Automatic circulating purification device and method for dry quenching circulating water
By designing a combination of multi-stage filtration circulating water tanks and elevated emergency water tanks, the automatic purification and reuse of circulating water in the dry quenching system is achieved, solving the problems of circulating water waste and equipment scaling, and improving system safety and equipment lifespan.
Patent Information
- Application Number
- CN202411292308.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-11-19
AI Technical Summary
In existing dry quenching systems, the circulating water supply scheme suffers from problems such as waste of demineralized water and scale buildup in equipment due to poor water quality, which affects equipment lifespan and safety.
The design incorporates a multi-stage filtration circulating water tank, which utilizes the height difference of the baffles to achieve natural sedimentation filtration. Combined with an elevated emergency water tank and a booster pump, it enables automatic purification and reuse of circulating water, preventing water quality deterioration and equipment scaling.
It achieves automatic purification of circulating water, saves energy, reduces impurity content, extends equipment life, and improves system safety and equipment operation stability.
Smart Images

Figure CN118976282A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an automatic circulation purification device and method for coke dry quenching circulation water, belonging to the field of metallurgical coking. Background Art
[0002] Coke dry quenching refers to a coke quenching method that uses inert gas to cool down red coke. During the coke dry quenching process, 1000℃ red coke is loaded from the top of the dry quenching furnace, and 130℃ low-temperature inert circulating gas is blown into the red coke layer in the cooling section of the dry quenching furnace by the circulating fan to absorb the sensible heat of the red coke. The cooled coke (below 200℃) is discharged from the bottom of the dry quenching furnace.
[0003] A water seal groove is provided on the top of the CDQ furnace to solve the sealing problem of the furnace top and play a role in cooling. The water seal groove cooperates with the furnace cover or water seal hood to prevent dust from escaping and air from leaking in. An emergency relief valve is provided on the top of the primary dust collector, which is also sealed by circulating water. Circulating water is also used in the water-cooling jacket to cool the red-hot coke powder.
[0004] At present, there are two common water supply schemes for water seal tanks or other water points. One is to use a water supply pump to pump desalted water into the water seal tank or other water points through a pipeline, and replenish water in time according to the water level. The disadvantage is that the desalted water is discharged after being supplied to the water seal tank or other cooling water points. Very few have set up a recovery system, but the purchase or self-made desalted water and the external drainage cause a large amount of desalted water waste. The second is to use the comprehensive water circulation system of the coking production process to supply water to the water seal tank or other water points for dry quenching through a water supply pump. The disadvantage of this water supply scheme is that the coking production water is directly used, the water quality is poor, and it contains a lot of calcium and magnesium ions. It will adhere to the equipment under long-term operation. If it is not cleaned in time, it will form a thick scale, making the bottom of the water seal tank unable to be cooled, causing the bottom weld of the inner ring of the water seal tank to crack; at the same time, if the water seal tank is cleaned frequently, it will also bring personal safety hazards; and frequent cleaning increases the labor intensity of workers and reduces the service life of water point equipment. Summary of the invention
[0005] The present invention aims to provide a method for automatic circulation purification of CDQ circulating water, which can automatically filter the CDQ circulating water and realize recycling at the same time, thus saving energy, reducing impurities in the circulating water, protecting key equipment from damage, and improving the operating safety of the entire CDQ system.
[0006] The present invention designs a multi-stage filtering circulating water tank, and realizes natural sedimentation filtration of circulating water through the height difference of the partition in the filtering water tank, thereby ensuring the cleanliness of the circulating water and having a low treatment cost; a high-position accident emergency water tank is designed to avoid water shortage in other water use points such as the furnace top water seal tank due to a short-term power outage; at the same time, the multi-stage filtering circulating water tank ensures the cleanliness of the circulating water, has a low treatment cost, and increases the service life of the furnace top water seal tank and other water use point equipment.
[0007] The present invention provides an automatic circulating purification device for CDQ circulating water. The whole device comprises: a main water supply tank, a high-position emergency water tank on the fourth floor of the CDQ furnace body, a primary purification water tank on the third floor of the CDQ furnace body, a secondary purification water tank on the first floor of the CDQ furnace, and three groups of booster pumps for cooling circulating water. The circulating water booster pump provides power to the whole device, and a water supply pump is provided at the outlet of the main water supply tank to replenish circulating water for the whole device. After the circulating water is purified in two stages, namely, the third floor and the first floor, the coke powder and impurities carried therein can be basically removed, thereby realizing automatic purification and circulation of water.
[0008] The main water supply tank is connected to the water supply pump, the secondary purified water tank, and the booster pump in sequence. The outlet section of the booster pump is connected to the water cooling sleeve and the high-level emergency water tank. The high-level emergency water tank is connected to the water seal tank. The water return pipes of the water seal tank and the water cooling sleeve are connected to the primary purified water tank on the third floor of the dry quenching furnace. The first-stage purified water tank and the second-stage purified water tank have the same structure, both of which are semi-enclosed water tank bodies. Three partition plates are arranged in the semi-enclosed water tank body. The partition plates are vertically arranged plates. The three plates are arranged from high to low, dividing the semi-enclosed water tank body into four different areas to achieve purification.
[0009] The circulating water is automatically purified and circulated after passing through the primary purification water tank and the secondary purification water tank.
[0010] The above device is further described as follows: The main water supply tank is connected to the circulating water system of the chemical production process. The main water supply tank is set to 5000mm×3000mm×2000mm. Its main function is to supply water to the entire circulation purification device to ensure a stable water volume; The secondary purified water tank is located on the first floor of the dry quenching furnace, and includes a semi-enclosed water tank body composed of a bottom wall and a side wall, with a specification of 3000mm×2000mm×1500mm. The water tank is divided into four different functional areas, namely, the water inlet area, the transition area 1, the transition area 2 and the water outlet area, through the partitions arranged in sequence along the horizontal direction; wherein a full flow trough is arranged on the upper part of the partition, an inlet pipe is arranged on the upper part of the side wall of the water inlet area, an outlet pipe is arranged on the upper end of the water outlet area, and a sewage pipe is arranged at the lower part of each functional area; its main functions are to collect the circulating water after the initial purification of the primary purified water tank and perform secondary purification, and to receive the circulating water supplemented by the main water supply tank of the circulation device and purify it. A float flowmeter is arranged in the water inlet area to establish a linkage relationship between the liquid level of the water inlet area and the water supply pump. When the liquid level of the water inlet area is lower than 1300mm, the water supply pump automatically starts to supplement the circulating water for the entire device.
[0011] The specification of the high-level emergency water tank is 2500mm×2000mm×1000mm. The upper part of the high-level emergency water tank is provided with a water inlet pipe and an overflow pipe, and the lower part is provided with a water outlet pipe and a sewage pipe; The specification of the first-level purified water tank is 1800mm×1000mm×1000mm; the main structure of the first-level purified water tank is basically the same as that of the second-level purified water tank.
[0012] Float switches are provided inside the primary purified water tank and the secondary purified water tank. The float switches control the liquid level of the water tank through the central control. When it is detected that the liquid level is lower than the set liquid level, the central control automatically replenishes water to the secondary filtered water tank through the water replenishment pump; when the float switch detects that the liquid level is higher than the set liquid level, the central control stops the water replenishment pump to replenish water.
[0013] The booster pumps for the circulating water are equipped with a dual power supply system, and the operation mode is one on and two on standby. An electric valve is installed at the outlet of each pump, and a chain relationship is established between the electric valves of the three pumps. When the booster pump in use stops due to power outage or failure, the electric valve of the standby pump automatically opens and the booster pump automatically starts.
[0014] The present invention provides an automatic circulation purification process for CDQ circulating water using the above device, which includes the following contents: (1) The main water supply tank is connected to the circulating water system of the chemical production process, and the main water supply tank is connected to the water supply pump, secondary purification water tank, booster pump, high-level emergency water tank, water cooling jacket, water seal tank and primary purification water tank in sequence; the main water supply tank uses the circulating water of the chemical production process to supply water to the secondary filter water tank; the secondary filter water tank supplies water to the high-level emergency water tank through the booster pump group; the high-level emergency water tank supplies water to the furnace top water seal tank and water cooling jacket; the primary filter water tank is used to filter the drained water from the furnace top water seal tank and supply water to the secondary filter water tank.
[0015] (2) The secondary purified water tank is located on the first floor of the CDQ furnace. It collects the circulating water after the initial purification in the primary purified water tank and performs secondary purification. At the same time, it receives the circulating water supplemented by the main water supply tank of the circulating purification device and purifies it. The circulating water after two-stage purification passes through the last water outlet area of the secondary purified water tank and is then transported by the circulating water booster pump to the high-level emergency water tank on the fourth floor of the CDQ furnace for use in water sealing tanks and other equipment; (3) Part of the water delivered to the dry quenching furnace body by the booster pump enters the high-level emergency water tank, and the other part of the water is directly delivered to the water-cooling jacket for use; under normal circumstances, the water coming out of the overflow pipe of the high-level emergency water tank is directly supplied to the water sealing tank for use. When water shortage occurs, the water is supplied to the water sealing tank through the lower water outlet pipe; (4) The water from the water seal tank and water cooling jacket enters the primary purification water tank on the third floor of the CDQ furnace. After primary purification, the water enters the water inlet area of the secondary purification water tank for secondary purification. (5) When it is detected that the liquid level inside the primary and secondary purified water tanks is lower than the set level, the central control automatically replenishes water to the secondary filter water tank through the water replenishment pump; when the float switch detects that the liquid level is higher than the set level, the central control stops the water replenishment pump to replenish water. When the liquid level in the water inlet area is lower than 1300mm, the water replenishment pump automatically starts to replenish circulating water for the entire device; Beneficial effects of the present invention: The present invention designs a multi-stage filtering circulating water tank to ensure the cleanliness of the circulating water, with low processing cost, and utilizes chemical circulating water, saving the cost of purchasing or making desalted water, eliminating the scaling phenomenon of water-using point equipment caused by the poor water quality of the coking comprehensive water circulating water, and avoiding the waste of circulating water resources. On the other hand, it also prolongs the service life of the water seal tank and other water-using equipment, and the service life of the water seal tank is extended from 8-12 months to 2.5-3 years. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the automatic circulation purification device for CDQ circulating water.
[0017] In the figure: 1 is the main water supply tank, 2 is the water supply pump, 3 is the secondary purification water tank, 4 is the booster pump, 5 is the high-level emergency water tank, 6 is the water cooling jacket, 7 is the water seal tank, and 8 is the primary purification water tank. DETAILED DESCRIPTION
[0018] The present invention is further illustrated by the following examples, but is not limited to the following examples. Example 1
[0019] like Figure 1As shown, this embodiment provides an automatic circulation purification device for CDQ circulating water, including: a main water supply tank 1, a high-level emergency water tank 5, a primary purification water tank 8, a secondary purification water tank 3, and a booster pump 4. The circulating water booster pump 4 provides power to the entire device, and a water supply pump 2 is provided at the outlet of the main water supply tank 1 to replenish circulating water for the entire device. After the circulating water is purified in three layers and one layer, the coke powder and impurities carried in it can be basically removed, realizing automatic purification and circulation of water. The high-level emergency water tank 5 is arranged on the fourth layer of the CDQ furnace body, the primary purification water tank 8 is arranged on the third layer of the CDQ furnace body, the secondary purification water tank 3 is arranged on the first layer of the CDQ furnace, and the booster pump 4 is a booster pump for three groups of ice-cold circulating water.
[0020] The main water supply tank 1 is connected to the water supply pump 2, the secondary purified water tank 3, and the booster pump 4 in sequence. The outlet section of the booster pump 4 is connected to the water cooling sleeve 6 and the high-level emergency water tank 5. The high-level emergency water tank 5 is connected to the water seal groove 7. The water return pipe of the water seal groove 7 and the water cooling sleeve 6 is connected to the primary purified water tank 8 of the third layer of the dry quenching furnace. The first-stage purified water tank 8 and the second-stage purified water tank 3 have the same structure, both of which are semi-enclosed water tank bodies. Three partition plates are arranged in the semi-enclosed water tank body. The partition plates are vertically arranged plates. The three plates are arranged from high to low, dividing the semi-enclosed water tank body into four different areas to achieve purification; no chemicals are needed, and purification is achieved from high to low by relying on gravity sedimentation.
[0021] The circulating water is automatically purified and circulated after passing through the primary purified water tank 8 and the secondary purified water tank 3.
[0022] The above device is further described as follows: The main water supply tank 1 is connected to the circulating water system of the chemical production process. The main water supply tank is set to 5000mm×3000mm×2000mm. Its main function is to supply water to the entire circulation purification device to ensure a stable water volume; The secondary purified water tank 3 is located on the first floor of the dry quenching furnace, and includes a semi-enclosed water tank body composed of a bottom wall and a side wall, with a specification of 3000mm×2000mm×1500mm. The water tank is divided into 4 different functional areas, namely, the water inlet area, the transition area 1, the transition area 2 and the water outlet area, through the partitions arranged in sequence along the horizontal direction; wherein a full flow trough is arranged on the upper part of the partition, an inlet pipe is arranged on the upper part of the side wall of the water inlet area, an outlet pipe is arranged on the upper end of the water outlet area, and a sewage pipe is arranged at the lower part of each functional area; its main functions are to collect the circulating water after the initial purification of the primary purified water tank and perform secondary purification, and to receive the circulating water supplemented by the main water supply tank of the circulation device and purify it. A float flowmeter is arranged in the water inlet area to establish a linkage relationship between the liquid level of the water inlet area and the water supply pump. When the liquid level of the water inlet area is lower than 1300mm, the water supply pump automatically starts to supplement the circulating water for the entire device.
[0023] The specification of the high-position emergency water tank 5 is 2500mm×2000mm×1000mm, and the upper part of the high-position emergency water tank is provided with a water inlet pipe and an overflow pipe, and the lower part is provided with a water outlet pipe and a sewage pipe; The specification of the primary purified water tank 8 is 1800mm×1000mm×1000mm; the main structure of the primary purified water tank is basically the same as that of the secondary purified water tank.
[0024] Float switches are provided inside the primary purified water tank 8 and the secondary purified water tank 3. The float switches control the liquid level of the water tanks through the central control. When the liquid level is detected to be lower than the set liquid level, the central control automatically replenishes water to the secondary filtered water tank through the water replenishment pump; when the float switch detects that the liquid level is higher than the set liquid level, the central control stops the water replenishment pump to replenish water.
[0025] The booster pump 4 of the circulating water is equipped with a dual power supply system, and the operation mode is one on and two on standby. An electric valve is installed at the outlet of each pump, and a chain relationship is established between the electric valves of the three pumps. When the booster pump in use stops due to power outage or failure, the electric valve of the standby pump automatically opens and the booster pump automatically starts.
[0026] The present invention provides an automatic circulation purification process for CDQ circulating water using the above device, which includes the following contents: (1) The main water supply tank is connected to the circulating water system of the chemical production process, and the main water supply tank is connected to the water supply pump, secondary purification water tank, booster pump, high-level emergency water tank, water cooling jacket, water seal tank and primary purification water tank in sequence; the main water supply tank uses the circulating water of the chemical production process to supply water to the secondary filter water tank; the secondary filter water tank supplies water to the high-level emergency water tank through the booster pump group; the high-level emergency water tank supplies water to the furnace top water seal tank and water cooling jacket; the primary filter water tank is used to filter the drained water from the furnace top water seal tank and supply water to the secondary filter water tank.
[0027] (2) The secondary purified water tank is located on the first floor of the CDQ furnace. It collects the circulating water after the initial purification in the primary purified water tank and performs secondary purification. At the same time, it receives the circulating water supplemented by the main water supply tank of the circulating purification device and purifies it. The circulating water after two-stage purification passes through the last water outlet area of the secondary purified water tank and is then transported by the circulating water booster pump to the high-level emergency water tank on the fourth floor of the CDQ furnace for use in water sealing tanks and other equipment; (3) Part of the water delivered to the dry quenching furnace body by the booster pump enters the high-level emergency water tank, and the other part of the water is directly delivered to the water-cooling jacket for use; under normal circumstances, the water coming out of the overflow pipe of the high-level emergency water tank is directly supplied to the water sealing tank for use. When water shortage occurs, the water is supplied to the water sealing tank through the lower water outlet pipe; (4) The water from the water seal tank and water cooling jacket enters the primary purification water tank on the third floor of the CDQ furnace. After primary purification, the water enters the water inlet area of the secondary purification water tank for secondary purification. (5) When the liquid level in the water inlet area is lower than 1300mm, the water replenishment pump automatically starts to replenish circulating water for the entire device; specifically: float switches are set inside the primary purification water tank and the secondary purification water tank. The float switches control the water tank liquid level through the central control. When the liquid level is detected to be lower than the set level, the central control automatically replenishes water to the secondary filtration water tank through the water replenishment pump; when the float switch detects that the liquid level is higher than the set level, the central control stops the water replenishment pump to replenish water.
[0028] The above device was tried out in four CDQ furnaces of TISCO Coking Plant, which reduced the workload of personnel in frequently cleaning the water seal tanks, saved water resources, extended the service life of the CDQ water seal tanks, and achieved the dual goals of energy saving and safety.
Claims
1. An automatic circulation purification device for CDQ circulating water, characterized in that include: Main make-up water tank, high-level emergency water tank, primary purified water tank, secondary purified water tank, and booster pump; the booster pump is used to provide power to the entire device, and a make-up water pump is set at the outlet of the main make-up water tank to replenish circulating water for the entire device; the main make-up water tank is connected to the make-up water pump, the secondary purified water tank, and the booster pump in sequence, the outlet section of the booster pump is connected to the water cooling jacket and the high-level emergency water tank, the high-level emergency water tank is connected to the water seal tank, the water seal tank and the water return pipe of the water cooling jacket are connected to the primary purified water tank, and the circulating water is automatically purified and circulated after passing through the primary purified water tank and the secondary purified water tank.
2. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The high-level emergency water tank is set on the fourth floor of the dry quenching furnace body, the first-level purification water tank is set on the third floor of the dry quenching furnace body, and the second-level purification water tank is set on the first floor of the dry quenching furnace.
3. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The first-stage purified water tank and the second-stage purified water tank have the same structure, both of which are semi-enclosed water tank bodies. Three partition plates are arranged in the semi-enclosed water tank body. The partition plates are vertically arranged plates. The three plates are arranged from high to low, dividing the semi-enclosed water tank body into four different areas to achieve purification.
4. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The main water supply tank is connected to the circulating water system of the chemical production process, and the main water supply tank is set to 5000mm×3000mm×2000mm.
5. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The secondary purified water tank is located on the first floor of the dry quenching furnace, and includes a semi-enclosed water tank body composed of a bottom wall and a side wall, with a specification of 3000mm×2000mm×1500mm. The water tank is divided into four different functional areas, namely, a water inlet area, a transition area 1, a transition area 2 and a water outlet area, by partition plates arranged in sequence along the transverse direction; wherein a full flow trough is arranged on the upper part of the partition plate, a water inlet pipe is arranged on the upper part of the side wall of the water inlet area, a water outlet pipe is arranged on the upper end of the water outlet area, and a sewage pipe is arranged at the lower part of each functional area; the specification of the primary purified water tank is 1800mm×1000mm×1000mm; the main structure of the primary purified water tank is basically the same as that of the secondary purified water tank.
6. The automatic circulation purification device for CDQ circulating water according to claim 5 is characterized by: A float flow meter is installed in the water inlet area, and a linkage relationship is established between the liquid level in the water inlet area and the water supply pump.
7. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The specifications of the high-level emergency water tank are 2500mm×2000mm×1000mm. A water inlet pipe and an overflow pipe are arranged at the upper part of the high-level emergency water tank, and a water outlet pipe and a sewage pipe are arranged at the lower part.
8. The automatic circulation purification device for CDQ circulating water according to claim 1 is characterized by: The booster pump is equipped with a dual power supply system, and the operating mode is one on and two on standby; an electric valve is installed at the outlet of each booster pump, and a chain relationship is established between the electric valves of the three pumps. When the booster pump in use stops due to power outage or failure, the electric valve of the standby pump automatically opens and the booster pump automatically starts.
9. A process for automatic circulation purification of coke dry quenching circulating water, using the automatic circulation purification device for coke dry quenching circulating water according to any one of claims 1 to 8, characterized in that Includes the following: (1) The main water supply tank is connected to the circulating water system of the chemical production process, and the main water supply tank is connected to the water supply pump, the secondary purification water tank, the booster pump, the high-level emergency water tank, the water cooling jacket, the water seal tank and the primary purification water tank in sequence; the main water supply tank uses the circulating water of the chemical production process to supply water to the secondary filter water tank; the secondary filter water tank supplies water to the high-level emergency water tank through the booster pump group; the high-level emergency water tank supplies water to the furnace top water seal tank and the water cooling jacket; the primary filter water tank is used to filter the water from the furnace top water seal tank and supply water to the secondary filter water tank; (2) The secondary purified water tank is located on the first floor of the CDQ furnace. It collects the circulating water after the initial purification in the primary purified water tank and performs secondary purification. At the same time, it receives the circulating water supplemented by the main water supply tank of the circulating purification device and purifies it. The circulating water after two-stage purification passes through the last water outlet area of the secondary purified water tank and is then transported by the circulating water booster pump to the high-level emergency water tank on the fourth floor of the CDQ furnace for water sealing. (3) Part of the water delivered to the dry quenching furnace body by the booster pump enters the high-level emergency water tank, and the other part of the water is directly delivered to the water-cooling jacket for use; under normal circumstances, the water coming out of the overflow pipe of the high-level emergency water tank is directly supplied to the water sealing tank for use. When water shortage occurs, the water is supplied to the water sealing tank through the lower water outlet pipe; (4) The water from the water seal tank and the water cooling jacket enters the primary purification water tank on the third floor of the CDQ furnace. After primary purification, the water enters the water inlet area of the secondary purification water tank for secondary purification.
10. The automatic circulation purification process for CDQ circulating water according to claim 9, characterized in that: When the liquid level in the water inlet area is lower than 1300mm, the water replenishment pump starts automatically to replenish circulating water for the entire device; specifically: float switches are set inside the primary purified water tank and the secondary purified water tank. The float switches control the water tank liquid level through the central control. When the liquid level is detected to be lower than the set level, the central control automatically replenishes water to the secondary filter water tank through the water replenishment pump; when the float switch detects that the liquid level is higher than the set level, the central control stops the water replenishment pump to replenish water.
Citation Information
Patent Citations
Power failure emergency device and method for blast furnace cooling water system
CN110804683A
Automatic circulating water supply system for cooling water of dry quenching water seal
CN113698947A
Recycling and circulating water replenishing system for coke oven sewage
CN220176145U