the opening and closing cover 9, and the other end slides along the fixed slider, and a hinge 6 is provided at the connection between the opening and closing cover 9 and the automatic scanner protection box 3, as shown in FIG. Figure 2 As shown, the arc-shaped pull rod 5 enables the opening range of the opening and closing cover 9 to be 0-90°, and a double-row track 4 is provided inside the opening and closing cover 9. When the opening range of the opening and closing cover 9 is 90°, the track 4 is kept horizontal with the bottom end of the automatic scanner protection box 3, and the bottom end of the automatic scanner protection box 3 is also provided with a double-row track 4. When the track 4 is opened within the range of 90°, the track 4 on the opening and closing cover 9 is connected with the track 4 on the automatic scanner protection box 3;
[0036] Please continue to refer to Figure 2A connecting plate 7 is provided on the track 4, and the connecting plate 7 is slidably connected to the track 4, and a pulley is provided at the bottom of the connecting plate 7, and the pulley is clamped inside the track 4. The pulley is rotated by a micro motor, so that the connecting plate 7 is driven to slide on the track 4 during the rotation of the pulley. An automatic three-dimensional scanner 2 is installed on the top of the connecting plate 7. When the opening and closing cover 9 is closed, the connecting plate 7 stays on the track 4 at one end of the bottom end of the automatic scanner protection box 3. When the automatic three-dimensional scanner 2 installed on the connecting plate 7 needs to be used, the opening and closing cover 9 is opened to fully open the arc pull rod 5, that is, the opening and closing cover 9 is opened to 90°, so that the lower end of the opening and closing cover 9 and the automatic scanner protection box 3 are horizontal, the track 4 on the opening and closing cover 9 is combined into a long track for the automatic three-dimensional scanner 2 to slide, so that the connecting plate 7 slides out through the pulley and stops in the middle of the track 4 on the opening and closing cover 9, and the operation of the automatic three-dimensional scanner 2 is started. The automatic three-dimensional scanner 2 can adopt the model: Leica MS60, and the automatic three-dimensional scanner 2 can perform horizontal 360° rotation and vertical 360° rotation functions based on the base, and can perform all-round rotation scanning on the front tunnel excavation section to obtain the three-dimensional position information of each point on the surrounding rock surface of the front tunnel excavation section.
[0037] It should be noted that the connection between the track 4 on the opening and closing cover 9 and the track 4 on the automatic scanner protection box 3 has a relative 45° slope, so that the two parts of the track 4 can be merged into a 90° connection without colliding with each other, and when the two parts of the track 4 are opened, they can remain horizontal and the connecting plate 7 can slide smoothly on the track 4 at the two connections.
[0038] Please refer to Figure 1 As shown, the excavation trolley 1 is arranged inside the tunnel after the secondary lining construction is completed, and a step is arranged inside the tunnel. The excavation trolley 1 is placed on the step, and the step is arranged inside the tunnel after the secondary lining construction is completed. The excavation trolley 1 is pushed in front of the section of tunnel excavation, and the total station 10 is arranged in the area where the secondary lining construction is completed and the deformation is basically stable in the tunnel, and the placement position is used as a reference point. The reference point is used as a reference point for positioning the automatic three-dimensional scanner 2. The total station 10 is positioned to the position of the reflective patch 8 to determine the coordinates of the automatic scanner protection box 3, and provide reference coordinates for the automatic three-dimensional scanner 2.
[0039] The method for using the automatic three-dimensional scanning trolley for tunnel excavation section is as follows:
[0040] Step 1: Determine the reference point, by measuring the control point outside the tunnel, determine the reference point in the area where the secondary lining construction is completed and the deformation is basically stable in the tunnel, place the total station 10 on the reference point, and the reference point is used as the reference point for positioning the automated three-dimensional scanning trolley;
[0041] Step 2: Determine the reference coordinates. According to the reference points confirmed in step 1, use a total station to determine the four reflective patches 8 in front to obtain the position coordinates of the automatic scanner protection box 3, and provide reference coordinates for the automatic three-dimensional scanner 2;
[0042] Step 3: Open the scanner protection box, by opening the opening and closing cover 9 at one end of the automatic scanner protection box 3, so that the opening and closing cover 9 and the bottom end of the automatic scanner protection box 3 form a horizontal position, so that the automatic three-dimensional scanner 2 inside the automatic scanner protection box 3 can be driven out to the top end of the horizontally placed opening and closing cover 9;
[0043] Step 4: Calculate the position of the scanner, start the automatic three-dimensional scanner 2 that has completed step 4, and calculate the position of the automatic three-dimensional scanner 2 according to the distance of the automatic three-dimensional scanner on the track 4 and the position coordinates measured in step 2;
[0044] The specific calculation method is as follows:
[0045] Assume that the position coordinates of the total station 10 are:
[0046] O(x0, y0, z0);
[0047] The position coordinates of the three reflective stickers on the excavation trolley 1 are:
[0048] A(x1, y1, z1);
[0049] B(x2, y2, z2);
[0050] C(x3,y3,z3);
[0051] The position coordinates of the reflective patch on the back of the automatic scanner protection box 3 are:
[0052] D(x4, y4, z4);
[0053] The position coordinate O of the total station 10 is measured by the measuring wire outside the tunnel. Then, with point O as the reference point, the position coordinates of the four reflective stickers A, B, C, and D on the side of the total station are measured. After the position coordinates of each point are measured, the position coordinate calculation method of the automated three-dimensional scanner 2 is as follows:
[0054]
[0055] Normal vector of plane ABC
[0056]
[0057] Where:
[0058] a=(y1-y2)(z1-z3)-(y1-y3)(z1-z2)
[0059] b=(x1-x3)(z1-z2)-(x1-x2)(z1-z3)
[0060] c=(x1-x2)(y1-y3)-(x1-x3)(y1-y2)
[0061] The normal vector passes through point D and is parallel to ABC The equation of the straight line is:
[0062]
[0063] The center of the automatic three-dimensional scanner 2 is coaxial with the center of the reflective patch on the back of the automatic scanner protection box 3. It can move forward and backward along the track under control. Assuming that the moving distance on the track is l, the spatial position coordinates of the three-dimensional scanner can be calculated as E (x, y, z):
[0064]
[0065]
[0066] Solving the system of equations can obtain the spatial position coordinates of the 3D scanner as E (x, y, z);
[0067] Step 5: Start scanning, so that the automatic three-dimensional scanner 2 is turned on and performs a full-scale scan of the surrounding rock of the tunnel excavation section, and obtains the three-dimensional position information of point i of the tunnel excavation section as follows:
[0068]
[0069] After the initial support is constructed, the initial support surface of the area is scanned using the same method to obtain the three-dimensional position information of the initial support surface corresponding to point i.
[0070] express;
[0071] The calculation formula for the thickness of the initial support at point i is:
[0072]
[0073] By scanning each point of the spatial cross section through a three-dimensional scanning operation, the initial support thickness of each point in the cross section area can be calculated and evaluated by using the above algorithm;
[0074] Step 6: Return to the operation. After the control module in step 5 successfully saves the coordinate positions of each point on the tunnel excavation section, feedback the closing information to the automatic three-dimensional scanner 2 and the automatic scanner protection box 3 to restore the automatic three-dimensional scanner 2 to its initial position.
[0075] Please refer to Figure 4 and Figure 5 As shown, the total station 10 is arranged on a bracket, and the bracket enables the total station 10 to work stably. When the total station 10 is turned on, the reflective patch 8 is found according to the step 2, because the reflective patch 8 can reflect strong light inside the tunnel, so that the total station 10 can quickly measure the distance of the reflective patch 8 reflecting the strong light, and obtain a position coordinate of the automatic scanner protection box 3 inside the tunnel. The reference coordinate of the total station 10 set in step 1 is the reference point, so that the position coordinate and the reference coordinate are calculated to obtain the coordinate of the back of the automatic scanner protection box 3;
[0076] In the step 3, the distance that the automated three-dimensional scanner 2 moves forward is a set value, and the control module can control the motor on the pulley on the connecting plate 7 to set the rotation time and rotation speed, so that the connecting plate 7 drives the automated three-dimensional scanner 2 to move forward the set distance, and then according to the coordinates of the back of the automated scanner protection box 3 obtained in the steps 1 and 2, the coordinates of the automated three-dimensional scanner 2 during use can be calculated, thereby obtaining the coordinates of the automated three-dimensional scanner 2 set on the tunnel excavation trolley 1 at the tunnel entrance;
[0077] In step 5, the coordinates of the automated three-dimensional scanner 2 determined in step 4 are used as a new reference. After uploading the coordinates of each point of the scanned tunnel excavation section to the control module, the coordinate distance between each point of the tunnel excavation section and the reference point is calculated, and the actual contour line of the surrounding rock after tunnel excavation can be effectively determined. By comparing the actual contour line with the designed contour line at the initial stage of tunnel excavation, the over-excavation and under-excavation values of the blasting excavation can be calculated, thereby evaluating the tunnel blasting excavation effect.
[0078] The above are only a few embodiments of the present application and do not constitute any form of limitation to the present application. Although the present application is disclosed as above with preferred embodiments, it is not intended to limit the present application. Any technician familiar with the profession, without departing from the scope of the technical solution of the present application, using the technical content disclosed above to make slight changes or modifications are equivalent to equivalent implementation cases and fall within the scope of the technical solution.
Claims
1. A trolley device for automatic three-dimensional scanning of tunnel excavation sections, characterized in that: include: An excavation trolley (1) is arranged near the tunnel excavation section; An automatic scanner protection box (3) is located at one end of the excavation trolley (1) close to the tunnel excavation section. The automatic scanner protection box (3) is a hollow box having an opening and closing cover (9) at one end. An automatic three-dimensional scanner (2) is arranged inside the automatic scanner protection box (3); The opening and closing cover (9) is hinged to the automatic scanner protection box (3), and the opening and closing cover (9) and the inner sides of the automatic scanner protection box (3) are connected via an arc-shaped pull rod (5); A reflective patch (8) is arranged on the outer side of one end of the automatic scanner protection box (3) relative to the opening and closing cover (9), and the reflective patch (8) is also arranged on the top and both sides of the excavation trolley (1); A total station (10), wherein the total station (10) is placed in an area in the tunnel where the secondary lining construction is completed and the deformation is stable, and the placement position is used as a reference point, and the reference point is used as a reference point for positioning the automated three-dimensional scanner (2); A control module receives and feeds back the contour coordinates of the tunnel excavation section scanned by the automated three-dimensional scanner (2), and calculates the coordinates transmitted by the automated three-dimensional scanner (2) and the coordinates of the reference point, so that the tunnel excavation section forms an actual tunnel contour line in the control module according to the calculated coordinates.
2. The automatic three-dimensional scanning trolley device for tunnel excavation section according to claim 1 is characterized in that: The arc-shaped pull rod (5) is in the shape of a quarter of a circle, one end of the arc-shaped pull rod (5) is connected to the inner side of the opening and closing cover (9), and the other end of the arc-shaped pull rod (5) is connected to the inner side of the opening and closing cover (9).
3. The automatic three-dimensional scanning trolley device for tunnel excavation section according to claim 2 is characterized in that: The arc-shaped pull rod (5) is provided with a slide groove, and a fixed slide block is provided inside the automatic scanner protection box (3). One end of the arc-shaped pull rod (5) is hinged to the opening and closing cover (9), and the other end slides along the fixed slide block.
4. The automatic three-dimensional scanning trolley device for tunnel excavation section according to claim 1 is characterized in that: Tracks (4) are provided at the inner bottom end of the automatic scanner protection box (3) and the inner side of the opening and closing cover (9). When the opening and closing cover (9) is fully opened by the arc-shaped pull rod (5), the tracks (4) on the opening and closing cover (9) are combined into a long track for the automatic three-dimensional scanner (2) to slide.
5. The automatic three-dimensional scanning trolley device for tunnel excavation section according to claim 4 is characterized in that: The track (4) at the bottom end of the automatic scanner protection box (3) and the track (4) on the opening and closing cover (9) are connected with a 45° inclined surface relative to each other, so that when the opening and closing cover (9) is closed, the ends of the tracks are exactly combined at 90° and no collision occurs.
6. The automatic three-dimensional scanning trolley device for tunnel excavation section according to claim 5, characterized in that: A sliding connecting plate (7) is provided on the two rails (4), the automated three-dimensional scanner (2) is located on the top of the connecting plate (7), a pulley is provided at the bottom of the connecting plate (7), the pulley is driven by a motor, the motor is connected to the control module, and the control module controls the start and stop of the motor.
7. A method for using a tunnel excavation section automatic three-dimensional scanning trolley, characterized in that: include: Step 1: Determine the reference point by measuring the control point outside the tunnel, determine the reference point in the area where the secondary lining construction is completed and the deformation is basically stable in the tunnel, place a total station (10) on the reference point, and the reference point is used as the reference point for positioning the automated three-dimensional scanning trolley; Step 2: Determine the reference coordinates. Based on the reference points confirmed in step 1, use a total station (10) to determine the four reflective patches (8) in front to obtain the position coordinates of the automatic scanner protection box (3), and provide reference coordinates for the automatic three-dimensional scanner (2); Step 3: Open the automatic scanner protection box, by opening the opening and closing cover (9) at one end of the automatic scanner protection box (3), so that the opening and closing cover (9) and the bottom of the automatic scanner protection box (3) form a horizontal position, so that the automatic three-dimensional scanner (2) inside the automatic scanner protection box (3) can be driven out to the opening and closing cover (9) in a horizontal state; Step 4: Calculate the position of the scanner, start the automated three-dimensional scanner (2) that has completed step 4, and calculate the position of the automated three-dimensional scanner (2) based on the distance of the automated three-dimensional scanner (2) on the track (4) and the position coordinates measured in step 2; Step 5: Start scanning, so that the automated three-dimensional scanner (2) starts and performs a full-scale scan of the surrounding rock of the tunnel excavation section, obtains the coordinate position of each point of the tunnel excavation section, saves it, and uploads it to the control module; Step 6: Return to the operation. After the control module in step 5 successfully saves the coordinate positions of each point on the tunnel excavation section, feedback closing information is sent to the automated three-dimensional scanner (2) and the automated scanner protection box (3) to restore the automated three-dimensional scanner (2) to its initial position.