Electron beam melting device and method for preparing niobium-based ultra-high-temperature alloy through electron beam melting device

By combining the structures such as water tank, heat sink and fan in the electron beam smelting device, the hot gas in the smelting furnace is mixed with cooling water and heat dissipated, solving the safety risks caused by high-temperature gas discharge and the low efficiency of cooling pipes, and improving the Heat dissipation efficiency and safety.

CN118960387AInactive Publication Date: 2024-11-15CHINA NONFERROUS METALS HANGYE (BEIJING) NEW MATERIALS TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411026148.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During electron beam smelting, the direct discharge of high-temperature gas may cause safety risks, and the efficiency is inefficient when dissipating heat with cooling pipes.

Method used

An electron beam smelting device is designed, using structures such as water tank, heat sink, fan, air pump and air outlet pipe to mix the hot air in the smelting furnace with cooling water and discharge it through a pressure relief valve to achieve rapid heat dissipation and heat dissipation through the fan and heat dissipation. The chip accelerates the heat dissipation process.

Benefits of technology

It improves the heat dissipation efficiency in the smelting furnace, reduces the risk of heat injury for staff members, and avoids the safety hazards of direct discharge of high-temperature gases.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0004968589780000011
    Figure HDA0004968589780000011
  • Figure HDA0004968589780000021
    Figure HDA0004968589780000021
  • Figure HDA0004968589780000031
    Figure HDA0004968589780000031
Patent Text Reader

Abstract

The invention provides an electron beam melting device and a method for preparing niobium-based ultra-high-temperature alloy through the device. The electron beam melting device comprises a base, an electron beam melting furnace body is fixedly installed at the top of the base, and an electron gun is fixedly installed at the top of the electron beam melting furnace body. According to the electron beam melting device and the method for preparing the niobium-based ultra-high-temperature alloy through the electron beam melting device, the water tank, the cooling fins, the air inlet pipe, the fixing frame, the draught fan, the air pump, the air pipe, the air outlet pipe and other structures are matched with one another; according to the electron beam smelting furnace, hot air in the electron beam smelting furnace body can be blown into the water tank through the air outlet pipe and the air inlet pipe to be mixed with cooling water, so that the hot air in the electron beam smelting furnace body is cooled and then discharged through the pressure release valve, and therefore heat dissipation can be rapidly conducted on the interior of the electron beam smelting furnace body; and the heat dissipation efficiency in the furnace is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of electron beam melting, and in particular to an electron beam melting device and a method for preparing a niobium-based ultrahigh temperature alloy by using the device. Background Art

[0002] Electron beam melting is carried out under high vacuum conditions. The cathode is heated by the high voltage electric field and emits electrons. The electrons gather into a beam and move toward the anode at a very high speed under the action of the accelerating voltage. After passing through the anode, they are accurately bombarded onto the bottom ingot and material in the crystallizer under the action of the focusing coil and the deflection coil, so that the bottom ingot is melted to form a molten pool. The material is also continuously melted and drips into the molten pool, thus realizing the melting process.

[0003] After the alloy is melted in an electron beam melting furnace, due to the high temperature during melting, especially for the melting of niobium-based ultra-high temperature alloys, the temperature in the furnace can reach 1100-1500°C after melting. When the melting is completed, in order to quickly take out the alloy after melting, a cooling device will be used to dissipate the heat in the furnace. The hot air in the furnace is blown out through a fan and then directly discharged, thereby achieving the effect of quickly dissipating the heat in the furnace. However, since the temperature in the furnace is relatively high at this time, if it is discharged directly, the high-temperature gas will quickly escape into the working environment, which may easily cause danger. If a cooling pipe is used directly to dissipate the heat in the furnace, the heat conductivity of the cooling pipe is limited, thereby reducing the heat dissipation efficiency.

[0004] Therefore, it is necessary to provide an electron beam melting device and a method for preparing a niobium-based ultrahigh temperature alloy using the device to solve the above technical problems. Summary of the invention

[0005] The present invention provides an electron beam melting device and a method for preparing a niobium-based ultrahigh temperature alloy using the device, which solves the problems of danger caused by directly discharging high-temperature gas in a furnace and reduced heat dissipation efficiency by using a cooling pipe for heat dissipation.

[0006] In order to solve the above technical problems, the present invention provides an electron beam melting device, comprising:

[0007] A base, a body of the electron beam melting furnace is fixedly mounted on the top of the base, and an electron gun is fixedly mounted on the top of the body of the electron beam melting furnace;

[0008] A clamp pot, wherein the clamp pot is arranged on the inner side of the electron beam melting furnace body, a water cooling pipe is arranged inside the clamp pot, a water inlet pipe is fixedly installed at the input end of the water cooling pipe, and a water outlet pipe is fixedly installed at the output end of the water cooling pipe;

[0009] A water tank, the water tank is fixedly mounted on the inner side of the base, a mounting groove is provided on the side of the water tank, a through groove is provided on the top of the water tank, the through groove extends to the bottom of the water tank, the interior of the through groove and the interior of the mounting groove are connected, a plurality of heat sinks are provided on the inner side of the mounting groove, the tops and bottoms of the plurality of heat sinks are both arranged inside the water tank, a mounting plate is fixedly mounted on the inner side of the through groove, a water pump is fixedly mounted on the top of the mounting plate, a water filling pipe and an air inlet pipe are respectively fixedly mounted on the top of the water tank, and a pressure relief valve is fixedly mounted on one side of the water tank;

[0010] An air pump, wherein the air pump is fixedly mounted on the back of the electron beam melting furnace body, an air inlet pipe is fixedly mounted on the output end of the air pump, the output end of the air inlet pipe is arranged inside the electron beam melting furnace body, an air outlet pipe is fixedly mounted on the back of the electron beam melting furnace body, and the air outlet pipe is fixedly mounted on the top of the air inlet pipe;

[0011] A fixed frame is fixedly installed on the bottom of the base, and a fan is fixedly installed on the inner side surface of the fixed frame.

[0012] Preferably, a door body is rotatably connected to the front side of the electron beam melting furnace body, and an observation window is fixedly installed on the front side of the door body.

[0013] Preferably, ventilation windows are fixedly installed on both sides of the base, a thermometer is fixedly installed on the front side of the base, and a detection probe of the thermometer is arranged on the inner side of the water tank.

[0014] Preferably, the water outlet pipe is fixedly installed on the top of the water tank, the water inlet pipe is fixedly installed on the output end of the water pump, and the input end of the water pump is arranged inside the water tank.

[0015] Preferably, the output end of the air intake pipe is arranged inside the water tank.

[0016] Preferably, the bottom thread of the outer side surface of the fixing frame is connected to a thread ring, and the inner side surface of the thread ring is fixedly mounted with a filter.

[0017] Preferably, the clamp pot is arranged at the bottom of the electron gun.

[0018] Preferably, a rotation groove is provided on the outer side of the thread ring, a rotation block is rotatably connected to the inner side of the rotation groove, a rotation plate is fixedly installed on one side of the rotation block, a connecting plate is fixedly installed on one side of the rotation plate, and a cleaning brush is fixedly installed on the top of the connecting plate.

[0019] Preferably, the top of the cleaning brush is attached to the bottom of the filter.

[0020] In order to solve the above problems, the present invention also provides a method for preparing a niobium-based ultra-high temperature alloy by an electron beam melting device, comprising the following steps: S1, material preparation: according to the alloy ratio, the alloying element metal raw material Zr is added to the charging funnel of the electron beam melting furnace body, and the metal raw material Nb is placed in the crucible of the electron beam melting furnace body. During the whole preparation process, the temperature of the crucible is maintained at 200°C. In order to maintain the temperature of the clamp pot, the fan and the water pump are started, so that the water pump transports the cooling water inside the water tank to the inside of the water cooling pipe through the water inlet pipe, so that the water cooling pipe dissipates heat to the clamp pot and maintains the temperature of the clamp pot. At this time, the water outlet pipe transports the heated water to the inside of the water tank. At this time, the fan blows upward from the inside of the fixed frame, so that the external wind passes through the side of the heat sink, so that the heat extracted from the inside of the water tank by the heat sink is blown out of the inside of the base through the ventilation window, thereby dissipating the heat of the water inside the water tank;

[0021] S2, preheating: close the door of the electron beam melting furnace body, turn on the electron gun mechanical pump, electron gun diffusion pump, melting chamber mechanical pump, melting chamber Roots pump, and melting chamber diffusion pump in sequence, so that the vacuum degree of the electron beam melting furnace body is less than 5×10-2Pa, and the vacuum degree of the electron gun chamber is less than 5×10-3Pa; set the high voltage of the electron gun to 25kW, preheat the high voltage for 10min, turn off the high voltage, set the electron gun beam current to 70mA, preheat the beam current for 10min, and turn off the electron gun beam current;

[0022] S3, raw material smelting: turn on the high voltage and beam current of the electron gun at the same time, bombard the alloy raw materials in the crucible with the electron gun after stabilization, increase the electron gun beam current to 450mA, and the rate of beam current increase is 4mA / s, until the alloy raw materials are completely melted, maintain the electron beam current at 400mA for alloy smelting, and the smelting time is 35min;

[0023] S4, directional solidification: after the alloy is melted, reduce the electron beam current to 100mA;

[0024] S4. Post-processing: After the alloy melt is melted into an alloy ingot, the electron gun is turned off, and the alloy is cooled in the electron beam melting chamber with the furnace for 25 minutes. At this time, the user starts the air pump to blow air into the interior of the electron beam melting furnace body, so that the hot air inside the electron beam melting furnace body enters the interior of the air inlet pipe through the air outlet pipe, and then the air inlet pipe transports the hot air to the interior of the water tank, mixes with the cooling water inside the water tank, and then discharges it through the pressure relief valve, and then opens the door of the electron beam melting furnace body to take out the alloy.

[0025] Compared with the related art, the electron beam melting device and the method for preparing niobium-based ultrahigh temperature alloy by the device provided by the present invention have the following beneficial effects:

[0026] The present invention provides an electron beam melting device and a method for preparing a niobium-based ultrahigh temperature alloy using the device. Through the cooperation of structures such as a water tank, a heat sink, an air inlet pipe, a fixing frame, a fan, an air pump, an air pipe and an air outlet pipe, when the device is in continuous use, the hot air inside the electron beam melting furnace body can be blown into the inside of the water tank through the air outlet pipe and the air inlet pipe, and mixed with cooling water, so as to cool the hot air inside the electron beam melting furnace body, and then discharge it through a pressure relief valve. In this way, the inside of the electron beam melting furnace body can be quickly dissipated, the efficiency of heat dissipation in the furnace is increased, and the direct discharge of the hot air inside the electron beam melting furnace body can be avoided to cause burns to the staff, thereby increasing safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 A schematic structural diagram of a first embodiment of an electron beam melting device provided by the present invention;

[0028] Figure 2 for Figure 1 The schematic diagram of the cross-sectional structure of the electron beam melting furnace body is shown;

[0029] Figure 3 for Figure 2 The schematic diagram of the water tank structure from top view shown;

[0030] Figure 4 for Figure 2 The schematic diagram of the bottom structure of the water tank shown;

[0031] Figure 5 for Figure 2 The schematic diagram of the back structure of the electron beam melting furnace body is shown;

[0032] Figure 6 This is a schematic structural diagram of a second embodiment of an electron beam melting device provided by the present invention.

[0033] Numbers in the figure: 1. frame, 2. base, 21. electron beam melting furnace body, 22. door, 23. observation window, 24. electron gun, 25. ventilation window, 26. temperature meter, 3. water tank, 31. mounting groove, 32. heat sink, 33. through groove, 34. mounting plate, 35. water pump, 36. water pipe, 37. air inlet pipe, 38. pressure relief valve, 4. fixing frame, 41. fan, 42. threaded ring, 43. filter, 5. clamp pot, 51. water cooling pipe, 52. water outlet pipe, 53. water inlet pipe, 6. air pump, 61. air pipe, 62. air outlet pipe, 7. rotating groove, 71. rotating block, 72. rotating plate, 73. connecting plate, 74. cleaning brush. DETAILED DESCRIPTION

[0034] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.

[0035] First embodiment

[0036] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 ,in, Figure 1 A schematic structural diagram of a first embodiment of an electron beam melting device provided by the present invention; Figure 2 for Figure 1 The schematic diagram of the cross-sectional structure of the electron beam melting furnace body is shown; Figure 3 for Figure 2 The schematic diagram of the water tank structure from top view shown; Figure 4 for Figure 2 The schematic diagram of the bottom structure of the water tank shown; Figure 5 for Figure 2 The back structure diagram of the electron beam melting furnace body is shown. An electron beam melting device comprises: a base 2, on the top of which an electron beam melting furnace body 21 is fixedly mounted, and on the top of which an electron gun 24 is fixedly mounted;

[0037] A clamp pot 5, wherein the clamp pot 5 is arranged on the inner side of the electron beam melting furnace body 21, and a water cooling pipe 51 is arranged inside the clamp pot 5, a water inlet pipe 53 is fixedly installed at the input end of the water cooling pipe 51, and a water outlet pipe 52 is fixedly installed at the output end of the water cooling pipe 51;

[0038] A water tank 3, the water tank 3 is fixedly mounted on the inner side of the base 2, a mounting groove 31 is provided on the side of the water tank 3, a through groove 33 is provided on the top of the water tank 3, the through groove 33 extends to the bottom of the water tank 3, the interior of the through groove 33 and the interior of the mounting groove 31 are interconnected, a plurality of heat sinks 32 are provided on the inner side of the mounting groove 31, the tops and bottoms of the plurality of heat sinks 32 are both arranged inside the water tank 3, a mounting plate 34 is fixedly mounted on the inner side of the through groove 33, a water pump 35 is fixedly mounted on the top of the mounting plate 34, a water supply pipe 36 and an air intake pipe 37 are respectively fixedly mounted on the top of the water tank 3, and a pressure relief valve 38 is fixedly mounted on one side of the water tank 3;

[0039] An air pump 6, the air pump 6 is fixedly installed on the back of the electron beam melting furnace body 21, an air inlet pipe 61 is fixedly installed on the output end of the air pump 6, the output end of the air inlet pipe 61 is arranged inside the electron beam melting furnace body 21, an air outlet pipe 62 is fixedly installed on the back of the electron beam melting furnace body 21, and the air outlet pipe 62 is fixedly installed on the top of the air inlet pipe 37;

[0040] The fixing frame 4 is fixedly mounted on the bottom of the base 2 , and a fan 41 is fixedly mounted on the inner side surface of the fixing frame 4 .

[0041] The electron beam melting furnace body 21 includes: an electron gun 24: which is the core component of the electron beam melting furnace, including a gun head, a focusing coil and a deflection coil, etc.; a feeding system: used to feed raw materials into the melting chamber, which can be fed mechanically in a longitudinal or transverse manner, or a feeding bin can be used; an ingot casting system: including a crystallizer (clamp pot 5), an ingot pulling mechanism and an ingot discharging mechanism, etc.; a vacuum system: composed of a vacuum unit, a vacuum chamber, a vacuum pipeline and valves, and a vacuum measurement system, etc., used to maintain a high vacuum environment in the melting chamber; a power supply system: including a main power supply (electron gun power supply), a control power supply and an operating power supply, etc.; a cooling system: used to cool the electron gun, the crystallizer and other components to ensure the normal operation of the equipment;

[0042] The cooling system of the electron beam melting furnace body 21 is composed of a water tank 3, a heat sink 32, a water pump 35 and a fan 41;

[0043] There are multiple heat sinks 32, and the tops and bottoms of the multiple heat sinks 32 are arranged inside the water tank 3, so that the heat inside the water tank 3 can be discharged, and then the heat sink 32 is blown by the fan 41, so that the cooling water inside the water tank 3 can be cooled.

[0044] The water cooling pipes 51 are evenly arranged inside the tongs pot 5 , so as to achieve the effect of cooling the tongs pot 5 .

[0045] The front of the electron beam melting furnace body 21 is rotatably connected to a door body 22, and an observation window 23 is fixedly installed on the front of the door body 22;

[0046] When in use, the door 22 facilitates the user to add and take out materials, and the observation window 23 facilitates the user to observe the interior of the electron beam melting furnace body 21 .

[0047] Ventilation windows 25 are fixedly mounted on both sides of the base 2 , a temperature meter 26 is fixedly mounted on the front side of the base 2 , and a detection probe of the temperature meter 26 is arranged on the inner side of the water tank 3 .

[0048] The heat inside the base 2 can be conveniently discharged through the ventilation window 25, and the temperature inside the water tank 3 can be monitored in real time through the thermometer 26 when in use, so as to increase the power of the fan 41 and speed up the heat dissipation of the heat sink 32.

[0049] The water outlet pipe 52 is fixedly installed on the top of the water tank 3 , the water inlet pipe 53 is fixedly installed on the output end of the water pump 35 , and the input end of the water pump 35 is arranged inside the water tank 3 .

[0050] The output end of the air inlet pipe 37 is arranged inside the water tank 3 .

[0051] The bottom of the outer side of the fixing frame 4 is threadedly connected to a thread ring 42 , and a filter screen 43 is fixedly installed on the inner side of the thread ring 42 .

[0052] By installing the threaded ring 42 at the bottom of the outer side of the fixing frame 4, the gas entering the fixing frame 4 can be filtered during use, thereby preventing dust from entering the fixing frame 4 and affecting subsequent heat dissipation.

[0053] The tongs pot 5 is disposed at the bottom of the electron gun 24 .

[0054] The working principle of an electron beam melting device provided by the present invention is as follows:

[0055] According to the alloy ratio, the alloying element metal raw material Zr is added to the charging funnel of the electron beam melting furnace body 21, and the metal raw material Nb is placed in the crucible 5 of the electron beam melting furnace body 21. During the whole preparation process, the temperature of the crucible 5 is maintained at 200°C. In order to maintain the temperature of the tongs pot 5, the fan 41 and the water pump 35 are started, so that the water pump 35 transports the cooling water inside the water tank 3 to the inside of the water cooling pipe 51 through the water inlet pipe 53, so that the water cooling pipe 51 dissipates heat to the tongs pot 5 and maintains the temperature of the tongs pot 5. At this time, the water outlet pipe 53 transports the heated water to the inside of the water tank 3. At this time, the fan 41 blows air upward from the inside of the fixed frame 4, so that the external wind passes through the side of the heat sink 32, so that the heat extracted from the inside of the water tank 3 by the heat sink 32 is blown out of the inside of the base 2 through the ventilation window 25, thereby dissipating the heat of the water inside the water tank 3;

[0056] Close the door 22 of the electron beam melting furnace body 21, and start the mechanical pump of the electron gun 24, the electron gun diffusion pump, the mechanical pump of the melting chamber, the roots pump of the melting chamber, and the diffusion pump of the melting chamber in sequence, so that the vacuum degree of the electron beam melting furnace body 21 is less than 5×10-2Pa, and the vacuum degree of the electron gun 24 chamber is less than 5×10-3Pa; set the high voltage of the electron gun 24 to 25kW, preheat the high voltage for 10min, turn off the high voltage, set the beam current of the electron gun 24 to 70mA, preheat the beam current for 10min, and turn off the beam current of the electron gun 24;

[0057] The raw materials are simultaneously turned on the high voltage and beam current of the electron gun 24. After stabilization, the alloy raw materials in the crucible 5 are bombarded with the electron gun 24. The electron gun beam current is increased to 450 mA, and the rate of beam current increase is 4 mA / s, until all the alloy raw materials are melted. The electron beam current is maintained at 400 mA for alloy melting, and the melting time is 35 minutes.

[0058] After the alloy is melted, reduce the electron beam current to 100mA;

[0059] After the alloy melt is melted into an alloy ingot, the electron gun 24 is turned off, and the alloy is cooled in the electron beam melting chamber for 25 minutes. At this time, the user starts the air pump 6 to blow air into the interior of the electron beam melting furnace body 21, so that the hot air inside the electron beam melting furnace body 21 enters the interior of the air inlet pipe 37 through the air outlet pipe 62, and then the air inlet pipe 37 transports the hot air to the interior of the water tank 3, mixes with the cooling water inside the water tank 3, and then discharges it through the pressure relief valve 38, and then opens the door 22 of the electron beam melting furnace body 21 to take out the alloy.

[0060] Compared with the related art, the electron beam melting device provided by the present invention has the following beneficial effects:

[0061] By cooperating with each other through structures such as the water tank 3, the heat sink 32, the air inlet pipe 37, the fixed frame 4, the fan 41, the air pump 6, the air pipe 61 and the air outlet pipe 62, when continuing to be used, the hot air inside the electron beam melting furnace body 21 can be blown into the interior of the water tank 3 through the air outlet pipe 62 and the air inlet pipe 37, and mixed with the cooling water, so as to cool the hot air inside the electron beam melting furnace body 21, and then discharged through the pressure relief valve 38. In this way, the interior of the electron beam melting furnace body 21 can be quickly dissipated, the efficiency of heat dissipation in the furnace is increased, and the direct discharge of the hot air inside the electron beam melting furnace body 21 can be avoided to cause burns to the staff, thereby increasing safety.

[0062] Second embodiment

[0063] Please refer to Figure 6 Based on the electron beam melting device provided in the first embodiment of the present application, the second embodiment of the present application provides another electron beam melting device. The second embodiment is only a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.

[0064] Specifically, the difference of the electron beam melting device provided in the second embodiment of the present application is that, in an electron beam melting device, a rotating groove 7 is provided on the outer side surface of the thread ring 42, and a rotating block 71 is rotatably connected to the inner side surface of the rotating groove 7, a rotating plate 72 is fixedly installed on one side of the rotating block 71, a connecting plate 73 is fixedly installed on one side of the rotating plate 72, and a cleaning brush 74 is fixedly installed on the top of the connecting plate 73.

[0065] The top of the cleaning brush 73 is attached to the bottom of the filter screen 43 .

[0066] The working principle of an electron beam melting device provided by the present invention is as follows:

[0067] When a lot of dust accumulates on the filter 43 after long-term use, the user can rotate the rotating plate 72 to make the rotating plate 72 drive the rotating block 71 to rotate on the inner side of the rotating groove 7, so that the rotating block 71 and the rotating groove 7 limit the rotating plate 72, and then make the connecting plate 73 drive the cleaning brush 73 to rotate, so that the cleaning brush 73 cleans the filter 43 to prevent dust from accumulating on the filter 43.

[0068] Compared with the related art, the electron beam melting device provided by the present invention has the following beneficial effects:

[0069] By cooperating with the structures such as the rotating groove 7, the rotating block 71, the rotating plate 72, the connecting plate 73 and the cleaning brush 74, when in use, the rotating plate 72 can drive the cleaning brush 74 through the connecting plate 73 to clean the dust at the bottom of the filter 43, so as to avoid dust accumulation on the filter 43, thereby causing blockage of the filter 43 and affecting the heat dissipation effect.

[0070] In order to solve the above problems, the present invention also provides a method for preparing a niobium-based ultra-high temperature alloy by an electron beam melting device, comprising the following steps: S1, material preparation: according to the alloy ratio, the alloying element metal raw material Zr is added to the charging funnel of the electron beam melting furnace body 21, and the metal raw material Nb is placed in the crucible 5 of the electron beam melting furnace body 21. During the whole preparation process, the temperature of the crucible 5 is maintained at 200°C. In order to maintain the temperature of the clamp pot 5, the fan 41 and the water pump 35 are started, so that the water pump 35 transports the cooling water inside the water tank 3 to the inside of the water cooling pipe 51 through the water inlet pipe 53, so that the water cooling pipe 51 dissipates heat to the clamp pot 5 and maintains the temperature of the clamp pot 5. At this time, the water outlet pipe 53 transports the heated water to the inside of the water tank 3. At this time, the fan 41 blows upward from the inside of the fixed frame 4, so that the external wind passes through the side of the heat sink 32, so that the heat extracted from the inside of the water tank 3 by the heat sink 32 is blown out of the inside of the base 2 through the ventilation window 25, thereby dissipating the water inside the water tank 3;

[0071] S2, preheating: close the door 22 of the electron beam melting furnace body 21, turn on the electron gun 24 mechanical pump, electron gun diffusion pump, melting chamber mechanical pump, melting chamber Roots pump, and melting chamber diffusion pump in sequence, so that the vacuum degree of the electron beam melting furnace body 21 is less than 5×10-2Pa, and the vacuum degree of the electron gun 24 chamber is less than 5×10-3Pa; set the high voltage of the electron gun 24 to 25kW, preheat the high voltage for 10min, turn off the high voltage, set the beam current of the electron gun 24 to 70mA, preheat the beam current for 10min, and turn off the beam current of the electron gun 24;

[0072] S3, raw material smelting: turn on the high voltage and beam current of the electron gun 24 at the same time, bombard the alloy raw material in the crucible 5 with the electron gun 24 after stabilization, increase the electron gun beam current to 450mA, and increase the beam current at a rate of 4mA / s until all the alloy raw materials are melted, maintain the electron beam current at 400mA for alloy smelting, and the smelting time is 35min;

[0073] S4, directional solidification: after the alloy is melted, reduce the electron beam current to 100mA;

[0074] S4, post-processing: after the alloy melt is melted into an alloy ingot, the electron gun 24 is turned off, and the alloy is cooled in the electron beam melting chamber with the furnace for 25 minutes. At this time, the user starts the air pump 6 to make the air pump 6 blow air into the inside of the electron beam melting furnace body 21, so that the hot air inside the electron beam melting furnace body 21 enters the inside of the air inlet pipe 37 through the air outlet pipe 62, and then the air inlet pipe 37 transports the hot air to the inside of the water tank 3, mixes with the cooling water inside the water tank 3, and then discharges it through the pressure relief valve 38, and then opens the door 22 of the electron beam melting furnace body 21 to take out the alloy.

[0075] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. An electron beam melting device, characterized in that: include: A base, a body of the electron beam melting furnace is fixedly mounted on the top of the base, and an electron gun is fixedly mounted on the top of the body of the electron beam melting furnace; A clamp pot, wherein the clamp pot is arranged on the inner side of the electron beam melting furnace body, a water cooling pipe is arranged inside the clamp pot, a water inlet pipe is fixedly installed at the input end of the water cooling pipe, and a water outlet pipe is fixedly installed at the output end of the water cooling pipe; A water tank, the water tank is fixedly mounted on the inner side of the base, a mounting groove is provided on the side of the water tank, a through groove is provided on the top of the water tank, the through groove extends to the bottom of the water tank, the interior of the through groove and the interior of the mounting groove are connected, a plurality of heat sinks are provided on the inner side of the mounting groove, the tops and bottoms of the plurality of heat sinks are both arranged inside the water tank, a mounting plate is fixedly mounted on the inner side of the through groove, a water pump is fixedly mounted on the top of the mounting plate, a water filling pipe and an air inlet pipe are respectively fixedly mounted on the top of the water tank, and a pressure relief valve is fixedly mounted on one side of the water tank; An air pump, wherein the air pump is fixedly mounted on the back of the electron beam melting furnace body, an air inlet pipe is fixedly mounted on the output end of the air pump, the output end of the air inlet pipe is arranged inside the electron beam melting furnace body, an air outlet pipe is fixedly mounted on the back of the electron beam melting furnace body, and the air outlet pipe is fixedly mounted on the top of the air inlet pipe; A fixed frame is fixedly installed on the bottom of the base, and a fan is fixedly installed on the inner side surface of the fixed frame.

2. The electron beam melting device according to claim 1, characterized in that: The front side of the electron beam melting furnace body is rotatably connected with a door body, and the front side of the door body is fixedly installed with an observation window.

3. The electron beam melting device according to claim 2, characterized in that: Ventilation windows are fixedly installed on both sides of the base, a thermometer is fixedly installed on the front of the base, and a detection probe of the thermometer is arranged on the inner side of the water tank.

4. The electron beam melting device according to claim 3, characterized in that: The water outlet pipe is fixedly installed on the top of the water tank, the water inlet pipe is fixedly installed on the output end of the water pump, and the input end of the water pump is arranged inside the water tank.

5. The electron beam melting device according to claim 4, characterized in that: The output end of the air intake pipe is arranged inside the water tank.

6. The electron beam melting device according to claim 5, characterized in that: The bottom of the outer side surface of the fixing frame is threadedly connected to a thread ring, and the inner side surface of the thread ring is fixedly mounted with a filter screen.

7. The electron beam melting device according to claim 1, characterized in that: The clamp pot is arranged at the bottom of the electron gun.

8. The electron beam melting device according to claim 6, characterized in that: A rotating groove is formed on the outer side of the threaded ring, a rotating block is rotatably connected to the inner side of the rotating groove, a rotating plate is fixedly installed on one side of the rotating block, a connecting plate is fixedly installed on one side of the rotating plate, and a cleaning brush is fixedly installed on the top of the connecting plate.

9. The electron beam melting device according to claim 8, characterized in that: The top of the cleaning brush 73 is attached to the bottom of the filter screen 43 .

10. A method for preparing a niobium-based ultrahigh temperature alloy using an electron beam melting device, characterized in that: The following steps are involved: S1. Material preparation: according to the alloy ratio, the alloying element metal raw material Zr is added into the charging funnel of the electron beam melting furnace body, and the metal raw material Nb is placed into the crucible of the electron beam melting furnace body. During the whole preparation process, the temperature of the crucible is kept at 200°C. In order to maintain the temperature of the tongs pot, the fan and the water pump are started, so that the water pump transports the cooling water inside the water tank to the inside of the water cooling pipe through the water inlet pipe, so that the water cooling pipe dissipates the heat of the tongs pot and maintains the temperature of the tongs pot. At this time, the water outlet pipe transports the heated water to the inside of the water tank. At this time, the fan blows upward from the inside of the fixed frame, so that the external wind passes through the side of the heat sink, so that the heat extracted from the inside of the water tank by the heat sink is blown out of the inside of the base through the ventilation window, so as to dissipate the heat of the water inside the water tank; S2, preheating: close the door of the electron beam melting furnace body, turn on the electron gun mechanical pump, electron gun diffusion pump, melting chamber mechanical pump, melting chamber Roots pump, and melting chamber diffusion pump in sequence, so that the vacuum degree of the electron beam melting furnace body is less than 5×10-2Pa, and the vacuum degree of the electron gun chamber is less than 5×10-3Pa; set the high voltage of the electron gun to 25kW, preheat the high voltage for 10min, turn off the high voltage, set the electron gun beam current to 70mA, preheat the beam current for 10min, and turn off the electron gun beam current; S3, raw material smelting: turn on the high voltage and beam current of the electron gun at the same time, bombard the alloy raw materials in the crucible with the electron gun after stabilization, increase the electron gun beam current to 450mA, and the rate of beam current increase is 4mA / s, until the alloy raw materials are completely melted, maintain the electron beam current at 400mA for alloy smelting, and the smelting time is 35min; S4, directional solidification: after the alloy is melted, reduce the electron beam current to 100mA; S4. Post-processing: After the alloy melt is melted into an alloy ingot, the electron gun is turned off, and the alloy is cooled in the electron beam melting chamber with the furnace for 25 minutes. At this time, the user starts the air pump to blow air into the interior of the electron beam melting furnace body, so that the hot air inside the electron beam melting furnace body enters the interior of the air inlet pipe through the air outlet pipe, and then the air inlet pipe transports the hot air to the interior of the water tank, mixes with the cooling water inside the water tank, and then discharges it through the pressure relief valve, and then opens the door of the electron beam melting furnace body to take out the alloy.