Pumped storage power station upper and lower reservoir combined flood regulation calculation method and system

Through the water balance model based on the design of the flood process group, the problem of neglecting water level impact in the calculation of flood regulation of pumped storage power stations is solved, and the accurate calculation and rapid adjustment of water level changes in upper and lower reservoirs is achieved, providing a new calculation method and technical basis.

CN118964778APending Publication Date: 2024-11-15SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410893166.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing flood regulation calculation method for pumped storage power stations ignores the impact of the water level of the upper and lower reservoirs on the water exchange volume and leakage flow between reservoirs, resulting in calculation deviations.

Method used

The water level change process is derived based on the design flood process group. By traversing the time period of each designed flood process, the end water level of the upper and lower reservoirs is assumed and corrected according to the water volume equilibrium equation, the water level change process is derived from the time period to realize the joint flood regulation calculation of the upper and lower reservoirs. .

Benefits of technology

Improves calculation accuracy and speed, can perform flood process regulation calculation under any initial conditions, is suitable for any pumped storage power station state, is simple and flexible, provides new calculation methods and technical foundations, laying the foundation for intelligence and informatization .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118964778A_ABST
    Figure CN118964778A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of reservoir flood regulation, and provides a pumped storage power station upper and lower reservoir combined flood regulation calculation method and system. According to the pumped storage power station upper and lower reservoir combined flood regulation calculation method, design flood processes under different flood encountering times are established based on a design flood process group derivation model, all time periods of each design flood process are traversed, the assumed values of the final water levels of the upper and lower reservoirs at the end of the time periods are proposed, and the final water levels of the upper and lower reservoirs at the end of the time periods are calculated. And continuously correcting according to a water balance equation so as to deduce the water level change process of the upper and lower reservoirs period by period, and carrying out joint flood regulation calculation on the upper and lower reservoirs of the pumped storage power station, so that the calculation speed is high, the corresponding time is short and the solving precision is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of reservoir flood regulation, and in particular relates to a calculation method and system for combined flood regulation of upper and lower reservoirs of a pumped storage power station. Background Art

[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] At present, the calculation method for flood regulation of pumped-storage power stations mainly focuses on the flood regulation calculation of the lower reservoir of the pumped-storage power station. The most unfavorable combination of floods entering the reservoir is found by sliding superposition of the power generation flow of the power station and the flood flow. It fails to consider the impact of floods on the water levels of the upper and lower reservoirs under the actual operation of the pumped-storage power station, and ignores the impact of the water levels of the upper and lower reservoirs on the water exchange volume and discharge volume between the reservoirs, which ultimately leads to calculation deviations of the flood levels of the upper and lower reservoirs of the pumped-storage power station. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a method and system for calculating the joint flood regulation of the upper and lower reservoirs of a pumped-storage power station. The method and system are based on a derivation model of a design flood process group, establish a design flood process under different flood encounter times, and traverse each time period of each design flood process to propose an assumed value of the final water level of the upper and lower reservoirs at the end of the time period, and continuously correct it according to the water balance equation, so as to deduce the water level change process of the upper and lower reservoirs time by time period, and perform the joint flood regulation calculation of the upper and lower reservoirs of the pumped-storage power station.

[0005] In order to achieve the above object, the present invention adopts the following technical solution:

[0006] A first aspect of the present invention provides a calculation method for combined flood regulation of upper and lower reservoirs of a pumped storage power station.

[0007] In one or more embodiments, a method for calculating combined flood regulation of upper and lower reservoirs of a pumped storage power station is provided, comprising:

[0008] Based on the relationship between the load instruction of the power grid and the output flow and input flow of the pumped storage power station at the initial and final water levels of the upper reservoir and the lower reservoir, a flow calculation model for the pumped storage power station unit is constructed;

[0009] By adjusting the design flood phase of the upper and lower reservoirs of the pumped storage power station, multiple design flood process lines are generated and recorded to obtain a design flood process group;

[0010] Traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions;

[0011] Based on the flow calculation model of the pumped storage power station unit, the target unit flow value under the current assumed conditions is obtained, the gap between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value is compared, the final water level values ​​of the upper reservoir and the lower reservoir under the assumed conditions are updated, and the target flow value is recalculated;

[0012] The unit flow value obtained by water balance of the upper reservoir and the lower reservoir is subtracted from the target unit flow value. When the set accuracy is met, the calculation of the next period starts until the calculation period ends. After traversing all the design flood processes in the design flood process group, the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station is obtained;

[0013] Based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir is determined respectively. According to the relationship between the water level and storage capacity and the principle of water balance, the storage capacity process and the downstream flow process are calculated.

[0014] A second aspect of the present invention provides a combined flood regulation calculation system for upper and lower reservoirs of a pumped storage power station.

[0015] In one or more embodiments, a pumped storage power station upper and lower reservoir combined flood regulation calculation system includes:

[0016] A unit flow calculation model building module is used to build a pumped storage power station unit flow calculation model based on the relationship between the power grid load instruction and the output flow and input flow of the pumped storage power station at the initial and final water levels of the upper reservoir and the initial and final water levels of the lower reservoir;

[0017] A design flood process group calculation module, which is used to generate and record multiple design flood process lines by adjusting the design flood phase of the upper reservoir and the lower reservoir of the pumped storage power station to obtain a design flood process group;

[0018] The module for calculating the assumed unit flow value is used to traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions;

[0019] The target flow value recalculation module is used to obtain the target unit flow value under the current assumed conditions based on the unit flow calculation model of the pumped storage power station, compare the difference between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value, update the upper reservoir and the lower reservoir end water level values ​​under the assumed conditions, and recalculate the target flow value;

[0020] The reservoir water level process group calculation module is used to make a difference between the unit flow value obtained by water balance of the upper reservoir and the lower reservoir and the target unit flow value, and start the calculation of the next period after the set accuracy is met until the calculation period ends. After traversing all the design flood processes in the design flood process group, the water level process groups of the upper reservoir and the lower reservoir of the pumped storage power station are obtained;

[0021] The storage capacity and downstream flow process calculation module is used to determine the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, and calculate its storage capacity process and downstream flow process according to the water level storage capacity relationship and water balance principle.

[0022] A third aspect of the present invention provides a computer-readable storage medium.

[0023] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps in the above-mentioned calculation method for combined flood regulation of upper and lower reservoirs of a pumped-storage power station.

[0024] A fourth aspect of the present invention provides an electronic device.

[0025] An electronic device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps in the above-mentioned method for calculating combined flood regulation of upper and lower reservoirs of a pumped storage power station are implemented.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] (1) The present invention starts from the principle of water balance and gives the water balance relationship between the upper and lower reservoirs of a pumped-storage power station. By performing joint flood regulation calculation on the upper and lower reservoirs, the change process of the water levels of the upper and lower reservoirs under various flood conditions is obtained, and a joint flood regulation calculation method for the upper and lower reservoirs is proposed accordingly. Moreover, by performing water level process trial calculations in sequence in each time period, the method can perform regulation calculations in sequence according to the flood process under any initial conditions of the upper and lower reservoirs. A program (such as Python) can be written to handle the joint flood regulation calculation of the upper and lower reservoirs of a pumped-storage power station under any state of the upper and lower reservoirs and any flood process, which is easier to implement.

[0028] (2) The combined flood regulation calculation method of the upper and lower reservoirs of the present invention has a simple principle, is easy and flexible to operate, and is easy to realize in real time. The water levels at the end of each period of the upper and lower reservoirs in the trial calculation process are improved based on the difference between the flow rates of the upper and lower reservoir units and the flow rates of the target units, and the water balance calculation is performed for each period. The calculation speed is fast, the response time is short, and the solution accuracy is high.

[0029] (3) The combined flood regulation calculation method of the upper and lower reservoirs of the present invention can provide support for the calculation of water level parameters in the subsequent design process of the pumped-storage power station and the flood level warning calculation in actual operation; this technology provides a new calculation method and technology for the combined flood regulation calculation of the upper and lower reservoirs of the pumped-storage power station, and also lays the foundation for the intelligentization and informatization of flood regulation in pumped-storage power stations. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0031] Figure 1 is a schematic diagram of an electronic device according to an embodiment of the present invention;

[0032] Figure 2 A schematic flow chart of a method for calculating combined flood regulation of upper and lower reservoirs of a pumped storage power station according to an embodiment of the present invention;

[0033] Figure 3 It is a schematic structural diagram of a combined flood regulation system for upper and lower reservoirs of a pumped storage power station according to an embodiment of the present invention;

[0034] Figure 4 It is a curve diagram showing the relationship between the water level and storage capacity of the upper reservoir of the pumped storage power station in the embodiment of the present invention;

[0035] Figure 5 It is a curve diagram showing the relationship between the water level and storage capacity of the lower reservoir of the pumped storage power station in the embodiment of the present invention;

[0036] Figure 6 It is a curve diagram showing the relationship between the water level and discharge flow of the upper reservoir of the pumped storage power station in the embodiment of the present invention;

[0037] Figure 7 It is a curve diagram showing the relationship between the water level and discharge flow of the lower reservoir of the pumped storage power station in the embodiment of the present invention;

[0038] Figure 8 It is a design flood process diagram included in the design flood process group in the embodiment of the present invention;

[0039] Fig. 9 It is a calculation result diagram of the water level variation process of the upper reservoir of the pumped storage power station in the embodiment of the present invention;

[0040] Fig.10 This is a diagram showing the calculation results of the water level variation process of the lower reservoir of a pumped storage power station in an embodiment of the present invention. DETAILED DESCRIPTION

[0041] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0042] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.

[0043] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0044] Reference Figure 1 , a schematic diagram of an electronic device is given. It should be noted that, Figure 1 The electronic device 100 shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.

[0045] like Figure 1 As shown, the electronic device 100 includes a central processing unit (CPU) 101, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 102 or a program loaded from a storage part 108 into a random access memory (RAM) 103. In the RAM 103, various programs and data required for system operation are also stored. The central processing unit 101, the ROM 102, and the RAM 103 are connected to each other via a bus 104. An input / output (I / O) interface 105 is also connected to the bus 104.

[0046] The following components are connected to the I / O interface 105: an input section 106 including a keyboard, a mouse, etc.; an output section 107 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 108 including a hard disk, etc.; and a communication section 109 including a network interface card such as a local area network (LAN) card, a modem, etc. The communication section 109 performs communication processing via a network such as the Internet. A drive 110 is also connected to the I / O interface 105 as needed. A removable medium 111, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 110 as needed, so that a computer program read therefrom is installed into the storage section 108 as needed.

[0047] When the central processing unit 101 in the electronic device of this embodiment executes the program, the following is achieved: Figure 2 The steps in the calculation method for combined flood regulation of the upper and lower reservoirs of a pumped storage power station are shown.

[0048] Figure 2 FIG. 1 is a flow chart of a method for calculating a combined flood regulation of upper and lower reservoirs of a pumped storage power station according to an embodiment of the present invention. Figure 2 The calculation method for combined flood regulation of the upper and lower reservoirs of the pumped storage power station in this embodiment may include:

[0049] S201, constructing a flow calculation model for pumped-storage power station units based on the relationship between the grid load command and the output flow and input flow of the pumped-storage power station at the initial and final water levels of the upper reservoir and the lower reservoir.

[0050] In step S201, the grid load instruction includes two parts: a pumped storage power station output instruction sequence and a pumped storage input instruction sequence. Each part includes multiple output and input instruction values ​​issued by the power grid to the pumped storage power station. The output and input calculation method of the pumped storage power station is:

[0051]

[0052] or

[0053] Among them, N out 、N in A is the output and input of the pumped storage power station unit respectively; out , A in are the output and input coefficients of the pumped storage power station units respectively; Q e It is the flow rate of pumped storage power station units; They are the average water levels of the upper and lower reservoirs of the pumped-storage power station respectively.

[0054] Based on the grid load instruction and the initial and final water levels of the upper and lower reservoirs, the unit flow calculation model is:

[0055]

[0056] or

[0057] Among them, Q e,out , Q e,in They are the output and input flow of the pumped storage power station units respectively; They are the output and input command values ​​issued by the power grid to the pumped storage power station; They are the initial and final water levels of the upper reservoir of the pumped storage power station during the period; They are the initial and final water levels of the lower reservoir of the pumped storage power station; A out and A in They are the output and input coefficients of the pumped-storage power station units respectively.

[0058] S202, a design flood phase adjustment method of the upper reservoir and the lower reservoir of the pumped storage power station is adopted to generate and record a plurality of design flood process lines to obtain a design flood process group.

[0059] In step S202, the design flood phase adjustment method of the upper and lower reservoirs of the pumped storage power station is:

[0060]

[0061] in, is the i-th flood process matrix in the design flood process group; is the design flood process matrix of the upper and lower reservoirs of the pumped storage power station; T is the number of flood regulation calculation periods; t is the length of the design flood process matrix of the upper and lower reservoirs of the pumped storage power station.

[0062] The design flood process groups are:

[0063]

[0064] in, is the design flood process group of the pumped storage power station; N is the number of design floods in the design flood process group of the pumped storage power station; It is the Nth flood process matrix in the design flood process group.

[0065] S203, traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions.

[0066] In step S203, the design flood process group is traversed, and the design flood process group is traversed. arrive The calculations are carried out sequentially, and the final water levels of the upper and lower reservoirs of the pumped-storage power station are assumed one by one in each time period for each design flood process.

[0067] According to the water balance equation, a calculation model for the water volume change in the upper and lower reservoirs of a pumped storage power station is established. The calculation method is as follows:

[0068]

[0069]

[0070] Where, ΔV up,t , ΔV down,t are the water volume changes in the upper and lower reservoirs of the pumped storage power station during period t; Q n,t The design flood process currently traversed Flood flow in the middle period t; d tis the length of time period t; q up,t ,q down,t are the discharge flows of the upper and lower reservoirs of the pumped storage power station during period t, respectively, and are determined by the relationship between the water level of the upper and lower reservoirs and the discharge flow f(q)=H.

[0071] S204, based on the unit flow calculation model of the pumped storage power station, obtain the target unit flow value under the current assumed conditions, compare the gap between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value, update the final water level values ​​of the upper reservoir and the lower reservoir under the assumed conditions, and recalculate the target flow value.

[0072] In step S204, the target unit flow value calculation process under the current assumption is:

[0073]

[0074] or

[0075] in, is the target unit flow value in time period t under the generating condition of the pumped storage power station; is the target unit flow value in time period t under the pumping condition of the pumped storage power station; are the initial water levels of the upper and lower reservoirs of the pumped storage power station during period t, respectively; They are the assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped-storage power station during period t.

[0076] The process of updating the assumed upper and lower reservoir final water level values ​​and recalculating the target flow value is as follows:

[0077] Calculate the unit flow corresponding to the upper and lower reservoirs of the pumped storage power station:

[0078]

[0079] Among them, Q e,up,t , Q e,down,t They are the unit flow rates of the upper and lower reservoirs of the pumped-storage power station corresponding to time period t.

[0080] Calculate the difference between the unit flow corresponding to the upper and lower reservoirs of the pumped storage power station and the target unit flow value:

[0081] In the power generation condition of pumped storage power station:

[0082]

[0083] In pumping conditions of pumped storage power station:

[0084]

[0085] Among them, ΔQ′ e,up,t , ΔQ′ e,down,t They are the differences between the unit flow corresponding to the upper and lower reservoirs of the pumped-storage power station and the target flow value.

[0086] According to the difference between the unit flow rate corresponding to the upper and lower reservoirs and the target flow rate value, update the assumed final water level values ​​of the upper and lower reservoirs:

[0087]

[0088] in, is the flow correlation coefficient in the update function, which can be 0.001 to 0.005; is the correlation coefficient of reservoir water level in the update function, which can be 0.001 to 0.005; They are the normal water level and dead water level of the upper reservoir of the pumped storage power station; They are the normal water level and dead water level of the lower reservoir of the pumped-storage power station respectively. They are the assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped storage power station before the update; They are respectively the updated assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped-storage power station.

[0089] Recalculate the target unit flow value based on the updated upper and lower reservoir final water level values (or ) size.

[0090] S205, subtract the unit flow value obtained through water balance of the upper reservoir and the lower reservoir from the target unit flow value, and start the calculation of the next period after the set accuracy is met until the end of the calculation period. After traversing all the design flood processes in the design flood process group, the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station is obtained.

[0091] In S205, the accuracy conditions required for starting the next period calculation are as follows:

[0092]

[0093] or

[0094] When the iteration process meets the accuracy condition, the calculation of the period t is stopped, and the final water levels of the upper and lower reservoirs of the pumped storage power station in period t are obtained. And start the calculation of the next period.

[0095] It should be noted here that the accuracy can be set according to the actual situation and will not be described in detail here.

[0096] The initial water level condition for the next period is calculated as follows:

[0097]

[0098]

[0099] in, They are the initial water level conditions of the upper and lower reservoirs of the pumped storage power station during period t+1.

[0100] Going through the design flood process Then, the water level process of the upper and lower reservoirs of the pumped storage power station under the design flood process can be obtained. and Its structure is as follows:

[0101]

[0102] in, are the nth design flood process After flood regulation calculation, the corresponding water level process of the upper and lower reservoirs of the pumped storage power station; are the initial water levels of the upper and lower reservoirs of the pumped storage power station in time period t during the nth design flood process; They are the final water levels of the upper and lower reservoirs of the pumped-storage power station in time period T during the nth design flood process.

[0103] Traversal Design Flood Process Group After completing the design flood process, the water level process group of the upper and lower reservoirs of the pumped storage power station can be obtained. and Its structure is as follows:

[0104]

[0105] in, They are the water level process groups of the upper and lower reservoirs of the pumped storage power station respectively.

[0106] S206, based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, respectively determine the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir, and calculate their storage capacity process and downstream flow process according to the water level storage capacity relationship and the water balance principle.

[0107] In step S206, in the process of determining the reservoir water level corresponding to the highest water level of the upper and lower reservoirs, the matrix structure of the upper reservoir water level process group of the pumped storage power station is:

[0108]

[0109] in, It represents the initial water level of the upper reservoir in the first design flood process of the pumped storage power station in period 1; It represents the initial water level of the upper reservoir in the pumped storage power station during the first design flood process in period T; It represents the final water level of the upper reservoir in the pumped storage power station during the first design flood process in period T; It represents the initial water level of the upper reservoir in period 1 during the Nth design flood process of the pumped storage power station; Initial water level of the upper reservoir at the pumped storage power station during the Nth design flood process in period T; It represents the final water level of the upper reservoir in the Nth design flood process of the pumped storage power station in the period T. Determine the row number i and column number j where the largest element is located, then row number i represents the design flood process number n corresponding to the highest water level in the upper reservoir, and column number j represents the period t corresponding to the highest water level in the upper reservoir. The water level process matrix structure of the lower reservoir of the pumped storage power station is the same as that of the upper reservoir, and the method for determining the design flood process number where the highest water level is located and the period of occurrence of the highest water level are the same as those of the upper reservoir.

[0110] The method for calculating the storage capacity of the upper and lower reservoirs of a pumped storage power station is as follows:

[0111] According to the relationship between the water level and storage capacity of the upper and lower reservoirs of the pumped storage power station, f(H) = V, the upper and lower reservoir water level process group matrix can be converted into the upper and lower reservoir storage capacity process group matrix and The two have the same structure, where the upper reservoir capacity process group matrix structure is:

[0112]

[0113] in, It is the process group matrix of the upper reservoir capacity of the pumped storage power station; is the storage capacity of the upper reservoir of the pumped storage power station in the nth design flood process and time period t. The calculation method of the storage capacity process group matrix of the lower reservoir is the same as that of the upper reservoir.

[0114] The method for calculating the discharge flow of the upper and lower reservoirs of a pumped storage power station is as follows:

[0115] For the upper reservoir of the pumped storage power station, according to the upper reservoir water level process group matrix The average water level process of the period can be calculated to obtain the average water level process group matrix of the upper reservoir period

[0116]

[0117] in, The process group matrix of the average water level of the upper reservoir of the pumped storage power station during the period; It is the average water level of the upper reservoir of the pumped storage power station in time period t under the nth design flood process.

[0118] For the lower reservoir of a pumped storage power station, the average water level process matrix of the lower reservoir period is The calculation method is the same as that of the upper reservoir.

[0119] According to the relationship between the water level of the upper and lower reservoirs and the discharge flow f(H=q), the discharge flow process group matrix q of the upper and lower reservoirs of the pumped storage power station can be calculated: up,array With q down,array , the two have the same structure, where the upper reservoir discharge flow process group matrix q up,array The structure is:

[0120]

[0121] Among them, q up,array It is the discharge flow process group matrix of the upper reservoir of the pumped storage power station; It is the discharge flow of the upper reservoir of the pumped storage power station in time period t under the nth design flood process.

[0122] Taking a pumped-storage power station in a certain county of a certain province as an example, a combined flood regulation calculation method for the upper and lower reservoirs of a pumped-storage power station of the present invention is used to perform combined flood regulation calculation for the upper and lower reservoirs of the pumped-storage power station in the region, to illustrate the effectiveness and rationality of the present invention.

[0123] The installed capacity of the pumped storage power station is 1800MW, with 6 units installed, and the capacity of each unit is 300MW. The catchment area above the dam site of the power station is 4.3km 2 , normal water level is 1326.00m, storage capacity below normal water level is 12.67 million m 3 , dead water level 1298.0m, dead reservoir capacity 1.06 million m 3 , regulating reservoir capacity 11.84 million m 3 The catchment area above the lower reservoir dam site is 25.31km 2 , normal water level is 902.00m, and the storage capacity below normal water level is 14.36 million m 3 , dead water level 865.00m, dead reservoir capacity 2.47 million m 3 , regulating reservoir capacity 11.9 million m 3 , rated head 425.00m.

[0124] (1) Input settings of the upper and lower reservoir joint flood regulation calculation model

[0125] According to 80% and 56% of the installed capacity of the pumped storage power station, the output value and input value of the pumped storage power station in the power grid load instruction are respectively used, as shown in Table 1:

[0126] Table 1 Pumped storage power station grid load instruction sequence (unit: MW)

[0127]

[0128] The number of calculation periods for flood regulation of the upper and lower reservoirs of the pumped storage power station is 96, with a period length of 1 hour, and the number of periods for the input and output process of the unit is 12, with a period length of 1 hour. The output coefficient of the pumped storage power station is 8.3, and the input coefficient is 6.64.

[0129] The relationship between water level and storage capacity of the upper and lower reservoirs of a pumped storage power station is as follows: Figure 4 and Figure 5 As shown in the figure, the relationship between the water level of the upper and lower reservoirs and the discharge flow is as follows: Figure 6 and Figure 7 shown.

[0130] The design flood for this flood regulation calculation is calculated using the 1% probability flood of the upper reservoir. Considering that the upper and lower reservoirs are close to each other and are in the same basin, it can be assumed that the upper and lower reservoirs enter the reservoir at the same time. The 1% flood flow process is shown in Table 2:

[0131] Table 2 1% probability flood flow process of pumped storage power station (unit: m 3 / s)

[0132]

[0133]

[0134] (2) Design flood process group generation

[0135] Based on the 1% probability flood flow process of the pumped storage power station, a number of design flood flow process lines are generated and recorded by phase adjustment. Considering the most unfavorable encounter between the flood process and the working state of the pumped storage power station, 12 kinds of flood encounter times under the overlapping conditions of the two are taken to obtain the design flood process group. Figure 8 shown.

[0136] (3) Calculation results of combined flood regulation of upper and lower reservoirs of pumped storage power stations

[0137] Depend on Fig. 9 As shown in the figure, the effects of the design floods under the 12 flood encounter times on the water level change process of the upper reservoir of the pumped storage power station are different. Among them, the design flood 2 is the most unfavorable design flood process for the upper reservoir of the pumped storage power station among the 12 flood encounter times, and its highest water level is the highest among the 12 flood encounter times.

[0138] Similarly, by Fig.10As shown in the figure, the design floods under 12 flood encounter times have different effects on the change process of the lower reservoir of the pumped storage power station. Among them, the design flood 1 is the most unfavorable design flood process for the lower reservoir of the pumped storage power station among the 12 flood encounter times, and its highest water level is the highest among the 12 flood encounter times. It can be seen that the combined flood regulation calculation method of the upper and lower reservoirs of the pumped storage power station can quickly calculate the change process of the water level of the upper and lower reservoirs of the pumped storage power station under various design flood processes. At the same time, the flood regulation calculation process considers the influence of the power generation flow of the pumped storage power station under a given load on the storage capacity of the upper and lower reservoirs, and performs flood regulation calculation on it under the condition of satisfying the hydraulic connection between the upper and lower reservoirs of the pumped storage power station.

[0139] In addition, the combined flood regulation calculation method of the upper and lower reservoirs of the pumped storage power station according to the embodiment of the present invention has a simple principle, strong operability, and wide applicability, and can avoid the problems of slow solution speed, poor accuracy, and neglect of the hydraulic connection between the upper and lower reservoirs in the traditional flood regulation calculation method. At present, this method traverses each design flood in the design flood process group and performs flood regulation calculations on them one by one. In fact, since each design flood process is independent of each other, parallel calculation can be used to perform flood regulation calculations on multiple design flood processes at the same time to shorten the calculation time. In the future, in-depth research should be conducted on the parallelization improvement of the calculation method, and parallel calculation should be used to reduce the calculation time of the model under multiple design flood processes.

[0140] In particular, according to an embodiment of the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a computer readable medium, the computer program including a computer program for executing Figure 2 In such an embodiment, the computer program can be downloaded and installed from the network through the communication part 109, and / or installed from the removable medium 111. When the computer program is executed by the central processing unit 101, various functions defined in the apparatus of the present application are executed.

[0141] in, Figure 2 The computer program instructions corresponding to the method shown may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0142] A person skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing the relevant hardware through a computer program, and the program can be stored in a computer-readable storage medium, and when the program is executed, it can include the processes of the embodiments of the above-mentioned methods. The storage medium can be a disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM), etc.

[0143] Figure 3 Schematic diagram of the structure of a combined flood regulation calculation system for upper and lower reservoirs of a pumped storage power station according to an embodiment of the present invention. Figure 3 The calculation method of combined flood regulation of upper and lower reservoirs of pumped storage power station corresponds to Figure 3 As shown, the combined flood regulation calculation system for upper and lower reservoirs of a pumped storage power station in this embodiment may include:

[0144] The unit flow calculation model building module 301 is used to build a pumped storage power station unit flow calculation model based on the relationship between the power grid load instruction and the output flow and input flow of the pumped storage power station at the initial and final water levels of the upper reservoir and the lower reservoir.

[0145] In the unit flow calculation model building module 301, the grid load instruction includes two parts: a pumped storage power station output instruction sequence and a pumped storage input instruction sequence. Each part includes multiple output and input instruction values ​​issued by the grid to the pumped storage power station.

[0146] The flow calculation model of pumped storage power station units is:

[0147]

[0148] Among them, Q e,out , Q e,in They are the output and input flow of the pumped storage power station units respectively; They are the output and input command values ​​issued by the power grid to the pumped storage power station; They are the initial and final water levels of the upper reservoir of the pumped storage power station during the period; They are the initial and final water levels of the lower reservoir of the pumped storage power station; A out and A in They are the output and input coefficients of the pumped-storage power station units respectively.

[0149] The design flood process group calculation module 302 is used to generate and record multiple design flood process lines by adjusting the design flood phase of the upper reservoir and the lower reservoir of the pumped storage power station to obtain the design flood process group.

[0150] In the design flood process group calculation module 302, the design flood phase adjustment method of the upper reservoir and the lower reservoir of the pumped storage power station is:

[0151]

[0152] in, is the design flood process group of the pumped storage power station; N is the number of design floods in the design flood process group of the pumped storage power station; is the i-th flood process matrix in the design flood process group; is the design flood process matrix of the upper and lower reservoirs of the pumped storage power station; T is the number of flood regulation calculation periods; t is the length of the design flood process matrix of the upper and lower reservoirs of the pumped storage power station.

[0153] The assumed unit flow value calculation module 303 is used to traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions.

[0154] The target flow value recalculation module 304 is used to obtain the target unit flow value under the current assumed conditions based on the unit flow calculation model of the pumped storage power station, compare the difference between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value, update the upper reservoir and the lower reservoir end water level values ​​under the assumed conditions, and recalculate the target flow value.

[0155] In the target flow value recalculation module 304, the assumed final water level values ​​of the upper and lower reservoirs are updated according to the difference between the unit flow corresponding to the upper and lower reservoirs and the target flow value:

[0156]

[0157] in, is the flow correlation coefficient in the update function; is the reservoir water level correlation coefficient in the update function; They are the normal water level and dead water level of the upper reservoir of the pumped storage power station; are the normal water level and dead water level of the lower reservoir of the pumped storage power station; ΔQ′ e,up,t , ΔQ′ e,down,t They are the differences between the unit flow rates corresponding to the upper and lower reservoirs of the pumped storage power station and the target flow rates; They are the assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped storage power station before the update; They are respectively the updated assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped-storage power station.

[0158] The reservoir water level process group calculation module 305 is used to subtract the unit flow value obtained through water balance of the upper reservoir and the lower reservoir from the target unit flow value, and start the calculation of the next time period after meeting the set accuracy until the end of the calculation period. After traversing all the design flood processes in the design flood process group, the water level process groups of the upper reservoir and the lower reservoir of the pumped storage power station are obtained.

[0159] In the reservoir water level process group calculation module 305, the initial water level conditions of the upper and lower reservoirs of the pumped storage power station in the next period are: the assumed values ​​of the upper and lower reservoirs of the pumped storage power station at the previous moment.

[0160] The storage capacity and downstream flow process calculation module 306 is used to determine the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, and calculate its storage capacity process and downstream flow process according to the relationship between water level and storage capacity and the principle of water balance.

[0161] Figure 3 The specific implementation process of modules 301 to 306 in the combined flood regulation calculation system of the upper and lower reservoirs of the pumped storage power station is shown in FIG. Figure 2 The specific implementation process of steps S201 to 206 is the same as that of FIG. 1 and will not be described in detail here.

[0162] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A calculation method for combined flood regulation of upper and lower reservoirs of a pumped storage power station, It is characterized in that include: Based on the relationship between the load instruction of the power grid and the output flow and input flow of the pumped storage power station at the initial and final water levels of the upper reservoir and the lower reservoir, a flow calculation model for the pumped storage power station unit is constructed; By adjusting the design flood phase of the upper and lower reservoirs of the pumped storage power station, multiple design flood process lines are generated and recorded to obtain a design flood process group; Traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions; Based on the flow calculation model of the pumped storage power station unit, the target unit flow value under the current assumed conditions is obtained, the gap between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value is compared, the final water level values ​​of the upper reservoir and the lower reservoir under the assumed conditions are updated, and the target flow value is recalculated; The unit flow value obtained by water balance of the upper reservoir and the lower reservoir is subtracted from the target unit flow value. When the set accuracy is met, the calculation of the next period starts until the calculation period ends. After traversing all the design flood processes in the design flood process group, the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station is obtained; Based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir is determined respectively. According to the relationship between the water level and storage capacity and the principle of water balance, the storage capacity process and the downstream flow process are calculated.

2. The combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station as claimed in claim 1, It is characterized in that The grid load instruction includes two parts: a pumped storage power station output instruction sequence and a pumped storage input instruction sequence. Each part includes a plurality of output and input instruction values ​​issued by the grid to the pumped storage power station.

3. The combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station as claimed in claim 1, It is characterized in that The flow calculation model of pumped storage power station units is: Among them, Q e,out , Q e,in They are the output and input flow of the pumped storage power station units respectively; They are the output and input command values ​​issued by the power grid to the pumped storage power station; They are the initial and final water levels of the upper reservoir of the pumped storage power station during the period; They are the initial and final water levels of the lower reservoir of the pumped storage power station; A out and A in They are the output and input coefficients of the pumped-storage power station units respectively.

4. The combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station as claimed in claim 1, It is characterized in that The design flood phase adjustment method for the upper and lower reservoirs of a pumped storage power station is as follows: in, is the design flood process group of the pumped storage power station; N is the number of design floods in the design flood process group of the pumped storage power station; is the i-th flood process matrix in the design flood process group; is the Nth flood process matrix in the design flood process group; is the design flood process matrix of the upper and lower reservoirs of the pumped storage power station; T is the number of flood regulation calculation periods; t is the length of the design flood process matrix of the upper and lower reservoirs of the pumped storage power station.

5. The combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station as claimed in claim 1, It is characterized in that According to the difference between the unit flow rate corresponding to the upper and lower reservoirs and the target flow rate value, update the assumed final water level values ​​of the upper and lower reservoirs: in, is the flow correlation coefficient in the update function; is the reservoir water level correlation coefficient in the update function; They are the normal water level and dead water level of the upper reservoir of the pumped storage power station; are the normal water level and dead water level of the lower reservoir of the pumped storage power station; ΔQ e ' ,up,t , ΔQ e ' ,down,t They are the differences between the unit flow rates corresponding to the upper and lower reservoirs of the pumped storage power station and the target flow rates; They are the assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped storage power station before the update; They are respectively the updated assumed values ​​of the final water levels of the upper and lower reservoirs of the pumped-storage power station.

6. The combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station as claimed in claim 1, It is characterized in that The initial water level conditions of the upper and lower reservoirs of the pumped-storage power station in the next period are: the assumed values ​​of the upper and lower reservoirs of the pumped-storage power station at the previous moment.

7. A combined flood regulation calculation system for upper and lower reservoirs of a pumped storage power station, It is characterized in that include: A unit flow calculation model building module is used to build a pumped storage power station unit flow calculation model based on the relationship between the power grid load instruction and the output flow and input flow of the pumped storage power station at the initial and final water levels of the upper reservoir and the initial and final water levels of the lower reservoir; A design flood process group calculation module, which is used to generate and record multiple design flood process lines by adjusting the design flood phase of the upper reservoir and the lower reservoir of the pumped storage power station to obtain a design flood process group; The module for calculating the assumed unit flow value is used to traverse the design flood process group, assume the final water level of the upper reservoir and the final water level of the lower reservoir of the pumped storage power station in turn according to the time period for each design flood process, perform water balance calculation, and obtain the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions; The target flow value recalculation module is used to obtain the target unit flow value under the current assumed conditions based on the unit flow calculation model of the pumped storage power station, compare the difference between the unit flow values ​​corresponding to the upper reservoir and the lower reservoir under the current assumed conditions and the target unit flow value, update the upper reservoir and the lower reservoir end water level values ​​under the assumed conditions, and recalculate the target flow value; The reservoir water level process group calculation module is used to make a difference between the unit flow value obtained by water balance of the upper reservoir and the lower reservoir and the target unit flow value, and start the calculation of the next period after the set accuracy is met until the calculation period ends. After traversing all the design flood processes in the design flood process group, the water level process groups of the upper reservoir and the lower reservoir of the pumped storage power station are obtained; The storage capacity and downstream flow process calculation module is used to determine the reservoir water level process corresponding to the highest water level of the upper reservoir and the lower reservoir based on the water level process group of the upper reservoir and the lower reservoir of the pumped storage power station, and calculate its storage capacity process and downstream flow process according to the water level storage capacity relationship and water balance principle.

8. The combined flood regulation calculation system for upper and lower reservoirs of a pumped storage power station as claimed in claim 7, It is characterized in that The grid load instruction includes two parts: a pumped storage power station output instruction sequence and a pumped storage input instruction sequence. Each part includes a plurality of output and input instruction values ​​issued by the grid to the pumped storage power station.

9. A computer-readable storage medium having a computer program stored thereon, It is characterized in that When the program is executed by a processor, the steps in the calculation method for combined flood regulation of upper and lower reservoirs of a pumped storage power station as described in any one of claims 1 to 6 are implemented.

10. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, It is characterized in that When the processor executes the program, the steps in the combined flood regulation calculation method for the upper and lower reservoirs of a pumped storage power station are implemented as described in any one of claims 1-6.